Evaluation of Reliability: Worth and Value of Lost Load
Evaluation of Reliability: Worth and Value of Lost Load
Indexing terms: Reliability, Reliabilit indices, Customer interruption costs, Composite customer damage fiction, Customer outage costs, Incremental
customer outage costs, Value of lost Lad
ed by these surveys. This is the primary purpose not required. Instead, this paper concentrates on devel-
paper since such COC are observed to provide oping the cost model.
objective and consistent measures of the worth of sup-
ply. In addition the authors have reconsidered VOLL 2.2 Developing the cost model
y and numerically using the cost data For a particular service area, the cost model is a series
resulting from these studies. of values referred to as the composite customer damage
In order to achieve this an understanding of the per- function (CCDF) [XI which represent the costs due to
customer interruption costs (CIC) and the cus- supply interruptions as a function of interruption dura-
outage costs (COC) is required. These are tion for the particular customer mix. The following
d as follows: steps are followed to develop a CCDF:
CIC: the perceived individual customer or average 2.2. I Step A. Values of the perceived costs of
sector customer costs resulting from electricity inter- interruption (f) for the various interruption
ruptions. They are therefore system independent durations are obtained: Mail surveys were
COG: the expected total costs incurred by all the employed in the UMIST studies to obtain estimates for
customers connected to a particular network or service the CIC per interruption for residential, commercial,
area. They are calculated from the CIC and take into industrial and large user (>8MW) sectors. The survey
consideration the network performance data and load- procedures, sample sizes and the number of responses
ing information. They are therefore customer mix and are given and discussed in [SI. This paper concentrates
system dependent. on how the perceived customer interruption costs,
whose average sector values are presented in Table 1,
u § ~ o r n eoutage
~ costs (COC) can be processed into COC.
In order to facilitate analyses, it is important that the
2. I Factors affecting COC CIC data is collated according to the sector and where
From their definition, the customer outage costs of a possible grouped according to the SIC classes or sub-
service area and time period are a function of: sectors. The following definitions apply:
(i) the number of interruptions experienced Sector: This is a broad category which describes the
(ii) the duration of these interruptions main usage of electricity. It refers to the commercial,
the perceived interruption costs of the customers industrial, large user and residential categories.
SIC class: This is a subcategory of a sector as classi-
the numbers and mix of customers. fied under the 3-digit code of consumers, e.g. code 620
Consequently to evaluate the COC for a particular represents hotels and motels classes of the commercial
service area, at least two models must be established; a sector. The 3-digit code covers all categories of con-
scribing the performance of the power sumers.
the area and a cost model representing Subsector: This term defines a group of SIC classes,
IC for the mix of connected customers. under a category, which have a common characteristic.
third model, the load model, becomes For example all residential sector consumers, irrespec-
A brief overview of the system model is tive of SIC class, supplied under Economy 7 tariff are
classified under the Economy 7 subsector. In the light
COC, knowledge of the average failure of these definitions, a sector is formed by a number
rate (h) and the average duration of interruption (r) is SIC classes or subsectors which are representative of
these indices are derived from data the make-up of its population.
fault reporting scheme mentioned
earlier. They can also be deduced from the availability 2.2.2 Step B. The estimates for each interrup-
. Unfortunately these indices are tion are normalised b y dividing the costs by
uced from collected data and are specific to the per- either the annual energy consumed or the
systems and may not be suitable peak demand: Since they are system independent,
for predicting future performance especially if the rele- CIC would neither be suitable for comparing historical
hilosophies alter in or future performance of alternative network configu-
prediction of the rations nor for crossutility comparison. In order to
s are to be used in make these comparisons on a similar and consistent
values of 1 and r basis, the CIC per interruption are normalised with
techniques which, respect to either the customers’ annual energy con-
sumption (MWh) or with respect to their peak demand
(kW). These normalised costs are given by eqns. 1 and
2,
(in L/MWh) (1)
172 IEE Proc.-Gener. Transm. Distrib., Vol. 143, Na. 2, March 1996
each duration rr studied, the SIC classes’ normalised
(in L/kW) (2) costs are appropriately weighted to yield a composite
value for the overall sector, CE,y(r,) or CL&J.
where CIC,(r,) are the-costs incurred by customer x per Although some utility planners suggest that for short
interruption of duration Y, while E, and L, are the interruptions (say less than l h ) weighting by peak
user’s annual energy consumed and the peak demand, demand is more appropriate since losses are related to
respectively. a power shortage rather than an energy shortage [9], in
these studies weighting by both parameters is carried
2.2.3 Step C. If individual SIC classes or sub- out across the entire range of durations. Eqns. 7 and 8
sectors are sufficiently large, their normalised show the calculation of sector normalised costs for a
costs are first calculated before proceeding to general sector y consisting of ns subgroups with weight-
Step D, otherwise if retaining the SIC classes ing with respect to the annual energy consumed by SIC
or subsectors does not yield any meaningful class k and the SIC class peak demand, respectively:
results, the sector values are calculated at this
stage and Step D omitted:
(i) If SIC classes or subsectors are sufficiently large, C E , y (Tz) = kEns (in .Z/MWh) (7)
then the normalised CIC values for customers within 7 Ek
U -
the same SIC class are averaged to give the correspond- kEns
ing SIC class values. For a general SIC class k with y1
consumers these values, CE,k(rJand CL,k (YJ are given
by: CL,y(Tz) = kens (in L/kW) (8)
CE,x
-5-
U
LE’.
kEns
xEk
CE,k(Tz) = (in L/MWh) (3) Both sets of sector values (for the entire range of dura-
n
~
CE,y(G) = ~
c
XEY
CE,x
(in L/MWh) (5)
n 01 1 10 100 lo00 lo000
duration ,min
Fig. 1 Ratios of C
, to C
,
Residential (-), c6mmerciaY(- - -), industrial ( ), large user (- - -)
(in L/kW) (6)
2.2.4 Step D. The SIC class or subsector nor- The SCDFs for the sectors surveyed, combined for
malised costs are weighted to give the sector the three RECs involved in the surveys, are given in
values: When responses are adequate to enable subdi- Table 2. An analysis of these SCDFs indicates there is
vision of a sector into its constituent SIC classes, for an approximately constant ratio (see Fig. 1) between
Table 2: SCDFs for sectors investigated
SCDFs (f/MWh) SCDFs (f/
Duration Res. Comm Ind. L. user Res. Comm Ind. L. user
mom - 0.46 3.02 1.07 - 0.99 6.15 6.74
lmin - 0.48 3.13 1.07 - 1.02 6.47 6.74
20min 0.06 1.64 6.32 1.09 0.15 3.89 14.27 6.86
Ih 0.21 4.91 11.94 1.36 0.54 10.65 25.26 7.18
4h 1.44 18.13 32.59 1.52 3.72 39.04 72.22 8.86
8h - 37.06 53.36 1.71 - 78.65 120.11 9.71
24h - 47.58 67.10 2.39 - 99.98 150.38 13.35
IEE Proc.-Gener. Trunsm. Distrib., Vol. 143, No. 2, March 1996 173
the corresponding SCDF values for each sector, i.e. by implementing steps B and C only. The combined
between C,,(rJ and CLJri). This suggests a relation- REC SCDFs for the residential, commercial, industrial
ship between the two types of SCDFs. For any sector and large user sectors are given in Table 2.
y , this relationship can be shown to be empirically Also, during the surveys the respondents were asked
expressed by eqn. 9, to estimate CICs for only a limited number of outage
C L >Y
durations. It is therefore suggested that the SCDF val-
(in L/MWh) (9) ues for any intermediate durations within the specified
LFy x 8.76
range should be computed by linear interpolation while
where LFy is the load factor for sector y. This relation- those outside this range should be calculated using lin-
ship is important since it enables the ‘derivation of a ear extrapolation methods. The only exceptions being
single cost model rather than the pair that would be for,
expected from the two SCDFs. This is shown in the (a) outages of less than Imin, whose momentary
next and final stage of developing a cost model. SCDF values, where computed, should be assumed;
2.2.5 Step E. Finally the SCDF values are (b) residential sector outages less than 20min: in the
appropriately weighted in proportion to give case of the residential sector, the option to assume the
CCDF values; Cost of interruption surveys should be 20min SCDF values for shorter durations is given as
undertaken with specific objectives, such as system there is no real basis for assuming otherwise.
expansion, reinforcement or refurbishment. Further- The need for load information has gradually emerged
more, in order for the costs of the surveys to be justi- in the process of developing the load model. Although
fied, the projects involved should be considered not truly a load model because it only refers to the
substantive. Such projects are likely to affect all cus- annual energy consumed and peak demands (for the
tomer sectors supplied by the network under review. In customer or sector), this consumption information is
order to moderate the costs incurred, each SCDF value nonetheless loosely referred to as the load model.
for the sectors supplied is appropriately weighted to
yield a corresponding composite value, C(ri), for the 2.3 Calculating customer outage costs using
customer mix being considered. The expression for cal- CCDF
culating this composite value, assuming weighting by For any system or part of, the calculation of COC
the sector annual energy consumption, is given by involves the convolution of the cost model, the load
model and the system model. Assuming busbarj to be
a load point in a network consisting of b busbars, the
annual COC due to supply interruptions at the busbar
(COCJ and in the network (SCOC) are given by:
(in L/MWh)
where Ey is the annual energy consumed by sector y
and ny is the number of sectors connected to the sys-
tem under review. Energy consumption is used as the
moderating factor due to its information being readily
SCOC = ccocj
b
j€ b
(in .F) (13)
available, otherwise contribution at peak demand could Fig. 2 shows schematically the steps for calculating the
also be used. In instances where difficulties in disaggre- customer outage costs.
gating the load and therefore obtaining t.he load factors
may be encountered, the following expression which 2.4 Example
uses the supply point’s load factor (LF) may be used To illustrate the calculation of COCs, the following
instead: example, based on part of an actual 33kV network,
considers some proposed changes in order to remove
some obsolete switchgear. Figs. 3 and 4 show the sys-
tem before and after the proposed decommissioning of
obsolete switchgear around busbars 1 and 2. The
arrows show the points at which the network is con-
(in L/MWh) nected to the rest of the 33kV system. The analysis is
confined to buses 3 and 4 which are likely to be the
The series of values, C(r,), for the range of durations
most adversely affected by the proposed changes. The
studied forms the composite customer damage function
load, cost and system models are shown in Table 3.
(CCDF) for the associated network. This CCDF is
defined as the normalised costs due to power supply It should be noted that:
interruptions expressed as a function of the interrup- (i) the CCDF given in Table 3 is calculated by
tion duration for the customers and mix in the particu- weighting the appropriate SCDFs in Table 2 using the
lar service area [SI. The CCDF constitutes the cost load model data in accordance with eqn. 10
model used in evaluating customer outage costs (COC). (ii) the system model indices are derived from a reli-
It should be noted that in the UMIST surveys, only ability assessment of the two buses using the RELNET
the residential sector had sufficient responses to justify program which has been developed at UMIST [lo].
classification of the respondents into their constituent This program uses typical component failure and repair
subgroups. Consequently, only this sector’s results have data to compute the indices. However, in order to sim-
undergone the entire weighting process, represented by ulate the superior reliability of contemporary compo-
steps B to D, in order to obtain the SCDF. In the non- nents and to allow for degraded performance due to
residential sectors, the SCDFs are therefore obtained age, the failure rate and repair times for switchgear in
174 IEE Proc.-Genev. Transm. Distrib., Vol. 143, No. 2, March 1996
calculate normalised
CIC estimates, ie
CE& 1 and C&i 1
L
I
’
1 I
Fig. 4 are assumed to be two thirds of those of the cor- (a) Although the failure rates do not seem to
responding components in Fig. 3. increase very much, the average outage durations
Using the three models and applying eqns. 12 and 13, change significantly. The availability and security indi-
the COCs, SCOCs and ACOCs can be calculated. ces would be expected to capture these effects. How-
These are presented in Table 4. ever, they would scarcely be able to reflect the impacts
on the customers in the way the ACOCs do.
2.5 Discussion (b) Whichever index is used to measure reliability,
The results obtained from the above analysis lead to ACOC represents the incremental customer benefits or
the following comments: costs associated with the increase or decrease in the
IEE Proc.-Gener. Transm. Distrib.,Vol. 143, No. 2, March 1996 175
most likely the result of escalating the overall Ioad
weighted mean corresponding to l h (21.7lkWh) by
some index in accordance with:
1.7(1 + a)t = 2 (14)
This equation is satisfied for a = 4.4 and t = 4; where t
is interpreted to be the time (in years) between 1985
COCs suggests that the COC can be con- and 1989 whde a may be assumed to be the average
sidered as a supplementary reliability index. RPI over this period. The BlkWh has been increased
with the RPI since 1989 to the 22.345lkWh quoted in
the NGC review [4] and used by the Pool during 19921
93 (implying an average RPI of 4.06%); it is now
&2.389/kWh. No objective reasoning for adopting this
figure is available although the NGC review deemed a
value of around &2/kWh to be a reasonable ‘average’ or
central value. Despite this lack of justification, VOLL
bus 4 has had a very important role in the setting of Pool
payments. Lately there have also been proposals to
include VOLL as a factor in deciding the operational
Fig. 3 Network system before modpcution and planning security standards for the transmission
system. These applications are addressed below.
IEE Proc-Gener. Transm. Distrib., Vol. 143, No. 2, March 1996 179
7 BILLINTON, R., and ALLAN, R.N.: ‘Reliability assessment of
large electric power systems’ (Kluwer Press, 1988)
1 BILLINTON, R., and ALLAN, R.N.: ‘Reliability evaluation of 8 WACKER, G., and BILLINTON, R.: ‘Customer cost of electric
power systems’ (Plenum Press, 1984) service interruptions’, Proc. IEEE, 1989, 77, (6), pp. 919-930
2 Electricity Council: ‘Report on application of engineering recom- 9 GOUSHLEFF, D.C.: ‘Use of interruption costs in regional sup-
mendation P.215 security of supply’. A.C.E. Report No. 51, 1979 ply planning’. Ontario Hydro Report 80-301-K
3 Electricity Council: ‘Report of reliability investment in radial HV 10 ALLAN, R.N., SO, T.Y.P., and DA SILVA, M.G.: ‘Reliability
distribution systems with overhead lines’, A.C.E. Report No. 67, analysis of power system networks’. Users Manual for RELNET
1979 Version 4.1, October 1993
4 NGC: ‘A review of transmission security standards’, August 1994 11 The Electricity Council: ‘Guide to investment appraisal - Area
5 KARIUKI, K.K.: ‘Assessment of customer outage costs due to Boards’, December 1985
electric service interruptions’. PhD thesis, UMIST, October 1995 12 OFFER: ‘Report on constrained-on plant’, October 1992
6 ALLAN, R.N.: ‘VOLL fact or fiction’, Power Eng. J., 1995, 9,
~ 13 ‘The Regional Electricity Companies Share Offers - Main Pro-
(11, PP. 2 spectus’, November 1990
180 IEE Proc -Gener Transm Drstrrb , Vol 143, No 2, March 1996