Unit 4 - Labour Cost
Unit 4 - Labour Cost
2. Calculate the earnings under Taylor's differential piece rate from the given information
Rate per hour Rs 6
Standard time per unit 30 minutes
Differential piece rate to be applied:
75% of piece rate below standard
125% of piece rate at or about standard
In 8 hours of a day the actual output of the workers are A 15 units, B 25 units.
2. Calculate the earnings of workers A, B and C under straight piece system and merricks
multiple piece rate system from the following particulars
Normal rate per hour Rs 10.80
Standard time for unit 1 minute
Output per day is as follows:
A 390 units, B 450 units, C 600 units
working hours per day are 8
1. Calculate the earnings of X,Y and Z when their output in a day of 8 hours are X 75 units,
Y 80 units and Z 85 units
Guaranteed time rate is Rs 2 per hour and standard output is 10 units per hour. High piece rate is
fixed at 0.35 paise per unit.
2. The following particulars are given
Time rate Rs 10 per hour
High task 80 units per week
Piece rate above high task Rs 15 per unit
In a 40 hours week, the production of the workers was A 70 units B 80t units C 85 units
D 110 units
Calculate the wages of the workers under gantt's task and bonus plan.
Halsey plan
Workers will be paid a guaranteed hourly rate plus a percentage of wages for the time saved.
Earnings =time taken X time rate + bonus
Where bonus = ½ ( time saved X time rate)
1. The standard time for producing 100 articles is 50 hours. The rate of wages is Rs 1.5 0
per hour. The actual time taken for producing 100 articles is 42 hours. What are the
earnings of workers under the Halsey plan?
2. Standard time allowed for a job is 50 hours. The hourly rate of wages is Rs 2 per hour
plus a dearness at Rs 2.50 per hour worked. The actual time taken by the worker was 40
hours. calculate total wages on halsey plan.
Rowan plan
Earnings= time taken X time taken + bonus
Bonus = time saved / standard TimeX time takenX time rate per hour
Earnings = time taken X time rate + time saved/standard TimeX time taken X time rate.
1. From the following information, calculate bonus, total earnings and rate of earnings per
hour under the Rowan plan. Time allowed 6 hours, hourly rate Rs1.50, time taken 4
hours.
2. Shri Ganesh finished work in 120 hours as against 140 hours allowed. His hourly rate is
Rs 5. He gets a DA of Rs 16 per day of 8 hours worked in addition to his wages. calculate
his total earnings under the Rowan plan.
3.
Emerson efficiency plan:
Level of efficiency rate of bonus
Below 66.66% time wage
66.66% to 100% time wage +bonus 20% of time wage
Abov 100% time wage + 20% of bonus of time wage + 1% of bonus for every
1% increase in efficiency
● During work, Shree Pandav manufactured 300 articles. He received wages for 48 hours at
the rate of Rs 4 per hour. The estimated time to produce one article is 10 minutes and
under the incentive scheme, the time allowed is increased by 20%. Calculate his gross
wages according to:
1. piece work with the guaranteed weekly wage
2. Rowan premium bonus
3. halsey premium bonus.