0% found this document useful (0 votes)
41 views333 pages

Variation Calculation in Project Work

The document provides a detailed estimate and abstract of costs for the construction of a storm water drain and asphalt concreting works in Uday Marga Ward no-03. It includes descriptions of various construction activities, quantities, rates, and total costs, culminating in a grand total of approximately 14,296,759.97. Key components include dismantling, gravel filling, concreting, brick work, plastering, and asphalt work, along with safety and insurance provisions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views333 pages

Variation Calculation in Project Work

The document provides a detailed estimate and abstract of costs for the construction of a storm water drain and asphalt concreting works in Uday Marga Ward no-03. It includes descriptions of various construction activities, quantities, rates, and total costs, culminating in a grand total of approximately 14,296,759.97. Key components include dismantling, gravel filling, concreting, brick work, plastering, and asphalt work, along with safety and insurance provisions.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 333

Detailed Estimate & Abstract Of Cost

Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total
SN Description of work Nos Length Breadth Height Unit Quantity Rate Amount Remarks
Quantity
Dimantling of existing
1
structures
brick masonry wrks
drain inner portion 2 350.00 0.25 0.50 cum. 87.50
cum. 87.50 87.50 1015.00 88,812.50
2 Gravelling filling
Gravel filling in bed of excavated
material trench with approved
quality in layers not exceeding
15cm at a time and with adequate
watering till full consolidation as per
instruction of engineer
trench filling 2 350.00 0.60 0.80 cum. 336.00
drain bed 2 350.00 1.00 0.10 cum. 70.00
cum. 406.00 406.00 2534.25 1,028,905.50
3 Concreting work.
PCC(1:3:6) with screen river
aggregate and approved level, lines
abd dimension and curing all
complete as per specification and
instruction of engineer
(A) Bed PCC (1:3:6) 2 350.00 1.00 0.100 cum. 70.00
cum. 70.00 70.00 8183.01 572,810.70
Brick work (1:6) in with approved
quality of first class bricks in perfct
line and level, finished including
wetting the bricks packing the joints
4
and curing the complete in all types
and thickness of walls as per
specification and instruction of
engineer
drain wall-inner 2 350.00 0.38 0.80 m3 212.80
drain wall-outer 2 350.00 0.25 0.40 m3 70.00
m3 282.80 282.80 11580.15 3274866.42
12mm thick plaster (1:4) cement
sand plaster on wall of good finish,
including raking the joints, cleaning
5
and wetting the surface and curing
the works all the complete as per
instruction of engineer.
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 269.27 226186.80
Punning work: Cement punning of
6 3mm thick cement slurry on
plastered surface
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 252.59 212175.60
7 PCC 1:2:4 works
wall
drain wall-inner 2 350.00 0.38 0.050 m3 13.30
drain wall-outer 2 350.00 0.25 0.050 m3 8.75
tick drain 2 350.00 0.20 0.075 m3 10.50
m3 32.55 32.55 9,354.71 304495.81
8 Grader work
Sub-grade ( Existing pitch, gravel &
side shoulder cutting ), preparation
for designed road formation level
with grader machine.
road stretch 1 350.00 8.00 m2 2,800.00
350.00 m2 2,800.00 2,800.00 16.51 46228.00
Detailed Estimate & Abstract Of Cost
Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total
SN Description of work Nos Length Breadth Height Unit Quantity Rate Amount Remarks
Quantity
9 Preparation of Sub Base Work
Supplying and constrcution of sub-
base with watering and rolling by 8-
10 ton roller in layersnot exceeding
15cm at a time and with adequate
watering til full consolidation as per
instruction of engineer
road stretch 1 350.00 8.00 0.150 m3 420.00
portion 1 150.00 6.00 0.300 m3 270.00
m3 690.00 690.00 2,534.25 1748632.50
10 Preparation of base course

Supplying, Laying & grading of


crusher run material base course of
mentioned thickness and watering,
proper levelling and cambering of
road including compaction with
roller & haulling up to 10 m
distance , as per the instruction of
Engineer's all complete
road stretch 1 350.00 7.00 0.10 m3 245.00
350.00 m3 245.00 245.00 3665.81 898123.45
11 Prime Coat
Providing and spraying bituminious
prime coat of 60:40 including
cleaning the road surface using wire
brushes, broom etc. on base course
before applying prime coat
including supply of materials all
complete.
road stretch 1 350.00 7.00 m2 2,450.00
350.00 lit 2,450.00 2450.00 127.69 312840.50
12 Tack coat
Providing and spraying bituminious
tack coat including cleaning the
road surface using wire brushes,
broom etc. on the surface before
applying tack coat including supply
of materials all complete.
road stretch 1 350.00 7.00 m2 2,450.00
350.00 lit 1,225.00 1225.00 119.27 146105.75

13 Asphalt concreting work


Providing, mixing, laying of asphalt
concrete using machine crushed
aggregate of specified grading
premixed with bituminous binder
and filter as per drawing and
technical specifications.
road stretch 1 350.00 7.00 0.040 m3 98.00
350.00 m3 98.00 98.00 19289.93 1890413.14
14 Steel Reinforcement Work
Steel reinforcement bar including
stringtening,cutting, bending,
binding with 20 SWG wire and fixing
in positions as per drawings,
specifications, and complete work
as per instruction of engineer.
for cover slab :
10mm dia main bar @ 5" c/c 8760 1.00 0.617 kgs 5407.41 1752
No. of
15768 0.40 0.395 kgs 2491.73
8mm dia distribution bar @ 6" c/c cover slabs
kgs 7899.14 7899.14 108.20 854687.03
Detailed Estimate & Abstract Of Cost
Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total
SN Description of work Nos Length Breadth Height Unit Quantity Rate Amount Remarks
Quantity
15 Form work
Centering and shuttering with
wooden/plywood formworks for RCC
works including all necessary
propping, scaffolding, staging
supporting etc. all complete as per
specification and instruction of
engineer.
for cover slab : 1752 2.80 0.10 m2 490.56
m2 490.56 122.64 782.51 95967.03
16 P.C.C for R.C.C (1:2:4)
PCC (1:2:4) for R.C.C work
including mixing, laying, finishing to
approved level, lines and dimension
and curing all complete as per
specification and instruction of
engineer.
for cover slab : 1752 1.00 0.40 0.10 m3 70.08
m3 70.08 70.08 9354.71 655578.08
17 Site Clearance
Clearing of exisitng drain free from
debris, mud , stone , waste and
Depositing of outcasted debris to
site and dumping yard and site LS 15000.00
clearance after completion of work,
with all work complete
Sub-Total 10681300.10
Overhead @ 15% 1602195.02
Sub-Total 12283495.12
VAT @ 13% 1596854.37
Sub-Total 13880349.48
Contingencies @ 3% 416410.48
Grand Total 14296759.97
Detailed Estimate & Abstract Of Cost
Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with


SN Description of work Nos Length Breadth Height Unit Quantity Amount Remarks
Quantity OH
A
Provide Insurance of works,
materials,construction
1 equipments against accident to 1 PS 1.00 1.00 30000.00 30,000.00
workforce including
third party
Provide & Maintain protective safety
Equipments including Hats, Gloves,
2 Googles, Dust mask, First Aid Kit
1 PS 1.00 1.00 10000.00 10,000.00
with medicine for work force
Lab test of the construction materials as
3 rebar cement, brick, as per specified by 1 PS 1.00 1.00 15000.00 15,000.00
site incharge
Provide & Installation of Project
Information Board1.
4 2*.90 m Size as to Complete the Work
1 LS 1.00 1.00 5000.00 5,000.00
as Specified

1 Dimantling of existing structures


brick masonry works
drain inner portion 2 350.00 0.25 0.50 cum. 87.50
cum. 87.50 87.50 1853.57 162,187.37
2 Stone soling
Providing and laying of hand pack Stone
soling with 150 to 200 mm thick stones
and packing with smaller stone on
prepared surface as per Drawing and
Technical Specifications.
Unit = cum [For 5 cum]
trench filling 2 350.00 0.60 0.50 cum. 210.00
drain bed 2 350.00 1.00 0.10 cum. 70.00
cum. 280.00 280.00 7689.92 2,153,178.58
3 Concreting work.

PCCM15with screen river aggregate and


approved level, lines abd dimension and
curing all complete as per specification
and instruction of engineer

(A) Bed PCC M15 2 350.00 1.00 0.100 cum. 70.00


(B) Wall top PCC M15
drain wall-inner 2 350.00 0.38 0.050 m3 13.30
drain wall-outer 2 350.00 0.25 0.050 m3 8.75
tick drain 2 350.00 0.20 0.075 m3 10.50
cum. 102.55 102.55 10669.15 1,094,121.13
4 Brick masonry works
Brick work (1:6) in with approved quality
of first class bricks in perfct line and
level, finished including wetting the
bricks packing the joints and curing the
complete in all types and thickness of
walls as per specification and instruction
of engineer
drain wall-inner 2 350.00 0.38 0.80 m3 212.80
drain wall-outer 2 350.00 0.25 0.40 m3 70.00
m3 282.80 282.80 14298.82 4043706.13

Prepared By Checked By Approved By


Detailed Estimate & Abstract Of Cost
Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with


SN Description of work Nos Length Breadth Height Unit Quantity Amount Remarks
Quantity OH

12mm thick plaster (1:4) cement sand


plaster on wall of good finish, including
5 raking the joints, cleaning and wetting
the surface and curing the works all the
complete as per instruction of engineer.

drain wall-inner 2 350.00 0.80 m2 560.00


drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 324.29 272404.75
Punning work: Cement punning of 3mm
6
thick cement slurry on plastered surface
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 276.08 231907.62
7 Grader work
Sub-grade ( Existing pitch, gravel & side
shoulder cutting ), preparation for
designed road formation level with
grader machine.
road stretch 1 350.00 8.00 m2 2,800.00
350.00 m2 2,800.00 2,800.00 16.86 47220.23
8 Preparation of Sub Base Work

Supplying and constrcution of sub-base


with watering and rolling by 8-10 ton
roller in layersnot exceeding 15cm at a
time and with adequate watering til full
consolidation as per instruction of
engineer
road stretch 1 350.00 8.00 0.150 m3 420.00
ch. 0+220 to 0+350 depressed portion 1 150.00 6.00 0.300 m3 270.00
m3 690.00 690.00 3,357.97 2316996.67
9 Preparation of base course

Supplying, Laying & grading of crusher


run material base course of mentioned
thickness and watering, proper levelling
and cambering of road including
compaction with roller & haulling up to 10
m distance , as per the instruction of
Engineer's all complete
road stretch 1 350.00 7.00 0.10 m3 245.00
350.00 m3 245.00 245.00 4341.62 1063696.28
10 Prime Coat
Providing and spraying bituminious
prime coat of 60:40 including cleaning
the road surface using wire brushes,
broom etc. on base course before
applying prime coat including supply of
materials all complete.
road stretch 1 350.00 7.00 m2 2,450.00
350.00 lit 2,450.00 2450.00 191.16 468333.55
11 Tack coat
Providing and spraying bituminious tack
coat including cleaning the road surface
using wire brushes, broom etc. on the
surface before applying tack coat
including supply of materials all
complete.
road stretch 1 350.00 7.00 m2 2,450.00

Prepared By Checked By Approved By


Detailed Estimate & Abstract Of Cost
Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with


SN Description of work Nos Length Breadth Height Unit Quantity Amount Remarks
Quantity OH
350.00 lit 1,225.00 1225.00 178.99 219262.76

12 Asphalt concreting work


Providing, mixing, laying of asphalt
concrete using machine crushed
aggregate of specified grading premixed
with bituminous binder and filter as per
drawing and technical specifications.

road stretch 1 350.00 7.00 0.040 m3 98.00


350.00 m3 98.00 98.00 28280.51 2771490.18
13 Steel Reinforcement Work

Steel reinforcement bar including


stringtening,cutting, bending, binding
with 20 SWG wire and fixing in positions
as per drawings, specifications, and
complete work as per instruction of
engineer.
for cover slab :
10mm dia main bar @ 5" c/c 8760 1.00 0.617 kgs 5407.41 1752
No. of
15768 0.40 0.395 kgs 2491.73 cover
8mm dia distribution bar @ 6" c/c slabs
kgs 7899.14 7899.14 135.70 1071878.52
14 Form work

Centering and shuttering with


wooden/plywood formworks for RCC
works including all necessary propping,
scaffolding, staging supporting etc. all
complete as per specification and
instruction of engineer.
for cover slab : 1752 2.80 0.10 m2 490.56
m2 490.56 122.64 1046.98 128402.14
15 P.C.C for R.C.C M20
PCC M20 for R.C.C work including
mixing, laying, finishing to approved
level, lines and dimension and curing all
complete as per specification and
instruction of engineer.
for cover slab : 1752 1.00 0.40 0.10 m3 70.08
m3 70.08 70.08 11697.42 819755.12
16 Site Clearance
Clearing of exisitng drain free from
debris, mud , stone , waste and
Depositing of outcasted debris to site
and dumping yard and site clearance LS 15000.00
after completion of work, with all work
complete

Sub-Total 16884541.04
VAT @ 13% 2194990.33
Sub-Total 19134531.37

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with Remark


SN Norms No. Description of work Nos Length Breadth Height Unit Quantity Amount
Quantity OH s
General
A
works
Provide Insurance of works,
materials,construction
1 equipments against accident to 1 PS 1.00 1.00 30000.00 30,000.00
workforce including
third party

Provide & Maintain protective safety


Equipments including Hats, Gloves,
2 Googles, Dust mask, First Aid Kit
1 PS 1.00 1.00 10000.00 10,000.00
with medicine for work force

Lab test of the construction


3 materials as rebar cement, brick, as 1 PS 1.00 1.00 15000.00 15,000.00
per specified by site incharge
Provide & Installation of Project
Information Board1.
4 2*.90 m Size as to Complete the
1 LS 1.00 1.00
Work as Specified

B Road works
Dimantling of existing
1 DoR-2.4 (ii) B
structures
brick masonry works
drain inner portion 2 350.00 0.25 0.50 cum. 87.50
cum. 87.50 87.50
2 DoR-10.8 Stone soling
Providing and laying of hand pack
Stone soling with 150 to 200 mm
thick stones and packing with
smaller stone on prepared surface
as per Drawing and Technical
Specifications.
Unit = cum [For 5 cum]
trench filling 2 350.00 0.60 0.50 cum. 210.00
drain bed 2 350.00 1.00 0.10 cum. 70.00
cum. 280.00 280.00
3 DoR - 20.2 A Concreting work.
PCCM15with screen river aggregate
and approved level, lines abd
dimension and curing all complete
as per specification and instruction
of engineer
(A) Bed PCC M15 2 350.00 1.00 0.100 cum. 70.00
(B) Wall top PCC M15
drain wall-inner 2 350.00 0.38 0.050 m3 13.30
drain wall-outer 2 350.00 0.25 0.050 m3 8.75
tick drain 2 350.00 0.20 0.075 m3 10.50
cum. 102.55 102.55
4 DoR-25.1D Brick masonry works
Brick work (1:6) in with approved
quality of first class bricks in perfct
line and level, finished including
wetting the bricks packing the joints
and curing the complete in all types
and thickness of walls as per
specification and instruction of
engineer
drain wall-inner 2 350.00 0.38 0.80 m3 212.80
drain wall-outer 2 350.00 0.25 0.40 m3 70.00
m3 282.80 282.80

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with Remark


SN Norms No. Description of work Nos Length Breadth Height Unit Quantity Amount
Quantity OH s
12mm thick plaster (1:4) cement
sand plaster on wall of good finish,
including raking the joints, cleaning
5 DoR-25.4C
and wetting the surface and curing
the works all the complete as per
instruction of engineer.
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00
Punning work: Cement punning of
6 DUDBC:(11-20) 3mm thick cement slurry on
plastered surface
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00
7 DOR - 10.2 B Grader work
Sub-grade ( Existing pitch, gravel &
side shoulder cutting ), preparation
for designed road formation level
with grader machine.
road stretch 1 350.00 8.00 m2 2,800.00
350.00 m2 2,800.00 2,800.00
8 DoR-12.1 A Preparation of Sub Base Work
Supplying and constrcution of sub-
base with watering and rolling by 8-
10 ton roller in layersnot exceeding
15cm at a time and with adequate
watering til full consolidation as per
instruction of engineer
road stretch 1 350.00 8.00 0.150 m3 420.00
portion 1 150.00 6.00 0.300 m3 270.00
m3 690.00 690.00
9 DoR-12.7 A Preparation of base course

Supplying, Laying & grading of


crusher run material base course of
mentioned thickness and watering,
proper levelling and cambering of
road including compaction with
roller & haulling up to 10 m
distance , as per the instruction of
Engineer's all complete
road stretch 1 350.00 7.00 0.10 m3 245.00
350.00 m3 245.00 245.00
10 DOR-13.1A Prime Coat
Providing and spraying bituminious
prime coat of 60:40 including
cleaning the road surface using wire
brushes, broom etc. on base course
before applying prime coat
including supply of materials all
complete.
road stretch 1 350.00 7.00 m2 2,450.00
350.00 lit 2,450.00 2450.00
11 DoR-13.2A Tack coat
Providing and spraying bituminious
tack coat including cleaning the
road surface using wire brushes,
broom etc. on the surface before
applying tack coat including supply
of materials all complete.
road stretch 1 350.00 7.00 m2 2,450.00

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with Remark


SN Norms No. Description of work Nos Length Breadth Height Unit Quantity Amount
Quantity OH s
350.00 lit 1,225.00 1225.00

12 DoR 13.6 Asphalt concreting work


Providing, mixing, laying of asphalt
concrete using machine crushed
aggregate of specified grading
premixed with bituminous binder
and filter as per drawing and
technical specifications.
road stretch 1 350.00 7.00 0.040 m3 98.00
350.00 m3 98.00 98.00
13 DoR-20.5 Steel Reinforcement Work
Steel reinforcement bar including
stringtening,cutting, bending,
binding with 20 SWG wire and fixing
in positions as per drawings,
specifications, and complete work
as per instruction of engineer.
for cover slab :
10mm dia main bar @ 5" c/c 8760 1.00 0.617 kgs 5407.41 1752
No. of
15768 0.40 0.395 kgs 2491.73 cover
8mm dia distribution bar @ 6" c/c slabs
kgs 7899.14 7899.14
14 DoR-18.1a Form work
Centering and shuttering with
wooden/plywood formworks for RCC
works including all necessary
propping, scaffolding, staging
supporting etc. all complete as per
specification and instruction of
engineer.
for cover slab : 1752 2.80 0.10 m2 490.56
m2 490.56 122.64
15 DoR - 20.2 B P.C.C for R.C.C M20
PCC M20 for R.C.C work including
mixing, laying, finishing to
approved level, lines and dimension
and curing all complete as per
specification and instruction of
engineer.
for cover slab : 1752 1.00 0.40 0.10 m3 70.08
m3 70.08 70.08
16 Site Clearance
Clearing of exisitng drain free from
debris, mud , stone , waste and
Depositing of outcasted debris to
site and dumping yard and site LS
clearance after completion of work,
with all work complete
Sub-Total
VAT @ 13%
Sub-Total
Contingencies @ 3%
Grand Total

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF MUNICIPAL EXECUTIVE
BIRATNAGAR

BILL SUMMARY

PAYMENT CERTIFICATE -FIFTH


निर्माण
कार्यको Construction of Aarati Site at Hanuman Mandir
Date of agreement : 10/23/2079
नामः
Location Ward no.-2, Biratnagar Date of Work Order : 10/23/2079
ठेक्का नं: BMC/MOR/NCB/W-16/2079/080 Date of Completion : 10/30/2081
निर्माण
व्यवसायी ABHIYAN / DIBISHA JV
Extended Completion -
को नामः
As per Sigend
Cummulative Upto Previous IPC In The Current IPC
SN Description of Items Contract Amount Remarks
Amount (NRs) Amount(NRs) Amount Rs.
(NRs)
A.1 General works 155,000.00 120,000.00 120,000.00 -
A.2 Construction work 35,093,919.49 18,347,964.52 16,237,214.08 2,110,750.44

B Price Adjustment - 1,026,513.59 - 1,026,513.59


C Total Amount (A+B) 35,093,919.49 19,374,478.11 16,237,214.08 3,137,264.03
D VAT @13% C 4,562,209.53 2,518,682.15 2,110,837.83 407,844.32
E Total Bill Amount(C+D) 39,811,129.03 22,013,160.26 18,468,051.91 3,545,108.35
F Retention money @ 5% of C
G Advance Payment Deduction
H Advance Payment outstanding after
deduction
I Advance income [email protected]%C
J Liquidated damages (if any)

K Contractor's Development [email protected] of C

Total Amount Payable to the


L Contractor (Including VAT) (E-F-
I-J-K)
M Local Currency

Contractor Prepared By Checked By Approved By


Pages-11 of 333
म.ले.प.फारम नं: ५०४
बिराटनगर महानगरपालिका
साबिकको फारम नं: १६८
नगर कार्यापालिकाको कार्यालय
कार्यालय कोड नं.:
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
A Provisional Sum
General works:Provide Insurance
of works, materials,construction
1.0
equipments against accident to
workforce including third party PS 1.00 100,000.00 100,000.00 1.00 100,000.00 1.00 100,000.00 - - -
Provide & Maintain protective
safety Equipments including Hats,
2.0 Gloves, Googles, Dust mask, First
Aid Kit with medicine for work
force PS 1.00 15,000.00 15,000.00 1.00 15,000.00 - - 1.00 15,000.00 -
Lab test of the construction
3.0 materials as rebar cement, brick,
as per specified by site incharge PS 1.00 40,000.00 40,000.00 1.00 5,000.00 1.00 5,000.00 - - -
Total Provisional Sum 155,000.00 120,000.00 105,000.00 15,000.00
2 CONSTRUCTION WORK
Provide & Installation of Project
1.0 Information Board 1.2*0.9m Size
No.
as to Complete the work
Specified 1.00 10,000.00 10,000.00 1.00 10,000.00 1.00 10,000.00 - - -

Contractor Prepared By Checked By Approved By


Pages-12 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
PAVILION I - -
Earthwork -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
2.0 debris & brick bats of old m3
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. 12.58 200.00 2,516.00 12.64 2,528.10 12.64 2,528.10 - - (0.06)

Filling with earth or mixed soil


stacked at site in 150mm thick
layer on retaining walls including
3.0 watering, ramming, consolidation m3
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete.

5.45 300.00 1,635.00 4.44 1,332.90 4.44 1,332.90 - - 1.01

Contractor Prepared By Checked By Approved By


Pages-13 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Soling works
4.0 Stone soling works
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 1.64 3,000.00 4,920.00 2.22 6,664.50 2.22 6,664.50 - - (0.58)
lift.
5.0 Brick soling work
Providing and laying a single
layer flat brick soling on drainage
works on lanscape for preparation
of P.C.C. in which joints should be
packed by sand to the required
levels all complete as per
drawings, specifications and the
instructions of the Engineer. m2 1.57 700.00 1,099.03 1.86 1,303.75 1.86 1,303.75 - - (0.29)

Contractor Prepared By Checked By Approved By


Pages-14 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
6.0 PCC Works
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 0.93 10,000.00 9,300.00 1.18 11,763.75 1.18 11,763.75 - - (0.25)
7.0 RCC Works
Concrete Works for RCC (1:1.5:3)
M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer. m3 8.65 16,000.00 138,400.00 8.65 138,418.00 8.65 138,418.00 - - (0.00)
8.0 Steel reinforcement works
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 1.36 120,000.00 163,200.00 0.76 91,201.51 0.27 32,466.13 0.49 58,735.38 0.60

Contractor Prepared By Checked By Approved By


Pages-15 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
9.0 Centering and Shuttering Work
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 65.64 600.00 39,384.00 65.65 39,387.00 65.65 39,387.00 - - (0.00)
10.0 STONE PILLAR WORKS
Providingand placing stone pillar
above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.58 7,000.00 4,060.00 0.82 5,712.00 0.82 5,712.00 - - (0.24)

Contractor Prepared By Checked By Approved By


Pages-16 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
11.0 Wall Works - - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 9.87 15,000.00 148,050.00 9.86 147,975.00 9.86 147,975.00 - - 0.01
WOODEN WORKS
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
12.0 level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 0.61 250,000.00 152,500.00 0.62 154,838.75 0.62 154,838.75 - - (0.01)
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
13.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos 6.00 25,000.00 150,000.00 - - - - - - 6.00

Contractor Prepared By Checked By Approved By


Pages-17 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
14.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 0.39 250,000.00 97,500.00 0.39 97,920.00 0.39 97,920.00 - - (0.00)
MS STEEL WORKS
Providing and placing structural
steel tested grade Fe-250
equivalent NS, for structural work
including transportation, cutting,
15 connecting and placing in
position,treated with two coat of
anticorrosive paints, all complete
as per drawings, specifications
and instruction. kg 1,187.12 250.00 296,780.17 1,187.12 296,780.17 1,187.12 296,780.17 - - (1,143.88)
Providing and placing decking
sheet for concrete deck slab
including transportation, cutting,
16 connecting and placing in
position with welds and studs all
complete as per drawings,
specifications and instruction. m2 43.24 1,200.00 51,888.00 43.24 51,888.00 43.24 51,888.00 - - -

Contractor Prepared By Checked By Approved By


Pages-18 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Plastering and Painting Works
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
17 mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 56.69 300.00 17,007.00 - - - - - - 56.69
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
wall, ceiling, beams columns,
18 canopies, staircase, lobbies etc.,
all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m2 56.69 300.00 17,007.00 - - - - - - -
False ceiling works

Contractor Prepared By Checked By Approved By


Pages-19 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and placing false ceiling
with plyboard(one side veneer)
19 including the channels to drop
false ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 43.18 2,500.00 107,950.00 - - - - - - 43.18
Providing and applying PU paint
of approved manufacturer and
shade over primer of approved
manufacturer as per
manufacturer's specifications to
the surface of false ceiling all
20 complete as per drawings,
specifications and instruction.
The rates shall include for
surface preparation, scaffolding
etc., all complete as per the
manufacturer's recommendations
and as approved by the Engineer. m2 43.18 300.00 12,954.00 - - - - - - 43.18
21 Toughen glass Works
Providing and laying toughen
glass on roof including fixing with
silicon and necessary support all
complete as per drawing and
specification. m2 1.09 12,000.00 13,080.00 - - - - - - 1.09
22 Fibre cement board cladding for fascia - - -
Providing and laying fibre cement
board cladding on fascia all
complete as per design, drawing,
specification and instruction of
site engineer. rm 27.95 3,000.00 83,850.00 - - - - - - (27.95)

Contractor Prepared By Checked By Approved By


Pages-20 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
23 Waterproofing coating on roof - - -
Providing and laying
waterproofing coating on roof all
complete as per design, drawing,
specification and instruction of
site engineer. m2 43.24 500.00 21,620.00 - - - - - - 43.24
24 Cement punning finish on roof - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 43.24 400.00 17,296.00 - - - - - - 43.24
Timber plank on bench:-
Providing and laying timber plank
25 on bench all complete as per
design,drawing,specification and
instruction of site engineer m2 0.88 12,000.00 10,560.00 - - - - - - 0.88
PAVILION I I- - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
26 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 12.51 1,000.00 12,510.00 13.16 13,157.75 13.16 13,157.75 - - (0.65)

Contractor Prepared By Checked By Approved By


Pages-21 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
27 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 5.38 300.00 1,614.00 4.55 1,365.63 4.55 1,365.63 - - 0.83
28 Soling works - - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 1.83 3,000.00 5,490.00 2.28 6,828.18 2.28 6,828.18 - - (0.45)
lift.

Contractor Prepared By Checked By Approved By


Pages-22 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
29.0 PCC Works - - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 0.91 10,000.00 9,100.00 1.14 11,389.12 1.14 11,389.12 - - (0.23)
30.0 RCC Works - - -
Concrete Works for RCC (1:1.5:3)
M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer. m3 6.86 16,000.00 109,760.00 6.86 109,682.24 6.86 109,682.24 - - 0.00
31.0 Steel reinforcement works
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 1.08 120,000.00 129,600.00 0.42 50,609.77 0.25 29,911.07 0.17 20,698.70 0.66

Contractor Prepared By Checked By Approved By


Pages-23 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
32.0 Centering and Shuttering Work
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 21.69 600.00 13,014.00 21.69 13,014.84 21.69 13,014.84 - - (0.00)
33.0 STONE PILLAR WORKS

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.90 7,000.00 6,300.00 1.10 7,672.00 1.10 7,672.00 - - (0.20)

Contractor Prepared By Checked By Approved By


Pages-24 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
34.0 Wall Works - - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 7.27 15,000.00 109,050.00 7.27 109,036.53 7.27 109,036.53 - - 0.00
WOODEN WORKS
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
35.0 level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 1.43 250,000.00 357,500.00 1.43 356,661.40 1.43 356,661.40 - - 0.00
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
36.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos 7.00 25,000.00 175,000.00 - - - - - - 7.00
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
37.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 0.63 250,000.00 157,500.00 0.63 156,512.50 0.63 156,512.50 - - 0.00
38.0 MS STEEL WORKS
Providing and placing structural
steel tested grade Fe-250
equivalent NS, for structural work
including transportation, cutting,
38.0 connecting and placing in
position,treated with two coat of
anticorrosive paints, all complete
as per drawings, specifications
and instruction. kg 926.34 250.00 231,585.00 926.34 231,584.71 926.34 231,584.71 - - 0.00

Contractor Prepared By Checked By Approved By


Pages-25 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and placing decking
sheet for concrete deck slab
including transportation, cutting,
39.0 connecting and placing in
position with welds and studs all
complete as per drawings,
specifications and instruction. m2 36.18 6,000.00 217,080.00 36.18 217,080.00 36.18 217,080.00 - - -

Contractor Prepared By Checked By Approved By


Pages-26 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
40.0 Plastering and Painting Works
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 36.15 600.00 21,690.00 - - - - - - 36.15
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
wall, ceiling, beams columns,
41.0 canopies, staircase, lobbies etc.,
all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m3 36.15 300.00 10,845.00 - - - - - - 36.15

Contractor Prepared By Checked By Approved By


Pages-27 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
42.0 False ceiling works - - -
Providing and placing false ceiling
with plyboard(one side veneer)
including the channels to drop
false ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 36.18 2,500.00 90,450.00 - - - - - - 36.18
Providing and applying PU paint
of approved manufacturer and
shade over primer of approved
manufacturer as per
manufacturer's specifications to
the surface of false ceiling all
43.0 complete as per drawings,
specifications and instruction.
The rates shall include for
surface preparation, scaffolding
etc., all complete as per the
manufacturer's recommendations
and as approved by the Engineer. m2 36.18 300.00 10,854.00 - - - - - - 36.18
44.0 Fibre cement board cladding for fascia - - -
Providing and laying fibre cement
board cladding on fascia all
complete as per design, drawing,
specification and instruction of
site engineer. m2 42.30 2,500.00 105,750.00 - - - - - - 42.30
45.0 Waterproofing coating on roof - - -
Providing and laying
waterproofing coating on roof all
complete as per design, drawing,
specification and instruction of
site engineer. m2 36.18 500.00 18,090.00 - - - - - - 36.18

Contractor Prepared By Checked By Approved By


Pages-28 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
46.0 Cement punning finish on roof - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 10.48 400.00 4,192.00 - - - - - - 10.48
PAVILION III - - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
47.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 10.55 1,000.00 10,550.00 10.55 10,550.00 10.55 10,550.00 - - -
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
48.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 6.54 300.00 1,962.00 6.54 1,962.00 6.54 1,962.00 - - -

Contractor Prepared By Checked By Approved By


Pages-29 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Soling works - - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
49.0 sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 2.72 3,000.00 8,160.00 2.72 8,160.00 2.72 8,160.00 - - -
lift.
Providing and laying a single
layer flat brick soling on floor for
preparation of P.C.C. in which
50.0 joints should be packed by sand
to the required levels all
complete as per drawings,
specifications and the instructions
of the Engineer. m2 9.24 700.00 6,468.00 9.24 6,468.00 9.24 6,468.00 - - -

Contractor Prepared By Checked By Approved By


Pages-30 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
51.0 PCC Works - - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 2.35 10,000.00 23,500.00 2.35 23,500.00 2.35 23,500.00 - - -
52.0 RCC Works - - -
Concrete Works for RCC (1:1.5:3)
M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer. m3 5.82 16,000.00 93,120.00 - - - - - - 5.82
53.0 Steel reinforcement works - - -
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 0.91 120,000.00 109,200.00 - - - - - - 0.91

Contractor Prepared By Checked By Approved By


Pages-31 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
54.0 Centering and Shuttering Work - - -
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 77.62 600.00 46,572.00 - - - - - - 77.62
55.0 STONE PILLAR WORKS - - -

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 1.36 7,000.00 9,520.00 - - - - - - 1.36

Contractor Prepared By Checked By Approved By


Pages-32 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
56.0 Wall Works - - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 3.22 15,000.00 48,300.00 3.22 48,300.00 3.22 48,300.00 - - -
57.0 WOODEN WORKS - - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 2.27 250,000.00 567,500.00 - - - - - - 2.27
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
58.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. Nos. 7.00 25,000.00 175,000.00 - - - - - - 7.00
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
59.0 level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 2.29 250,000.00 572,500.00 - - - - - - 2.29
60.0 Waterproof plywood works - - -
Providing and placing waterproof
plywood for concrete deck slab
including transportation, cutting,
connecting and placing in
position with nails, hooks, etc. all
complete as per drawings,
specifications and instruction. m2 77.62 700.00 54,334.00 - - - - - - 77.62
61.0 Plastering and Painting Works - - -

Contractor Prepared By Checked By Approved By


Pages-33 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 8.24 600.00 4,944.00 8.16 4,896.00 - - 8.16 4,896.00 0.08
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
wall, ceiling, beams columns,
62.0 canopies, staircase, lobbies etc.,
all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m2 8.24 300.00 2,472.00 - - - - - - 8.24
63.0 False ceiling works - - -
Providing and placing false ceiling
with plyboard(one side veneer)
including the channels to drop
false ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 21.29 2,500.00 53,225.00 - - - - - - 21.29
Providing and applying PU paint
of approved manufacturer and
shade over primer of approved
manufacturer as per
manufacturer's specifications to
the surface of false ceiling all
64.0 complete as per drawings,
specifications and instruction.
The rates shall include for
surface preparation, scaffolding
etc., all complete as per the
manufacturer's recommendations
and as approved by the Engineer. m2 21.29 300.00 6,387.00 - - - - - - 21.29
65.0 WPC board for fascia - - -
Providing and laying WPC board
cladding on fascia all complete as
per design, drawing, specification
and instruction of site engineer. rm 55.80 2,500.00 139,500.00 - - - - - - 55.80
66.0 Waterproofing membrane on roof - - -

Contractor Prepared By Checked By Approved By


Pages-34 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and laying
waterproofing membrane on roof
all complete as per design,
drawing, specification and
instruction of site engineer. m2 77.62 700.00 54,334.00 - - - - - - 77.62
67.0 Panipatti - - -
Providing and laying 20mm. thick
Cement Water Bead (Pani Patti)
finished perfectly smooth
including necessary scaffolding,
raking the joint, wetting the
surface and curing all complete
work rm 55.80 400.00 22,320.00 - - - - - - 55.80

Contractor Prepared By Checked By Approved By


Pages-35 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
68.0 Flooring works - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 77.62 800.00 62,096.00 - - - - - - 77.62
3mm cement punning in 1:1 c/s
mortar in perfect line and level
69.0 including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 77.62 400.00 31,048.00 - - - - - - 77.62
Providing and laying of 25 mm
thick Telia tile paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
70.0 including curing on floor in
perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 9.24 3,400.00 31,416.00 - - - - - - 9.24

Contractor Prepared By Checked By Approved By


Pages-36 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and laying of stone slab
of approved thickness and color
on floor in perfect line and level
71.0 including joint sealing of joint,
grinding, polishing all complete
as per design, drawing,
specification and the instrution of
the site engineer. m2 3.96 7,000.00 27,720.00 - - - - - - 3.96
PAVILION IV - - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
72.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 11.33 1,000.00 11,330.00 16.61 16,607.00 16.61 16,607.00 - - (5.28)
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
73.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 8.27 300.00 2,481.00 12.32 3,695.07 12.32 3,695.07 - - (4.05)

Contractor Prepared By Checked By Approved By


Pages-37 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Soling works
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
74.0 sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 0.26 3,000.00 780.00 0.29 882.00 0.29 882.00 - - (0.03)
lift.
Providing and laying a single
layer flat brick soling on floor for
preparation of P.C.C. in which
75.0 joints should be packed by sand
to the required levels all
complete as per drawings,
specifications and the instructions
of the Engineer. m2 24.39 700.00 17,073.00 41.54 29,078.00 41.54 29,078.00 - - (17.15)

Contractor Prepared By Checked By Approved By


Pages-38 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
76.0 PCC Works
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 4.69 10,000.00 46,900.00 4.73 47,307.84 4.73 47,307.84 - - (0.04)
77.0 STONE PILLAR WORKS

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.59 25,000.00 14,750.00 0.58 14,560.00 0.58 14,560.00 - - 0.01
78.0 Wall Works
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 7.85 15,000.00 117,750.00 - - - - - - 7.85

Contractor Prepared By Checked By Approved By


Pages-39 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
79.0 WOODEN WORKS - - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 0.86 250,000.00 215,000.00 0.86 215,090.00 0.86 215,090.00 - - (0.00)
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
80.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos. 7.00 25,000.00 175,000.00 - - - - - - 7.00
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
81.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 1.23 250,000.00 307,500.00 1.23 307,856.56 1.23 307,856.56 - - (0.00)

Contractor Prepared By Checked By Approved By


Pages-40 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
82.0 Roofing works
Providing and placing waterproof
plywood for roofing including
transportation, cutting,
connecting and placing in
position with nails, hooks, etc. all
complete as per drawings,
specifications and instruction. m2 27.73 700.00 19,411.00 - - - - - - 27.73
Providing and placing ikotile for
roofing including transportation,
83.0 cutting, connecting and placing in
position with nails all complete as
per drawings, specifications and
instruction. m2 27.73 3,500.00 97,055.00 27.73 97,050.18 - - 27.73 97,050.18 0.00
84.0 Plastering and Painting Works
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 13.72 300.00 4,116.00 - - - - - - 13.72
85.0 False ceiling works - - -
Providing and placing false ceiling
with cement board including the
channels to drop false ceiling all
complete as per design, drawing,
specification and instruction of
site engineer. m2 16.00 2,500.00 40,000.00 - - - - - - 16.00

Contractor Prepared By Checked By Approved By


Pages-41 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and applying fire
retardant paint of approved
manufacturer and shade over
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
86.0 false ceiling all complete as per
drawings, specifications and
instruction. The rates shall
include for surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
m2 16.00 15,000.00 240,000.00 - - - - - - 16.00
approved by the Engineer.
87.0 WPC Panel for ceiling - - -
Providing and laying WPC Panel
for ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 12.73 2,400.00 30,552.00 - - - - - - 12.73
88.0 Waterproofing membrane on roof - - -
Providing and laying
waterproofing membrane on roof
all complete as per design,
drawing, specification and
instruction of site engineer. m2 27.73 500.00 13,865.00 - - - - - - 27.73

Contractor Prepared By Checked By Approved By


Pages-42 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
89.0 Flooring works - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 11.02 800.00 8,816.00 - - - - - - 11.02
3mm cement punning in 1:1 c/s
mortar in perfect line and level
90.0 including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 13.72 400.00 5,488.00 - - - - - - 13.72
Providing and laying of 25 mm
thick Telia tile paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
91.0 including curing on floor in
perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 8.20 3,400.00 27,880.00 - - - - - - 8.20

Contractor Prepared By Checked By Approved By


Pages-43 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and laying of 50mm
thick stone slab of approved
thickness and color on floor in
perfect line and level including
92.0 joint sealing of joint, grinding,
polishing all complete as per
design, drawing, specification and
the instrution of the site
engineer. m2 2.84 7,000.00 19,880.00 - - - - - - 2.84
Providing and laying of flagstone
of approved thickness and color
on floor in perfect line and level
93.0 including joint sealing of joint,
grinding, polishing all complete
as per design, drawing,
specification and the instrution of
the site engineer. m2 29.87 1,400.00 41,818.00 - - - - - - 29.87
Bells on roof:- Providing and
94.0 fixing design, drawing,
specification and instruction of
nos 36.00 6,000.00 216,000.00 - - - - - - 36.00
site engineer

Contractor Prepared By Checked By Approved By


Pages-44 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
MANDAP - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
95.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 9.72 1,000.00 9,720.00 12.01 12,008.00 12.01 12,008.00 - - (2.29)
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
96.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 5.62 300.00 1,686.00 8.32 2,494.80 8.32 2,494.80 - - (2.70)

Contractor Prepared By Checked By Approved By


Pages-45 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
97.0 Soling works
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 0.26 3,000.00 780.00 0.29 881.99 0.29 881.99 - - (0.03)
lift.
Providing and laying a single
layer flat brick soling on floor for
preparation of P.C.C. in which
98.0 joints should be packed by sand
to the required levels all
complete as per drawings,
specifications and the instructions
of the Engineer. m2 25.65 700.00 17,955.00 28.76 20,132.00 28.76 20,132.00 - - (3.11)

Contractor Prepared By Checked By Approved By


Pages-46 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
99.0 PCC Works
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 3.61 10,000.00 36,100.00 4.22 42,187.50 4.22 42,187.50 - - (0.61)
100.0 STONE PILLAR WORKS

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.59 7,000.00 4,130.00 0.58 4,076.80 0.58 4,076.80 - - 0.01
101.0 Wall Works
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 7.74 15,000.00 116,100.00 6.73 100,912.50 6.73 100,912.50 - - 1.01

Contractor Prepared By Checked By Approved By


Pages-47 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
102.0 WOODEN WORKS
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 0.86 250,000.00 215,000.00 0.86 215,090.00 0.86 215,090.00 - - (0.00)
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
103.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos. 7.00 25,000.00 175,000.00 - - - - - - 7.00
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
104.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 1.13 250,000.00 282,500.00 1.23 307,856.56 1.23 307,856.56 - - (0.10)

Contractor Prepared By Checked By Approved By


Pages-48 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
105.0 Roofing works
Providing and placing waterproof
plywood for roofing including
transportation, cutting,
connecting and placing in
position with nails, hooks, etc. all
complete as per drawings,
specifications and instruction. m2 27.73 700.00 19,411.00 - - - - - - 27.73
Providing and placing ikotile for
roofing including transportation,
106.0 cutting, connecting and placing in
position with nails all complete as
per drawings, specifications and
instruction. m2 27.73 2,500.00 69,325.00 27.73 69,321.56 - - 27.73 69,321.56 0.00
107.0 Plastering and Painting Works - - -
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 13.72 600.00 8,232.00 - - - - - - 13.72
108.0 False ceiling works - - -
Providing and placing false ceiling
with cement board including the
channels to drop false ceiling all
complete as per design, drawing,
specification and instruction of
site engineer. m2 9.00 2,500.00 22,500.00 - - - - - - 9.00
Providing and applying fire
retardant paint of approved
manufacturer and shade over
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
109.0 false ceiling all complete as per
drawings, specifications and
instruction. The rates shall
include for surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
m2 9.00 15,000.00 135,000.00 - - - - - - 9.00
approved by the Engineer.
110.0 WPC Panel for ceiling - - -
Providing and laying WPC Panel
for ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 18.00 1,500.00 27,000.00 - - - - - - 18.00
111.0 Waterproofing membrane on roof - - -

Contractor Prepared By Checked By Approved By


Pages-49 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and laying
waterproofing membrane on roof
all complete as per design,
drawing, specification and
instruction of site engineer. m2 27.73 600.00 16,638.00 - - - - - - 27.73

Contractor Prepared By Checked By Approved By


Pages-50 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
112.0 Flooring works - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 11.02 800.00 8,816.00 - - - - - - 11.02
3mm cement punning in 1:1 c/s
mortar in perfect line and level
113.0 including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 13.72 400.00 5,488.00 - - - - - - 13.72
Providing and laying of 25 mm
thick Telia tile paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
114.0 including curing on floor in
perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 8.20 3,500.00 28,700.00 - - - - - - 8.20
Providing and laying of 50mm
thick stone slab of approved
thickness and color on floor in
perfect line and level including
115.0 joint sealing of joint, grinding,
polishing all complete as per
design, drawing, specification and
the instrution of the site
engineer. m2 2.84 7,000.00 19,880.00 - - - - - - 2.84
Providing and laying of flagstone
of approved thickness and color
on floor in perfect line and level
116.0 including joint sealing of joint,
grinding, polishing all complete
as per design, drawing,
specification and the instrution of
the site engineer. m2 16.26 1,400.00 22,764.00 - - - - - - 16.26
Bells on roof:- Providing and
117.0 fixing design, drawing,
specification and instruction of
nos 36.00 10,000.00 360,000.00 - - - - - - 36.00
site engineer

Contractor Prepared By Checked By Approved By


Pages-51 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Landscape, drainage and
Boundary wall works - - -
118.0 Site Clearance Work - - -
Clearing and grubbing the site for
construction by removing 150mm
thick top soil including bushes,
small trees, levelling of undulated
ground, shorting and
stacking/storing selected top soil
for reuse in landscaping works,
disposing unsuitable materials
from site, etc., all complete as
per drawings, specifications and
instructions of the Engineer. m2 5,893.42 60.00 353,605.20 5,750.00 345,000.00 5,750.00 345,000.00 - - 143.42
Dismantling of existing structures
by manual means comprising of
cement concrete works including
scaffolding wherever necessary,
119.0
sorting the dismantled material,
disposal and stacking materials
with all lifts and leads of
1000meters m3 10.55 1,000.00 10,550.00 10.51 10,508.75 10.51 10,508.75 - - 0.04
Dismantling of existing blocks by
manual means comprising of
brick works including scaffolding
120.0 wherever necessary, sorting the
dismantled material, disposal and
stacking materials with all lifts
and leads of 1000meters m2 304.00 1,000.00 304,000.00 297.25 297,250.00 297.25 297,250.00 - - 6.75
Dismantling of barbed wire
fencing includong posts,
foundation concrete, backfilling of
121.0 pit by manual means including
disposal and stacking materials
with all lifts and leads of
1000meters rm 436.10 1,000.00 436,100.00 418.00 418,000.00 418.00 418,000.00 - - 18.10

Dismantling of steel including


122.0
dismembering by manual means
kg 968.40 120.00 116,208.00 968.40 116,208.00 1,298.70 155,844.00 (330.30) (39,636.00) -
Dismantling of granular courses
pavements and disposal of
123.0 dismantled materials upto a lead
of 1000 m, stacking materials all
by manual means m3 102.00 1,000.00 102,000.00 78.68 78,681.00 78.68 78,681.00 - - 23.32
Earthwork

Contractor Prepared By Checked By Approved By


Pages-52 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
124.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 1,797.24 250.00 449,310.00 1,245.87 311,468.10 1,045.70 261,425.08 200.17 50,043.02 551.37

Contractor Prepared By Checked By Approved By


Pages-53 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
125.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 216.67 300.00 65,001.00 354.29 106,287.00 354.29 106,287.00 - - (137.62)
Soling works
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
126.0
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 296.93 3,000.00 890,790.00 137.83 413,499.58 99.89 299,680.80 37.94 113,818.78 159.10
lift.
Providing and laying a single
layer flat brick soling on drainage
works on lanscape for preparation
of P.C.C. in which joints should be
127.0
packed by sand to the required
levels all complete as per
drawings, specifications and the
instructions of the Engineer. m2 1,621.11 700.00 1,134,777.00 532.26 372,584.41 418.38 292,863.16 113.89 79,721.25 1,088.85

Contractor Prepared By Checked By Approved By


Pages-54 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
128.0 PCC Works
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 384.15 10,000.00 3,841,500.00 177.47 1,774,695.12 108.50 1,084,983.75 68.97 689,711.37 206.68
129.0 RCC Works

Concrete Works for RCC (1:1.5:3)


M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer.
m3 15.87 16,000.00 253,920.00 16.97 271,492.00 - - 16.97 271,492.00 (1.10)
130.0 Centering and Shuttering Work
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 440.35 600.00 264,210.00 629.47 377,684.70 371.55 222,932.40 257.92 154,752.30 (189.12)
131.0
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 11.30 120,000.00 1,356,000.00 3.65 437,936.07 1.66 199,006.08 1.99 238,929.99 7.65

Contractor Prepared By Checked By Approved By


Pages-55 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
132.0 Wall Works
STONE MASONRY WORKS IN
CEMENT MORTAR
Providing and laying Random
Rubble stone masonry works on
retaining walls in cement mortar
(1:4) including providing
through/bond stone at required
interval including providing
required scaffolding, preparing
mortar and construction of wall to
any height and shape all
complete as per drawings,
specifications and instruction of
the engineer. m3 808.10 7,000.00 5,656,700.00 874.11 6,118,759.15 874.11 6,118,759.15 - - (66.01)
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
133.0 heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 44.64 15,000.00 669,600.00 28.34 425,163.75 17.84 267,562.50 10.51 157,601.25 16.30

Contractor Prepared By Checked By Approved By


Pages-56 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
PIPEWORKS FOR
WEEPHOLE AND
134.0
GEOTEXTILE WORKS FOR
- - - -
RETAINING
Providing WALLSstructural
and placing
steel tested grade Fe-250
equivalent NS, for structural work
including
transportation,cutting,connecting
and placing in position, treated
with two coat of anticorrosive
paints, all complete as per
drawings,specifications and
instruction.(80mmdi GI medium rm 246.14 700.00 172,298.00 244.32 171,024.00 244.32 171,024.00 - - 1.82
duty)
Providing and placing of Geo
Textile on retaining wall and
135.0
french drain as per the instruction
m2 3,107.32 80.00 248,585.60 1,146.00 91,680.00 1,146.00 91,680.00 - - 1,961.32
of engineer and Painting
Plastering
136.0 - - -
Works
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on internal walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 1,167.64 600.00 700,584.00 239.36 143,614.66 - - 239.36 143,614.66 928.28
Flushing pointing on the exterior
Brick wall of gate structure by
cement sand mortar of ratio 1:2
all complete as per drawings,
specificatios and instruction. The
rates shall include for scraping,
137.0
washing the surface with water,
surface preparation,
scaffolding,etc.,all complete as
per the manufacturer's
recommendations and as
approved by the Engineer.
m2 2.35 400.00 940.00 - - - - - - 2.35

Contractor Prepared By Checked By Approved By


Pages-57 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications on exterior plaster
138.0 all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m2 230.24 300.00 69,072.00 - - - - - - 230.24

Contractor Prepared By Checked By Approved By


Pages-58 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and laying 20mm. thick
Cement Water Bead (Pani Patti)
finished perfectly smooth
139.0 including necessary scaffolding,
raking the joint, wetting the
surface and curing all complete
work rm 112.45 400.00 44,980.00 - - - - - - 112.45
140.0 Flooring Work - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 38.08 800.00 30,464.00 - - - - - - 38.08
3mm cement punning in 1:1 c/s
mortar in perfect line and level
including trowelling and finishing
141.0 in smooth surface on risers of
steps on landscape works as per
design, drawing, specification and
instruction of site engineer. m2 1,123.24 400.00 449,296.00 - - - - - - 1,123.24
Providing and laying of flagstone
of approved thickness and color
on landscape works in perfect line
and level including joint sealing
142.0
of joint, grinding, polishing all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 1,668.10 1,400.00 2,335,340.00 - - - - - - 1,668.10
Providing and laying of 25 mm
thick Telia brick paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
143.0 including curing on landscape
works in perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 183.41 3,400.00 623,594.00 - - - - - - 183.41
Providing and laying stone slab of
approved quality and color over
PCC on pavements including
cement mortar of 1:3(cement
sand) in perfect line, level
finished with necessary pointing
144.0 in joints sloped towards drain line
all complete as per design,
drawing, specification and the
instrution of consultant and his
authorized representative.
Samples should be approves by
consultant. m2 13.36 7,000.00 93,520.00 - - - - - - 13.36

Contractor Prepared By Checked By Approved By


Pages-59 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Providing and laying of brick
pavement of approved thickness
and color on landscape works in
perfect line and level including
145.0 joint sealing of joint, grinding,
polishing all complete as per
design, drawing, specification and
the instrution of the site
engineer. m2 463.64 700.00 324,548.00 - - - - - - 463.64
Cement skirting works:-Providing
and laying cement punning
skirting on rammed earth walls
inside rooms in perfect line and
146.0 level with grouting all complete
as per design, drawing ,
specification and instruction of
consultant and his authorized
representative rm 6.94 600.00 4,164.00 - - - - - - 6.94
Waterproofing works:- Providing
and applying water proof coating
work necessary on cement
punning area after preparing the
147.0
surface all complete work as per
design, drawing , specification
and instruction of consultant and
his authorized representative rm 6.94 500.00 3,470.00 - - - - - - 6.94
148.0 FRENCH DRAIN WORKS - - -
Providing and laying subsurface
drain with perforated pipe of
100mm internal diameter of PVC,
closely joined perforations
ranging from 3mm to 6mm
depending upon size of material
surrounding the pipe with 150mm
bedding below the pipe and
300mm cushion above pipe, as
per drawing and specification. rm 202.00 800.00 161,600.00 120.00 96,000.00 120.00 96,000.00 - - 82.00

Contractor Prepared By Checked By Approved By


Pages-60 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
PEBBLES FOR COVERED
149.0
DRAIN AND TAP - - - -
Providing and laying pebbles for
drain cover and stone tap on
landscape works as per design,
drawing, specification and
instruction of site engineer. m3 1.97 10,000.00 19,700.00 - - - - - - 1.97
STEEL GRATING FOR
150.0
DRAINS and laying light duty
Providing
iron channel grates on drains in
perfect line and level including
finishing in smooth surface on
landscape as per design, drawing,
specification and instruction of
site engineer. kg 1,165.71 250.00 291,427.50 - - - - - - 1,165.71
Supplying and fitting of railing
with 50mm vertical MS circular
pipe of 500mm height at 2m
151.0 interval and 50mm black pipe
handrail including welding, joints,
and prmer painting asper drawing
and instructions all complete. m2 29.16 6,500.00 189,540.00 - - - - - - 29.16
GAMALA POTS ON
LANDSCAPE
Providing, molding and placing
gamala pots on landscape as per
design, drawing, specification and
instruction of site engineer. - - -
152.0 gamala 1 nos 8.00 1,000.00 8,000.00 - - - - - - 8.00
153.0 gamala 2 nos 5.00 1,000.00 5,000.00 - - - - - - 5.00
154.0 gamala 3 nos 2.00 1,000.00 2,000.00 - - - - - - 2.00

Contractor Prepared By Checked By Approved By


Pages-61 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
155.0 gamala 4 nos 1.00 1,000.00 1,000.00 - - - - - - 1.00
156.0 gamala 5 nos 3.00 1,000.00 3,000.00 - - - - - - 3.00
157.0 gamala 6 nos 10.00 1,000.00 10,000.00 - - - - - - 10.00
158.0 gamala 7 nos 6.00 1,000.00 6,000.00 - - - - - - 6.00
159.0 Wooden railing works - - -
Providing and placing seasoned
laminated timber rail on openings
of gates including transportation,
cutting, connecting and placing in
position with wood primer and
paint, all complete as per
drawings, specifications and
instruction. m2 4.27 2,500.00 10,675.00 - - - - - - 4.27
160.0 Wooden fascia works - - -
Providing and placing 25mm thk.
Treated hardwood fascia board
on roof including transportation,
cutting, connecting and placing in
position with wood primer and
paint, all complete as per
drawings, specifications and
instruction. m2 6.93 12,000.00 83,160.00 - - - - - - 6.93

Contractor Prepared By Checked By Approved By


Pages-62 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Waterproof plyboard on
161.0 - - -
roof
Providing and laying 10mm
waterproof plywood with one side
veneer in perfect line and level
above adobe insulation all
complete as per design, drawing,
specification and instruction of
consultant and his authorized
representative. Samples should
be approved by consultant. m2 30.74 700.00 21,518.00 - - - - - - 30.74
162.0 Iko-tile roofing works - - -
Providing and laying iko-tile
nailed and stacked over plyboard
on sloped roofs in perfect line and
level all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 30.74 3,500.00 107,590.00 - - - - - - 30.74

Contractor Prepared By Checked By Approved By


Pages-63 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
163.0 Structural steel Works - - -
Providing and placing structural
steel tested grade Fe-250
equivalent NS, for structural work
on gate roof including
transportation, cutting,
connecting and placing in
position,treated with two coat of
anticorrosive paints, all complete
as per drawings, specifications
and instruction. kg 745.43 250.00 186,357.50 - - - - - - 745.43
Providing and fabricating MS steel
gate and fixing in entrance
polished and finished in perfect
164.0
line, level as per design, drawing,
specification and instruction all
complete. kg 186.69 250.00 46,672.50 - - - - - - 186.69
Supplying and fitting of railing
with M.S. pipe including welding,
165.0 joints and primer painting as per
drawing and instructions all
complete m2 61.00 5,000.00 305,000.00 72.02 360,092.25 72.02 360,092.25 - - (11.02)
166.0 Shera board works
Providing, fabricating & fixing
shera board works on gate
finished in perfect line, level
along with all necessary
accessories all complete as per
design, drawing, specification and
instruction m2 2.60 2,500.00 6,500.00 - - - - - - 2.60
Supplying and Fixing Indian
pattern C.P. valves with wall
167.0
flange Including c.p. nipple all
nos 6.00 2,000.00 12,000.00 - - - - - - 6.00
complete set.
Supplying and Fixing CP Bib Cock
168.0 with wall flange,cp nipple all
complete set nos 3.00 4,000.00 12,000.00 - - - - - - 3.00
Supplying and Fixing 20 mm
CPVC pipe with pipe Jointing
materials (Tee, Elbow, Union),
making holes, clips and vent cowl
169.0
all complete set as per
specification and instruction.
(Mangalam, Panchakanya ,
Prince,Supreme or Equivalent. ) rm 125.88 800.00 100,704.00 - - - - - - 125.88
Providing and fixing PVC water
tank- brand Nepatop/Hilltake/
Panchakanya or equivalent, of
capacity 2000 ltrs. finished in
170.0
perfect line, level along with all
necessary accessories all
complete as per design, drawing,
specification and instruction nos 2.00 35,000.00 70,000.00 - - - - - - 2.00
PLANTATION WORKS - - -
Planting dubo grass on site
including digging, planting hole
171.0
10-20 cm depth using a metal rod
or hardwood peg. sqm 2,800.00 600.00 1,680,000.00 - - - - - - 2,800.00

Contractor Prepared By Checked By Approved By


Pages-64 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Planting rooted tree stump
cutting and bare root seedlings,
including pitting, transplanting,
composting and mulching, pit
size 10cm diameterx depth
compost volume of pit mix with
original soil.

Specifications for trees(3-4ft):-


Sami (Ficus benjamina)
Bougainvillea (Bougainvillea
172.0 glabra)
Mango (Magnifera Indica)
Neem (Azadirachta indica)
Parijat ((Nyctanthes arbor tristis)
Jasmine (Jasminum polyanthum)
Ashoka (Saraca asoca)
Supari (Areca catechu)
Bamboo (Bambusa vulgaris)
Gulmohar (Delonix regia)
Banana (Musa paradiscata)
Willow (Salix babylonica)
no 147.00 1,000.00 147,000.00 - - - - - - 147.00
Planting shrubs including digging,
173.0
planting hole, etc. all complete. ls 1.00 2,000.00 2,000.00 - - - - - - 1.00

- - -
LED strip light warm white
220V with soft bending
diffuser, philips
equivalent, 72 LED per
meter or equivalent for
174.0
bright and uniform
lighting, complete set with
fitting components and
installation, with junction rm 45.00 2,000.00 90,000.00 - - - - - - 45.00
box if necessary
LUMINAIRES ( FIXTURES) Outdoor
LED based Luminaries set all
complete. LEGERO, GE, Philips or
equivalent
7W Garden Spike, Anthracite,
175.0
Warm White,Floor Lamp, 220V,
warm white, IP 65 or above,
complete set with fitting
components and installation, with
junction box if necessary set 18.00 1,500.00 27,000.00 - - - - - - 18.00
30W LED outdoor wall washer
(Tubelight for indirect lighting),
176.0 3000K, IP 65 and above, 220 V,
complete set with fitting
components and installation set 16.00 1,500.00 24,000.00 - - - - - - 16.00

Contractor Prepared By Checked By Approved By


Pages-65 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
LUMINAIRES ( FIXTURES) Outdoor
LED based Luminaries set all
complete. LEGERO, GE, Philips or
equivalent,
6W 800lm Sleek small LED Track
177.0
Lighting, 220V, warm white, IP 65
or above, complete set with
fitting components and
installation, with junction box if
necessary set 24.00 1,500.00 36,000.00 - - - - - - 24.00
Up down Sconce light 10W
equivalent IP 65 and
above,2700K/3000K warm white,
178.0
complete set with fitting
components and installation, with
junction box if necessary set 4.00 1,500.00 6,000.00 - - - - - - 4.00
Wall recessed 12 inch to 24 inch
length, 10W equivalent (600-
800lm) LED warm white light,
179.0 220V, IP 65 or above, complete
set with fitting components and
installation, with junction box if
necessary set 61.00 2,000.00 122,000.00 - - - - - - 61.00
Street Light / Flood Light Philips
BGP704 equivalent 220V, 10000
lumens, warm white luminaires
with mount and all other
180.0
components complete set with
fitting components and
installation, with junction box if
necessary set 2.00 2,000.00 4,000.00 - - - - - - 2.00
12W ceiling recessed Warm white
luminaire set, 220V, complete set
181.0 with fitting components and
installation, with junction box if
necessary set 1.00 3,500.00 3,500.00 - - - - - - 1.00
9W directional LED ceiling
recessed light track light, all
182.0
complete,with junction box if
set 2.00 3,500.00 7,000.00 - - - - - - 2.00
necessary
Floor recessed (ground well) LED
luminaire 12 W, Warm white
183.0 220V, IP 65 or above, complete
set with fitting components and
installation set 14.00 1,500.00 21,000.00 - - - - - - 14.00
Post top LED warm white
luminaire 30W, 220V with
heritage style cast iron lamp post
of minimum 7 feet height from
184.0 ground level (to be bought in
consultation with architecture),
complete set with fitting
components and installation, with
junction box if necessary set 14.00 2,000.00 28,000.00 - - - - - - 14.00

Contractor Prepared By Checked By Approved By


Pages-66 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Street Light Philips BGP704
equivalent 220V, 10000 lumens,
warm white luminaires with
185.0
mount and all other components
complete set with fitting
components and installation set 2.00 3,000.00 6,000.00 - - - - - - 2.00
Installation, testing and
commissioning of 10 sq mm 2C,
armored copper cable from
existing point to distribution
186.0
board, underground via 32 mm
HDPE pipe, complete set with
fitting components and
installation Rm 40.00 1,200.00 48,000.00 - - - - - - 40.00
Electrical Outdoor distribution
box, Waterproof sealed with IP
rating of IP66 or above, made
with stainless steel with stand
187.0 kept 2 feet above ground level,
embedded door with required
copper bush, installation and
fitting cost of MCB ans switches
all included set 1.00 60,000.00 60,000.00 - - - - - - 1.00
Installation, testing and
188.0
comissioning of 16 way SPN DB set 1.00 5,000.00 5,000.00 - - - - - - 1.00
Installation testing and
189.0 commissioning of 6 A SP MCB, all
complete set 12.00 600.00 7,200.00 - - - - - - 12.00
Installation testing and
190.0 commissioning of 16 A SP MCB,
all complete set 2.00 600.00 1,200.00 - - - - - - 2.00
Installation testing and
191.0 commissioning of 32 A DP MCB,
all complete set 1.00 600.00 600.00 - - - - - - 1.00
Installation testing and
192.0 comissioning of 32 A DP Switch,
set 1.00 2,000.00 2,000.00 - - - - - - 1.00
all complete
Weatherproof Outdoor Junction
Box, IP 68 or above rated, JB with
193.0
option for sealing the incoming
and outgoing 2c wire set 30.00 2,000.00 60,000.00 - - - - - - 30.00
3*3 metal (Stainless Steel)
194.0 junction box with rubber gasket
for weather proofing set 10.00 3,500.00 35,000.00 - - - - - - 10.00
9m Pole for electric lighting single
195.0
arm set 2.00 75,000.00 150,000.00 - - - - - - 2.00
9m double arm pole for electrc
196.0
lighting set 1.00 15,000.00 15,000.00 - - - - - - 1.00
Installation, testing, and
commissioning of 2.5 sq mm 2C,
armored copper cable from the
197.0
distribution board to, light points
underground via 32 mm HDPE
pipe, all complete Rm 1,220.00 800.00 976,000.00 - - - - - - 1,220.00

Contractor Prepared By Checked By Approved By


Pages-67 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -

नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
किताबको ठेक्कामा
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
Chemical Earthing
Supply, Installation, testing and
commissioning of Chemical
198.0
Earthing System with including all
material and accessories to all
complete the works nos 1.00 50,000.00 50,000.00 - - - - - - 1.00
Supply , installation & testing of 8
199.0 SWG bare copper conductor from
Main panel to earth test pit Rm 10.00 800.00 8,000.00 - - - - - - 10.00

Contractor Prepared By Checked By Approved By


Pages-68 of 333
ठेक्का सम्बन्धी बिल-Fourth

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः 3.00
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः 65,676.00
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः 66,414.00
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः -
नापी किताब नं 4 काम सम्पन्न भएको मितिः -
सार्वजनि
क नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम कैफियत
निर्माण
किताबको ठेक्कामा
कार्य मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम बाँकी परिमाण
सम्पन्न
१ २ 3 4.00 5.00 6.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१० 16.00 17.00
भइसकेपछि
प्रत्येक
क. जम्मा रकम 35,093,919.49 16,690,861.00 14,581,414.31 2,109,446.69
ठेकदारबा
ट यही ख. 13% मु.अ.कर 4,562,209.53 2,169,811.93 1,895,583.86 274,228.07
ढाँचामा ग.Provisional Sum Amount 155,000.00 120,000.00 105,000.00 15,000.00
बिल घ. कुल जम्मा (क+ख) 39,811,129.03 18,980,672.93 16,581,998.17 2,398,674.76
प्रस्तुत
गराउनुप (16,690,861.00)
र्दछ ।
यो बिलबमोजिम काम भएको जम्मा रूः हाल काम भएको बाँकी 2,398,674.76 यस बिल बमोजिम गरिएको भुक्तानी
ठेकेदार
अघिल्लो बिलसम्म भुक्तानी भएको रूः कट्टा गर्नु पर्ने रू भौचर नं:
ले गरेकाभुक्तानी बिलको क्रम सङ्ख्याः
अघिल्लो क. मोबिलाइजेसन पेस्की रूः भुक्तानी मिति:
काममा
अघिल्लो र भुक्तानी बिलको भौ.नं. ख. मालसामानको पेस्की रूः भुक्तानी रकम रू
सो बापत ग. मेसिनरी औजारको बहाल रूः
ठेकदारला
घ. अग्रीम आय कर रकम रूः
र्इ भएको
ङ. धरौटी रकम रूः
हिसाब
समेत गरी च. अन्य कट्टी गर्ने पर्ने रकम रूः
अभिलेख खुद दिनु पर्ने रकम रूः
राख्न यो
फाराम तयार गर्नेको सहीः जाँच गर्नेको सहीः स्वीकृत गर्नेको सहीः
तर्जुमा निर्माण व्यवसायीको सही: नाम नाम नाम
गरिएको नाम: दर्जाः दर्जाः दर्जाः
हो । पदः मितिः मितिः मितिः
निर्माण मितिः
कार्यको
ठेक्काको
उद्देश्य यो बिलबमोजिम जम्मा रू .....................अक्षरमा .................................................................................... को चेक नं: ........................बुझिलिए ।
बिल तयार
गर्नु

Contractor Prepared By Checked By Approved By


Pages-69 of 333

बिराटनगर महानगरपालिका
नगर कार्यापालिकाको कार्यालय
कार्यालय कोड नं.:
ठेक्का सम्बन्धी बिल-FIFTH

योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
A Provisional Sum
General works:Provide Insurance
of works, materials,construction
1.0
equipments against accident to
workforce including third party PS 1.00 100,000.00 100,000.00 - 1.00 100,000.00 1.00 100,000.00 - -
Provide & Maintain protective
safety Equipments including Hats,
2.0 Gloves, Googles, Dust mask, First
Aid Kit with medicine for work
force PS 1.00 15,000.00 15,000.00 - 1.00 15,000.00 1.00 15,000.00 - -
Lab test of the construction
3.0 materials as rebar cement, brick,
as per specified by site incharge PS 1.00 40,000.00 40,000.00 - 1.00 5,000.00 1.00 5,000.00 - -
Total Provisional Sum 155,000.00 120,000.00 120,000.00 -
2 CONSTRUCTION WORK
Provide & Installation of Project
Information Board 1.2*0.9m Size
1.0 No.
as to Complete the work
Specified 1.00 10,000.00 10,000.00 - 1.00 10,000.00 1.00 10,000.00 - -

Contractor Prepared By Checked By Approved By


Pages-70 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
PAVILION I - -
Earthwork -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
2.0 debris & brick bats of old m3
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. 12.58 200.00 2,516.00 12.58 2,516.10 12.58 2,516.10 - -

Filling with earth or mixed soil


stacked at site in 150mm thick
layer on retaining walls including
3.0 watering, ramming, consolidation m3
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete.

5.45 300.00 1,635.00 4.44 1,332.90 4.44 1,332.90 - -

Contractor Prepared By Checked By Approved By


Pages-71 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Soling works - -
4.0 Stone soling works - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 1.64 3,000.00 4,920.00 1.64 4,924.50 1.64 4,924.50 - -
lift.
5.0 Brick soling work - -
Providing and laying a single
layer flat brick soling on drainage
works on lanscape for preparation
of P.C.C. in which joints should be
packed by sand to the required
levels all complete as per
drawings, specifications and the
instructions of the Engineer. m2 1.57 700.00 1,099.03 1.57 1,095.50 1.57 1,095.50 - -

Contractor Prepared By Checked By Approved By


Pages-72 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
6.0 PCC Works - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 0.93 10,000.00 9,300.00 0.93 9,263.75 0.93 9,263.75 - -
7.0 RCC Works - -
Concrete Works for RCC (1:1.5:3)
M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer. m3 8.65 16,000.00 138,400.00 8.65 138,418.00 8.65 138,418.00 - -
8.0 Steel reinforcement works - -
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 1.36 120,000.00 163,200.00 0.76 91,201.51 0.27 32,466.13 0.49 58,735.38

Contractor Prepared By Checked By Approved By


Pages-73 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
9.0 Centering and Shuttering Work - -
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 65.64 600.00 39,384.00 65.63 39,378.00 65.63 39,378.00 - -
10.0 STONE PILLAR WORKS - -
Providingand placing stone pillar
above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.58 7,000.00 4,060.00 0.57 4,004.00 0.57 4,004.00 - -

Contractor Prepared By Checked By Approved By


Pages-74 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
11.0 Wall Works - - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 9.87 15,000.00 148,050.00 9.86 147,975.00 9.86 147,975.00 - -
WOODEN WORKS - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
12.0 level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 0.61 250,000.00 152,500.00 0.61 152,499.99 0.61 152,499.99 - -
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
13.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos 6.00 25,000.00 150,000.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-75 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
14.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 0.39 250,000.00 97,500.00 0.39 97,920.00 0.39 97,920.00 - -
MS STEEL WORKS - -
Providing and placing structural
steel tested grade Fe-250
equivalent NS, for structural work
including transportation, cutting,
15 connecting and placing in
position,treated with two coat of
anticorrosive paints, all complete
as per drawings, specifications
and instruction. kg 1,187.12 250.00 296,780.17 1,187.12 296,780.16 1,187.12 296,780.16 - -
Providing and placing decking
sheet for concrete deck slab
including transportation, cutting,
16 connecting and placing in
position with welds and studs all
complete as per drawings,
specifications and instruction. m2 43.24 1,200.00 51,888.00 43.24 51,888.00 43.24 51,888.00 - -

Contractor Prepared By Checked By Approved By


Pages-76 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Plastering and Painting Works - -
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
17 mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 56.69 300.00 17,007.00 56.69 17,008.35 56.69 17,008.35 - -
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
wall, ceiling, beams columns,
18 canopies, staircase, lobbies etc.,
all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m2 56.69 300.00 17,007.00 - - - - - -
False ceiling works - -

Contractor Prepared By Checked By Approved By


Pages-77 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and placing false ceiling
with plyboard(one side veneer)
19 including the channels to drop
false ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 43.18 2,500.00 107,950.00 - - - - - -
Providing and applying PU paint
of approved manufacturer and
shade over primer of approved
manufacturer as per
manufacturer's specifications to
the surface of false ceiling all
20 complete as per drawings,
specifications and instruction.
The rates shall include for
surface preparation, scaffolding
etc., all complete as per the
manufacturer's recommendations
and as approved by the Engineer. m2 43.18 300.00 12,954.00 - - - - - -
21 Toughen glass Works - -
Providing and laying toughen
glass on roof including fixing with
silicon and necessary support all
complete as per drawing and
specification. m2 1.09 12,000.00 13,080.00 - - - - - -
22 Fibre cement board cladding for fascia - - -
Providing and laying fibre cement
board cladding on fascia all
complete as per design, drawing,
specification and instruction of
site engineer. rm 27.95 3,000.00 83,850.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-78 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
23 Waterproofing coating on roof - - -
Providing and laying
waterproofing coating on roof all
complete as per design, drawing,
specification and instruction of
site engineer. m2 43.24 500.00 21,620.00 - - - - - -
24 Cement punning finish on roof - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 43.24 400.00 17,296.00 - - - - - -
Timber plank on bench:-
Providing and laying timber plank
25 on bench all complete as per
design,drawing,specification and
instruction of site engineer m2 0.88 12,000.00 10,560.00 - - - - - -
PAVILION I I- - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
26 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 12.51 1,000.00 12,510.00 12.51 12,507.75 12.51 12,507.75 - -

Contractor Prepared By Checked By Approved By


Pages-79 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
27 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 5.38 300.00 1,614.00 4.55 1,365.63 4.55 1,365.63 - -
28 Soling works - - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 1.83 3,000.00 5,490.00 1.83 5,478.18 1.83 5,478.18 - -
lift.

Contractor Prepared By Checked By Approved By


Pages-80 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
29.0 PCC Works - - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 0.91 10,000.00 9,100.00 0.91 9,089.12 0.91 9,089.12 - -
30.0 RCC Works - - -
Concrete Works for RCC (1:1.5:3)
M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer. m3 6.86 16,000.00 109,760.00 6.86 109,682.24 6.86 109,682.24 - -
31.0 Steel reinforcement works - -
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 1.08 120,000.00 129,600.00 0.42 50,609.77 0.25 29,911.07 0.17 20,698.70

Contractor Prepared By Checked By Approved By


Pages-81 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
32.0 Centering and Shuttering Work - -
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 21.69 600.00 13,014.00 21.69 13,014.84 21.69 13,014.84 - -
33.0 STONE PILLAR WORKS - -

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.90 7,000.00 6,300.00 0.90 6,272.00 0.90 6,272.00 - -

Contractor Prepared By Checked By Approved By


Pages-82 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
34.0 Wall Works - - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 7.27 15,000.00 109,050.00 7.27 109,036.53 7.27 109,036.53 - -
WOODEN WORKS - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
35.0 level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 1.43 250,000.00 357,500.00 1.43 356,661.40 1.43 356,661.40 - -
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
36.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos 7.00 25,000.00 175,000.00 - - - - - -
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
37.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 0.63 250,000.00 157,500.00 0.63 156,512.50 0.63 156,512.50 - -
38.0 MS STEEL WORKS - -
Providing and placing structural
steel tested grade Fe-250
equivalent NS, for structural work
including transportation, cutting,
38.0 connecting and placing in
position,treated with two coat of
anticorrosive paints, all complete
as per drawings, specifications
and instruction. kg 926.34 250.00 231,585.00 926.34 231,584.71 926.34 231,584.71 - -

Contractor Prepared By Checked By Approved By


Pages-83 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and placing decking
sheet for concrete deck slab
including transportation, cutting,
39.0 connecting and placing in
position with welds and studs all
complete as per drawings,
specifications and instruction. m2 36.18 6,000.00 217,080.00 36.18 217,080.00 36.18 217,080.00 - -

Contractor Prepared By Checked By Approved By


Pages-84 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
40.0 Plastering and Painting Works - -
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 36.15 600.00 21,690.00 35.06 21,036.00 35.06 21,036.00 - -
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
wall, ceiling, beams columns,
41.0 canopies, staircase, lobbies etc.,
all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m3 36.15 300.00 10,845.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-85 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
42.0 False ceiling works - - -
Providing and placing false ceiling
with plyboard(one side veneer)
including the channels to drop
false ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 36.18 2,500.00 90,450.00 - - - - - -
Providing and applying PU paint
of approved manufacturer and
shade over primer of approved
manufacturer as per
manufacturer's specifications to
the surface of false ceiling all
43.0 complete as per drawings,
specifications and instruction.
The rates shall include for
surface preparation, scaffolding
etc., all complete as per the
manufacturer's recommendations
and as approved by the Engineer. m2 36.18 300.00 10,854.00 - - - - - -
44.0 Fibre cement board cladding for fascia - - -
Providing and laying fibre cement
board cladding on fascia all
complete as per design, drawing,
specification and instruction of
site engineer. m2 42.30 2,500.00 105,750.00 - - - - - -
45.0 Waterproofing coating on roof - - -
Providing and laying
waterproofing coating on roof all
complete as per design, drawing,
specification and instruction of
site engineer. m2 36.18 500.00 18,090.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-86 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
46.0 Cement punning finish on roof - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 10.48 400.00 4,192.00 - - - - - -
PAVILION III - - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
47.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 10.55 1,000.00 10,550.00 10.55 10,550.00 10.55 10,550.00 - -
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
48.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 6.54 300.00 1,962.00 6.54 1,962.00 6.54 1,962.00 - -

Contractor Prepared By Checked By Approved By


Pages-87 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Soling works - - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
49.0 sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 2.72 3,000.00 8,160.00 2.72 8,160.00 2.72 8,160.00 - -
lift.
Providing and laying a single
layer flat brick soling on floor for
preparation of P.C.C. in which
50.0 joints should be packed by sand
to the required levels all
complete as per drawings,
specifications and the instructions
of the Engineer. m2 9.24 700.00 6,468.00 9.24 6,468.00 9.24 6,468.00 - -

Contractor Prepared By Checked By Approved By


Pages-88 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
51.0 PCC Works - - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 2.35 10,000.00 23,500.00 2.35 23,500.00 2.35 23,500.00 - -
52.0 RCC Works - - -
Concrete Works for RCC (1:1.5:3)
M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer. m3 5.82 16,000.00 93,120.00 - - - - - -
53.0 Steel reinforcement works - - -
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 0.91 120,000.00 109,200.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-89 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
54.0 Centering and Shuttering Work - - -
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 77.62 600.00 46,572.00 - - - - - -
55.0 STONE PILLAR WORKS - - -

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 1.36 7,000.00 9,520.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-90 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
56.0 Wall Works - - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 3.22 15,000.00 48,300.00 3.22 48,300.00 3.22 48,300.00 - -
57.0 WOODEN WORKS - - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 2.27 250,000.00 567,500.00 - - - - - -
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
58.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. Nos. 7.00 25,000.00 175,000.00 - - - - - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
59.0 level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 2.29 250,000.00 572,500.00 - - - - - -
60.0 Waterproof plywood works - - -
Providing and placing waterproof
plywood for concrete deck slab
including transportation, cutting,
connecting and placing in
position with nails, hooks, etc. all
complete as per drawings,
specifications and instruction. m2 77.62 700.00 54,334.00 - - - - - -
61.0 Plastering and Painting Works - - -

Contractor Prepared By Checked By Approved By


Pages-91 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 8.24 600.00 4,944.00 8.16 4,896.00 - - 8.16 4,896.00
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
wall, ceiling, beams columns,
62.0 canopies, staircase, lobbies etc.,
all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m2 8.24 300.00 2,472.00 - - - - - -
63.0 False ceiling works - - -
Providing and placing false ceiling
with plyboard(one side veneer)
including the channels to drop
false ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 21.29 2,500.00 53,225.00 - - - - - -
Providing and applying PU paint
of approved manufacturer and
shade over primer of approved
manufacturer as per
manufacturer's specifications to
the surface of false ceiling all
64.0 complete as per drawings,
specifications and instruction.
The rates shall include for
surface preparation, scaffolding
etc., all complete as per the
manufacturer's recommendations
and as approved by the Engineer. m2 21.29 300.00 6,387.00 - - - - - -
65.0 WPC board for fascia - - -
Providing and laying WPC board
cladding on fascia all complete as
per design, drawing, specification
and instruction of site engineer. rm 55.80 2,500.00 139,500.00 - - - - - -
66.0 Waterproofing membrane on roof - - -

Contractor Prepared By Checked By Approved By


Pages-92 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and laying
waterproofing membrane on roof
all complete as per design,
drawing, specification and
instruction of site engineer. m2 77.62 700.00 54,334.00 - - - - - -
67.0 Panipatti - - -
Providing and laying 20mm. thick
Cement Water Bead (Pani Patti)
finished perfectly smooth
including necessary scaffolding,
raking the joint, wetting the
surface and curing all complete
work rm 55.80 400.00 22,320.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-93 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
68.0 Flooring works - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 77.62 800.00 62,096.00 - - - - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
69.0 including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 77.62 400.00 31,048.00 - - - - - -
Providing and laying of 25 mm
thick Telia tile paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
70.0 including curing on floor in
perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 9.24 3,400.00 31,416.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-94 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and laying of stone slab
of approved thickness and color
on floor in perfect line and level
71.0 including joint sealing of joint,
grinding, polishing all complete
as per design, drawing,
specification and the instrution of
the site engineer. m2 3.96 7,000.00 27,720.00 - - - - - -
PAVILION IV - - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
72.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 11.33 1,000.00 11,330.00 11.33 11,327.00 11.33 11,327.00 - -
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
73.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 8.27 300.00 2,481.00 8.27 2,480.07 8.27 2,480.07 - -

Contractor Prepared By Checked By Approved By


Pages-95 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Soling works - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
74.0 sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 0.26 3,000.00 780.00 0.26 792.00 0.26 792.00 - -
lift.
Providing and laying a single
layer flat brick soling on floor for
preparation of P.C.C. in which
75.0 joints should be packed by sand
to the required levels all
complete as per drawings,
specifications and the instructions
of the Engineer. m2 24.39 700.00 17,073.00 24.39 17,073.00 24.39 17,073.00 - -

Contractor Prepared By Checked By Approved By


Pages-96 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
76.0 PCC Works - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 4.69 10,000.00 46,900.00 4.69 46,915.68 4.69 46,915.68 - -
77.0 STONE PILLAR WORKS - -

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.59 25,000.00 14,750.00 0.58 14,560.00 0.58 14,560.00 - -
78.0 Wall Works - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 7.85 15,000.00 117,750.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-97 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
79.0 WOODEN WORKS - - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 0.86 250,000.00 215,000.00 0.86 215,090.00 0.86 215,090.00 - -
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
80.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos. 7.00 25,000.00 175,000.00 - - - - - -
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
81.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 1.23 250,000.00 307,500.00 1.23 307,856.56 1.23 307,856.56 - -

Contractor Prepared By Checked By Approved By


Pages-98 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
82.0 Roofing works - -
Providing and placing waterproof
plywood for roofing including
transportation, cutting,
connecting and placing in
position with nails, hooks, etc. all
complete as per drawings,
specifications and instruction. m2 27.73 700.00 19,411.00 27.73 19,410.03 27.73 19,410.03 - -
Providing and placing ikotile for
roofing including transportation,
83.0 cutting, connecting and placing in
position with nails all complete as
per drawings, specifications and
instruction. m2 27.73 3,500.00 97,055.00 27.73 97,050.18 - - 27.73 97,050.18
84.0 Plastering and Painting Works - -
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 13.72 300.00 4,116.00 - - - - - -
85.0 False ceiling works - - -
Providing and placing false ceiling
with cement board including the
channels to drop false ceiling all
complete as per design, drawing,
specification and instruction of
site engineer. m2 16.00 2,500.00 40,000.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-99 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and applying fire
retardant paint of approved
manufacturer and shade over
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
86.0 false ceiling all complete as per
drawings, specifications and
instruction. The rates shall
include for surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
m2 16.00 15,000.00 240,000.00 - - - - - -
approved by the Engineer.
87.0 WPC Panel for ceiling - - -
Providing and laying WPC Panel
for ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 12.73 2,400.00 30,552.00 - - - - - -
88.0 Waterproofing membrane on roof - - -
Providing and laying
waterproofing membrane on roof
all complete as per design,
drawing, specification and
instruction of site engineer. m2 27.73 500.00 13,865.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-100 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
89.0 Flooring works - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 11.02 800.00 8,816.00 - - - - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
90.0 including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 13.72 400.00 5,488.00 - - - - - -
Providing and laying of 25 mm
thick Telia tile paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
91.0 including curing on floor in
perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 8.20 3,400.00 27,880.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-101 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and laying of 50mm
thick stone slab of approved
thickness and color on floor in
perfect line and level including
92.0 joint sealing of joint, grinding,
polishing all complete as per
design, drawing, specification and
the instrution of the site
engineer. m2 2.84 7,000.00 19,880.00 - - - - - -
Providing and laying of flagstone
of approved thickness and color
on floor in perfect line and level
93.0 including joint sealing of joint,
grinding, polishing all complete
as per design, drawing,
specification and the instrution of
the site engineer. m2 29.87 1,400.00 41,818.00 - - - - - -
Bells on roof:- Providing and
94.0 fixing design, drawing,
specification and instruction of
nos 36.00 6,000.00 216,000.00 - - - - - -
site engineer

Contractor Prepared By Checked By Approved By


Pages-102 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
MANDAP - - -
Earthwork - - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
95.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 9.72 1,000.00 9,720.00 9.72 9,718.00 9.72 9,718.00 - -
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
96.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 5.62 300.00 1,686.00 5.61 1,683.60 5.61 1,683.60 - -

Contractor Prepared By Checked By Approved By


Pages-103 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
97.0 Soling works - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 0.26 3,000.00 780.00 0.27 804.00 0.27 804.00 - -
lift.
Providing and laying a single
layer flat brick soling on floor for
preparation of P.C.C. in which
98.0 joints should be packed by sand
to the required levels all
complete as per drawings,
specifications and the instructions
of the Engineer. m2 25.65 700.00 17,955.00 25.65 17,955.00 25.65 17,955.00 - -

Contractor Prepared By Checked By Approved By


Pages-104 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
99.0 PCC Works - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 3.61 10,000.00 36,100.00 3.61 36,075.00 3.61 36,075.00 - -
100.0 STONE PILLAR WORKS - -

Providing and placing stone pillar


above PCC in cement mortar
(1:4) all complete as per
drawings, specifications and
instruction of the engineer. m3 0.59 7,000.00 4,130.00 0.58 4,076.80 0.58 4,076.80 - -
101.0 Wall Works - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 7.74 15,000.00 116,100.00 7.74 116,100.00 7.74 116,100.00 - -

Contractor Prepared By Checked By Approved By


Pages-105 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
102.0 WOODEN WORKS - -
Providing, fabricating & fixing
salwood(agrath) wooden pillars
fixing in stone pillar with joint
properly finished in perfect line,
level along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction of the Engineer.. m3 0.86 250,000.00 215,000.00 0.86 215,090.00 0.86 215,090.00 - -
Engraving designs on wooden
pillars properly finished along
with all necessary accessories
103.0 along with wood primer all
complete as per design, drawing,
specification and instruction of
the Engineer.. nos. 7.00 25,000.00 175,000.00 - - - - - -
Providing, fabricating & fixing
salwood(agrath) wooden beams,
meths, etc. fixing in pillar with
joint properly polished and
104.0 finished in perfect line, level
along with all necessary
accessories along with wood
primer all complete as per
design, drawing, specification and
instruction m3 1.13 250,000.00 282,500.00 1.13 282,856.56 1.13 282,856.56 - -

Contractor Prepared By Checked By Approved By


Pages-106 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
105.0 Roofing works - -
Providing and placing waterproof
plywood for roofing including
transportation, cutting,
connecting and placing in
position with nails, hooks, etc. all
complete as per drawings,
specifications and instruction. m2 27.73 700.00 19,411.00 27.73 19,410.03 27.73 19,410.03 - -
Providing and placing ikotile for
roofing including transportation,
106.0 cutting, connecting and placing in
position with nails all complete as
per drawings, specifications and
instruction. m2 27.73 2,500.00 69,325.00 27.73 69,321.56 - - 27.73 69,321.56
107.0 Plastering and Painting Works - - -
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on brick walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 13.72 600.00 8,232.00 - - - - - -
108.0 False ceiling works - - -
Providing and placing false ceiling
with cement board including the
channels to drop false ceiling all
complete as per design, drawing,
specification and instruction of
site engineer. m2 9.00 2,500.00 22,500.00 - - - - - -
Providing and applying fire
retardant paint of approved
manufacturer and shade over
primer of approved manufacturer
as per manufacturer's
specifications to the surface of
109.0 false ceiling all complete as per
drawings, specifications and
instruction. The rates shall
include for surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
m2 9.00 15,000.00 135,000.00 - - - - - -
approved by the Engineer.
110.0 WPC Panel for ceiling - - -
Providing and laying WPC Panel
for ceiling all complete as per
design, drawing, specification and
instruction of site engineer. m2 18.00 1,500.00 27,000.00 - - - - - -
111.0 Waterproofing membrane on roof - - -

Contractor Prepared By Checked By Approved By


Pages-107 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and laying
waterproofing membrane on roof
all complete as per design,
drawing, specification and
instruction of site engineer. m2 27.73 600.00 16,638.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-108 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
112.0 Flooring works - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 11.02 800.00 8,816.00 - - - - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
113.0 including trowelling and finishing
in smooth surface on roof as per
design, drawing, specification and
instruction of site engineer. m2 13.72 400.00 5,488.00 - - - - - -
Providing and laying of 25 mm
thick Telia tile paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
114.0 including curing on floor in
perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 8.20 3,500.00 28,700.00 - - - - - -
Providing and laying of 50mm
thick stone slab of approved
thickness and color on floor in
perfect line and level including
115.0 joint sealing of joint, grinding,
polishing all complete as per
design, drawing, specification and
the instrution of the site
engineer. m2 2.84 7,000.00 19,880.00 - - - - - -
Providing and laying of flagstone
of approved thickness and color
on floor in perfect line and level
116.0 including joint sealing of joint,
grinding, polishing all complete
as per design, drawing,
specification and the instrution of
the site engineer. m2 16.26 1,400.00 22,764.00 - - - - - -
Bells on roof:- Providing and
117.0 fixing design, drawing,
specification and instruction of
nos 36.00 10,000.00 360,000.00 - - - - - -
site engineer

Contractor Prepared By Checked By Approved By


Pages-109 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Landscape, drainage and
Boundary wall works - - -
118.0 Site Clearance Work - - -
Clearing and grubbing the site for
construction by removing 150mm
thick top soil including bushes,
small trees, levelling of undulated
ground, shorting and
stacking/storing selected top soil
for reuse in landscaping works,
disposing unsuitable materials
from site, etc., all complete as
per drawings, specifications and
instructions of the Engineer. m2 5,893.42 60.00 353,605.20 5,750.00 345,000.00 5,750.00 345,000.00 - -
Dismantling of existing structures
by manual means comprising of
cement concrete works including
scaffolding wherever necessary,
119.0
sorting the dismantled material,
disposal and stacking materials
with all lifts and leads of
1000meters m3 10.55 1,000.00 10,550.00 10.51 10,508.75 10.51 10,508.75 - -
Dismantling of existing blocks by
manual means comprising of
brick works including scaffolding
120.0 wherever necessary, sorting the
dismantled material, disposal and
stacking materials with all lifts
and leads of 1000meters m2 304.00 1,000.00 304,000.00 297.25 297,250.00 297.25 297,250.00 - -
Dismantling of barbed wire
fencing includong posts,
foundation concrete, backfilling of
121.0 pit by manual means including
disposal and stacking materials
with all lifts and leads of
1000meters rm 436.10 1,000.00 436,100.00 418.00 418,000.00 418.00 418,000.00 - -

Dismantling of steel including


122.0
dismembering by manual means
kg 968.40 120.00 116,208.00 638.10 76,572.00 968.40 116,208.00 (330.30) (39,636.00)
Dismantling of granular courses
pavements and disposal of
123.0 dismantled materials upto a lead
of 1000 m, stacking materials all
by manual means m3 102.00 1,000.00 102,000.00 78.68 78,681.00 78.68 78,681.00 - -
Earthwork - -
Earthwork in excavation for
foundation along with dewatering
water simultaneously till
completion of foundation in all
types of soil including existing
124.0 debris & brick bats of old
structure if any up to 25 ft.depth
below as per the design, drawing,
specification & instructions of
consultant and his authorized
representative. m3 1,797.24 250.00 449,310.00 1,410.34 352,584.21 1,210.16 302,541.19 200.17 50,043.02

Contractor Prepared By Checked By Approved By


Pages-110 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Filling with earth or mixed soil
stacked at site in 150mm thick
layer on retaining walls including
125.0 watering, ramming, consolidation
and dressing as per drawing,
specifications and satisfaction to
site engineer all complete. m3 216.67 300.00 65,001.00 216.67 65,001.00 216.67 65,001.00 - -
Soling works - -
Providing and laying uncoursed
hand packed Dry Rubble Stone
soling of 150mm on landscape
works with out any special
dressing of stone including filling
interstices with suitable quarry
waste or stone chips or quarry
sand, watering, compacting using
126.0
appropriate mechanical
compaction means with all
contractors materials, handling,
placing etc. all complete as per
drawings, specifications and
instruction of the Engineer. The
complete item including all lead &
m3 296.93 3,000.00 890,790.00 305.36 916,068.65 267.42 802,249.87 37.94 113,818.78
lift.
Providing and laying a single
layer flat brick soling on drainage
works on lanscape for preparation
of P.C.C. in which joints should be
127.0
packed by sand to the required
levels all complete as per
drawings, specifications and the
instructions of the Engineer. m2 1,621.11 700.00 1,134,777.00 677.61 474,324.16 563.72 394,602.91 113.89 79,721.25

Contractor Prepared By Checked By Approved By


Pages-111 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
128.0 PCC Works - -
PCC (1:3:6) M10 for flooring on
landscape and drainage works in
perfect line and level with proper
compaction and curing at least 15
days including supply of materials
all complete as per design,
drawing, specification and
satisfaction to site engineer. m3 384.15 10,000.00 3,841,500.00 304.74 3,047,432.12 235.77 2,357,720.75 68.97 689,711.37
129.0 RCC Works - -

Concrete Works for RCC (1:1.5:3)


M20 on landscape and drainage
works in perfect line and level
with proper compaction and
curing for at least 15 days
including supply of materials all
complete as per design, drawing,
specification and satisfaction to
site engineer.
m3 15.87 16,000.00 253,920.00 16.97 271,492.00 - - 16.97 271,492.00
130.0 Centering and Shuttering Work - -
Centering and shuttering with
approved 19mm waterproofing
plywood for drain works at any
level with necessary mild steel
propping, scaffolding, staging
supporting. Cutting holes for
utilization works and removal of
formwork and lead upto 30 m etc
all complete as per instruction,
specification and drawing. m2 440.35 600.00 264,210.00 629.47 377,684.70 371.55 222,932.40 257.92 154,752.30
131.0 - -
Fe500 Reinforcement in PCC
including cutting, bending and
placing in position all complete as
per design, drawing, specification
and satisfaction to site engineer. mt 11.30 120,000.00 1,356,000.00 5.66 678,942.22 3.67 440,012.23 1.99 238,929.99

Contractor Prepared By Checked By Approved By


Pages-112 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
132.0 Wall Works - -
STONE MASONRY WORKS IN
CEMENT MORTAR
Providing and laying Random
Rubble stone masonry works on
retaining walls in cement mortar
(1:4) including providing
through/bond stone at required
interval including providing
required scaffolding, preparing
mortar and construction of wall to
any height and shape all
complete as per drawings,
specifications and instruction of
the engineer. m3 808.10 7,000.00 5,656,700.00 808.10 5,656,669.55 808.10 5,656,669.55 - -
Brick Masonry Works in
Superstructure ( 1 : 4 c/s )
Providing and laying first class
chimney fired brick of one or
more brick thick wall in cement
mortar 1:4 (1 cement : 4coarse
sand) in landscape works in all
133.0 heights and level including the
cost of single or multi stage
scaffolding, soaking bricks,
curing, raking joints, provision for
recesses, openings, toothing etc.,
all complete as per drawing,
specifications and instructions of
the Engineer.. m3 44.64 15,000.00 669,600.00 28.34 425,163.75 17.84 267,562.50 10.51 157,601.25

Contractor Prepared By Checked By Approved By


Pages-113 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
PIPEWORKS FOR
WEEPHOLE AND
134.0
GEOTEXTILE WORKS FOR
- - - -
RETAINING
Providing WALLSstructural
and placing
steel tested grade Fe-250
equivalent NS, for structural work
including
transportation,cutting,connecting
and placing in position, treated
with two coat of anticorrosive
paints, all complete as per
drawings,specifications and
instruction.(80mmdi GI medium rm 246.14 700.00 172,298.00 244.32 171,024.00 244.32 171,024.00 - -
duty)
Providing and placing of Geo
Textile on retaining wall and
135.0
french drain as per the instruction
m2 3,107.32 80.00 248,585.60 1,536.00 122,880.00 1,536.00 122,880.00 - -
of engineer and Painting
Plastering
136.0 - - -
Works
Providing and laying 12.5mm
thick plaster upto required line
and perfect smooth level as per
site condition in 1:4 cement sand
mortar on internal walls including
necessary scaffolding , cleaning &
wetting the surface, packing of
joints and proper curing for 15
days as per drawing, specification
and instruction all complete. m2 1,167.64 600.00 700,584.00 310.13 186,076.66 70.77 42,462.00 239.36 143,614.66
Flushing pointing on the exterior
Brick wall of gate structure by
cement sand mortar of ratio 1:2
all complete as per drawings,
specificatios and instruction. The
rates shall include for scraping,
137.0
washing the surface with water,
surface preparation,
scaffolding,etc.,all complete as
per the manufacturer's
recommendations and as
approved by the Engineer.
m2 2.35 400.00 940.00 - - - - - -
Providing and applying two or
more coats of exterior plastic
emulsion paint of approved
manufacturer and shade over a
coat of alkali resistant cement
primer of approved manufacturer
as per manufacturer's
specifications on exterior plaster
138.0 all complete as per drawings,
specifications and instruction.
The rates shall include for
scraping, washing the surface
with water, surface preparation,
scaffolding etc., all complete as
per the manufacturer's
recommendations and as
approved by the Engineer. m2 230.24 300.00 69,072.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-114 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and laying 20mm. thick
Cement Water Bead (Pani Patti)
finished perfectly smooth
139.0 including necessary scaffolding,
raking the joint, wetting the
surface and curing all complete
work rm 112.45 400.00 44,980.00 - - - - - -
140.0 Flooring Work - - -
Providing and laying minimum of
25mm and in average of 40 mm
thick Screed of 1:3:3 (Cement
Sand Chip) on thoroughly
chipped floor (to remove laitance,
caked mortar, loose sand, dirt
etc.) all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 38.08 800.00 30,464.00 - - - - - -
3mm cement punning in 1:1 c/s
mortar in perfect line and level
including trowelling and finishing
141.0 in smooth surface on risers of
steps on landscape works as per
design, drawing, specification and
instruction of site engineer. m2 1,123.24 400.00 449,296.00 - - - - - -
Providing and laying of flagstone
of approved thickness and color
on landscape works in perfect line
and level including joint sealing
142.0
of joint, grinding, polishing all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 1,668.10 1,400.00 2,335,340.00 - - - - - -
Providing and laying of 25 mm
thick Telia brick paving work in
(1:2) surki mortar and pointing
the joints with 1:1 C/S mortar
143.0 including curing on landscape
works in perfect line and level all
complete as per design, drawing,
specification and the instrution of
the site engineer. m2 183.41 3,400.00 623,594.00 - - - - - -
Providing and laying stone slab of
approved quality and color over
PCC on pavements including
cement mortar of 1:3(cement
sand) in perfect line, level
finished with necessary pointing
144.0 in joints sloped towards drain line
all complete as per design,
drawing, specification and the
instrution of consultant and his
authorized representative.
Samples should be approves by
consultant. m2 13.36 7,000.00 93,520.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-115 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Providing and laying of brick
pavement of approved thickness
and color on landscape works in
perfect line and level including
145.0 joint sealing of joint, grinding,
polishing all complete as per
design, drawing, specification and
the instrution of the site
engineer. m2 463.64 700.00 324,548.00 - - - - - -
Cement skirting works:-Providing
and laying cement punning
skirting on rammed earth walls
inside rooms in perfect line and
146.0 level with grouting all complete
as per design, drawing ,
specification and instruction of
consultant and his authorized
representative rm 6.94 600.00 4,164.00 - - - - - -
Waterproofing works:- Providing
and applying water proof coating
work necessary on cement
punning area after preparing the
147.0
surface all complete work as per
design, drawing , specification
and instruction of consultant and
his authorized representative rm 6.94 500.00 3,470.00 - - - - - -
148.0 FRENCH DRAIN WORKS - - -
Providing and laying subsurface
drain with perforated pipe of
100mm internal diameter of PVC,
closely joined perforations
ranging from 3mm to 6mm
depending upon size of material
surrounding the pipe with 150mm
bedding below the pipe and
300mm cushion above pipe, as
per drawing and specification. rm 202.00 800.00 161,600.00 120.00 96,000.00 120.00 96,000.00 - -

Contractor Prepared By Checked By Approved By


Pages-116 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
PEBBLES FOR COVERED
149.0
DRAIN AND TAP - - - -
Providing and laying pebbles for
drain cover and stone tap on
landscape works as per design,
drawing, specification and
instruction of site engineer. m3 1.97 10,000.00 19,700.00 - - - - - -
STEEL GRATING FOR
150.0 - -
DRAINS
Providing and laying light duty
iron channel grates on drains in
perfect line and level including
finishing in smooth surface on
landscape as per design, drawing,
specification and instruction of
site engineer. kg 1,165.71 250.00 291,427.50 - - - - - -
Supplying and fitting of railing
with 50mm vertical MS circular
pipe of 500mm height at 2m
151.0 interval and 50mm black pipe
handrail including welding, joints,
and prmer painting asper drawing
and instructions all complete. m2 29.16 6,500.00 189,540.00 - - - - - -
GAMALA POTS ON
LANDSCAPE - -
Providing, molding and placing
gamala pots on landscape as per
design, drawing, specification and
instruction of site engineer. - - -
152.0 gamala 1 nos 8.00 1,000.00 8,000.00 - - - - - -
153.0 gamala 2 nos 5.00 1,000.00 5,000.00 - - - - - -
154.0 gamala 3 nos 2.00 1,000.00 2,000.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-117 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
155.0 gamala 4 nos 1.00 1,000.00 1,000.00 - - - - - -
156.0 gamala 5 nos 3.00 1,000.00 3,000.00 - - - - - -
157.0 gamala 6 nos 10.00 1,000.00 10,000.00 - - - - - -
158.0 gamala 7 nos 6.00 1,000.00 6,000.00 - - - - - -
159.0 Wooden railing works - - -
Providing and placing seasoned
laminated timber rail on openings
of gates including transportation,
cutting, connecting and placing in
position with wood primer and
paint, all complete as per
drawings, specifications and
instruction. m2 4.27 2,500.00 10,675.00 - - - - - -
160.0 Wooden fascia works - - -
Providing and placing 25mm thk.
Treated hardwood fascia board
on roof including transportation,
cutting, connecting and placing in
position with wood primer and
paint, all complete as per
drawings, specifications and
instruction. m2 6.93 12,000.00 83,160.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-118 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Waterproof plyboard on
161.0 - - -
roof
Providing and laying 10mm
waterproof plywood with one side
veneer in perfect line and level
above adobe insulation all
complete as per design, drawing,
specification and instruction of
consultant and his authorized
representative. Samples should
be approved by consultant. m2 30.74 700.00 21,518.00 - - - - - -
162.0 Iko-tile roofing works - - -
Providing and laying iko-tile
nailed and stacked over plyboard
on sloped roofs in perfect line and
level all complete as per design,
drawing, specification and
instruction of consultant and his
authorized representative. m2 30.74 3,500.00 107,590.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-119 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
163.0 Structural steel Works - - -
Providing and placing structural
steel tested grade Fe-250
equivalent NS, for structural work
on gate roof including
transportation, cutting,
connecting and placing in
position,treated with two coat of
anticorrosive paints, all complete
as per drawings, specifications
and instruction. kg 745.43 250.00 186,357.50 - - - - - -
Providing and fabricating MS steel
gate and fixing in entrance
polished and finished in perfect
164.0
line, level as per design, drawing,
specification and instruction all
complete. kg 186.69 250.00 46,672.50 - - - - - -
Supplying and fitting of railing
with M.S. pipe including welding,
165.0 joints and primer painting as per
drawing and instructions all
complete m2 61.00 5,000.00 305,000.00 61.00 304,992.25 61.00 304,992.25 - -
166.0 Shera board works - -
Providing, fabricating & fixing
shera board works on gate
finished in perfect line, level
along with all necessary
accessories all complete as per
design, drawing, specification and
instruction m2 2.60 2,500.00 6,500.00 - - - - - -
Supplying and Fixing Indian
pattern C.P. valves with wall
167.0
flange Including c.p. nipple all
nos 6.00 2,000.00 12,000.00 - - - - - -
complete set.
Supplying and Fixing CP Bib Cock
168.0 with wall flange,cp nipple all
complete set nos 3.00 4,000.00 12,000.00 - - - - - -
Supplying and Fixing 20 mm
CPVC pipe with pipe Jointing
materials (Tee, Elbow, Union),
making holes, clips and vent cowl
169.0
all complete set as per
specification and instruction.
(Mangalam, Panchakanya ,
Prince,Supreme or Equivalent. ) rm 125.88 800.00 100,704.00 - - - - - -
Providing and fixing PVC water
tank- brand Nepatop/Hilltake/
Panchakanya or equivalent, of
capacity 2000 ltrs. finished in
170.0
perfect line, level along with all
necessary accessories all
complete as per design, drawing,
specification and instruction nos 2.00 35,000.00 70,000.00 - - - - - -
PLANTATION WORKS - - - -
Planting dubo grass on site
including digging, planting hole
171.0
10-20 cm depth using a metal rod
or hardwood peg. sqm 2,800.00 600.00 1,680,000.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-120 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Planting rooted tree stump
cutting and bare root seedlings,
including pitting, transplanting,
composting and mulching, pit
size 10cm diameterx depth
compost volume of pit mix with
original soil.

Specifications for trees(3-4ft):-


Sami (Ficus benjamina)
Bougainvillea (Bougainvillea
172.0 glabra)
Mango (Magnifera Indica)
Neem (Azadirachta indica)
Parijat ((Nyctanthes arbor tristis)
Jasmine (Jasminum polyanthum)
Ashoka (Saraca asoca)
Supari (Areca catechu)
Bamboo (Bambusa vulgaris)
Gulmohar (Delonix regia)
Banana (Musa paradiscata)
Willow (Salix babylonica)
no 147.00 1,000.00 147,000.00 - - - - - -
Planting shrubs including digging,
173.0
planting hole, etc. all complete. ls 1.00 2,000.00 2,000.00 - - - - - -

- - - -
LED strip light warm white
220V with soft bending
diffuser, philips
equivalent, 72 LED per
meter or equivalent for
174.0
bright and uniform
lighting, complete set with
fitting components and
installation, with junction rm 45.00 2,000.00 90,000.00 - - - - - -
box if necessary
LUMINAIRES ( FIXTURES) Outdoor
LED based Luminaries set all
complete. LEGERO, GE, Philips or
equivalent
7W Garden Spike, Anthracite,
175.0
Warm White,Floor Lamp, 220V,
warm white, IP 65 or above,
complete set with fitting
components and installation, with
junction box if necessary set 18.00 1,500.00 27,000.00 - - - - - -
30W LED outdoor wall washer
(Tubelight for indirect lighting),
176.0 3000K, IP 65 and above, 220 V,
complete set with fitting
components and installation set 16.00 1,500.00 24,000.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-121 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
LUMINAIRES ( FIXTURES) Outdoor
LED based Luminaries set all
complete. LEGERO, GE, Philips or
equivalent,
6W 800lm Sleek small LED Track
177.0
Lighting, 220V, warm white, IP 65
or above, complete set with
fitting components and
installation, with junction box if
necessary set 24.00 1,500.00 36,000.00 - - - - - -
Up down Sconce light 10W
equivalent IP 65 and
above,2700K/3000K warm white,
178.0
complete set with fitting
components and installation, with
junction box if necessary set 4.00 1,500.00 6,000.00 - - - - - -
Wall recessed 12 inch to 24 inch
length, 10W equivalent (600-
800lm) LED warm white light,
179.0 220V, IP 65 or above, complete
set with fitting components and
installation, with junction box if
necessary set 61.00 2,000.00 122,000.00 - - - - - -
Street Light / Flood Light Philips
BGP704 equivalent 220V, 10000
lumens, warm white luminaires
with mount and all other
180.0
components complete set with
fitting components and
installation, with junction box if
necessary set 2.00 2,000.00 4,000.00 - - - - - -
12W ceiling recessed Warm white
luminaire set, 220V, complete set
181.0 with fitting components and
installation, with junction box if
necessary set 1.00 3,500.00 3,500.00 - - - - - -
9W directional LED ceiling
recessed light track light, all
182.0
complete,with junction box if
set 2.00 3,500.00 7,000.00 - - - - - -
necessary
Floor recessed (ground well) LED
luminaire 12 W, Warm white
183.0 220V, IP 65 or above, complete
set with fitting components and
installation set 14.00 1,500.00 21,000.00 - - - - - -
Post top LED warm white
luminaire 30W, 220V with
heritage style cast iron lamp post
of minimum 7 feet height from
184.0 ground level (to be bought in
consultation with architecture),
complete set with fitting
components and installation, with
junction box if necessary set 14.00 2,000.00 28,000.00 - - - - - -
Street Light Philips BGP704
equivalent 220V, 10000 lumens,
warm white luminaires with
185.0
mount and all other components
complete set with fitting
components and installation set 2.00 3,000.00 6,000.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-122 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
किताबको ठेक्कामा स्वीकृत
मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
Installation, testing and
commissioning of 10 sq mm 2C,
armored copper cable from
existing point to distribution
186.0
board, underground via 32 mm
HDPE pipe, complete set with
fitting components and
installation Rm 40.00 1,200.00 48,000.00 - - - - - -
Electrical Outdoor distribution
box, Waterproof sealed with IP
rating of IP66 or above, made
with stainless steel with stand
187.0 kept 2 feet above ground level,
embedded door with required
copper bush, installation and
fitting cost of MCB ans switches
all included set 1.00 60,000.00 60,000.00 - - - - - -
Installation, testing and
188.0
comissioning of 16 way SPN DB set 1.00 5,000.00 5,000.00 - - - - - -
Installation testing and
189.0 commissioning of 6 A SP MCB, all
complete set 12.00 600.00 7,200.00 - - - - - -
Installation testing and
190.0 commissioning of 16 A SP MCB,
all complete set 2.00 600.00 1,200.00 - - - - - -
Installation testing and
191.0 commissioning of 32 A DP MCB,
all complete set 1.00 600.00 600.00 - - - - - -
Installation testing and
192.0 comissioning of 32 A DP Switch,
set 1.00 2,000.00 2,000.00 - - - - - -
all complete
Weatherproof Outdoor Junction
Box, IP 68 or above rated, JB with
193.0
option for sealing the incoming
and outgoing 2c wire set 30.00 2,000.00 60,000.00 - - - - - -
3*3 metal (Stainless Steel)
194.0 junction box with rubber gasket
for weather proofing set 10.00 3,500.00 35,000.00 - - - - - -
9m Pole for electric lighting single
195.0
arm set 2.00 75,000.00 150,000.00 - - - - - -
9m double arm pole for electrc
196.0
lighting set 1.00 15,000.00 15,000.00 - - - - - -
Installation, testing, and
commissioning of 2.5 sq mm 2C,
armored copper cable from the
197.0
distribution board to, light points
underground via 32 mm HDPE
pipe, all complete Rm 1,220.00 800.00 976,000.00 - - - - - -
Chemical Earthing
Supply, Installation, testing and
commissioning of Chemical
198.0
Earthing System with including all
material and accessories to all
complete the works nos 1.00 50,000.00 50,000.00 - - - - - -
Supply , installation & testing of 8
199.0 SWG bare copper conductor from
Main panel to earth test pit Rm 10.00 800.00 8,000.00 - - - - - -

Contractor Prepared By Checked By Approved By


Pages-123 of 333
योजनाको नामः Construction of Aarati Site at Hanuman Mandir बिलको क्रम सङ्ख्याः
योजना कार्यान्वयन हुने स्थानः Ward no.-2, Biratnagar कार्य आदेश मितिः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV काम सम्पन्न गर्नु पर्ने मितिः
ठेक्का पट्टाको सङ्केतः BMC/MOR/NCB/W-16/2079/080 म्याद थप/भेरिएसन मितिः
नापी किताब नं 5 काम सम्पन्न भएको मितिः
ठेक्का सम्बन्धी बिल-Fifth
सार्वजनि
नापी कामको विवरण परिमाण सूची (BOQ) बमोजिमको भेरिएसन भएकोमा सो बमोजिमको हालसम्म अध्यावधिक काम भएको अघिल्लो बिलमा चढेको हाल भएको काम
ककिताबको ठेक्कामा स्वीकृत
निर्माण मुख्य र सहायक क्रियाकलाप
पाना नं एकाइ परिमाण स्वीकृत दर जम्मा रकम परिमाण दर जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम परिमाण जम्मा रकम
कार्य१ २ 3 4.00 5.00 6.00 7.00 8.00 9.00 10.00 ११=५x१० 12.00 १३=५x१२ १४=१०-१२ १५=८-१०
सम्पन्न
भइसकेपछि
क. जम्मा रकम 35,093,919.49 - 18,347,964.52 16,237,214.08 2,110,750.44
प्रत्येक
ख. Physical Adjustment - 1,026,513.59 1,026,513.59
ठेकदारबा
ट यही ग. 13% मु.अ.कर 4,562,209.53 - 2,518,682.15 2,244,284.60 274,397.56
ढाँचामा घ.Provisional Sum Amount 155,000.00 120,000.00 120,000.00 -
बिल ङ. कुल जम्मा (क+ख+ग+घ) 39,811,129.03 - 22,013,160.26 19,628,012.27 2,385,148.00
प्रस्तुत
गराउनुप
र्दछ ।
यो बिलबमोजिम काम भएको जम्मा रूः हाल काम भएको बाँकी दिनुपर्ने रूः 2,385,148.00 यस बिल बमोजिम गरिएको भुक्ता
ठेकेदार
अघिल्लो बिलसम्म भुक्तानी भएको रूः कट्टा गर्नु पर्ने रू भौचर नं:
ले गरेका भुक्तानी बिलको क्रम सङ्ख्याः
अघिल्लो क. मोबिलाइजेसन पेस्की रूः भुक्तानी मिति:
काममा र भुक्तानी बिलको भौ.नं.
अघिल्लो ख. मालसामानको पेस्की रूः भुक्तानी रकम रू
सो बापत ग. मेसिनरी औजारको बहाल रूः
ठेकदारला
घ. अग्रीम आय कर रकम रूः
र्इ भएको
ङ. धरौटी रकम रूः
हिसाब
समेत गरी च. अन्य कट्टी गर्ने पर्ने रकम रूः
अभिलेख खुद दिनु पर्ने रकम रूः
राख्न यो
फाराम तयार गर्नेको सहीः जाँच गर्नेको सहीः
तर्जुमा निर्माण व्यवसायीको सही: नाम नाम
गरिएको नाम: दर्जाः दर्जाः
हो । पदः मितिः मितिः
निर्माण मितिः
कार्यको
ठेक्काको
उद्देश्य यो बिलबमोजिम जम्मा रू .....................अक्षरमा ....................................................................................को चेक नं: ........................बुझिलिए ।
बिल तयार
गर्नु

Contractor Prepared By Checked By Approved By


Pages-124 of 333
म.ले.प.फारम नं: ५०४
राटनगर महानगरपालिका
साबिकको फारम नं: १६८
र्यापालिकाको कार्यालय
कार्यालय कोड नं.:
का सम्बन्धी बिल-FIFTH

4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

Contractor Prepared By Checked By Approved By


Pages-125 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

1.01

Contractor Prepared By Checked By Approved By


Pages-126 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

0.01

Contractor Prepared By Checked By Approved By


Pages-127 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

(0.00)

0.60

Contractor Prepared By Checked By Approved By


Pages-128 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.01

0.01

Contractor Prepared By Checked By Approved By


Pages-129 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.01

6.00

Contractor Prepared By Checked By Approved By


Pages-130 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

Contractor Prepared By Checked By Approved By


Pages-131 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

Contractor Prepared By Checked By Approved By


Pages-132 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

43.18

43.18

1.09

(27.95)

Contractor Prepared By Checked By Approved By


Pages-133 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

43.24

43.24

0.88

0.00

Contractor Prepared By Checked By Approved By


Pages-134 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.83

0.00

Contractor Prepared By Checked By Approved By


Pages-135 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

0.00

0.66

Contractor Prepared By Checked By Approved By


Pages-136 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

0.00

Contractor Prepared By Checked By Approved By


Pages-137 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

0.00

7.00

0.00

0.00

Contractor Prepared By Checked By Approved By


Pages-138 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

Contractor Prepared By Checked By Approved By


Pages-139 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

1.09

36.15

Contractor Prepared By Checked By Approved By


Pages-140 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

36.18

36.18

42.30

36.18

Contractor Prepared By Checked By Approved By


Pages-141 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

10.48

Contractor Prepared By Checked By Approved By


Pages-142 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

Contractor Prepared By Checked By Approved By


Pages-143 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

5.82

0.91

Contractor Prepared By Checked By Approved By


Pages-144 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

77.62

1.36

Contractor Prepared By Checked By Approved By


Pages-145 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

2.27

7.00

2.29

77.62

Contractor Prepared By Checked By Approved By


Pages-146 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.08

8.24

21.29

21.29

55.80

Contractor Prepared By Checked By Approved By


Pages-147 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

77.62

55.80

Contractor Prepared By Checked By Approved By


Pages-148 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

77.62

77.62

9.24

Contractor Prepared By Checked By Approved By


Pages-149 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

3.96

0.00

0.00

Contractor Prepared By Checked By Approved By


Pages-150 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

Contractor Prepared By Checked By Approved By


Pages-151 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

0.01

7.85

Contractor Prepared By Checked By Approved By


Pages-152 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

7.00

(0.00)

Contractor Prepared By Checked By Approved By


Pages-153 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

0.00

13.72

16.00

Contractor Prepared By Checked By Approved By


Pages-154 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

16.00

12.73

27.73

Contractor Prepared By Checked By Approved By


Pages-155 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

11.02

13.72

8.20

Contractor Prepared By Checked By Approved By


Pages-156 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

2.84

29.87

36.00

Contractor Prepared By Checked By Approved By


Pages-157 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

0.01

Contractor Prepared By Checked By Approved By


Pages-158 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.01)

Contractor Prepared By Checked By Approved By


Pages-159 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

0.01

Contractor Prepared By Checked By Approved By


Pages-160 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(0.00)

7.00

(0.00)

Contractor Prepared By Checked By Approved By


Pages-161 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

0.00

13.72

9.00

9.00

18.00

Contractor Prepared By Checked By Approved By


Pages-162 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

27.73

Contractor Prepared By Checked By Approved By


Pages-163 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

11.02

13.72

8.20

2.84

16.26

36.00

Contractor Prepared By Checked By Approved By


Pages-164 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

143.42

0.04

6.75

18.10

330.30

23.32

386.90

Contractor Prepared By Checked By Approved By


Pages-165 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

(8.43)

943.50

Contractor Prepared By Checked By Approved By


Pages-166 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

79.41

(1.10)

(189.12)

5.64

Contractor Prepared By Checked By Approved By


Pages-167 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

0.00

16.30

Contractor Prepared By Checked By Approved By


Pages-168 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

1.82

1,571.32

857.51

2.35

230.24

Contractor Prepared By Checked By Approved By


Pages-169 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

112.45

38.08

1,123.24

1,668.10

183.41

13.36

Contractor Prepared By Checked By Approved By


Pages-170 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

463.64

6.94

6.94

82.00

Contractor Prepared By Checked By Approved By


Pages-171 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

1.97

1,165.71

29.16

8.00
5.00
2.00

Contractor Prepared By Checked By Approved By


Pages-172 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00
1.00
3.00
10.00
6.00

4.27

6.93

Contractor Prepared By Checked By Approved By


Pages-173 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

30.74

30.74

Contractor Prepared By Checked By Approved By


Pages-174 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

745.43

186.69

0.00

2.60

6.00

3.00

125.88

2.00

2,800.00

Contractor Prepared By Checked By Approved By


Pages-175 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

147.00

1.00

45.00

18.00

16.00

Contractor Prepared By Checked By Approved By


Pages-176 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

24.00

4.00

61.00

2.00

1.00

2.00

14.00

14.00

2.00

Contractor Prepared By Checked By Approved By


Pages-177 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

40.00

1.00

1.00

12.00

2.00

1.00

1.00

30.00

10.00

2.00

1.00

1,220.00

1.00

10.00

Contractor Prepared By Checked By Approved By


Pages-178 of 333
4.00
10/23/2079
10/30/2081
-
-
का सम्बन्धी बिल-Fifth
कैफियत

बाँकी परिमाण
16.00 17.00

यस बिल बमोजिम गरिएको भुक्तानी

स्वीकृत गर्नेको सहीः


नाम
दर्जाः
मितिः

Contractor Prepared By Checked By Approved By


Pages -179 of 333
म.ले.प.फारम नं:
५०३
बिराटनगर महानगरपालिका साबिकको फारम
नगर कार्यापालिकाको कार्यालय नं:१७१
कार्यालय कोड नं.:
FIFTH MEASUREMENT BILL
पाना नं:
नापी नं: ५ सम्झौता विवरणः
निर्माण व्यवसायीको नामः ABHIYAN / DIBISHA JV
सम्झौता भएको मितिः 10/23/2079
BMC/MOR/NCB/W-16/2079/080
ठेक्का नं: कार्य सम्पन्न गर्नुपर्ने मि 10/30/2081
निर्माण कConstruction of Aarati Site at Hanuman Mandir कार्य आदेश मितिः 10/23/2079
कार्य स्थWard no.-2, Biratnagar नापी लिइएको मिति 3/17/2081
कार्य सम्पन्न मितिः

FIFTH MEASUREMENT SHEET


अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
A General works
General works:Provide Insurance of works,
1 materials,construction equipments against accident to 0.00
workforce including third party 1.00 1.00 PS 1.00 0.00 100000.00
Provide & Maintain protective safety Equipments
2 including Hats, Gloves, Googles, Dust mask, First Aid 0.00
Kit with medicine for work force 1.00 - PS 1.00 0.00 15000.00
Lab test of the construction materials as rebar cement,
3 0.00
brick, as per specified by site incharge 1.00 1.00 PS 1.00 0.00 5000.00
Provide & Installation of Project Information Board
1 0.00
1.2*.90 m Size as to Complete the Work as Specified 1.00 1.00 No. 1.00 0.00 10000.00
PAVILION I -
2 Earthwork

Earthwork in excavation for foundation along with


dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
1.00 2.25 1.00 0.90 cum 2.03
1.00 2.30 1.00 0.90 cum 2.07
1.00 1.70 0.85 0.90 cum 1.30
1.00 3.70 1.30 0.90 cum 4.33
1.00 1.90 0.90 0.90 cum 1.54

Contractor Prepared By Checked By Approved By


Pages -180 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
2.00 0.90 0.90 0.60 cum 0.97
1.00 0.90 0.75 0.60 cum 0.41
Sub-Total 12.64
On hold 0.06
12.58 Total= 12.58 0.00 200.00 0.00
3 Filling
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
From previous bill
1.00 2.25 1.00 0.30 cum 0.67
1.00 2.30 1.00 0.30 cum 0.69
1.00 1.70 0.85 0.30 cum 0.43
1.00 3.70 1.30 0.30 cum 1.44
1.00 1.90 0.90 0.30 cum 0.51
2.00 0.90 0.90 0.30 cum 0.49
1.00 0.90 0.75 0.30 cum 0.20
4.44 Total= 4.44 0.00 300.00 0.00

4 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.
1.00 2.25 1.00 0.15 cum 0.34
1.00 2.30 1.00 0.15 cum 0.35
1.00 1.70 0.85 0.15 cum 0.22
1.00 3.70 1.30 0.15 cum 0.72
1.00 1.90 0.90 0.15 cum 0.26
2.00 0.90 0.90 0.15 cum 0.24
1.00 0.90 0.75 0.15 cum 0.10
Sub-Total 2.22
On hold 0.58
1.64 Total= 1.64 0.00 3000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -181 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
5 Brick soling work
Providing and laying a single layer flat brick soling on
drainage works on lanscape for preparation of P.C.C.
in which joints should be packed by sand to the
required levels all complete as per drawings,
specifications and the instructions of the Engineer.
1.00 1.75 0.85 sqm 1.49
1.00 1.50 0.25 sqm 0.38
Sub-Total 1.86
On hold 0.30
1.56 Total= 1.56 0.00 700.00 0.00
6 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

From previous bill


1.00 2.25 1.00 0.08 cum 0.17
1.00 2.30 1.00 0.08 cum 0.17
1.00 1.70 0.85 0.08 cum 0.11
1.00 3.70 1.30 0.08 cum 0.36
1.00 1.90 0.90 0.08 cum 0.13
2.00 0.90 0.90 0.08 cum 0.12
1.00 0.90 0.75 0.08 cum 0.05
seating portion 1.00 1.75 0.50 0.08 cum 0.07
Sub-Total 1.18
On hold 0.25
0.93 Total= 0.93 0.00 10000.00 0.00

7 RCC Works
Concrete Works for RCC (1:1.5:3) M20 on landscape
and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer.
2.000 2.100 0.900 0.300 cum 1.13
1.000 4.300 0.900 0.250 cum 0.97
2.000 1.050 0.900 0.250 cum 0.47
9.000 0.300 0.300 0.750 cum 0.61
2.000 0.300 0.600 1.100 cum 0.40
1.000 43.240 0.100 cum 4.32

Contractor Prepared By Checked By Approved By


Pages -182 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.000 0.875 0.075 cum 0.07
2.000 6.400 0.450 0.100 cum 0.58
4.000 0.600 0.450 0.100 cum 0.11
From Previous Bill 8.65 Total= 8.65 0.0 16000.00 0.00
8 Steel reinforcement works
Fe500 Reinforcement in PCC including cutting,
bending and placing in position all complete as per
design, drawing, specification and satisfaction to site
engineer.
Bar Bending Schedule For P-1
Item Dia of bar Shape Size No. of items C.L Nos. of bar Total Length Wt/kg Total Weight
footing 12mm .9x0.9 4.00 1.05 12.00 50.40 0.89 44.73

Combined P1 12.00 4.05*.9 1.00 4.20 6.00 25.20 0.89 22.37


2.00 1.05 27.00 56.70 0.89 50.32

column 0.3x0.3 12.00 0.3x0.3 7.00 1.30 8.00 72.80 0.89 64.61

column 0.6x0.3 12.00 0.6x0.3 2.00 1.50 12.00 36.00 0.89 31.95

Stirrups 8.00 0.3x0.3 7.00 1.19 8.00 66.64 0.39 26.29

8.00 0.6x0.3 2.00 1.63 10.00 32.60 0.39 12.86


For DPC 10 1.00 3.5 3.00 10.50 0.62 6.48
10 2.00 0.55 3.00 3.30 0.62 2.04
For Sill level 10 3.00 0.55 3.00 4.95 0.62 3.05
10 3.00 0.35 3.00 3.15 0.62 1.94
Horizontal bars 8 1.00 0.4 18.00 7.20 0.39 2.81
8 1.00 0.35 3.00 1.05 0.39 0.41
8 2.00 0.3 3.00 1.80 0.39 0.70
This Bill
Hidden Beam 16 2.00 4.87 3.00 29.22 1.58 46.17
16 3.00 3.65 3.00 32.85 1.58 51.91
Stirrups 8 1.00 0.3 57.00 17.10 0.39 6.67
Slab 12 1.00 4.6 18.00 82.80 0.89 73.60
10 1.00 4.6 44.00 202.40 0.62 124.94
Distribution 10 1.00 9.7 31.00 300.70 0.62 185.62
From Previous Bill 0.27 tonne Total= 0.76 0.49 120000.00 58735.38

Contractor Prepared By Checked By Approved By


Pages -183 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
9 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing.
Column 300x300, 9 nos of column 2.000 6.000 0.250 sqm. 3.00
Column 600x300, 2 nos of column 1.000 10.400 0.250 sqm. 2.60
2.000 3.900 0.250 sqm. 1.95
9.000 1.200 0.750 sqm. 8.10
2.000 1.800 1.100 sqm. 3.96
1.000 43.240 sqm. 43.24
1.000 0.875 sqm. 0.88
2.000 6.400 0.150 sqm. 1.92
Sub-Total 65.65
On hold 0.01
From Previous Bill 65.63 Total= 65.63 0.00 600.00 0.00
10 STONE PILLAR WORKS
Providingand placing stone pillar above PCC in
cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Small Stone 3.00 0.40 0.40 0.55 cum. 0.26
3.00 0.40 0.40 1.15 cum. 0.55
Sub-Total 0.82
On hold 0.24
0.58 Total= 0.58 0.00 7000.00 0.00

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
11 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
brick wall 1.00 4.00 0.40 4.10 cum 6.56
brick wall 4.00 0.65 0.45 4.10 cum 4.80
Deduction cum 0.00
brick wall -4.00 0.40 0.40 2.33 cum -1.49
9.87 Total= 9.87 0.00 15000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -184 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
12 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
150mmx150mm 3.00 0.15 0.15 3.06 cum 0.21
150mmx150mm 3.00 0.15 0.15 2.48 cum 0.17
wooden casing 3.00 1.10 0.13 0.35 cum 0.15
50mm wooden pole 12.00 1.90 0.00 cum 0.04
25mm wooden pole 24.00 1.90 0.00 cum 0.02
wooden plates 6.00 0.40 0.40 0.03 cum 0.02
0.61 Total= 0.61 0.00 250000.00 0.00
Engraving designs on wooden pillars properly finished
13.0 along with all necessary accessories along with wood
primer all complete as per design, drawing,
specification and instruction of the Engineer..
0.00 Nos 0.00
0.00 Total= 0.00 0.00 25000.00 0.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
14 polished and finished in perfect line, level along with all
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
WB beam 5.000 4.587 0.100 0.100 cum 0.23
WB beam 3.000 3.851 0.100 0.100 cum 0.12
meth 12.000 0.052 0.075 cum 0.05
0.39 Total= 0.39 0.00 250000.00 0.00

15 MS STEEL WORKS
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work including
transportation, cutting, connecting and placing in
position,treated with two coat of anticorrosive paints,
all complete as per drawings, specifications and
instruction.
90mmx90mm 4.00 2.35 14.00 kg 131.60
9.00 2.58 14.00 kg 325.08

Contractor Prepared By Checked By Approved By


Pages -185 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
12mm Base plate 18.00 0.25 0.25 94.20 kg 105.98
4.00 0.50 0.25 94.20 kg 47.10
12mm Top plate 9.00 0.18 0.18 94.20 kg 25.96
2.00 0.18 0.48 94.20 kg 15.66
100mmx100mmx 4mm post 13.000 2.725 11.730 kg 415.54
100mmx100mmx 4mm beam 7.000 4.594 11.730 kg 377.21
100mmx100mmx 4mm beam 5.000 5.400 11.730 kg 316.71
7% for nuts, bolts, plates 77.66 kg 77.66
Total 1,838.50
On Hold 651.38
1187.12 Total= 1187.12 0.00 250.00 0.00

Providing and placing decking sheet for concrete deck


16 slab including transportation, cutting, connecting and
placing in position with welds and studs all complete
as per drawings, specifications and instruction.
1.000 43.240 Sqm 43.24

43.24 43.24 0.00 1200.00 0.00


17 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete.
brick wall 1.000 9.000 2.750 24.75
brick wall 4.000 2.197 2.750 24.17
brick wall 8.000 0.450 2.325 8.37
column 2.000 1.800 0.400 1.44
bench 1.000 4.500 0.375 1.69
Deduction
brick wall -8.000 0.400 2.325 -3.72
56.69 56.69 0.00 300.00 0.00

Contractor Prepared By Checked By Approved By


Pages -186 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
18 specifications to the surface of wall, ceiling, beams
columns, canopies, staircase, lobbies etc., all complete
as per drawings, specifications and instruction. The
rates shall include for scraping, washing the surface
with water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer. sqm 0.00
0.00 0.00 0.00 300.00 0.00
19 False ceiling works
Providing and placing false ceiling with plyboard(one
side veneer) including the channels to drop false
ceiling all complete as per design, drawing,
specification and instruction of site engineer. sqm 0.00
0.00 0.00 0.00 2500.00 0.00

Providing and applying PU paint of approved


manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
20 the surface of false ceiling all complete as per
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. sqm 0.00
0.00 0.00 0.00 300.00 0.00
21 Toughen glass Works
Providing and laying toughen glass on roof including
fixing with silicon and necessary support all complete
as per drawing and specification. sqm 0.00
0.00 0.00 0.00 12000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -187 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
22 Fibre cement board cladding for fascia
Providing and laying fibre cement board cladding on
fascia all complete as per design, drawing,
specification and instruction of site engineer. 0.00 sqm 0.00
0.00 0.00 0.00 3000.00 0.00

23 Waterproofing coating on roof


Providing and laying waterproofing coating on roof all
complete as per design, drawing, specification and
instruction of site engineer. 0.00 sqm 0.00
0.00 0.00 0.00 500.00 0.00
24 Cement punning finish on roof
3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth
surface on roof as per design, drawing, specification
and instruction of site engineer. 0.00 sqm 0.00
0.00 0.00 0.00 400.00 0.00
Timber plank on bench:- Providing and laying timber
25 plank on bench all complete as per
design,drawing,specification and instruction of site
engineer 0.00 sqm 0.00
0.00 0.00 0.00 12000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -188 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
PAVILION I I-
26 Earthwork

Earthwork in excavation for foundation along with


dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
1.00 5.60 0.90 0.60 cum. 3.02
1.00 2.35 0.83 1.00 cum. 1.94
1.00 5.75 1.10 1.00 cum. 6.33
1.00 2.20 0.85 1.00 cum. 1.87
Sub-Total 13.16
On hold 0.65
12.51 Total= 12.51 0.00 1000.00 0.00

Filling with earth or mixed soil stacked at site in


150mm thick layer on retaining walls including
27 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
1.00 5.60 0.90 0.30 cum. 1.51
1.00 2.35 0.83 0.30 cum. 0.58
1.00 5.75 1.10 0.30 cum. 1.90
1.00 2.20 0.85 0.30 cum. 0.56
4.55 Total= Cum 4.55 0.00 300.00 0.00

28 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

1.00 5.60 0.90 0.15 cum 0.76


1.00 2.35 0.83 0.15 cum 0.29

Contractor Prepared By Checked By Approved By


Pages -189 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 5.75 1.10 0.15 cum 0.95
1.00 2.20 0.85 0.15 cum 0.28
Sub-Total 2.28
On hold 0.45
1.83 Total= Cum 1.83 0.00 3000.00 0.00
29 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

1.00 5.60 0.90 0.075 cum 0.38


1.00 2.35 0.83 0.075 cum 0.15
1.00 5.75 1.10 0.075 cum 0.47
1.00 2.20 0.85 0.075 cum 0.14
Sub-Total 1.14
On hold 0.23
0.91 Total= Cum 0.91 0.00 10000.00 0.00

30 RCC Works
Concrete Works for RCC (1:1.5:3) M20 on landscape
and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer.
Grid 3-4 footing 2.000 0.900 0.900 0.300 cum 0.49
Wall footing 1.000 5.000 1.150 0.250 cum 1.44
concrete pedestal-single post 8.000 0.300 0.300 0.750 cum 0.54
concrete pedestal-double post 2.000 0.300 0.600 1.100 cum 0.40
RCC SLAB 1.000 36.180 0.100 cum 3.62
Concrete band 2.000 4.196 0.450 0.100 cum 0.38
6.86 Total= cum 6.86 0.00 16000.00 0.00

31 Steel reinforcement works


Fe500 Reinforcement in PCC including cutting,
bending and placing in position all complete as per
design, drawing, specification and satisfaction to site
engineer.
Bar Bending Schedule For P-2
Item Dia of bar Shape Size No. of items C.L Nos. of bar Total Length Wt/kg Total Weight
footing 12mm .9x0.9 2.00 1.05 13.00 27.30 0.89 24.23

Combined footing P2 12.00 4.9*.9 1.00 5.05 6.00 30.30 0.89 26.89
1.00 1.05 33.00 34.65 0.89 30.75

Contractor Prepared By Checked By Approved By


Pages -190 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
column 0.3x0.3 12.00 0.3x0.3 8.00 1.30 8.00 83.20 0.89 73.84

column 12.00 0.6x0.3 2.00 1.50 12.00 36.00 0.89 31.95

Stirrups 8.00 0.3x0.3 8.00 1.19 7.00 66.64 0.39 26.29

8.00 0.6x0.3 2.00 1.63 10.00 32.60 0.39 12.86

For DPC 10.00 1.00 4.30 3.00 12.90 0.62 8.00


10.00 1.00 3.90 3.00 11.70 0.62 7.25
8.00 1.00 0.45 22.00 9.90 0.39 3.86
8.00 1.00 0.45 19.00 8.55 0.39 3.33
This Bill 8.00 1.00 6.40 32.00 204.80 0.39 79.87
8.00 1.00 4.70 43.00 202.10 0.39 78.82
Cutpiece area 8.00 1.00 1.24 7.00 8.68 0.39 3.39
8.00 1.00 1.05 9.00 9.45 0.39 3.69
8.00 1.00 1.15 7.00 8.05 0.39 3.14
8.00 1.00 1.15 8.00 9.20 0.39 3.59
0.25 Total= kgs 0.42 0.17 120000.00 20698.70
32 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing.

Grid 3-4 footing 2.000 3.600 0.300 sqm 2.16


Wall footing 1.000 12.300 0.250 sqm 3.08
concrete pedestal-single post 8.000 1.200 0.750 sqm 7.20
concrete pedestal-double post 2.000 1.800 1.100 sqm 3.96
RCC SLAB 1.000 36.180 0.100 sqm 3.62
Concrete band 4.000 4.196 0.100 sqm 1.68
21.69 Total= sqm 21.69 0.00 600.00 0.00
33 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Small Stone 2.00 0.40 0.40 0.55 cum. 0.18
5.00 0.40 0.40 1.15 cum. 0.92
Sub-Total 1.10
On hold 0.20
0.90 Total= Cum 0.90 0.00 7000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -191 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
34 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
brick wall 1.000 4.196 0.450 4.110 cum 7.76
Deduction 0.00
brick wall -1.000 0.390 0.450 2.800 cum -0.49

7.27 Total= cum 7.27 0.00 15000.00 0.00


35 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
150mmx150mm 2.00 0.15 0.15 3.60 cum. 0.16
150mmx150mm 7.00 0.15 0.15 2.80 cum. 0.44
wooden casing 7.00 1.10 0.13 0.60 cum. 0.60
50mm wooden pole 28.00 2.03 0.00 cum. 0.11
25mm wooden pole 56.00 2.03 0.00 cum. 0.06
wooden plates 14.00 0.40 0.40 0.03 cum. 0.06
1.43 Total= Cum 1.43 0.00 250000.00 0.00

Engraving designs on wooden pillars properly finished


36.0 along with all necessary accessories along with wood
primer all complete as per design, drawing,
specification and instruction of the Engineer..
0.00 Nos 0.000
0.00 Total= 0.000 0.00 25000.00 0.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
37 polished and finished in perfect line, level along with all
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
WB beam 5.000 6.375 0.100 0.100 cum. 0.319
WB beam 5.000 3.962 0.100 0.100 cum. 0.198

Contractor Prepared By Checked By Approved By


Pages -192 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
meth 28.000 0.052 0.075 cum. 0.109
0.63 Total= Cum 0.63 0.00 250000.00 0.00

38 MS STEEL WORKS
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work including
transportation, cutting, connecting and placing in
position,treated with two coat of anticorrosive paints,
all complete as per drawings, specifications and
instruction. Kg/m
100mmx100mmx 4mm post 12.000 2.775 11.730 kg 390.61
100mmx100mmx 4mm beam 1.000 15.764 11.730 kg 184.91
100mmx100mmx 4mm beam 6.000 1.987 11.730 kg 139.85
100mmx100mmx 4mm beam 4.000 1.363 11.730 kg 63.95
75mmx75mmx 4mm bench 1.000 7.650 8.590 kg 65.71
50mmx50mmx 3.6mm bench 2.000 2.100 4.930 kg 20.71
7% for nuts, bolts, plates 60.6016 kg 60.60
926.34 Total= Kg 926.34 0.00 250.00 0.00

Providing and placing decking sheet for concrete deck


39 slab including transportation, cutting, connecting and
placing in position with welds and studs all complete
as per drawings, specifications and instruction.
36.18 1.000 36.180 Sqm 36.18 0.00 6000.00 0.00
40 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. sqm. 0.0
brick wall 1.000 10.485 3.175 33.28
brick wall 2.000 0.450 2.800 2.52
column pedestal 2.000 1.800 0.400 1.44
Deduction 0.00
brick wall -2.000 0.390 2.800 -2.18
35.06 35.06 0.00 600.00 0.00

Contractor Prepared By Checked By Approved By


Pages -193 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
41 specifications to the surface of wall, ceiling, beams
columns, canopies, staircase, lobbies etc., all complete
as per drawings, specifications and instruction. The
rates shall include for scraping, washing the surface
with water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer. sqm. 0.0
0.0 0.0 0.00 300.00 0.00
42 False ceiling works
Providing and placing false ceiling with plyboard(one
side veneer) including the channels to drop false 0.00
ceiling all complete as per design, drawing,
specification and instruction of site engineer. 0.0 sqm. - 0.0 0.00 2500.00
Providing and applying PU paint of approved
manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
the surface of false ceiling all complete as per
43 0.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. 0.0 sqm. - 0.0 0.00 300.00

44 Fibre cement board cladding for fascia


Providing and laying fibre cement board cladding on
fascia all complete as per design, drawing, 0.00
specification and instruction of site engineer. 0.0 sqm. 0.0 0.00 2500.00

45 Waterproofing coating on roof


Providing and laying waterproofing coating on roof all
complete as per design, drawing, specification and 0.00
instruction of site engineer. 0.0 sqm. 0.0 0.00 500.00

46 Cement punning finish on roof


3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth 0.00
surface on roof as per design, drawing, specification
and instruction of site engineer. 0.0 sqm. 0.0 0.00 400.00

Contractor Prepared By Checked By Approved By


Pages -194 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
PAVILION III-
47 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
Pavilion 3A 1.00 9.20 1.00 0.60 cum 5.52
1.00 9.30 0.90 0.60 cum 5.02
1.00 0.90 1.00 0.60 cum 0.54
1.00 0.90 1.05 0.60 cum 0.57

Pavilion 3B 1.00 8.20 1.00 0.60 cum 4.92


1.00 8.00 0.90 0.60 cum 4.32
1.00 2.00 0.70 0.60 cum 0.84
1.00 2.00 0.70 0.60 cum 0.84
Total= cum 22.57
10.55 Net payable quantity cum 10.55 0.00 1000.00 0.00
12.02 On hold quantity cum
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
48 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
Pavilion 3A 1.00 8.30 1.00 0.75 cum 6.23
Pavilion 3B 1.00 8.30 1.00 0.75 cum 6.23
Total= cum 12.45
6.54 Net payable quantity cum 6.54 0.00 300.00 0.00
5.91 On hold quantity cum

49 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

Pavilion 3A 1.00 9.20 1.00 0.15 cum 1.38


1.00 9.30 0.90 0.15 cum 1.26

Contractor Prepared By Checked By Approved By


Pages -195 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 0.90 1.00 0.15 cum 0.14
1.00 0.90 1.05 0.15 cum 0.14
Pavilion 3B 1.00 8.20 1.00 0.15 cum 1.23
1.00 8.00 0.90 0.15 cum 1.08
1.00 2.00 0.70 0.15 cum 0.21
1.00 2.00 0.70 0.15 cum 0.21
Total= cum 5.64
2.72 Net payable quantity cum 2.72 0.00 3000.00 0.00
2.92 On hold quantity cum
Brick soling works
Providing and laying a single layer flat brick soling on
floor for preparation of P.C.C. in which joints should be
packed by sand to the required levels all complete as
per drawings, specifications and the instructions of the
Engineer.
Pavilion 3A 1.00 8.30 1.00 sqm 8.30
Pavilion 3B 1.00 8.30 1.00 sqm 8.30
Total= sqm 16.60
9.24 Net payable quantity sqm 9.24 0.00 700.00 0.00
7.36 On hold quantity sqm
51 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

Pavilion 3A 1.00 9.20 1.00 0.08 cum 0.69


1.00 9.30 0.90 0.08 cum 0.63
1.00 0.90 1.00 0.08 cum 0.07
1.00 0.90 1.05 0.08 cum 0.07
seating area 1.00 8.80 1.50 0.08 cum 0.99
Pavilion 3B 1.00 8.20 1.00 0.08 cum 0.61
1.00 8.00 0.90 0.08 cum 0.54
1.00 2.00 0.70 0.08 cum 0.11
1.00 2.00 0.70 0.08 cum 0.11
seating area 1.00 8.80 1.50 0.08 cum 0.99
Total= cum 4.80
2.35 Net payable quantity cum 2.35 0.00 10000.00 0.00
2.45 On hold quantity cum

Contractor Prepared By Checked By Approved By


Pages -196 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
52 RCC Works
Concrete Works for RCC (1:1.5:3) M20 on landscape
and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer. 0.00 cum. 0.00
0.00 0.00 0.00 16000.00 0.00
53 Steel reinforcement works
Fe500 Reinforcement in PCC including cutting,
bending and placing in position all complete as per
design, drawing, specification and satisfaction to site
engineer. 0.00 kgs 0.00
0.00 0.00 0.00 120000.00 0.00
54 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging 0.00
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing. 0.00 sqm. 0.00 0.00 600.00
55 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in 0.00


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer. 0.00 cum. 0.00 0.00 7000.00

Contractor Prepared By Checked By Approved By


Pages -197 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
56 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
Pavilion 3A 2.00 8.80 0.25 0.85 cum 3.74
2.00 1.00 0.25 0.85 cum 0.43
Pavilion 3B 2.00 8.80 0.25 0.90 cum 3.96
2.00 1.00 0.25 0.90 cum 0.45
Total= cum 8.58
3.22 Net payable quantity cum 3.22 0.00 15000.00 0.00
5.35 On hold quantity cum
57 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories 0.00
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
0.0 cum. 0.0 0.00 250000.00
Engraving designs on wooden pillars properly finished
along with all necessary accessories along with wood
58 0.00
primer all complete as per design, drawing,
specification and instruction of the Engineer.. 0.0 Nos 0.0 0.00 25000.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
polished and finished in perfect line, level along with all
59
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction 0.0 0.0
Total 0.0 cum. 0.0 0.00 250000.00 0.00

60 Waterproof plywood works


Providing and placing waterproof plywood for concrete
deck slab including transportation, cutting, connecting
and placing in position with nails, hooks, etc. all 0.00
complete as per drawings, specifications and
instruction. 0.0 sqm. 0.0 0.00 700.00

Contractor Prepared By Checked By Approved By


Pages -198 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
61 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting 4896.00
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. 0.0 sqm. 8.16 8.16 600.00
Base Plaster of two pavilion 4.00 8.70 0.2 sqm. 7.0
4.00 1.50 0.2 sqm. 1.2

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
62 specifications to the surface of wall, ceiling, beams 0.00
columns, canopies, staircase, lobbies etc., all complete
as per drawings, specifications and instruction. The
rates shall include for scraping, washing the surface
with water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer. 0.0 sqm. 0.0 0.00 300.00

63 False ceiling works


Providing and placing false ceiling with plyboard(one
side veneer) including the channels to drop false 0.00
ceiling all complete as per design, drawing,
specification and instruction of site engineer. 0.0 sqm. 0.0 0.00 2500.00
Providing and applying PU paint of approved
manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
the surface of false ceiling all complete as per
64 0.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. 0.0 sqm. 0.0 0.00 300.00

Contractor Prepared By Checked By Approved By


Pages -199 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

65 WPC board for fascia


Providing and laying WPC board cladding on fascia all
complete as per design, drawing, specification and 0.00
instruction of site engineer. 0.0 sqm. 0.0 0.00 2500.00

66 Waterproofing membrane on roof


Providing and laying waterproofing membrane on roof
all complete as per design, drawing, specification and 0.00
instruction of site engineer. 0.0 sqm. 0.0 0.00 700.00

67 Panipatti
Providing and laying 20mm. thick Cement Water Bead
(Pani Patti) finished perfectly smooth including
0.00
necessary scaffolding, raking the joint, wetting the
surface and curing all complete work 0.0 rm 0.0 0.00 400.00

68 Flooring works

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance,
0.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative.
0.0 sqm. 0.0 0.00 800.00
3mm cement punning in 1:1 c/s mortar in perfect line
69 and level including trowelling and finishing in smooth 0.00
surface on roof as per design, drawing, specification
and instruction of site engineer. 0.0 sqm. 0.0 0.00 400.00
Providing and laying of 25 mm thick Telia tile paving
work in (1:2) surki mortar and pointing the joints with
70 1:1 C/S mortar including curing on floor in perfect line 0.00
and level all complete as per design, drawing,
specification and the instrution of the site engineer. 0.0 sqm. 0.0 0.00 3400.00
Providing and laying of stone slab of approved
thickness and color on floor in perfect line and level
71 including joint sealing of joint, grinding, polishing all 0.00
complete as per design, drawing, specification and the
instrution of the site engineer. 0.0 sqm. 0.0 0.00 7000.00

Contractor Prepared By Checked By Approved By


Pages -200 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
PAVILION IV-
72 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
2.00 4.10 0.80 0.80 cum 5.25
2.00 2.30 0.80 0.80 cum 2.94
2.00 6.20 0.45 0.65 cum 3.63
2.00 5.30 0.45 0.65 cum 3.10
For stone pillar 4.00 0.75 0.75 0.75 cum 1.69
Sub-Total 16.61
On hold 5.28
11.33 Total= Cum 11.33 0.00 1000.00 0.00
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
73 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
1.00 2.87 2.87 1.00 cum 8.24
4.00 5.50 0.40 0.30 cum 2.64
4.00 4.55 0.30 0.15 cum 0.82
4.00 3.45 0.30 0.15 cum 0.62
Sub-Total 12.32
On hold 4.05
8.27 Total= Cum 8.27 0.00 300.00 0.00

Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
74 quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

4.00 0.70 0.70 0.15 cum. 0.29


Sub-Total 0.29
On hold 0.03
0.26 Total= Cum 0.26 0.00 3000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -201 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
75 Brick soling works
Providing and laying a single layer flat brick soling on
floor for preparation of P.C.C. in which joints should be
packed by sand to the required levels all complete as
per drawings, specifications and the instructions of the
Engineer.
2.00 4.10 0.50 sqm 4.10
2.00 2.30 0.50 sqm 2.30
2.00 3.95 0.25 sqm 1.98
2.00 3.45 0.25 sqm 1.73
2.00 4.55 0.30 sqm 2.73
2.00 3.95 0.30 sqm 2.37
2.00 5.15 0.30 sqm 3.09
2.00 4.55 0.30 sqm 2.73
2.00 6.00 0.40 sqm 4.80
2.00 5.15 0.40 sqm 4.12
Area 4.00 2.90 sqm 11.60
Sub-Total 41.54
On hold 17.15
24.39 Total= sqm 24.39 0.00 700.00 0.00
76 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

Steps 1.000 24.000 0.460 0.075 cum 0.83


Steps 1.000 20.480 0.734 0.075 cum 1.13
Steps 1.000 18.080 0.600 0.075 cum 0.81
Steps 1.000 15.680 0.600 0.075 cum 0.71
Steps 1.000 13.280 0.300 0.075 cum 0.30
stone 4.000 0.660 0.660 0.075 cum 0.13
FLOOR 1.000 3.320 3.320 0.075 cum 0.83
Sub-Total 4.73
On hold 0.04
4.69 Total= Cum 4.69 0.00 10000.00 0.00
77 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Column 16.00 0.20 0.20 0.91 cum. 0.58
0.58 Total= Cum 0.58 0.00 25000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -202 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
78 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
1st Step 2.00 3.40 0.25 1.50 cum 2.55
1st Step 2.00 2.85 0.25 1.50 cum 2.14
2nd step 2.00 3.95 0.25 0.10 cum 0.20
2nd step 2.00 3.45 0.25 0.10 cum 0.17
3rd Step 2.00 4.55 0.25 0.55 cum 1.25
3rd Step 2.00 3.95 0.25 0.55 cum 1.09
4th Step 2.00 5.15 0.25 0.10 cum 0.26
4th Step 2.00 4.55 0.25 0.10 cum 0.23
5th Step 2.00 6.00 0.25 0.10 cum 0.30
5th Step 2.00 5.15 0.25 0.10 cum 0.26
8.44 Total= Cum 8.44 0.00 15000.00 0.00
79 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
75mmx75mm 16.000 0.075 0.075 2.253 cum. 0.20
wooden casing 16.000 0.400 0.069 0.250 cum. 0.11
50mm wooden pole 64.000 2.225 0.002 cum. 0.28
25mm wooden pole 128.000 2.225 0.0005 cum. 0.14
wooden plates 32.000 0.400 0.400 0.0250 cum. 0.13
0.86 Total= Cum 0.86 0.00 250000.00 0.00

Engraving designs on wooden pillars properly finished


80.0 along with all necessary accessories along with wood
primer all complete as per design, drawing,
specification and instruction of the Engineer..
0.000 Nos 0.00
0.00 Total= Nos 0.00 0.00 25000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -203 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing, fabricating & fixing salwood(agrath) wooden


beams, meths, etc. fixing in pillar with joint properly
81 polished and finished in perfect line, level along with all
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
MB beam 10.000 4.000 0.075 0.100 cum. 0.30
IB beam 24.000 0.576 0.075 0.075 cum. 0.08
IB1 beam 4.000 4.000 0.075 0.075 cum. 0.09
CB beam 10.000 5.153 0.075 0.075 cum. 0.29
diagonal struts 4.000 2.300 0.050 0.050 cum. 0.02
truss 4.000 6.435 0.050 0.050 cum. 0.06
truss 4.000 4.092 0.075 0.075 cum. 0.09
purlin 4.000 13.084 0.075 0.075 cum. 0.29
1.23 Total= Cum 1.23 0.00 250000.00 0.00

82 Roofing works
Providing and placing waterproof plywood for roofing
including transportation, cutting, connecting and
placing in position with nails, hooks, etc. all complete
as per drawings, specifications and instruction.
4.000 6.932 27.73
27.7 sqm. 27.73 0.00 700.00 0.00

Providing and placing ikotile for roofing including


83 transportation, cutting, connecting and placing in 97050.19
position with nails all complete as per drawings,
specifications and instruction. 0.0 sqm. 27.73 27.73 3500.00
4.000 6.932 27.73
84 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting 0.00
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. 0.0 sqm. 0.00 300.00

Contractor Prepared By Checked By Approved By


Pages -204 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
85 False ceiling works
Providing and placing false ceiling with cement board
including the channels to drop false ceiling all 0.00
complete as per design, drawing, specification and
instruction of site engineer. 0.0 sqm. 0.00 2500.00

Providing and applying fire retardant paint of approved


manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
86 the surface of false ceiling all complete as per 0.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. 0.0 sqm. 0.00 15000.00
87 WPC Panel for ceiling
Providing and laying WPC Panel for ceiling all
complete as per design, drawing, specification and 0.00
instruction of site engineer. 0.0 sqm. 0.00 2400.00
88 Waterproofing membrane on roof
Providing and laying waterproofing membrane on roof
all complete as per design, drawing, specification and 0.00
instruction of site engineer. 0.0 sqm. 0.00 500.00
89 Flooring works

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance,
0.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative.
0.0 sqm. 0.00 800.00
3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth
90 0.00
surface on roof as per design, drawing, specification
and instruction of site engineer. 0.0 sqm. 0.00 400.00
Providing and laying of 25 mm thick Telia tile paving
work in (1:2) surki mortar and pointing the joints with
91 1:1 C/S mortar including curing on floor in perfect line 0.00
and level all complete as per design, drawing,
specification and the instrution of the site engineer. 0.0 sqm. 0.00 3400.00
Providing and laying of 50mm thick stone slab of
approved thickness and color on floor in perfect line
92 and level including joint sealing of joint, grinding, 0.00
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. 0.0 sqm. 0.00 7000.00

Contractor Prepared By Checked By Approved By


Pages -205 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Providing and laying of flagstone of approved
thickness and color on floor in perfect line and level
93 including joint sealing of joint, grinding, polishing all 0.00
complete as per design, drawing, specification and the
instrution of the site engineer. 0.0 sqm. 0.00 1400.00
Bells on roof:- Providing and fixing design, drawing,
94 0.00
specification and instruction of site engineer 0.0 Nos 0.00 6000.00
MANDAP
95 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
2.00 3.70 0.80 0.60 cum 3.55
2.00 3.45 0.80 0.60 cum 3.31
2.00 5.50 0.60 0.45 cum 2.97
2.00 3.30 0.60 0.45 cum 1.78
Inside Mandap 4.00 0.70 0.70 0.20 cum 0.39
Sub-Total 12.01
On hold 2.29
9.72 Total= Cum 9.72 0.00 1000.00 0.00
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
96 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
2.00 3.70 0.80 0.30 cum 1.78
2.00 3.40 0.80 0.30 cum 1.63
2.00 5.50 0.60 0.30 cum 1.98
2.00 3.30 0.60 0.30 cum 1.19
1.00 2.90 0.60 cum 1.74
Sub-Total 8.32
On hold 2.70
5.62 Total= Cum 5.62 0.00 300.00 0.00

Contractor Prepared By Checked By Approved By


Pages -206 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
97 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

4.00 0.70 0.70 0.15 cum. 0.29


Sub-Total 0.29
On hold 0.03
0.26 Total= Cum 0.26 0.00 3000.00 0.00
98 Brick soling works
Providing and laying a single layer flat brick soling on
floor for preparation of P.C.C. in which joints should be
packed by sand to the required levels all complete as
per drawings, specifications and the instructions of the
Engineer.

2.00 3.40 0.50 sqm 3.40


2.00 5.50 0.60 sqm 6.60
2.00 3.30 0.60 sqm 3.96
2.00 2.70 0.25 sqm 1.35
2.00 3.70 0.25 sqm 1.85
Area 4.00 2.90 sqm 11.60
Sub-Total 28.76
On hold 3.11
25.65 Total= Sqm 25.65 0.00 700.00 0.00
99 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

2.00 3.70 0.50 0.075 cum. 0.28


2.00 3.40 0.50 0.075 cum. 0.26
1 step soiling 2.00 5.50 0.60 0.075 cum. 0.49
2.00 3.30 0.60 0.075 cum. 0.30
1st step top PCC 2.00 5.50 0.60 0.075 cum. 0.49
2.00 4.90 0.60 0.075 cum. 0.44
2nd step 2.00 4.90 0.60 0.075 cum. 0.44
2.00 4.30 0.60 0.075 cum. 0.39

Contractor Prepared By Checked By Approved By


Pages -207 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
3rd step 2.00 4.30 0.30 0.075 cum. 0.19
Area 1.00 3.20 3.20 0.075 cum. 0.77
4.00 0.75 0.75 0.075 cum. 0.17
Sub-Total 4.22
On hold 0.61
3.61 Total= Cum 3.61 0.00 10000.00 0.00
100 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Column 16.00 0.20 0.20 0.91 cum. 0.58
0.58 Total= Cum 0.58 0.00 7000.00 0.00
Brick Masonry Works in Superstructure ( 1 : 4
c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
cement : 4coarse sand) in landscape works in all
101
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
Steps 1.000 20.480 0.300 0.561 cum 3.440
Steps 1.000 18.080 0.300 0.075 cum 0.400
Steps 1.000 15.680 0.300 0.075 cum 0.350
Steps 1.000 13.280 0.230 1.164 3.550
7.74 Total= Cum 7.74 0.00 15000.00 0.00
102 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer.. -
75mmx75mm 16.000 0.075 0.075 2.253 cum. 0.20
wooden casing 16.000 0.400 0.069 0.250 cum. 0.11
50mm wooden pole 64.000 2.225 0.002 cum. 0.28
25mm wooden pole 128.000 2.225 0.0005 cum. 0.14
wooden plates 32.000 0.400 0.400 0.0250 cum. 0.13
0.86 Total= Cum 0.86 0.00 250000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -208 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Engraving designs on wooden pillars properly finished
along with all necessary accessories along with wood
103.0
primer all complete as per design, drawing,
specification and instruction of the Engineer..
-
0.000 Total= - 0.00 0.00 25000.00 0.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
polished and finished in perfect line, level along with all
104
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
MB beam 10.000 4.000 0.075 0.100 cum. 0.30
IB beam 24.000 0.576 0.075 0.075 cum. 0.08
IB1 beam 4.000 4.000 0.075 0.075 cum. 0.09
CB beam 10.000 5.153 0.075 0.075 cum. 0.29
diagonal struts 4.000 2.300 0.050 0.050 cum. 0.02
truss 4.000 6.435 0.050 0.050 cum. 0.06
truss 4.000 4.092 0.075 0.075 cum. 0.09
purlin 4.000 13.084 0.075 0.075 cum. 0.29
Sub-Total 1.23
On hold 0.10
1.13 Total= Cum 1.13 0.00 250000.00 0.00
105 Roofing works
Providing and placing waterproof plywood for roofing
including transportation, cutting, connecting and
placing in position with nails, hooks, etc. all complete
as per drawings, specifications and instruction.
4.000 6.932 27.73
27.73 - 27.73 0.00 700.00 0.00
Providing and placing ikotile for roofing including
106 transportation, cutting, connecting and placing in 69321.56
position with nails all complete as per drawings,
specifications and instruction. sqm. - 27.73 27.73 2500.00
4.000 6.932 27.73
107 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting 0.00
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. sqm. - 0.00 600.00

Contractor Prepared By Checked By Approved By


Pages -209 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

108 False ceiling works


Providing and placing false ceiling with cement board
including the channels to drop false ceiling all 0.00
complete as per design, drawing, specification and
instruction of site engineer. sqm. - 0.00 2500.00

Providing and applying fire retardant paint of approved


manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
109 the surface of false ceiling all complete as per 0.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. sqm. - 0.00 15000.00
110 WPC Panel for ceiling
Providing and laying WPC Panel for ceiling all
complete as per design, drawing, specification and 0.00
instruction of site engineer. sqm. - 0.00 1500.00
111 Waterproofing membrane on roof
Providing and laying waterproofing membrane on roof
all complete as per design, drawing, specification and 0.00
instruction of site engineer. sqm. - 0.00 600.00
112 Flooring works

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance, 0.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative. sqm. - 0.00 800.00
3mm cement punning in 1:1 c/s mortar in perfect line
113 and level including trowelling and finishing in smooth 0.00
surface on roof as per design, drawing, specification
and instruction of site engineer. sqm. - 0.00 400.00
Providing and laying of 25 mm thick Telia tile paving
work in (1:2) surki mortar and pointing the joints with
114 1:1 C/S mortar including curing on floor in perfect line 0.00
and level all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 0.00 3500.00
Providing and laying of 50mm thick stone slab of
approved thickness and color on floor in perfect line
115 and level including joint sealing of joint, grinding, 0.00
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 0.00 7000.00

Contractor Prepared By Checked By Approved By


Pages -210 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing and laying of flagstone of approved


thickness and color on floor in perfect line and level
116 including joint sealing of joint, grinding, polishing all 0.00
complete as per design, drawing, specification and the
instrution of the site engineer. sqm. - 0.00 1400.00
Bells on roof:- Providing and fixing design, drawing,
117 0.00
specification and instruction of site engineer Nos - 0.00 10000.00
Landscape, drainage and Boundary wall works
118 Site Clearance Work
Clearing and grubbing the site for construction by
removing 150mm thick top soil including bushes, small
trees, levelling of undulated ground, shorting and
stacking/storing selected top soil for reuse in
landscaping works, disposing unsuitable materials
from site, etc., all complete as per drawings,
specifications and instructions of the Engineer.
1.00 80.00 50.00 sqm 4000.00
1.00 20.00 50.00 sqm 1000.00
1.00 50.00 15.00 Sqm 750.00
5750.00 Total= sqm 5750.00 0.00 60.00 0.00
119 Dismantling
Dismantling of existing structures by manual means
comprising of cement concrete works including
scaffolding wherever necessary, sorting the dismantled
material, disposal and stacking materials with all lifts
and leads of 1000meters
5.00 0.25 0.25 1.70 cum 0.53
14.00 0.25 0.25 1.60 cum 1.40
8.00 0.25 0.25 2.10 cum 1.05
1.00 1.10 1.00 0.15 cum 0.17
1.00 3.70 1.30 0.15 cum 0.72
1.00 6.20 3.20 0.15 cum 2.98
1.00 1.00 3.20 0.15 cum 0.48
1.00 4.90 5.20 0.13 cum 3.19
10.51 Total= Cum 10.51 0.00 1000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -211 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Dismantling of existing blocks by manual means
comprising of brick works including scaffolding
120 wherever necessary, sorting the dismantled material,
disposal and stacking materials with all lifts and leads
of 1000meters
2.00 5.50 3.00 sqm 10.50
1.00 6.50 3.00 sqm 10.50
1.00 30.00 1.50 sqm 32.50
1.00 20.00 6.00 sqm 27.00
1.00 15.00 5.75 sqm 21.75
1.00 195.00 Sqm 195.00
297.25 Total= sqm 297.25 0.00 1000.00 0.00
Dismantling of barbed wire fencing includong posts,
foundation concrete, backfilling of pit by manual means
121
including disposal and stacking materials with all lifts
and leads of 1000meters
4.00 29.50 Rm 118.00
6.00 50.00 Rm 300.00
418.0 Total= Rm 418.00 0.00 1000.00 0.00

Dismantling of steel including dismembering by


122
manual means
Exterior wall 1.00 23.50 1.20 kg 423.00 15.00
Gate 1.00 2.70 2.10 kg 198.45 35.00
Small gate 1.00 1.80 2.00 kg 126.00 35.00
Gate 1.00 4.50 3.50 kg 551.25 35.00
Sub-Total 1,298.70
On hold 330.30
1,298.70 Total= Kg 968.40 -330.30 120.00 -39636.00
Dismantling of granular courses pavements and
123 disposal of dismantled materials upto a lead of 1000
m, stacking materials all by manual means
existing pathways and pavement surfaces 1.00 200.00 0.15 cum. 30.00
existing pathways and pavement surfaces 1.00 324.54 0.15 cum. 48.68
78.68 Total= Cum 78.68 0.00 1000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -212 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
124 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
for RT Walls (From North To South) 1.00 3.70 0.30 1.20 cum. 1.33
1.00 2.00 0.30 0.90 cum. 0.54
1.00 6.85 0.30 1.20 cum. 2.47
1.00 4.00 1.00 1.50 cum. 6.00
1.00 3.90 1.00 1.50 cum. 5.85
1.00 8.80 1.00 1.50 cum. 13.20
1.00 4.75 1.10 1.50 cum. 7.84
1.00 1.10 1.00 1.50 cum. 1.65
1.00 11.30 1.00 1.50 cum. 16.95
2.00 1.00 1.00 1.50 cum. 3.00
1.00 4.45 1.00 1.50 cum. 6.68
1.00 3.40 1.00 1.50 cum. 5.10
1.00 4.75 1.00 1.50 cum. 7.13
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.45 cum. 1.45
1.00 5.50 0.85 0.45 cum. 2.10
1.00 5.20 0.85 0.65 cum. 2.87
1.00 5.90 0.85 1.20 cum. 6.02
1.00 3.00 0.60 0.95 cum. 1.71
1.00 1.50 0.60 0.95 cum. 0.85
1.00 1.30 0.60 0.95 cum. 0.74
1.00 2.50 0.60 0.95 cum. 1.42
1.00 1.20 0.60 0.95 cum. 0.68
1.00 2.10 0.60 0.95 cum. 1.20
1.00 5.40 0.60 0.95 cum. 3.08
1.00 4.60 0.60 0.95 cum. 2.62

Contractor Prepared By Checked By Approved By


Pages -213 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.95 cum. 1.31
1.00 1.65 0.60 0.95 cum. 0.94
1.00 2.10 0.60 0.45 cum. 0.57
1.00 1.30 0.60 0.30 cum. 0.23
1.00 3.00 0.60 0.90 cum. 1.62
1.00 13.50 0.60 0.90 cum. 7.29
for RS Walls (From North to South) -4th step 1.00 15.10 0.60 0.90 cum. 8.15
Whole Kund of Radius 3.15m 1.00 31.16 0.80 cum. 24.93
Outer wall extra depth 0.15m 1.00 17.20 0.50 0.15 cum. 1.29
First step extra 0.15m depth 1.00 10.40 0.60 0.15 cum. 0.94
French Drain 1.00 120.00 0.60 0.60 cum. 43.20
Retaining Wall 1.00 2.90 0.75 1.20 cum. 2.61
East side 1.00 9.40 0.75 1.20 cum. 8.46
East side 1.00 6.80 0.75 1.20 cum. 6.12
East side 1.00 6.90 0.75 0.45 cum. 2.33
East side 1.00 8.40 0.75 1.10 cum. 6.93
East side 1.00 5.20 0.75 1.10 cum. 4.29
East side 1.00 7.10 0.75 1.10 cum. 5.86
East side 1.00 8.80 0.75 1.10 cum. 7.26
East side 1.00 6.50 1.00 2.00 cum. 13.00
South east side 1.00 2.20 1.00 2.00 cum. 4.40
South side 1.00 28.50 0.90 2.00 cum. 51.30
Brick wall south side 1.00 20.50 0.90 1.00 cum. 18.45
Brick wall west side 1.00 4.00 0.90 1.00 cum. 3.60
River bank wall 1.00 8.50 2.00 2.00 cum. 34.00
1.00 9.50 2.00 2.00 cum. 38.00
1.00 6.50 1.75 1.20 cum. 13.65
1.00 4.45 1.75 1.20 cum. 9.35
1.00 6.43 1.75 1.20 cum. 13.50
1.00 0.80 1.75 1.20 cum. 1.68
1.00 5.10 1.75 1.20 cum. 10.71
1.00 2.32 1.75 1.20 cum. 4.87
1.00 3.30 1.75 1.20 cum. 6.93
1.00 11.10 1.75 1.20 cum. 23.31
1.00 1.45 1.75 1.20 cum. 3.05
1.00 3.95 1.75 1.20 cum. 8.30
1.00 7.50 1.75 1.20 cum. 15.75
1.00 1.80 1.75 1.20 cum. 3.78
Concrete Drain 1.00 12.68 0.60 0.50 cum. 3.80
1.00 10.90 0.60 0.50 cum. 3.27
1.00 2.00 0.60 0.50 cum. 0.60
1.00 1.65 0.60 0.50 cum. 0.49
1.00 1.28 0.60 0.50 cum. 0.38
1.00 4.40 0.60 0.50 cum. 1.32
1.00 7.25 0.60 0.50 cum. 2.18
1.00 7.40 0.60 0.50 cum. 2.22
Contractor Prepared By Checked By Approved By
Pages -214 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 1.00 0.60 0.50 cum. 0.30
1.00 6.90 0.60 0.50 cum. 2.07
1.00 7.30 0.60 0.50 cum. 2.19
1.00 3.50 0.60 0.50 cum. 1.05
1.00 9.90 0.60 0.50 cum. 2.97
1.00 9.50 0.60 0.50 cum. 2.85
1.00 5.10 0.60 0.50 cum. 1.53
1.00 6.00 0.60 0.50 cum. 1.80
1.00 11.20 0.60 0.50 cum. 3.36
1.00 1.50 0.60 0.50 cum. 0.45
1.00 8.35 0.60 0.50 cum. 2.51
1.00 3.10 0.60 0.50 cum. 0.93
1.00 1.80 0.60 0.50 cum. 0.54
1.00 7.50 0.60 0.50 cum. 2.25
1.00 2.40 0.60 0.50 cum. 0.72
1.00 3.60 0.60 0.50 cum. 1.08
1.00 3.00 0.60 0.50 cum. 0.90
1.00 1.30 0.60 0.50 cum. 0.39
1.00 6.00 0.60 0.75 cum. 2.70
1.00 22.00 0.60 0.75 cum. 9.90
Shiv mandir east 1.00 13.00 0.60 0.50 cum. 3.90
Shiv mandir north 1.00 9.20 0.60 0.50 cum. 2.76
Catch Basin 3.00 1.00 1.00 1.05 cum. 3.15
RO Base 1.00 31.00 1.50 1.50 cum. 69.75
RE 1.00 33.80 1.50 1.50 cum. 76.05
RE 1.00 13.00 1.50 1.50 cum. 29.25
RE 1.00 4.30 1.00 2.00 cum. 8.60
RE 1.00 9.00 1.00 1.70 cum. 15.30
RC 3.00 3.50 5.30 3.30 cum. 183.65
RS1 1.00 20.00 0.75 1.00 cum. 15.00
RS2 1.00 19.50 0.75 1.40 cum. 20.47
RS3 1.00 19.50 0.75 2.10 cum. 30.71
RS4 1.00 23.90 0.75 1.00 cum. 17.92
RE 1.00 13.00 0.40 0.45 cum. 2.34
1.00 29.70 0.40 0.45 cum. 5.35
1.00 24.70 0.40 0.45 cum. 4.45
1.00 11.50 0.40 0.45 cum. 2.07
1.00 10.40 0.40 0.45 cum. 1.87
1.00 13.90 0.40 0.45 cum. 2.50
1.00 10.90 0.40 0.45 cum. 1.96
1.00 11.50 0.40 0.45 cum. 2.07
1.00 5.50 0.40 0.45 cum. 0.99
1.00 28.00 0.40 0.45 cum. 5.04
1.00 24.70 0.40 0.45 cum. 4.45
1.00 11.90 0.40 0.45 cum. 2.14
For Soling & PCC
PCC P2 1.00 6.10 6.90 0.15 cum. 6.31

Contractor Prepared By Checked By Approved By


Pages -215 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 5.80 6.80 0.15 cum. 5.92
Deduction (1.00) 4.40 0.55 0.15 cum. (0.36)
Stone Pillar (10.00) 0.40 0.40 0.15 cum. (0.24)
1.00 7.50 4.20 0.15 cum. 4.73
1.00 7.30 4.20 0.15 cum. 4.60
(1.00) 1.77 0.05 0.15 cum. (0.01)
(1.00) 0.60 0.30 0.15 cum. (0.03)
(1.00) 4.10 0.50 0.15 cum. (0.31)
(1.00) 0.70 0.37 0.15 cum. (0.04)
1.00 6.60 1.25 0.15 cum. 1.24
RCC 1.00 6.30 1.15 0.22 cum. 1.63
RCC 1.00 4.45 1.00 0.22 cum. 1.00
RCC 1.00 3.10 1.10 0.22 cum. 0.77
RCC 1.00 1.20 2.50 0.22 cum. 0.67
P3 1.00 11.30 4.95 0.15 cum. 8.39
1.00 11.05 5.20 0.15 cum. 8.62
PCC At Aarati Side 1.00 5.40 4.80 0.25 cum. 6.48
1.00 4.55 1.95 0.25 cum. 2.22
1.00 2.10 3.47 0.25 cum. 1.82
1.00 7.20 3.03 0.25 cum. 5.45
1.00 9.45 3.93 0.25 cum. 9.27
1.00 2.00 3.22 0.25 cum. 1.61
1.00 1.70 1.50 0.25 cum. 0.64
1.00 1.20 9.00 0.22 cum. 2.43
1.00 6.00 0.07 0.22 cum. 0.09
1.00 14.50 0.70 0.22 cum. 2.28
1.00 0.70 5.40 0.22 cum. 0.85
1.00 1.12 4.40 0.22 cum. 1.10
1.00 1.65 3.80 0.22 cum. 1.41
1.00 1.05 3.90 0.22 cum. 0.92
1.00 1.70 2.18 0.22 cum. 0.83
1.00 2.63 4.83 0.22 cum. 2.85
1.00 0.90 9.70 0.22 cum. 1.96
1.00 1.00 9.55 0.22 cum. 2.15
Stone masonry 1.00 31.00 1.86 0.30 cum. 17.30
1.00 10.40 1.73 0.30 cum. 5.40
1.00 9.90 1.38 0.30 cum. 4.10
1.00 9.50 1.76 0.30 cum. 5.02
1.00 9.90 1.05 0.30 cum. 3.12
1.00 8.90 1.05 0.30 cum. 2.80
1.00 7.30 0.92 0.30 cum. 2.01
1.00 6.60 0.45 0.75 cum. 2.23
This Bill
Soling Exv
N. RS 8& RS 9 1.00 2.16 2.23 0.525 cum. 2.53
RS 9 RS 10 1.00 22.70 1.36 0.525 cum. 16.21
N .RS 8 WALL 1.00 4.25 0.40 0.525 cum. 0.89
N.RC 1.00 3.20 3.80 0.525 cum. 6.38

Contractor Prepared By Checked By Approved By


Pages -216 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
rs 1 ganesh mandir 1.00 5.00 0.45 0.525 cum. 1.18
RS 1 & RS 2 PIPAL S 1.00 3.70 2.50 0.525 cum. 4.86
RS 1 & RS 2 TREE 1.00 4.40 1.98 0.525 cum. 4.57
RS 1 & RS 2 TREE 1.00 5.30 2.35 0.525 cum. 6.54
last step 1.00 20.00 0.80 0.525 cum. 8.40
1.00 18.90 0.80 0.525 cum. 7.94
1.00 13.80 0.80 0.525 cum. 5.80
1.00 4.10 0.80 0.525 cum. 1.72
1.00 2.98 0.55 0.525 cum. 0.86
For Cutting at bed Retaining wall 1.00 20 2.32 0.6 cum. 27.84
1.00 16 0.8 0.5 cum. 6.40
1.00 8.4 0.48 0.5 cum. 2.02
Drain Exv 1.00 89.90 0.60 0.75 cum. 40.46
Water Reserve 1.00 5.10 1.50 Area cum. 7.66
1.00 0.50 0.65 0.625 cum. 0.20
1.00 2.55 0.30 0.625 cum. 0.48
Ramp Brick Wall 1.00 12.20 0.45 1 cum. 5.49
Ramp Brick Wall 1.00 12.20 0.45 0.50 cum. 2.75
For Main Gate
Foundation 4.00 1.20 1.20 1.50 cum 8.64
For Beam 2.00 3.75 0.30 0.75 cum 1.69
2.00 1.80 0.30 0.75 cum 0.81
For Boundary Wall 1.00 1.70 0.50 0.90 cum 0.77
Power House 1.00 1.80 1.80 0.60 cum 1.94
Ramp Excavation 1.00 20.30 2.83 0.30 cum 17.26
Steps near Water reserve 1.00 4.85 1.20 1.00 cum 5.82
1.00 2.65 1.05 0.75 cum 2.09
1,210.16 Total= Cum 1,410.34 200.17 250.00 50043.02
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
125 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
for RT Walls (From North To South) 1.00 3.70 1.00 0.30 cum. 1.11
1.00 2.00 1.00 0.30 cum. 0.60
1.00 6.85 1.00 0.30 cum. 2.05
1.00 4.00 1.00 0.30 cum. 1.20
1.00 3.90 1.00 0.30 cum. 1.17
1.00 8.80 1.00 0.30 cum. 2.64
1.00 4.75 1.10 0.30 cum. 1.57
1.00 1.10 1.00 0.30 cum. 0.33
1.00 11.30 1.00 0.30 cum. 3.39
2.00 1.00 1.00 0.30 cum. 0.60
1.00 4.45 1.00 0.30 cum. 1.34
1.00 3.40 1.00 0.30 cum. 1.02
1.00 4.75 1.00 0.30 cum. 1.43
Contractor Prepared By Checked By Approved By
Pages -217 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.30 cum. 0.97
1.00 5.50 0.85 0.30 cum. 1.40
1.00 5.20 0.85 0.30 cum. 1.33
1.00 5.90 0.85 0.30 cum. 1.50
1.00 3.00 0.60 0.30 cum. 0.54
1.00 1.50 0.60 0.30 cum. 0.27
1.00 1.30 0.60 0.30 cum. 0.23
1.00 2.50 0.60 0.30 cum. 0.45
1.00 1.20 0.60 0.30 cum. 0.22
1.00 2.10 0.60 0.30 cum. 0.38
1.00 5.40 0.60 0.30 cum. 0.97
1.00 4.60 0.60 0.30 cum. 0.83
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.30 cum. 0.41
1.00 1.65 0.60 0.30 cum. 0.30
1.00 2.10 0.60 0.30 cum. 0.38
1.00 1.30 0.60 0.30 cum. 0.23
1.00 3.00 0.60 0.30 cum. 0.54
1.00 13.50 0.60 0.30 cum. 2.43
for RS Walls (From North to South) -4th step 1.00 15.10 0.60 0.30 cum. 2.72
Outer wall 1.00 17.20 0.50 0.30 cum. 2.58
First step 1.00 10.40 0.60 0.30 cum. 1.87
French Drain 1.00 120.00 0.60 0.30 cum. 21.60
East side 1.00 6.50 0.50 1.00 cum. 3.25
South east side 1.00 2.20 0.50 1.00 cum. 1.10
South side 1.00 28.50 0.50 1.00 cum. 14.25
Brick wall south side 1.00 20.50 0.50 1.00 cum. 10.25
Brick wall west side 1.00 4.00 0.50 1.00 cum. 2.00
River bank wall 1.00 8.50 0.50 1.00 cum. 4.25
1.00 9.50 0.50 1.00 cum. 4.75
1.00 6.50 0.50 1.20 cum. 3.90

Contractor Prepared By Checked By Approved By


Pages -218 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 4.45 0.50 1.20 cum. 2.67
1.00 6.43 0.50 1.20 cum. 3.86
1.00 0.80 0.50 1.20 cum. 0.48
1.00 5.10 0.50 1.20 cum. 3.06
1.00 2.32 0.50 1.20 cum. 1.39
1.00 3.30 0.50 1.20 cum. 1.98
1.00 11.10 0.50 1.20 cum. 6.66
1.00 1.45 0.50 1.20 cum. 0.87
1.00 3.95 0.50 1.20 cum. 2.37
1.00 7.50 0.50 1.20 cum. 4.50
1.00 1.80 0.50 1.20 cum. 1.08
1.00 2.90 0.50 0.90 cum. 1.31
1.00 9.40 0.50 0.90 cum. 4.23
1.00 6.80 0.50 0.90 cum. 3.06
1.00 6.90 0.50 0.90 cum. 3.11
1.00 8.40 0.50 0.90 cum. 3.78
1.00 5.20 0.50 0.90 cum. 2.34
1.00 7.10 0.50 0.90 cum. 3.20
1.00 8.80 0.50 0.90 cum. 3.96
Mandap Area 1.00 5.00 4.50 1.00 cum. 22.50
Between P3 and Mandap 1.00 5.00 4.00 0.50 cum. 10.00
Mandap east slope area (from cad) 1.00 15.00 1.00 cum. 15.00
Catch Basain 12.00 0.20 0.70 0.90 cum. 1.51
RO Base 1.00 31.00 0.50 0.90 cum. 13.95
RE 1.00 33.80 0.50 0.90 cum. 15.21
RE 1.00 13.00 0.50 0.90 cum. 5.85
RE 1.00 4.30 0.50 0.90 cum. 1.94
RE 1.00 9.00 0.50 0.90 cum. 4.05
RC 3.00 3.50 5.30 0.90 cum. 50.09
RS1 1.00 20.00 0.75 0.90 cum. 13.50
RS2 1.00 19.50 0.75 0.90 cum. 13.16
RS3 1.00 19.50 0.75 0.90 cum. 13.16
RS4 1.00 23.90 0.75 0.90 cum. 16.13
Sub-Total 354.29
On hold 137.62
216.67 Total= Cum 216.67 0.00 300.00 0.00

Contractor Prepared By Checked By Approved By


Pages -219 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
126 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

for RT Walls (From North To South) 1.00 3.70 0.90 0.15 cum. 0.50
1.00 2.00 0.90 0.15 cum. 0.27
1.00 6.75 0.90 0.15 cum. 0.91
1.00 4.00 0.90 0.15 cum. 0.54
1.00 3.80 0.90 0.15 cum. 0.51
1.00 8.80 0.90 0.15 cum. 1.19
1.00 4.75 0.90 0.15 cum. 0.64
1.00 1.10 0.90 0.15 cum. 0.15
1.00 11.30 0.90 0.15 cum. 1.53
2.00 1.00 0.90 0.15 cum. 0.14
1.00 4.45 0.90 0.15 cum. 0.60
1.00 3.40 0.90 0.15 cum. 0.46
1.00 4.75 0.90 0.15 cum. 0.64
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.15 cum. 0.48
1.00 5.50 0.85 0.15 cum. 0.70
1.00 5.20 0.85 0.15 cum. 0.66
1.00 5.90 0.85 0.15 cum. 0.75
1.00 3.00 0.60 0.15 cum. 0.27
1.00 1.50 0.60 0.15 cum. 0.13
1.00 1.30 0.60 0.15 cum. 0.12
1.00 2.50 0.60 0.15 cum. 0.22
1.00 1.20 0.60 0.15 cum. 0.11
1.00 2.10 0.60 0.15 cum. 0.19
1.00 5.30 0.60 0.15 cum. 0.48
1.00 4.60 0.60 0.15 cum. 0.41
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.15 cum. 0.21
1.00 1.65 0.60 0.15 cum. 0.15
1.00 2.10 0.60 0.15 cum. 0.19
1.00 1.30 0.60 0.15 cum. 0.12
1.00 3.00 0.60 0.15 cum. 0.27
1.00 13.50 0.60 0.15 cum. 1.21
for RS Walls (From North to South) -4th step 1.00 15.00 0.60 0.15 cum. 1.35
Outer wall 1.00 17.10 0.60 0.15 cum. 1.54
First step 1.00 10.40 0.60 0.15 cum. 0.94
center 1.00 8.04 0.60 0.15 cum. 0.72
for RT Walls (From North To South) 1.00 2.90 0.75 0.15 cum. 0.33
Contractor Prepared By Checked By Approved By
Pages -220 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 9.40 0.75 0.15 cum. 1.06
1.00 6.80 0.75 0.15 cum. 0.76
1.00 6.90 0.75 0.15 cum. 0.78
1.00 8.40 0.75 0.15 cum. 0.95
1.00 5.20 0.75 0.15 cum. 0.59
1.00 7.10 0.75 0.15 cum. 0.80
1.00 8.80 0.75 0.15 cum. 0.99
East side 1.00 6.50 0.90 0.15 cum. 0.88
South east side 1.00 2.20 0.90 0.15 cum. 0.30
South side 1.00 28.50 0.90 0.15 cum. 3.85
River bank wall 1.00 8.50 2.00 0.15 cum. 2.55
1.00 9.50 2.00 0.15 cum. 2.85
1.00 6.50 1.75 0.15 cum. 1.71
1.00 4.45 1.75 0.15 cum. 1.17
1.00 6.43 1.75 0.15 cum. 1.69
1.00 0.80 1.75 0.15 cum. 0.21
1.00 5.10 1.75 0.15 cum. 1.34
1.00 2.32 1.75 0.15 cum. 0.61
1.00 3.30 1.75 0.15 cum. 0.87
1.00 11.10 1.75 0.15 cum. 2.91
1.00 1.45 1.75 0.15 cum. 0.38
1.00 3.95 1.75 0.15 cum. 1.04
1.00 7.50 1.75 0.15 cum. 1.97
1.00 1.80 1.75 0.15 cum. 0.47
RO Base 1.00 31.00 1.50 0.20 cum. 9.30
RE 1.00 33.80 1.50 0.20 cum. 10.14
RE 1.00 13.00 1.50 0.20 cum. 3.90
RE 1.00 4.30 1.00 0.20 cum. 0.86
RE 1.00 9.00 1.00 0.20 cum. 1.80
RC 3.00 3.50 5.30 0.20 cum. 11.13
RS1 1.00 20.00 0.75 0.20 cum. 3.00
RS2 1.00 19.50 0.75 0.20 cum. 2.93
RS3 1.00 19.50 0.75 0.20 cum. 2.93
RS4 1.00 23.90 0.75 0.20 cum. 3.58
RE 1.00 13.00 0.40 0.20 cum. 1.04
1.00 29.70 0.40 0.20 cum. 2.38
1.00 24.70 0.40 0.20 cum. 1.98
1.00 11.50 0.40 0.20 cum. 0.92
1.00 10.40 0.40 0.20 cum. 0.83
1.00 13.90 0.40 0.20 cum. 1.11
1.00 10.90 0.40 0.20 cum. 0.87
1.00 11.50 0.40 0.20 cum. 0.92
1.00 5.50 0.40 0.20 cum. 0.44
1.00 28.00 0.40 0.20 cum. 2.24
1.00 24.70 0.40 0.20 cum. 1.98
1.00 11.90 0.40 0.20 cum. 0.95
RCC 1.00 6.30 1.15 0.20 cum. 1.45

Contractor Prepared By Checked By Approved By


Pages -221 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RCC 1.00 4.45 1.00 0.20 cum. 0.89
RCC 1.00 3.10 1.10 0.20 cum. 0.68
RCC 1.00 1.20 2.50 0.20 cum. 0.60
PCC At Aarati Side 1.00 5.40 4.80 0.20 cum. 5.18
1.00 4.55 1.95 0.20 cum. 1.77
1.00 2.10 3.47 0.20 cum. 1.46
1.00 7.20 3.03 0.20 cum. 4.36
1.00 9.45 3.93 0.20 cum. 7.42
1.00 2.00 3.22 0.20 cum. 1.29
1.00 1.70 1.50 0.20 cum. 0.51
1.00 1.20 9.00 0.20 cum. 2.16
1.00 6.00 0.07 0.20 cum. 0.08
1.00 14.50 0.70 0.20 cum. 2.03
1.00 0.70 5.40 0.20 cum. 0.76
1.00 1.12 4.40 0.20 cum. 0.98
1.00 1.65 3.80 0.20 cum. 1.25
1.00 1.05 3.90 0.20 cum. 0.82
1.00 1.70 2.18 0.20 cum. 0.74
1.00 2.63 4.83 0.20 cum. 2.53
1.00 0.90 9.70 0.20 cum. 1.75
1.00 1.00 9.55 0.20 cum. 1.91
1.00 14.42 9.55 0.20 cum. 27.54
1.00 2.30 9.55 0.20 cum. 4.39
1.00 1.24 9.55 0.20 cum. 2.37
1.00 1.23 9.55 0.20 cum. 2.35
1.00 10.11 9.55 0.20 cum. 19.31
1.00 11.12 9.55 0.20 cum. 21.24
soling 1.00 31 1.86 0.15 cum. 8.65
1.00 9.6 0.83 0.15 cum. 1.20
1.00 9.8 0.95 0.15 cum. 1.40
1.00 10.3 0.86 0.15 cum. 1.33
1.00 9.3 0.95 0.15 cum. 1.33
1.00 10.4 1.73 0.15 cum. 2.70
1.00 9.9 1.38 0.15 cum. 2.05
1.00 9.5 1.76 0.15 cum. 2.51
1.00 9.9 1.05 0.15 cum. 1.56
1.00 8.9 1.05 0.15 cum. 1.40
1.00 7.3 0.92 0.15 cum. 1.01
1.00 6.6 0.45 0.15 cum. 0.45
1.00 10 1.24 0.15 cum. 1.86
1.00 4.4 0.45 0.15 cum. 0.30
1.00 4.4 2.4 0.15 cum. 1.58
1.00 3.5 1.5 0.15 cum. 0.79
1.00 4 2.4 0.15 cum. 1.44
1.00 4.4 2.4 0.15 cum. 1.58
1.00 3.4 1.8 0.15 cum. 0.92

Contractor Prepared By Checked By Approved By


Pages -222 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
This Bill
N. RS 8& RS 9 1.00 2.16 2.23 0.15 cum. 0.72
RS 9 RS 10 1.00 22.70 1.36 0.15 cum. 4.63
N .RS 8 WALL 1.00 4.25 0.40 0.15 cum. 0.26
N.RC 1.00 3.20 3.80 0.15 cum. 1.82
rs 1 ganesh mandir 1.00 5.00 0.45 0.15 cum. 0.34
RS 1 & RS 2 PIPAL S 1.00 3.70 2.50 0.15 cum. 1.39
RS 1 & RS 2 TREE 1.00 4.40 1.98 0.15 cum. 1.31
RS 1 & RS 2 TREE 1.00 5.30 2.35 0.15 cum. 1.87
last step 1.00 20.00 0.80 0.15 cum. 2.40
1.00 18.90 0.80 0.15 cum. 2.27
1.00 13.80 0.80 0.15 cum. 1.66
1.00 4.10 0.80 0.15 cum. 0.49
1.00 2.98 0.55 0.15 cum. 0.25
Ramp Soling 1.00 20.30 2.83 0.15 Cum 8.63
Ramp Excavation 1.00 20.30 2.83 0.15 cum 8.63
Steps near Water reserve 1.00 4.85 1.20 0.15 cum 0.87
1.00 2.65 1.05 0.15 cum 0.42
267.41 Total= Cum 305.35 37.94 3000.00 113818.78
127 Brick soling work
Providing and laying a single layer flat brick soling on
drainage works on lanscape for preparation of P.C.C.
in which joints should be packed by sand to the
required levels all complete as per drawings,
specifications and the instructions of the Engineer.
From kund to Mandap 1.00 16.50 1.25 sqm. 20.63
From tree to shiv mandir 1.00 30.30 1.50 sqm. 45.45
north of P3-A 1.00 4.32 1.25 sqm. 5.40
South of P3-A 1.00 4.00 1.25 sqm. 5.00
Towards baba ramdev temple 1.00 6.50 1.50 sqm. 9.75
towards bishwokarma temple 2.00 7.00 1.25 sqm. 17.50
Towards P4 1.00 6.20 1.25 sqm. 7.75
For P4 1.00 3.00 1.50 sqm. 4.50
For P4 1.00 4.50 1.50 sqm. 6.75
Near P2 1.00 3.50 1.25 sqm. 4.38
Infront of ram mandir (Dia-4.9m outer and 2.1m inner) 1.00 15.39 sqm. 15.39
Around Kund 1.00 33.34 sqm. 33.34
From kund to p1 1.00 1.50 2.00 sqm. 3.00
Near Mandap 1.00 2.50 1.50 sqm. 3.75
1.00 4.00 1.50 sqm. 6.00
1.00 1.00 1.50 sqm. 1.50
To Ramdev Baba temple 1.00 7.00 1.50 sqm. 10.50
Concrete Drainage 1.00 12.68 0.60 sqm. 7.61
1.00 10.90 0.60 sqm. 6.54
1.00 2.00 0.60 sqm. 1.20

Contractor Prepared By Checked By Approved By


Pages -223 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 1.65 0.60 sqm. 0.99
1.00 1.28 0.60 sqm. 0.77
1.00 4.40 0.60 sqm. 2.64
1.00 7.25 0.60 sqm. 4.35
1.00 7.40 0.60 sqm. 4.44
1.00 1.00 0.60 sqm. 0.60
1.00 6.90 0.60 sqm. 4.14
1.00 7.30 0.60 sqm. 4.38
1.00 3.50 0.60 sqm. 2.10
1.00 9.90 0.60 sqm. 5.94
1.00 9.50 0.60 sqm. 5.70
1.00 5.10 0.60 sqm. 3.06
1.00 6.00 0.60 sqm. 3.60
1.00 11.20 0.60 sqm. 6.72

Contractor Prepared By Checked By Approved By


Pages -224 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 1.50 0.60 sqm. 0.90
1.00 8.35 0.60 sqm. 5.01
1.00 3.10 0.60 sqm. 1.86
1.00 1.80 0.60 sqm. 1.08
1.00 7.50 0.60 sqm. 4.50
1.00 2.40 0.60 sqm. 1.44
1.00 3.60 0.60 sqm. 2.16
1.00 3.00 0.60 sqm. 1.80
1.00 1.30 0.60 sqm. 0.78
1.00 6.00 0.60 sqm. 3.60
1.00 22.00 0.60 sqm. 13.20
Shiv mandir east 1.00 13.00 0.60 sqm. 7.80
Shiv mandir north 1.00 9.20 0.60 sqm. 5.52
Catch Basin 3.00 1.00 1.00 sqm. 3.00
1.00 20.50 0.75 sqm. 15.38
1.00 4.00 0.75 sqm. 3.00
Parking 1.00 4.00 20.50 sqm. 82.00
PCC P2 1.00 6.10 6.90 sqm. 42.09
1.00 5.80 6.80 sqm. 39.44
Deduction (1.00) 4.40 0.55 sqm. (2.42)
Stone Pillar (10.00) 0.40 0.40 sqm. (1.60)
1.00 7.50 4.20 sqm. 31.50
1.00 7.30 4.20 sqm. 30.66
(1.00) 1.77 0.05 sqm. (0.09)
(1.00) 0.60 0.30 sqm. (0.18)
(1.00) 4.10 0.50 sqm. (2.05)
(1.00) 0.70 0.37 sqm. (0.26)
1.00 6.60 1.25 sqm. 8.25
This Bill -
Drain Exv 1.00 89.90 0.50 sqm. 44.95
Water Reserve 1.00 7.90 0.38 sqm. 2.96
1.00 0.50 0.65 sqm. 0.33
1.00 2.55 0.30 sqm. 0.76
Ramp Brick Wall 1.00 12.20 0.45 sqm. 5.49
Ramp Brick Wall 1.00 12.20 0.45 sqm. 5.49
For Main Gate -
Foundation 4.00 1.20 1.20 sqm. 5.76
For Beam 2.00 3.75 0.30 sqm. 2.25
2.00 1.80 0.30 sqm. 1.08
For Boundary Wall 1.00 1.70 0.50 sqm. 0.85
Power House 1.00 1.80 1.80 sqm. 3.24
Ramp Excavation 1.00 12.20 3.00 sqm. 36.60
p2 west 1.00 3.3 1.25 sqm. 4.13
563.72 Total= Sqm 677.61 113.89 700.00 79721.25
128 PCC Works

Contractor Prepared By Checked By Approved By


Pages -225 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

Bottom of Kunda 1.00 8.06 0.10 cum. 0.81


1st Step Wall 1.00 17.10 0.75 0.08 cum. 0.96
2nd Step 1.00 13.75 0.75 0.08 cum. 0.77
3rd Step 1.00 10.40 0.60 0.08 cum. 0.47
Tree Protection Wall 1.00 1.50 0.35 0.08 cum. 0.04
Tree Protection Wall 1.00 1.40 0.35 0.08 cum. 0.04
2nd Step 1.00 13.75 0.19 0.08 cum. 0.20
1.00 13.75 0.42 0.08 cum. 0.43
3rd Step 1.00 10.40 0.70 0.08 cum. 0.55
for RT Walls (From North To South) 1.00 3.70 0.90 0.08 cum. 0.25
1.00 2.00 0.90 0.08 cum. 0.14
1.00 6.75 0.90 0.08 cum. 0.46
1.00 4.00 0.90 0.08 cum. 0.27
1.00 3.80 0.90 0.08 cum. 0.26
1.00 8.80 0.90 0.08 cum. 0.59
1.00 4.75 0.90 0.08 cum. 0.32
1.00 1.10 0.90 0.08 cum. 0.07
1.00 11.30 0.90 0.08 cum. 0.76
2.00 1.00 0.90 0.08 cum. 0.14
1.00 4.45 0.90 0.08 cum. 0.30
1.00 3.40 0.90 0.08 cum. 0.23
1.00 4.75 0.90 0.08 cum. 0.32
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.08 cum. 0.24
1.00 5.50 0.85 0.08 cum. 0.35
1.00 5.20 0.85 0.08 cum. 0.33
1.00 5.90 0.85 0.08 cum. 0.38
1.00 3.00 0.60 0.08 cum. 0.13
1.00 1.50 0.60 0.08 cum. 0.07
1.00 1.30 0.60 0.08 cum. 0.06
1.00 2.50 0.60 0.08 cum. 0.11
1.00 1.20 0.60 0.08 cum. 0.05
1.00 2.10 0.60 0.08 cum. 0.09
1.00 5.30 0.60 0.08 cum. 0.24
1.00 4.60 0.60 0.08 cum. 0.21
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.08 cum. 0.10
1.00 1.65 0.60 0.08 cum. 0.07
1.00 2.10 0.60 0.08 cum. 0.09
1.00 1.30 0.60 0.08 cum. 0.06
1.00 3.00 0.60 0.08 cum. 0.13
1.00 13.50 0.60 0.08 cum. 0.61

Contractor Prepared By Checked By Approved By


Pages -226 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
for RS Walls (From North to South) -4th step 1.00 15.00 0.60 0.08 cum. 0.67
Outer wall 1.00 17.10 0.60 0.08 cum. 0.77
First step 1.00 10.40 0.60 0.08 cum. 0.47
center 1.00 8.04 0.60 0.08 cum. 0.36
From kund to Mandap 1.00 16.50 1.25 0.10 cum. 2.06
From tree to shiv mandir 1.00 30.30 1.50 0.10 cum. 4.55
north of P3-A 1.00 4.32 1.25 0.10 cum. 0.54
South of P3-A 1.00 4.00 1.25 0.10 cum. 0.50
Towards baba ramdev temple 1.00 6.50 1.50 0.10 cum. 0.98
towards bishwokarma temple 2.00 7.00 1.25 0.10 cum. 0.88
Towards P4 1.00 6.20 1.25 0.10 cum. 0.78
For P4 1.00 3.00 1.50 0.10 cum. 0.45
For P4 1.00 4.50 1.50 0.10 cum. 0.68
Near P2 1.00 3.50 1.25 0.10 cum. 0.44
Infront of ram mandir (Dia-4.9m outer and 2.1m inner) 1.00 15.49 0.10 cum. 1.55
Around Kund 1.00 34.35 0.10 cum. 3.44
From kund to p1 1.00 1.50 2.00 0.10 cum. 0.30
Near Mandap 1.00 2.50 1.50 0.10 cum. 0.38
1.00 4.00 1.50 0.10 cum. 0.60
1.00 1.00 1.50 0.10 cum. 0.15
To Ramdev Baba temple 1.00 7.00 1.50 0.10 cum. 1.05
Concrete Drainage 1.00 12.68 0.60 0.10 cum. 0.76
1.00 10.90 0.60 0.10 cum. 0.65
1.00 2.00 0.60 0.10 cum. 0.12
1.00 1.65 0.60 0.10 cum. 0.10
1.00 1.28 0.60 0.10 cum. 0.08
1.00 4.40 0.60 0.10 cum. 0.26
1.00 7.25 0.60 0.10 cum. 0.44
1.00 7.40 0.60 0.10 cum. 0.44
1.00 1.00 0.60 0.10 cum. 0.06
1.00 6.90 0.60 0.10 cum. 0.41
1.00 7.30 0.60 0.10 cum. 0.44
1.00 3.50 0.60 0.10 cum. 0.21
1.00 9.90 0.60 0.10 cum. 0.59
1.00 9.50 0.60 0.10 cum. 0.57
1.00 5.10 0.60 0.10 cum. 0.31
1.00 6.00 0.60 0.10 cum. 0.36
1.00 11.20 0.60 0.10 cum. 0.67
1.00 1.50 0.60 0.10 cum. 0.09
1.00 8.35 0.60 0.10 cum. 0.50
1.00 3.10 0.60 0.10 cum. 0.19
1.00 1.80 0.60 0.10 cum. 0.11
1.00 7.50 0.60 0.10 cum. 0.45
1.00 2.40 0.60 0.10 cum. 0.14
1.00 3.60 0.60 0.10 cum. 0.22
1.00 3.00 0.60 0.10 cum. 0.18
Contractor Prepared By Checked By Approved By
Pages -227 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 1.30 0.60 0.10 cum. 0.08
1.00 6.00 0.60 0.10 cum. 0.36
1.00 22.00 0.60 0.10 cum. 1.32
Shiv mandir east 1.00 13.00 0.60 0.10 cum. 0.78
Shiv mandir north 1.00 9.20 0.60 0.10 cum. 0.55
Catch Basin 3.00 1.00 1.00 0.10 cum. 0.10
1.00 20.50 0.75 0.10 cum. 1.54
1.00 4.00 0.75 0.10 cum. 0.30
Parking 1.00 4.00 20.50 0.10 cum. 8.20
Concrete Drainage 2.00 12.68 0.10 0.35 cum. 0.44
2.00 10.90 0.10 0.35 cum. 0.38
2.00 2.00 0.10 0.35 cum. 0.07
2.00 1.65 0.10 0.35 cum. 0.06
2.00 1.28 0.10 0.35 cum. 0.04
2.00 4.40 0.10 0.35 cum. 0.15
2.00 7.25 0.10 0.35 cum. 0.25
2.00 7.40 0.10 0.35 cum. 0.26
2.00 1.00 0.10 0.35 cum. 0.03
2.00 6.90 0.10 0.35 cum. 0.24
2.00 7.30 0.10 0.35 cum. 0.26
2.00 3.50 0.10 0.35 cum. 0.12
2.00 9.90 0.10 0.35 cum. 0.35
2.00 9.50 0.10 0.35 cum. 0.33
2.00 5.10 0.10 0.35 cum. 0.18
2.00 6.00 0.10 0.35 cum. 0.21
2.00 11.20 0.10 0.35 cum. 0.39
2.00 1.50 0.10 0.35 cum. 0.05
2.00 8.35 0.10 0.35 cum. 0.29
2.00 3.10 0.10 0.35 cum. 0.11
2.00 1.80 0.10 0.35 cum. 0.06
2.00 7.50 0.10 0.35 cum. 0.26
2.00 2.40 0.10 0.35 cum. 0.08
2.00 3.60 0.10 0.35 cum. 0.13
2.00 3.00 0.10 0.35 cum. 0.11
2.00 1.30 0.10 0.35 cum. 0.05
2.00 6.00 0.10 0.50 cum. 0.30
2.00 22.00 0.10 0.50 cum. 1.10
Shiv mandir east 2.00 13.00 0.10 0.40 cum. 0.52
Shiv mandir north 2.00 9.20 0.10 0.40 cum. 0.37
1.00 4.40 0.50 0.08 cum. 0.17
1.00 20.00 0.50 0.08 cum. 0.75
1.00 37.00 0.45 0.08 cum. 1.25
Base PCC cum.
RO 1.00 31.00 1.50 0.10 cum. 4.65
RE 1.00 33.80 1.50 0.10 cum. 5.07
RE 1.00 13.00 1.50 0.10 cum. 1.95

Contractor Prepared By Checked By Approved By


Pages -228 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RE 1.00 4.30 1.00 0.10 cum. 0.43
RE 1.00 9.00 1.00 0.10 cum. 0.90
RC 3.00 3.50 5.30 0.10 cum. 5.57
RS1 1.00 20.00 0.75 0.08 cum. 1.13
RS2 1.00 19.50 0.75 0.08 cum. 1.10
RS3 1.00 19.50 0.75 0.08 cum. 1.10
RS4 1.00 23.90 0.75 0.08 cum. 1.34
GL cum.
RO 1.00 31.00 1.50 0.08 cum. 3.49
RE 1.00 33.80 1.50 0.08 cum. 3.80
RE 1.00 13.00 1.50 0.08 cum. 1.46
RE 1.00 4.30 1.00 0.075 cum. 0.32
RE 1.00 9.00 1.00 0.075 cum. 0.67
Top cum.
RO 1.00 31.00 0.60 0.10 cum. 1.86
RE 1.00 33.80 1.00 0.10 cum. 3.38
RE 1.00 13.00 1.00 0.10 cum. 1.30
RE 1.00 4.30 1.00 0.10 cum. 0.43
RE 1.00 9.00 1.00 0.10 cum. 0.90
RC 3.00 3.50 0.50 0.10 cum. 0.53
RS1 1.00 20.00 0.35 0.10 cum. 0.70

Contractor Prepared By Checked By Approved By


Pages -229 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RS2 1.00 19.50 0.35 0.10 cum. 0.68
RS3 1.00 19.50 0.35 0.10 cum. 0.68
RS4 1.00 23.90 0.35 0.10 cum. 0.84
RE 1.00 13.00 0.40 0.08 cum. 0.39
1.00 29.70 0.40 0.08 cum. 0.89
1.00 24.70 0.40 0.08 cum. 0.74
1.00 11.50 0.40 0.08 cum. 0.35
1.00 10.40 0.40 0.08 cum. 0.31
1.00 13.90 0.40 0.08 cum. 0.42
1.00 10.90 0.40 0.08 cum. 0.33
1.00 11.50 0.40 0.08 cum. 0.35
1.00 5.50 0.40 0.08 cum. 0.17
1.00 28.00 0.40 0.08 cum. 0.84
1.00 24.70 0.40 0.08 cum. 0.74
1.00 11.90 0.40 0.08 cum. 0.36
For Soling & PCC
PCC P2 1.00 6.10 6.90 0.08 cum. 3.16
1.00 5.80 6.80 0.08 cum. 2.96
Deduction (1.00) 4.40 0.55 0.08 cum. (0.18)
Stone Pillar (10.00) 0.40 0.40 0.08 cum. (0.12)
1.00 7.50 4.20 0.08 cum. 2.36
1.00 7.30 4.20 0.08 cum. 2.30
(1.00) 1.77 0.05 0.08 cum. (0.01)
(1.00) 0.60 0.30 0.08 cum. (0.01)
(1.00) 4.10 0.50 0.08 cum. (0.15)
(1.00) 0.70 0.37 0.08 cum. (0.02)
1.00 6.60 1.25 0.08 cum. 0.62
RCC 1.00 6.30 1.15 0.08 cum. 0.54
RCC 1.00 4.45 1.00 0.08 cum. 0.33
RCC 1.00 3.10 1.10 0.08 cum. 0.26
RCC 1.00 1.20 2.50 0.08 cum. 0.22
P3 1.00 11.30 4.95 0.08 cum. 4.20
1.00 11.05 5.20 0.08 cum. 4.31
PCC At Aarati Side 1.00 5.40 4.80 0.10 cum. 2.59
1.00 4.55 1.95 0.10 cum. 0.89
1.00 2.10 3.47 0.10 cum. 0.73
1.00 7.20 3.03 0.10 cum. 2.18
1.00 9.45 3.93 0.10 cum. 3.71
1.00 2.00 3.22 0.10 cum. 0.65
1.00 1.70 1.50 0.10 cum. 0.26
1.00 1.20 9.00 0.10 cum. 1.08
1.00 6.00 0.07 0.10 cum. 0.04
1.00 14.50 0.70 0.10 cum. 1.02
1.00 0.70 5.40 0.10 cum. 0.38
1.00 1.12 4.40 0.10 cum. 0.49
1.00 1.65 3.80 0.10 cum. 0.63
1.00 1.05 3.90 0.10 cum. 0.41
1.00 1.70 2.18 0.10 cum. 0.37

Contractor Prepared By Checked By Approved By


Pages -230 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 2.63 4.83 0.10 cum. 1.27
1.00 0.90 9.70 0.10 cum. 0.87
1.00 1.00 9.55 0.10 cum. 0.96
1.00 0.90 9.70 0.10 cum. 0.87
1.00 1.00 9.55 0.10 cum. 0.96
1.00 14.42 9.55 0.10 cum. 13.77
1.00 2.30 9.55 0.10 cum. 2.20
1.00 1.24 9.55 0.10 cum. 1.18
1.00 1.23 9.55 0.10 cum. 1.17
1.00 10.11 9.55 0.10 cum. 9.66
1.00 11.12 9.55 0.10 cum. 10.62
pcc 1.000 31.000 1.86 0.075 cum. 4.32
1.000 9.600 0.83 0.075 cum. 0.60
1.000 9.800 0.95 0.075 cum. 0.70
1.000 10.300 0.86 0.075 cum. 0.66
1.000 9.300 0.95 0.075 cum. 0.66
1.000 10.400 1.73 0.075 cum. 1.35
1.000 9.900 1.38 0.075 cum. 1.02
1.000 9.500 1.76 0.075 cum. 1.25
1.000 9.900 1.05 0.075 cum. 0.78
1.000 8.900 1.05 0.075 cum. 0.70
1.000 7.300 0.92 0.075 cum. 0.50
1.000 6.600 0.45 0.075 cum. 0.22
1.000 4.400 0.45 0.075 cum. 0.15
pcc for rcc 1.000 3.4 2.2 0.1 cum. 0.75
1.000 4.5 3.8 0.1 cum. 1.71
1.000 26.1 1.14 0.1 cum. 2.98
1.000 24.8 1.16 0.1 cum. 2.88
1.000 23.6 1.2 0.1 cum. 2.83
1.000 23 2.2 0.1 cum. 5.06
1.000 10 2.13 0.1 cum. 2.13
1.000 11.1 2.61 0.1 cum. 2.90
1.000 9.9 0.85 0.1 cum. 0.84
1.000 9.7 0.75 0.1 cum. 0.73
1.000 9.7 0.75 0.1 cum. 0.73
1.000 9.65 0.75 0.1 cum. 0.72
1.000 9.6 0.75 0.1 cum. 0.72
1.000 9.5 0.75 0.1 cum. 0.71
1.000 9.5 0.75 0.1 cum. 0.71
1.000 9.5 0.75 0.1 cum. 0.71

Contractor Prepared By Checked By Approved By


Pages -231 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.000 9.6 0.75 0.1 cum. 0.72
1.000 10 0.95 0.1 cum. 0.95
This Bill
N. RS 8& RS 9 1.00 2.16 2.23 0.075 cum. 0.36
RS 9 RS 10 1.00 22.70 1.36 0.075 cum. 2.32
N .RS 8 WALL 1.00 4.25 0.40 0.075 cum. 0.13
N.RC 1.00 3.20 3.80 0.075 cum. 0.91
rs 1 ganesh mandir 1.00 5.00 0.45 0.075 cum. 0.17
RS 1 & RS 2 PIPAL S 1.00 3.70 2.50 0.075 cum. 0.69
RS 1 & RS 2 TREE 1.00 4.40 1.98 0.075 cum. 0.65
RS 1 & RS 2 TREE 1.00 5.30 2.35 0.075 cum. 0.93
last step 1.00 20.00 0.80 0.075 cum. 1.20
1.00 18.90 0.80 0.075 cum. 1.13
1.00 13.80 0.80 0.075 cum. 0.83
1.00 4.10 0.80 0.075 cum. 0.25
1.00 2.98 0.55 0.075 cum. 0.12
Drain Base 1.00 89.90 0.50 0.1 cum. 4.50
Drain Wall 2.00 89.90 0.50 0.1 cum. 8.99
Water Reserve 1.00 7.90 0.38 0.075 cum. 0.22
1.00 0.50 0.65 0.075 cum. 0.02
1.00 2.55 0.30 0.075 cum. 0.06
Ramp Brick Wall 1.00 12.20 0.45 0.075 cum. 0.41
Ramp Brick Wall 1.00 12.20 0.45 0.075 cum. 0.41
For Main Gate -
Foundation 4.00 1.20 1.20 0.075 cum. 0.43
For Beam 2.00 3.75 0.30 0.075 cum. 0.17
2.00 1.80 0.30 0.075 cum. 0.08
For Boundary Wall Base 1.00 1.70 0.50 0.075 cum. 0.06
for Boundary Wall Band 1.00 1.70 0.50 0.1 Cum 0.09
Power House 1.00 1.80 1.80 0.075 cum. 0.24
Steps near Water reserve 1.00 4.85 1.20 0.15 cum 0.87
1.00 2.65 1.05 0.15 cum 0.42

p2 west 1.00 3.3 1.25 0.075 cum. 0.31


PCC For RCC
p1and p2 east 1.00 5.35 1.03 0.10 cum. 0.55
p1and p2 east 1.00 1.25 0.90 0.10 cum. 0.11
p1and p2 east 1.00 5.80 2.47 0.10 cum. 1.43
p1and p2 east 1.00 3.20 1.85 0.10 cum. 0.59
p1and p2 east 1.00 2.50 2.30 0.10 cum. 0.58
1.00 11.00 1.00 0.10 cum. 1.10
p2 east step 1.00 1.85 1.60 0.10 cum. 0.30
p2 east step 1.00 5.95 0.47 0.10 cum. 0.28

Contractor Prepared By Checked By Approved By


Pages -232 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RC .S . STEP1 1.00 9.73 0.83 0.10 cum. 0.81
RC .S . STEP2 1.00 9.16 0.46 0.10 cum. 0.42
RC .S . STEP3 1.00 8.50 0.44 0.10 cum. 0.37
RC .S . STEP4 1.00 8.70 0.40 0.10 cum. 0.35
RC .S . STEP5 1.00 8.60 0.44 0.10 cum. 0.38
RC .S . STEP6 1.00 8.50 0.44 0.10 cum. 0.37
RC .S . STEP7 1.00 8.32 0.43 0.10 cum. 0.36
RC .S . STEP8 1.00 8.06 0.42 0.10 cum. 0.34
RC .S . STEP9 1.00 7.42 0.43 0.10 cum. 0.32
RC .S . STEP10 1.00 6.36 0.72 0.10 cum. 0.46
RS 8 & RS9 1.00 15.90 2.36 0.10 cum. 3.75
TREE S STEP 1 1.00 4.60 0.73 0.10 cum. 0.34
TREE S STEP 2 1.00 5.90 0.60 0.10 cum. 0.35
TREE S STEP 3 1.00 6.80 0.43 0.10 cum. 0.29
STEP 4 1.00 17.00 0.75 0.10 cum. 1.28
RS 1 & RS 2 PIPAL S 1.00 3.70 2.60 0.10 cum. 0.96
RS 1 & RS 2 TREE 1.00 4.40 2.08 0.10 cum. 0.92
RS 1 & RS 2 TREE 1.00 5.30 2.45 0.10 cum. 1.30
RC M 1.00 3.50 4.70 0.10 cum. 1.64
RC N 1.00 3.50 4.60 0.10 cum. 1.61
N. RS 4& RS 5 1.00 16.90 2.49 0.10 cum. 4.21
-
RC M& RCN steps 1 1.00 9.70 0.83 0.10 cum. 0.81
RC M& RCN steps 2 1.00 9.70 0.45 0.10 cum. 0.44
RC M& RCN steps 3 1.00 9.70 0.45 0.10 cum. 0.44
RC M& RCN steps 4 1.00 9.80 0.45 0.10 cum. 0.44
RC M& RCN steps 5 1.00 9.80 0.45 0.10 cum. 0.44
RC M& RCN steps 6 1.00 9.90 0.45 0.10 cum. 0.45
RC M& RCN steps 7 1.00 10.00 0.45 0.10 cum. 0.45
RC M& RCN steps 8 1.00 10.15 0.45 0.10 cum. 0.46
RC M& RCN steps 9 1.00 10.40 0.43 0.10 cum. 0.45
RC M& RCN steps 10 1.00 11.00 0.92 0.10 cum. 1.01
RS 8 & RS9 N. 1.00 15.90 1.98 0.10 cum. 3.15
RS 9 & RS10 1ST STEPS 1.00 12.50 0.58 0.10 cum. 0.73
RS 9 & RS10 2ST STEPS 1.00 10.67 0.89 0.10 cum. 0.95
last step 1.00 20.00 0.80 0.10 cum. 1.60
1.00 18.90 0.80 0.10 cum. 1.51
1.00 13.80 0.80 0.10 cum. 1.10
1.00 4.10 0.80 0.10 cum. 0.33
1.00 2.98 0.55 0.10 cum. 0.16
Steps near Water reserve 1.00 4.85 1.20 0.10 cum 0.58
1.00 2.65 1.05 0.10 cum 0.28
1.00 2.20 2.10 0.10 cum 0.46

Contractor Prepared By Checked By Approved By


Pages -233 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
235.77 Total= cum. 304.74 68.97 10,000.00 689711.37
129 RCC Works
Concrete Works for RCC (1:1.5:3) M20 on landscape
and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer. 0.00 cum. 16.97 16.97 16000.00 271492.00
At Ramp 1.00 32.50 2.83 0.15 cum. 13.81
Gate Footing 4.00 1.20 1.20 0.3 cum 1.73
Beam 2.00 4.60 0.25 0.25 cum 0.58
2.00 2.70 0.25 0.25 cum 0.34
Pillar 4.00 0.30 0.30 0.9 cum 0.32
Slab Near Shiva Mandir 1.00 3.40 0.75 0.075 cum 0.19

Fe500 Reinforcement in PCC including cutting,


131 bending and placing in position all complete as per 238929.99
design, drawing, specification and satisfaction to site
engineer. 3.67 tonne 5.66 1.99 120000.00

Bar Bending Schedule For Boundary


Item Dia of bar Shape Size No. of items C.L Nos. of bar T.Length Wt/kg Total Weight
Sill 12mm 1.00 4.20 3.00 12.60 0.89 11.18
12 mm 1.00 20.00 3.00 60.00 0.89 53.25
12 mm 1.00 28.50 3.00 85.50 0.89 75.88
12 mm 1.00 2.00 3.00 6.00 0.89 5.33
12 mm 1.00 6.50 3.00 19.50 0.89 17.31
C hook 8.00 14.00 0.50 1.00 7.00 0.39 2.76
8.00 67.00 0.50 1.00 33.50 0.39 13.07
8.00 96.00 0.45 1.00 43.20 0.39 16.85
8.00 7.00 0.45 1.00 3.15 0.39 1.23
8.00 22.00 0.45 1.00 9.90 0.39 3.86

For mandap and pavillion-IV


12.00 16.00 1.15 4.00 73.60 0.89 65.32
12.00 16.00 2.90 4.00 185.60 0.89 164.72

Slabs 1.5m 12.00 2.00 1.40 4.00 11.20 0.89 9.94


12.00 2.00 0.50 10.00 10.00 0.89 8.88
Slabs 1.2m 12.00 4.00 1.00 4.00 16.00 0.89 14.20
12.00 4.00 0.40 8.00 12.80 0.89 11.36

Contractor Prepared By Checked By Approved By


Pages -234 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
For Retaining wall at river side Main Bar 8.00 1.00 91.10 8.00 728.80 0.3951 287.92
Distribution Bar 8.00 1.00 1.50 460.00 690.00 0.3951 272.59
Top Band 8.00 1.00 91.10 6.00 546.60 0.3951 215.94
8.00 1.00 1.00 460.00 460.00 0.3951 181.73
RC Base Main Distribution 8.00 3.00 5.30 18.00 286.20 0.3951 113.07
8.00 3.00 3.50 27.00 283.50 0.3951 112.00
For PCC Area Dia spacing Area Areal wt
8.00 0.20 7.24 3.95 28.62
8.00 0.20 4.45 3.95 17.58
8.00 0.20 3.41 3.95 13.47
8.00 0.20 3.00 3.95 11.85
8.00 0.20 55.94 3.95 220.98
8.00 0.20 57.46 3.95 227.00
8.00 0.20 25.92 3.95 102.40
8.00 0.20 8.87 3.95 35.05
8.00 0.20 7.30 3.95 28.83
8.00 0.20 21.78 3.95 86.04
8.00 0.20 37.09 3.95 146.53
8.00 0.20 6.45 3.95 25.48
8.00 0.20 2.55 3.95 10.07
8.00 0.20 10.80 3.95 42.67
8.00 0.20 0.42 3.95 1.66
8.00 0.20 10.15 3.95 40.10
8.00 0.20 3.78 3.95 14.93
8.00 0.20 4.91 3.95 19.38
8.00 0.20 6.27 3.95 24.77
8.00 0.20 4.10 3.95 16.18
8.00 0.20 3.70 3.95 14.61
8.00 0.20 12.67 3.95 50.04
8.00 0.20 8.73 3.95 34.49
8.00 0.20 9.55 3.95 37.73
8.00 0.30 7.48 2.63 19.70
8.00 0.30 17.10 2.63 45.04
8.00 0.30 29.75 2.63 78.36
8.00 0.30 28.77 2.63 75.77
8.00 0.30 28.32 2.63 74.59
8.00 0.30 50.60 2.63 133.27
8.00 0.30 21.30 2.63 56.10
8.00 0.30 28.97 2.63 76.30
8.00 0.30 8.42 2.63 22.16
8.00 0.30 7.27 2.63 19.16
8.00 0.30 7.27 2.63 19.16
8.00 0.30 7.24 2.63 19.06
8.00 0.30 7.20 2.63 18.96
8.00 0.30 7.13 2.63 18.77
8.00 0.30 7.13 2.63 18.77
8.00 0.30 7.13 2.63 18.77

Contractor Prepared By Checked By Approved By


Pages -235 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
8.00 0.30 7.20 2.63 18.96
8.00 0.30 9.50 2.63 25.02
This Bill
p1and p2 east 8.00 0.30 5.51 2.63 14.51
p1and p2 east 8.00 0.30 1.13 2.63 2.96
p1and p2 east 8.00 0.30 14.33 2.63 37.73
p1and p2 east 8.00 0.30 5.92 2.63 15.59
p1and p2 east 8.00 0.30 5.75 2.63 15.14
8.00 0.30 11.00 2.63 28.97
p2 east step 8.00 0.30 2.96 2.63 7.80
p2 east step 8.00 0.30 2.80 2.63 7.37
RC .S . STEP1 8.00 0.30 8.08 2.63 21.27
RC .S . STEP2 8.00 0.30 4.21 2.63 11.10
RC .S . STEP3 8.00 0.30 3.74 2.63 9.85
RC .S . STEP4 8.00 0.30 3.48 2.63 9.17
RC .S . STEP5 8.00 0.30 3.78 2.63 9.97
RC .S . STEP6 8.00 0.30 3.74 2.63 9.85
RC .S . STEP7 8.00 0.30 3.58 2.63 9.42
RC .S . STEP8 8.00 0.30 3.39 2.63 8.92
RC .S . STEP9 8.00 0.30 3.19 2.63 8.40
RC .S . STEP10 8.00 0.30 4.58 2.63 12.06
RS 8 & RS9 8.00 0.30 37.52 2.63 98.83
TREE S STEP 1 8.00 0.30 3.36 2.63 8.84
TREE S STEP 2 8.00 0.30 3.54 2.63 9.32
TREE S STEP 3 8.00 0.30 2.92 2.63 7.70
STEP 4 8.00 0.30 12.75 2.63 33.58
RS 1 & RS 2 PIPAL S 8.00 0.30 9.62 2.63 25.34
RS 1 & RS 2 TREE 8.00 0.30 9.15 2.63 24.10
RS 1 & RS 2 TREE 8.00 0.30 12.99 2.63 34.20
RC M 8.00 0.30 16.45 2.63 43.33
RC N 8.00 0.30 16.10 2.63 42.40
N. RS 4& RS 5 8.00 0.30 42.08 2.63 110.83
- -
RC M& RCN steps 1 8.00 0.30 8.05 2.63 21.20
RC M& RCN steps 2 8.00 0.30 4.36 2.63 11.50
RC M& RCN steps 3 8.00 0.30 4.36 2.63 11.50
RC M& RCN steps 4 8.00 0.30 4.41 2.63 11.61
RC M& RCN steps 5 8.00 0.30 4.41 2.63 11.61
RC M& RCN steps 6 8.00 0.30 4.46 2.63 11.73
RC M& RCN steps 7 8.00 0.30 4.50 2.63 11.85
RC M& RCN steps 8 8.00 0.30 4.57 2.63 12.03
RC M& RCN steps 9 8.00 0.30 4.47 2.63 11.78
RC M& RCN steps 10 8.00 0.30 10.12 2.63 26.65
RS 8 & RS9 N. 8.00 0.30 31.48 2.63 82.92
Contractor Prepared By Checked By Approved By
Pages -236 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RS 9 & RS10 1ST STEPS 8.00 0.30 7.25 2.63 19.09
RS 9 & RS10 2ST STEPS 8.00 0.30 9.50 2.63 25.01
last step 8.00 0.30 16.00 2.63 42.14
8.00 0.30 15.12 2.63 39.82
8.00 0.30 11.04 2.63 29.08
8.00 0.30 3.28 2.63 8.64
8.00 0.30 1.64 2.63 4.32
Steps near Water reserve 8.00 0.30 5.82 2.63 15.33
8.00 0.30 2.78 2.63 7.33
8.00 0.30 4.62 2.63 12.17
Ramp 8.00 0.20 92.08 3.95 363.79
For Gate Foudation 12.00 4.00 1.20 32.00 153.60 0.89 136.53
Gate Beam 1 12.00 2.00 5.30 6.00 63.60 0.89 56.53
Stirrups 8.00 2.00 0.95 35.00 66.50 0.39 25.94
Gate Beam 2 12.00 2.00 3.35 6.00 40.20 0.89 35.73
8.00 2.00 0.95 22.00 41.80 0.39 16.30
Column 16.00 4.00 6.00 4.00 96.00 1.58 151.70
12.00 4.00 6.00 4.00 96.00 0.89 85.33
Slab Near Shiva Mandir 8.00 1.00 3.40 5.00 17.00 0.39 6.63
8.00 1.00 0.75 23.00 17.25 0.39 6.73
Total= 5,657.85
130 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing.
Concrete Drainage 4.00 12.68 0.35 sqm. 17.75
4.00 10.90 0.35 sqm. 15.26
4.00 2.00 0.35 sqm. 2.80
4.00 1.65 0.35 sqm. 2.31
4.00 1.28 0.35 sqm. 1.79
4.00 4.40 0.35 sqm. 6.16
4.00 7.25 0.35 sqm. 10.15
4.00 7.40 0.35 sqm. 10.36
4.00 1.00 0.35 sqm. 1.40
4.00 6.90 0.35 sqm. 9.66
4.00 7.30 0.35 sqm. 10.22
4.00 3.50 0.35 sqm. 4.90
4.00 9.90 0.35 sqm. 13.86
4.00 9.50 0.35 sqm. 13.30
4.00 5.10 0.35 sqm. 7.14
4.00 6.00 0.35 sqm. 8.40
4.00 11.20 0.35 sqm. 15.68
4.00 1.50 0.35 sqm. 2.10

Contractor Prepared By Checked By Approved By


Pages -237 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
4.00 8.35 0.35 sqm. 11.69
4.00 3.10 0.35 sqm. 4.34
4.00 1.80 0.35 sqm. 2.52
4.00 7.50 0.35 sqm. 10.50
4.00 2.40 0.35 sqm. 3.36
4.00 3.60 0.35 sqm. 5.04
4.00 3.00 0.35 sqm. 4.20
4.00 1.30 0.35 sqm. 1.82
4.00 6.00 0.50 sqm. 12.00
4.00 22.00 0.50 sqm. 44.00
Shiv mandir east 4.00 13.00 0.40 sqm. 20.80
Shiv mandir north 4.00 9.20 0.40 sqm. 14.72
Base PCC Sides
RO 1.00 31.00 2.00 0.10 sqm. 6.20
RE 1.00 33.80 2.00 0.10 sqm. 6.76
RE 1.00 13.00 2.00 0.10 sqm. 2.60
RE 1.00 4.30 2.00 0.10 sqm. 0.86
RE 1.00 9.00 2.00 0.10 sqm. 1.80
RC 3.00 3.50 2.00 0.10 sqm. 2.10
RS1 1.00 20.00 2.00 0.075 sqm. 3.00
RS2 1.00 19.50 2.00 0.075 sqm. 2.93
RS3 1.00 19.50 2.00 0.075 sqm. 2.93
RS4 1.00 23.90 2.00 0.075 sqm. 3.58
GL
RO 1.00 31.00 2.00 0.075 sqm. 4.65
RE 1.00 33.80 2.00 0.075 sqm. 5.07
RE 1.00 13.00 2.00 0.075 sqm. 1.95
RE 1.00 4.30 2.00 0.075 sqm. 0.64
RE 1.00 9.00 2.00 0.075 sqm. 1.35
Top
RO 1.00 31.00 2.00 0.10 sqm. 6.20
RE 1.00 33.80 2.00 0.10 sqm. 6.76
RE 1.00 13.00 2.00 0.10 sqm. 2.60
RE 1.00 4.30 2.00 0.10 sqm. 0.86
RE 1.00 9.00 2.00 0.10 sqm. 1.80
RC 3.00 3.50 2.00 0.10 sqm. 2.10
RS1 1.00 20.00 2.00 0.10 sqm. 4.00
RS2 1.00 19.50 2.00 0.10 sqm. 3.90
RS3 1.00 19.50 2.00 0.10 sqm. 3.90
RS4 1.00 23.90 2.00 0.10 sqm. 4.78
This Bill Sides
Drain Wall 2.00 89.90 2.00 0.5 sqm. 179.80
p1and p2 east 1.00 5.35 1.00 0.15 sqm. 0.80
p1and p2 east 1.00 1.25 1.00 0.15 sqm. 0.19
p1and p2 east 1.00 5.8 1.00 0.15 sqm. 0.87
p1and p2 east 1.00 3.2 1.00 0.15 sqm. 0.48
p1and p2 east 1.00 2.5 1.00 0.15 sqm. 0.38

Contractor Prepared By Checked By Approved By


Pages -238 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
11
p2 east step 1.00 1.85 1.00 0.15 sqm. 0.28
p2 east step 1.00 5.95 1.00 0.15 sqm. 0.89
RC .S . STEP1 1.00 9.73 1.00 0.15 sqm. 1.46
RC .S . STEP2 1.00 9.16 1.00 0.15 sqm. 1.37
RC .S . STEP3 1.00 8.5 1.00 0.15 sqm. 1.28
RC .S . STEP4 1.00 8.7 1.00 0.15 sqm. 1.31
RC .S . STEP5 1.00 8.6 1.00 0.15 sqm. 1.29
RC .S . STEP6 1.00 8.5 1.00 0.15 sqm. 1.28
RC .S . STEP7 1.00 8.32 1.00 0.15 sqm. 1.25
RC .S . STEP8 1.00 8.06 1.00 0.15 sqm. 1.21
RC .S . STEP9 1.00 7.42 1.00 0.15 sqm. 1.11
RC .S . STEP10 1.00 6.36 1.00 0.15 sqm. 0.95
RS 8 & RS9 1.00 15.9 1.00 0.15 sqm. 2.39
TREE S STEP 1 1.00 4.6 1.00 0.15 sqm. 0.69
TREE S STEP 2 1.00 5.9 1.00 0.15 sqm. 0.89
TREE S STEP 3 1.00 6.8 1.00 0.15 sqm. 1.02
STEP 4 1.00 17 1.00 0.15 sqm. 2.55
RS 1 & RS 2 PIPAL S 1.00 3.7 1.00 0.15 sqm. 0.56
RS 1 & RS 2 TREE 1.00 4.4 1.00 0.15 sqm. 0.66
RS 1 & RS 2 TREE 1.00 5.3 1.00 0.15 sqm. 0.79
RC M 1.00 3.5 1.00 0.15 sqm. 0.53
RC N 1.00 3.5 1.00 0.15 sqm. 0.53
N. RS 4& RS 5 1.00 16.9 1.00 0.15 sqm. 2.53
-
RC M& RCN steps 1 1.00 9.7 1.00 0.15 sqm. 1.45
RC M& RCN steps 2 1.00 9.7 1.00 0.15 sqm. 1.45
RC M& RCN steps 3 1.00 9.7 1.00 0.15 sqm. 1.45
RC M& RCN steps 4 1.00 9.8 1.00 0.15 sqm. 1.47
RC M& RCN steps 5 1.00 9.8 1.00 0.15 sqm. 1.47
RC M& RCN steps 6 1.00 9.9 1.00 0.15 sqm. 1.49
RC M& RCN steps 7 1.00 10 1.00 0.15 sqm. 1.50
RC M& RCN steps 8 1.00 10.15 1.00 0.15 sqm. 1.52
RC M& RCN steps 9 1.00 10.4 1.00 0.15 sqm. 1.56
RC M& RCN steps 10 1.00 11 1.00 0.15 sqm. 1.65
RS 8 & RS9 N. 1.00 15.9 1.00 0.15 sqm. 2.39
RS 9 & RS10 1ST STEPS 1.00 12.5 1.00 0.15 sqm. 1.88
RS 9 & RS10 2ST STEPS 1.00 10.67 1.00 0.15 sqm. 1.60
At Ramp 2.00 32.50 1.00 0.15 sqm. 9.75
Gate Footing 4.00 1.20 4.00 0.3 sqm. 5.76
Beam 2.00 4.60 2.00 0.25 sqm. 4.60
2.00 2.70 2.00 0.25 sqm. 2.70
Pillar 4.00 0.30 4.00 0.9 sqm. 4.32
For Boundary Wall Base 1.00 1.70 2.00 0.075 cum. 0.26
Contractor Prepared By Checked By Approved By
Pages -239 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
for Boundary Wall Band 1.00 1.70 2.00 0.1 Cum 0.34
371.55 Total= Sqm 629.47 257.92 600.00 154752.30
STONE MASONRY WORKS IN CEMENT MORTAR
Providing and laying Random Rubble stone masonry
works on retaining walls in cement mortar (1:4)
including providing through/bond stone at required
132
interval including providing required scaffolding,
preparing mortar and construction of wall to any height
and shape all complete as per drawings, specifications
and instruction of the engineer.
for RT Walls (From North To South) 1.00 3.70 0.68 2.00 cum 5.00
1.00 2.00 0.68 2.00 cum 2.70
1.00 6.85 0.68 2.00 cum 9.25
1.00 4.00 0.68 2.00 cum 5.40
1.00 3.90 0.68 2.00 cum 5.27
1.00 8.80 0.68 2.00 cum 11.88
1.00 4.75 0.68 2.00 cum 6.41
1.00 1.10 0.68 2.00 cum 1.49
1.00 11.30 0.68 2.00 cum 15.26
2.00 1.00 0.68 2.00 cum 2.70
1.00 4.45 0.68 2.00 cum 6.01
1.00 3.40 0.68 2.00 cum 4.59
1.00 4.75 0.68 2.00 cum 6.41
for RS Walls (From North To South) -2nd step 1.00 3.80 0.60 1.15 cum 2.62
1.00 5.50 0.60 1.15 cum 3.79
1.00 5.20 0.60 1.15 cum 3.59
1.00 5.90 0.60 1.15 cum 4.07
1.00 3.00 0.43 1.00 cum 1.28
1.00 1.50 0.43 1.00 cum 0.64
1.00 1.30 0.43 1.00 cum 0.55
1.00 2.50 0.43 1.00 cum 1.06
1.00 1.20 0.43 1.00 cum 0.51
1.00 2.10 0.43 1.00 cum 0.89
1.00 5.40 0.43 1.00 cum 2.30
1.00 4.60 0.43 1.00 cum 1.95
for RS Walls (From North to South) -3rd step 1.00 2.30 0.43 1.00 cum 0.98
1.00 1.65 0.43 1.00 cum 0.70
1.00 2.10 0.43 1.00 cum 0.89
1.00 1.30 0.43 1.00 cum 0.55
1.00 3.00 0.43 1.00 cum 1.28
1.00 13.50 0.43 1.00 cum 5.74
for RS Walls (From North to South) -4th step 1.00 15.10 0.43 1.00 cum 6.42
1st Step Wall 1.00 17.10 0.43 0.80 cum 5.81
2nd Step 1.00 13.75 0.50 0.30 cum 2.06
3rd Step 1.00 10.40 0.60 0.30 cum 1.87
Tree Protection Wall 2.00 1.50 0.35 0.80 cum 0.84
Tree Protection Wall 1.00 1.40 0.35 0.80 cum 0.39
for RT Walls (From North To South) 1.00 2.90 0.60 1.00 cum 1.74

Contractor Prepared By Checked By Approved By


Pages -240 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 9.40 0.60 1.20 cum 6.77
1.00 6.80 0.60 1.10 cum 4.49
1.00 6.90 0.60 1.10 cum 4.55
1.00 8.40 0.60 1.10 cum 5.54
1.00 5.20 0.60 1.10 cum 3.43
1.00 7.10 0.60 1.10 cum 4.69
1.00 8.80 0.60 1.10 cum 5.81
1.00 6.50 0.68 1.90 cum 8.40
1.00 2.20 0.68 1.90 cum 2.84
1.00 28.50 0.68 1.90 cum 36.82
1.00 8.50 0.98 3.77 cum 31.40
1.00 9.50 0.98 3.77 cum 35.10
1.00 6.50 0.98 3.00 cum 19.11
1.00 4.45 0.98 3.00 cum 13.08
1.00 6.43 0.98 3.00 cum 18.90
1.00 0.80 0.98 3.00 cum 2.35
1.00 5.10 0.98 3.00 cum 14.99
1.00 2.32 0.98 3.00 cum 6.82
1.00 3.30 0.98 3.00 cum 9.70
1.00 11.10 0.98 3.00 cum 32.63
1.00 1.45 0.98 3.00 cum 4.26
1.00 3.95 0.98 3.00 cum 11.61
for RS Walls (From North to South) -3rd step 1.00 7.50 0.98 3.00 cum 22.05
1.00 1.80 0.98 3.00 cum 5.29
Base cum
RO 1.00 31.00 1.50 1.20 cum 55.80
RE 1.00 33.80 1.50 1.20 cum 60.84
RE 1.00 13.00 1.50 1.20 cum 23.40
RE 1.00 4.30 1.00 0.90 cum 3.87
Above PCC cum
RO 1.00 31.00 1.05 2.30 cum 74.87
RE 1.00 33.80 1.25 1.10 cum 46.48
RE 1.00 13.00 1.25 1.10 cum 17.88
RE 1.00 4.30 0.75 1.10 cum 3.55
RE 1.00 9.00 0.75 2.00 cum 13.50
cum -
RC1 1.00 10.70 1.08 3.00 cum 34.51
RC2 1.00 11.20 1.08 3.00 cum 36.12
RC3 1.00 10.20 1.08 3.00 cum 32.89
RS1 1.00 20.00 0.40 0.750 cum 6.00
RS2 1.00 19.50 0.40 0.750 cum 5.85
RS3 1.00 19.50 0.40 0.750 cum 5.85
RS4 1.00 23.90 0.40 0.750 cum 7.17
RE 1.00 13.00 0.40 1.00 cum 5.20
1.00 29.70 0.40 0.75 cum 8.91
1.00 24.70 0.40 0.75 cum 7.41
1.00 11.50 0.40 0.75 cum 3.45
1.00 10.40 0.40 0.75 cum 3.12

Contractor Prepared By Checked By Approved By


Pages -241 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 13.90 0.40 0.75 cum 4.17
1.00 10.90 0.40 0.75 cum 3.27
1.00 11.50 0.40 0.75 cum 3.45
1.00 5.50 0.40 0.75 cum 1.65
1.00 28.00 0.40 0.75 cum 8.40
1.00 24.70 0.40 0.75 cum 7.41
1.00 11.90 0.40 0.75 cum 3.57
Stone Masonry work 1.00 31.00 1.86 0.30 cum 17.30
1.00 10.40 1.73 0.30 cum 5.40
1.00 9.90 1.38 0.30 cum 4.10
1.00 9.50 1.76 0.30 cum 5.02
1.00 9.90 1.05 0.30 cum 3.12
1.00 8.90 1.05 0.30 cum 2.80
1.00 7.30 0.92 0.30 cum 2.01
1.00 6.60 0.45 0.75 cum 2.23
1.00 9.80 1.15 0.30 cum 3.38
1.00 10.30 1.03 0.30 cum 3.18
1.00 9.30 1.10 0.30 cum 3.07
Sub-Total 985.73
On hold 177.63
808.10 Total= Cum 808.10 0.00 7000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -242 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
133 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
1.00 20.50 0.50 0.90 cum. 9.23
2.00 4.00 0.50 0.90 cum. 1.80
west 1.00 1.40 0.25 1.20 cum. 0.42
west 1.00 1.00 0.25 0.90 cum. 0.23
west 1.00 1.00 0.25 0.90 cum. 0.23
South 1.00 8.00 0.25 0.90 cum. 1.80
South 1.00 9.00 0.25 0.90 cum. 2.03
1.00 5.00 0.25 0.70 cum. 0.88
1.00 5.10 0.25 0.70 cum. 0.89
1.00 2.00 0.25 0.70 cum. 0.35
This Bill
Boundary Wall 1.00 1.70 0.50 0.90 Cum 0.77
1.00 1.70 0.25 1.20 Cum 0.51
At Ramp Support Wall 1.00 12.20 0.38 1.00 Cum 4.57
1.00 12.20 0.38 0.30 Cum 1.37
Water Reserve area 1.00 7.90 0.25 1.35 Cum 2.67
1.00 4.00 0.25 0.45 Cum 0.45
At Step 1.00 2.80 0.30 0.20 Cum 0.17
17.84 Total= cum. 28.34 10.51 15000.00 157601.25
PIPEWORKS FOR WEEPHOLE AND GEOTEXTILE
134
WORKS FOR RETAINING WALLS
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work including
transportation,cutting,connecting and placing in
position, treated with two coat of anticorrosive paints,
all complete as per drawings,specifications and
instruction.(80mmdi GI medium duty)
From Previous Bill 1.00 120.00 rm 120.00
1.00 105.00 rm 105.00

1.00 19.32 rm 19.32

244.32 Total= Rm 244.32 0.00 700.00 0.00


135 GEO TEXTILE FOR RETAINING WALLS
Providing and placing of Geo Textile on retaining wall
and french drain as per the instruction of engineer
From Previous Bill
1.0 120.00 1.50 sqm 180.00
river bank 1.0 72.40 3.00 sqm 217.20
Contractor Prepared By Checked By Approved By
Pages -243 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
upper retaining wall 1.0 105.00 1.50 sqm 157.50
-
1.0 197.10 3.00 sqm 591.30

Contractor Prepared By Checked By Approved By


Pages -244 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.0 195.00 2.00 Sqm 390.00
1536.00 Total= Sqm 1,536.00 0.00 80.00 0.00
136 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on internal walls
including necessary scaffolding , cleaning & wetting
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete.
Road Side Wall Parking
2.00 5.20 0.80 8.32
2.00 5.10 0.80 8.16
1.00 7.90 1.50 11.85
1.00 7.90 1.10 8.69
1.00 9.90 1.20 11.88
1.00 9.00 1.10 9.90
1.00 1.15 1.45 1.67
1.00 1.80 1.80 3.24
1.00 1.15 1.55 1.78
1.00 1.80 1.90 3.42
1.00 1.20 1.55 1.86
This Bill
Upper Side Walls 1.00 111.40 0.66 73.65
River Side Wall R0 1.00 31.00 2.75 85.25
RE 1.00 33.80 1.50 50.70
RC 3.00 9.60 1.03 29.76
70.77 sqm. - 310.13 239.36 600.00 143614.66

Flushing pointing on the exterior Brick wall of gate


structure by cement sand mortar of ratio 1:2 all
complete as per drawings, specificatios and
137 instruction. The rates shall include for scraping, 0.00
washing the surface with water, surface preparation,
scaffolding,etc.,all complete as per the manufacturer's
recommendations and as approved by the Engineer.
sqm. - 0.00 400.00

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
specifications on exterior plaster all complete as per
138 0.00
drawings, specifications and instruction. The rates
shall include for scraping, washing the surface with
water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer.
sqm. - 0.00 300.00

Contractor Prepared By Checked By Approved By


Pages -245 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Providing and laying 20mm. thick Cement Water Bead
(Pani Patti) finished perfectly smooth including
139 0.00
necessary scaffolding, raking the joint, wetting the
surface and curing all complete work sqm. - 0.00 400.00

140 Flooring Work

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance, 0.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative. sqm. - 0.00 800.00
3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth
141 surface on risers of steps on landscape works as per 0.00
design, drawing, specification and instruction of site
engineer. sqm. - 0.00 400.00
Providing and laying of flagstone of approved
thickness and color on landscape works in perfect line
142 and level including joint sealing of joint, grinding, 0.00
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 0.00 1400.00

Providing and laying of 25 mm thick Telia brick paving


work in (1:2) surki mortar and pointing the joints with
143 1:1 C/S mortar including curing on landscape works in 0.00
perfect line and level all complete as per design,
drawing, specification and the instrution of the site
engineer. sqm. - 0.00 3400.00

Providing and laying stone slab of approved quality


and color over PCC on pavements including cement
mortar of 1:3(cement sand) in perfect line, level
144 finished with necessary pointing in joints sloped 0.00
towards drain line all complete as per design,
drawing, specification and the instrution of consultant
and his authorized representative. Samples should be
approves by consultant. sqm. - 0.00 7000.00

Providing and laying of brick pavement of approved


thickness and color on landscape works in perfect line
145 and level including joint sealing of joint, grinding, 0.00
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 0.00 700.00

Contractor Prepared By Checked By Approved By


Pages -246 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Cement skirting works:-Providing and laying cement


punning skirting on rammed earth walls inside rooms
146 in perfect line and level with grouting all complete as 0.00
per design, drawing , specification and instruction of
consultant and his authorized representative sqm. - 0.00 600.00
Waterproofing works:- Providing and applying water
proof coating work necessary on cement punning area
147 after preparing the surface all complete work as per 0.00
design, drawing , specification and instruction of
consultant and his authorized representative sqm. - 0.00 500.00

Providing and laying subsurface drain with perforated


pipe of 100mm internal diameter of PVC, closely joined
148 perforations ranging from 3mm to 6mm depending
upon size of material surrounding the pipe with 150mm
bedding below the pipe and 300mm cushion above
pipe, as per drawing and specification.
1 120.00 rm 120.00
120.00 Total= rm 120.00 0.00 800.00 0.00

149 PEBBLES FOR COVERED DRAIN AND TAP


Providing and laying pebbles for drain cover and stone
tap on landscape works as per design, drawing, 0.00
specification and instruction of site engineer. 0.0 0.0 m2 0.0 0.0 0.00 10000.00

150 STEEL GRATING FOR DRAINS


Providing and laying light duty iron channel grates on
drains in perfect line and level including finishing in
smooth surface on landscape as per design, drawing,
specification and instruction of site engineer. kg
concrete drain grate 1.000 153.35 0.36 5 kgs 276.03
276.03 Total= kgs 276.03 0.00 250.00 0.00
Supplying and fitting of railing with 50mm vertical MS
circular pipe of 500mm height at 2m interval and
151 50mm black pipe handrail including welding, joints, 0.00
and prmer painting asper drawing and instructions all
complete. 0.0 0.0 m2 0.00 0.00 0.00 6500.00

Contractor Prepared By Checked By Approved By


Pages -247 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
GAMALA POTS ON LANDSCAPE
Providing, molding and placing gamala pots on
landscape as per design, drawing, specification and
instruction of site engineer.
152 gamala 1 0 0.00 nos 0.00 0.00 1000.00 0.00
153 gamala 2 0 0.00 nos 0.00 0.00 1000.00 0.00
154 gamala 3 0 0.00 nos 0.00 0.00 1000.00 0.00
155 gamala 4 0 0.00 nos 0.00 0.00 1000.00 0.00
156 gamala 5 0 0.00 nos 0.00 0.00 1000.00 0.00
157 gamala 6 0 0.00 nos 0.00 0.00 1000.00 0.00
158 gamala 7 0 0.00 nos 0.00 0.00 1000.00 0.00
159 Wooden railing works
Providing and placing seasoned laminated timber rail
on openings of gates including transportation, cutting,
connecting and placing in position with wood primer 0.00 0.00
and paint, all complete as per drawings, specifications
and instruction. 0.00 0.00 cum 0.00 2500.00

160 Wooden fascia works


Providing and placing 25mm thk. Treated hardwood
fascia board on roof including transportation, cutting,
connecting and placing in position with wood primer 0.00 0.00
and paint, all complete as per drawings, specifications
and instruction. 0.00 0.00 sqm 0.00 12000.00

161 Waterproof plyboard on roof


Providing and laying 10mm waterproof plywood with
one side veneer in perfect line and level above adobe
insulation all complete as per design, drawing, 0.00 0.00
specification and instruction of consultant and his
authorized representative. Samples should be
approved by consultant. 0.00 0.00 sqm 0.00 700.00

162 Iko-tile roofing works


Providing and laying iko-tile nailed and stacked over
plyboard on sloped roofs in perfect line and level all
complete as per design, drawing, specification and 0.00 0.00
instruction of consultant and his authorized
representative. 0.00 0.00 sqm 0.00 3500.00

Contractor Prepared By Checked By Approved By


Pages -248 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
163 Structural steel Works
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work on gate roof
including transportation, cutting, connecting and 0.00 0.00
placing in position,treated with two coat of
anticorrosive paints, all complete as per drawings,
specifications and instruction. 0.00 0.00 kgs 0.00 250.00

Providing and fabricating MS steel gate and fixing in


164 entrance polished and finished in perfect line, level as 0.00 0.00
per design, drawing, specification and instruction all
complete. 0.00 0.00 kgs 0.00 250.00

Supplying and fitting of railing with M.S. pipe including


165 welding, joints and primer painting as per drawing and
instructions all complete
Boundary wall A 1.00 1.40 0.35 m2 0.49
2.00 1.00 0.65 m2 1.30
1.00 1.00 1.60 m2 1.60
Boundary wall B 1.00 9.00 0.65 m2 5.85
1.00 3.00 2.10 m2 6.30
1.00 8.00 0.65 m2 5.20
Boundary wall E 1.00 2.00 0.65 m2 1.30
1.00 1.00 1.60 m2 1.60
1.00 1.98 0.88 m2 1.74
1.00 3.03 0.53 m2 1.60
1.00 5.00 1.60 m2 8.00
1.00 5.10 0.53 m2 2.70
1.00 6.50 1.60 m2 10.40
1.00 2.14 0.53 m2 1.13
1.00 14.25 1.60 m2 22.80
Sub-Total 72.02
On hold 11.02

Contractor Prepared By Checked By Approved By


Pages -249 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
61.00 Total= m2 61.00 0.00 5000.00 0.00

166 Shera board works


Providing, fabricating & fixing shera board works on
gate finished in perfect line, level along with all 0.00
necessary accessories all complete as per design,
drawing, specification and instruction 0.00 0.00 m2 0.00 0.00 0.00 2500.00
STONE TAP FIXTURES AND FITTINGS
Supplying and Fixing Indian pattern C.P. valves with
167 0.00
wall flange Including c.p. nipple all complete set. 0.00 0.00 nos 0.00 0.00 0.00 2000.00
Supplying and Fixing CP Bib Cock with wall flange,cp
0.00
168 nipple all complete set 0.00 0.00 nos 0.00 0.00 0.00 4000.00
Supplying and Fixing 20 mm CPVC pipe with pipe
Jointing materials (Tee, Elbow, Union), making holes,
169 clips and vent cowl all complete set as per 0.00
specification and instruction. (Mangalam,
Panchakanya , Prince,Supreme or Equivalent. ) 0.00 0.00 rm 0.00 0.00 0.00 800.00
Providing and fixing PVC water tank- brand
Nepatop/Hilltake/ Panchakanya or equivalent, of
capacity 2000 ltrs. finished in perfect line, level along 0.00
with all necessary accessories all complete as per
170 design, drawing, specification and instruction 0.00 0.00 nos 0.00 0.00 0.00 35000.00
PLANTATION WORKS
Planting dubo grass on site including digging, planting
hole 10-20 cm depth using a metal rod or hardwood 0.00
171 peg. 0 sqm 0.00 0.00 600.00

Planting rooted tree stump cutting and bare root


seedlings, including pitting, transplanting, composting
and mulching, pit size 10cm diameterx depth compost
volume of pit mix with original soil.

Specifications for trees(3-4ft):-


Sami (Ficus benjamina)
Bougainvillea (Bougainvillea glabra)
Mango (Magnifera Indica) 0.00
Neem (Azadirachta indica)
Parijat ((Nyctanthes arbor tristis)
Jasmine (Jasminum polyanthum)
Ashoka (Saraca asoca)
Supari (Areca catechu)
Bamboo (Bambusa vulgaris)
Gulmohar (Delonix regia)
Banana (Musa paradiscata)
Willow (Salix babylonica)
172 0 no 0.00 0.00 1000.00
Planting shrubs including digging, planting hole, etc. all
0.00
173 complete. 0 ls 0.00 0.00 2000.00
Electrical

Contractor Prepared By Checked By Approved By


Pages -250 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

LED strip light warm white 220V with soft bending


diffuser, philips equivalent, 72 LED per meter or
equivalent for bright and uniform lighting, complete set 0.00
with fitting components and installation, with junction
174 box if necessary 0 rm 0.00 0.00 2000.00

LUMINAIRES ( FIXTURES) Outdoor LED based


Luminaries set all complete. LEGERO, GE, Philips or
equivalent
7W Garden Spike, Anthracite, Warm White,Floor 0.00
Lamp, 220V, warm white, IP 65 or above, complete set
with fitting components and installation, with junction
175 box if necessary 0 set 0.00 0.00 1500.00
30W LED outdoor wall washer (Tubelight for indirect
lighting), 3000K, IP 65 and above, 220 V, complete set 0.00
176 with fitting components and installation 0 set 0.00 0.00 1500.00
LUMINAIRES ( FIXTURES) Outdoor LED based
Luminaries set all complete. LEGERO, GE, Philips or
equivalent,
6W 800lm Sleek small LED Track Lighting, 220V, 0.00
warm white, IP 65 or above, complete set with fitting
components and installation, with junction box if
177 necessary 0 set 0.00 0.00 1500.00
Up down Sconce light 10W equivalent IP 65 and
above,2700K/3000K warm white, complete set with
0.00
fitting components and installation, with junction box if
178 necessary 0 set 0.00 0.00 1500.00
Wall recessed 12 inch to 24 inch length, 10W
equivalent (600-800lm) LED warm white light, 220V, IP
0.00
65 or above, complete set with fitting components and
179 installation, with junction box if necessary 0 set 0.00 0.00 2000.00
Street Light / Flood Light Philips BGP704 equivalent
220V, 10000 lumens, warm white luminaires with
mount and all other components complete set with 0.00
fitting components and installation, with junction box if
180 necessary 0 set 0.00 0.00 2000.00
12W ceiling recessed Warm white luminaire set, 220V,
complete set with fitting components and installation, 0.00
181 with junction box if necessary 0 set 0.00 0.00 3500.00
9W directional LED ceiling recessed light track light, all
0.00
182 complete,with junction box if necessary 0 set 0.00 0.00 3500.00
Floor recessed (ground well) LED luminaire 12 W,
Warm white 220V, IP 65 or above, complete set with 0.00
183 fitting components and installation 0 set 0.00 0.00 1500.00

Post top LED warm white luminaire 30W, 220V with


heritage style cast iron lamp post of minimum 7 feet
height from ground level (to be bought in consultation 0.00
with architecture), complete set with fitting components
and installation, with junction box if necessary
184 0 set 0.00 0.00 2000.00

Contractor Prepared By Checked By Approved By


Pages -251 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Street Light Philips BGP704 equivalent 220V, 10000
lumens, warm white luminaires with mount and all
0.00
other components complete set with fitting
185 components and installation 0 set 0.00 0.00 3000.00

Installation, testing and commissioning of 10 sq mm


2C, armored copper cable from existing point to
0.00
distribution board, underground via 32 mm HDPE pipe,
complete set with fitting components and installation
186 0 Rm 0.00 0.00 1200.00

Electrical Outdoor distribution box, Waterproof sealed


with IP rating of IP66 or above, made with stainless
steel with stand kept 2 feet above ground level, 0.00
embedded door with required copper bush, installation
and fitting cost of MCB ans switches all included
187 0 set 0.00 0.00 60000.00
Installation, testing and comissioning of 16 way SPN
0.00
188 DB 0 set 0.00 0.00 5000.00
Installation testing and commissioning of 6 A SP MCB,
0.00
189 all complete 0 set 0.00 0.00 600.00

Contractor Prepared By Checked By Approved By


Pages -252 of 333
FIFTH MEASUREMENT SHEET
अघिल्लो यस हालसम्म
नापी नापीबाट परिमाण सूची
काम/सेवाको विवरण यस नापीको मापनको आयाम अध्यावधिक
क्र.सं. किताबमा कायम (BoQ) मा जम्मा रकम
काम भएको
चढेको भएको उल्लिखित दर
क्रियाकलाप परिमाण संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ३ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Installation testing and commissioning of 16 A SP
0.00
190 MCB, all complete 0 set 0.00 0.00 600.00
Installation testing and commissioning of 32 A DP
0.00
191 MCB, all complete 0 set 0.00 0.00 600.00
Installation testing and comissioning of 32 A DP
0.00
192 Switch, all complete 0 set 0.00 0.00 2000.00
Weatherproof Outdoor Junction Box, IP 68 or above
rated, JB with option for sealing the incoming and 0.00
193 outgoing 2c wire 0 set 0.00 0.00 2000.00
3*3 metal (Stainless Steel) junction box with rubber
0.00
194 gasket for weather proofing 0 set 0.00 0.00 3500.00
195 9m Pole for electric lighting single arm 0 set 0.00 0.00 75000.00 0.00
196 9m double arm pole for electrc lighting 0 set 0.00 0.00 15000.00 0.00
Installation, testing, and commissioning of 2.5 sq mm
2C, armored copper cable from the distribution board
0.00
to, light points underground via 32 mm HDPE pipe, all
197 complete 0 Rm 0.00 0.00 800.00
Chemical Earthing
Supply, Installation, testing and commissioning of
0.00
Chemical Earthing System with including all material
198 and accessories to all complete the works 0 nos 0.00 0.00 50000.00
Supply , installation & testing of 8 SWG bare copper
0.00
199 conductor from Main panel to earth test pit 0 Rm 0.00 0.00 800.00
Sub-Total 2110750.45
Price Adjustment 0.00
VAT @ 13% 274397.56
Net Total with VAT only 2385148.01
Provisonal Sum Amount 0.00
Grand Total with Vat and PS 2385148.01

Contractor Prepared By Checked By Approved By


Pages -253 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
A General works
General works:Provide Insurance of works,
1 materials,construction equipments against accident to 100000.00
workforce including third party 1.00 PS 1.00 1.00 100000.00
Provide & Maintain protective safety Equipments
2 including Hats, Gloves, Googles, Dust mask, First Aid 15000.00
Kit with medicine for work force - PS 1.00 1.00 15000.00
3 Lab test of the construction materials as rebar cement, 5000.00
brick, as per specified by site incharge 1.00 PS 1.00 1.00 5000.00
Provide & Installation of Project Information Board
1 10000.00
1.2*.90 m Size as to Complete the Work as Specified 1.00 No. 1.00 1.00 10000.00
PAVILION I -
2 Earthwork

Earthwork in excavation for foundation along with


dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
1.00 2.25 1.00 0.90 cum 2.03
1.00 2.30 1.00 0.90 cum 2.07
1.00 1.70 0.85 0.90 cum 1.30
1.00 3.70 1.30 0.90 cum 4.33
1.00 1.90 0.90 0.90 cum 1.54

Contractor Prepared By Checked By Approved By


Pages -254 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
2.00 0.90 0.90 0.60 cum 0.97
1.00 0.90 0.75 0.60 cum 0.41
Total= 12.64 12.64 200.00 2528.10
3 Filling
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
From previous bill
1.00 2.25 1.00 0.30 cum 0.67
1.00 2.30 1.00 0.30 cum 0.69
1.00 1.70 0.85 0.30 cum 0.43
1.00 3.70 1.30 0.30 cum 1.44
1.00 1.90 0.90 0.30 cum 0.51
2.00 0.90 0.90 0.30 cum 0.49
1.00 0.90 0.75 0.30 cum 0.20
Total= 4.44 4.44 300.00 1332.90

4 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.
1.00 2.25 1.00 0.15 cum 0.34
1.00 2.30 1.00 0.15 cum 0.35
1.00 1.70 0.85 0.15 cum 0.22
1.00 3.70 1.30 0.15 cum 0.72
1.00 1.90 0.90 0.15 cum 0.26
2.00 0.90 0.90 0.15 cum 0.24
1.00 0.90 0.75 0.15 cum 0.10
Total= 2.22 2.22 3000.00 6664.50

Contractor Prepared By Checked By Approved By


Pages -255 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
5 Brick soling work
Providing and laying a single layer flat brick soling on
drainage works on lanscape for preparation of P.C.C.
in which joints should be packed by sand to the
required levels all complete as per drawings,
specifications and the instructions of the Engineer.
1.00 1.75 0.85 sqm 1.49
1.00 1.50 0.25 sqm 0.38
Total= 1.86 1.86 700.00 1303.75
6 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

From previous bill


1.00 2.25 1.00 0.08 cum 0.17
1.00 2.30 1.00 0.08 cum 0.17
1.00 1.70 0.85 0.08 cum 0.11
1.00 3.70 1.30 0.08 cum 0.36
1.00 1.90 0.90 0.08 cum 0.13
2.00 0.90 0.90 0.08 cum 0.12
1.00 0.90 0.75 0.08 cum 0.05
seating portion 1.00 1.75 0.50 0.08 cum 0.07
Total= 1.18 1.18 10000.00 11763.75

7 RCC Works
Concrete Works for RCC (1:1.5:3) M20 on landscape
and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer.
2.000 2.100 0.900 0.300 cum 1.13
1.000 4.300 0.900 0.250 cum 0.97
2.000 1.050 0.900 0.250 cum 0.47
9.000 0.300 0.300 0.750 cum 0.61
2.000 0.300 0.600 1.100 cum 0.40
1.000 43.240 0.100 cum 4.32

Contractor Prepared By Checked By Approved By


Pages -256 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.000 0.875 0.075 cum 0.07
2.000 6.400 0.450 0.100 cum 0.58
4.000 0.600 0.450 0.100 cum 0.11
Total= 8.65 8.7 16000.00 138418.00
8 Steel reinforcement works
Fe500 Reinforcement in PCC including cutting,
bending and placing in position all complete as per
design, drawing, specification and satisfaction to site
engineer.
Total= 1.36 1.36 120000.00 162960.00

Contractor Prepared By Checked By Approved By


Pages -257 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
9 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing.
Column 300x300, 9 nos of column 2.000 6.000 0.250 sqm. 3.00
Column 600x300, 2 nos of column 1.000 10.400 0.250 sqm. 2.60
2.000 3.900 0.250 sqm. 1.95
9.000 1.200 0.750 sqm. 8.10
2.000 1.800 1.100 sqm. 3.96
1.000 43.240 sqm. 43.24
1.000 0.875 sqm. 0.88
2.000 6.400 0.150 sqm. 1.92
Total= 65.65 65.65 600.00 39387.00
10 STONE PILLAR WORKS
Providingand placing stone pillar above PCC in
cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Small Stone 3.00 0.40 0.40 0.55 cum. 0.26
3.00 0.40 0.40 1.15 cum. 0.55
Total= 0.82 0.82 7000.00 5712.00

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
11 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
brick wall 1.00 4.00 0.40 4.10 cum 6.56
brick wall 4.00 0.65 0.45 4.10 cum 4.80
Deduction cum 0.00
brick wall -4.00 0.40 0.40 2.33 cum -1.49
Total= 9.87 9.87 15000.00 148050.00

Contractor Prepared By Checked By Approved By


Pages -258 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
12 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
150mmx150mm 3.00 0.15 0.15 3.06 cum 0.21
150mmx150mm 3.00 0.15 0.15 2.48 cum 0.17
wooden casing 3.00 1.10 0.13 0.35 cum 0.15
50mm wooden pole 12.00 1.90 0.00 cum 0.04
25mm wooden pole 24.00 1.90 0.00 cum 0.02
wooden plates 6.00 0.40 0.40 0.03 cum 0.02
Total= 0.61 0.61 250000.00 152500.00

Engraving designs on wooden pillars properly finished


13.0 along with all necessary accessories along with wood
primer all complete as per design, drawing,
specification and instruction of the Engineer..
7.00 Nos 7.00
Total= 7.00 7.00 25000.00 175000.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
14 polished and finished in perfect line, level along with all
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
WB beam 5.000 4.587 0.100 0.100 cum 0.23
WB beam 3.000 3.851 0.100 0.100 cum 0.12
meth 12.000 0.052 0.075 cum 0.05
Total= 0.39 0.39 250000.00 97500.00

15 MS STEEL WORKS
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work including
transportation, cutting, connecting and placing in
position,treated with two coat of anticorrosive paints,
all complete as per drawings, specifications and
instruction.
90mmx90mm 4.00 2.35 14.00 kg 131.60
9.00 2.58 14.00 kg 325.08

Contractor Prepared By Checked By Approved By


Pages -259 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
12mm Base plate 18.00 0.25 0.25 94.20 kg 105.98
4.00 0.50 0.25 94.20 kg 47.10
12mm Top plate 9.00 0.18 0.18 94.20 kg 25.96
2.00 0.18 0.48 94.20 kg 15.66
100mmx100mmx 4mm post 13.000 2.725 11.730 kg 415.54
100mmx100mmx 4mm beam 7.000 4.594 11.730 kg 377.21
100mmx100mmx 4mm beam 5.000 5.400 11.730 kg 316.71
7% for nuts, bolts, plates 77.66 kg 77.66
Total= 1838.50 1838.50 250.00 459625.07

Providing and placing decking sheet for concrete deck


16 slab including transportation, cutting, connecting and
placing in position with welds and studs all complete
as per drawings, specifications and instruction.
1.000 43.240 Sqm 43.24
43.24 43.24 1200.00 51888.00
17 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete.
brick wall 1.000 9.000 2.750 24.75
brick wall 4.000 2.197 2.750 24.17
brick wall 8.000 0.450 2.325 8.37
column 2.000 1.800 0.400 1.44
bench 1.000 4.500 0.375 1.69
Deduction
brick wall -8.000 0.400 2.325 -3.72
56.69 56.69 300.00 17008.35

Contractor Prepared By Checked By Approved By


Pages -260 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
18 specifications to the surface of wall, ceiling, beams
columns, canopies, staircase, lobbies etc., all complete
as per drawings, specifications and instruction. The
rates shall include for scraping, washing the surface
with water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer. sqm 56.69
56.69 56.69 300.00 17008.35
19 False ceiling works
Providing and placing false ceiling with plyboard(one
side veneer) including the channels to drop false
ceiling all complete as per design, drawing,
specification and instruction of site engineer. sqm 43.18
43.18 43.18 2500.00 107950.00

Providing and applying PU paint of approved


manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
20 the surface of false ceiling all complete as per
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. sqm 43.18
43.18 43.18 300.00 12954.00
21 Toughen glass Works
Providing and laying toughen glass on roof including
fixing with silicon and necessary support all complete
as per drawing and specification. sqm 1.09
1.09 1.09 12000.00 13104.00

Contractor Prepared By Checked By Approved By


Pages -261 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
22 Fibre cement board cladding for fascia
Providing and laying fibre cement board cladding on
fascia all complete as per design, drawing,
specification and instruction of site engineer. sqm 27.95
27.95 27.95 3000.00 83850.00

23 Waterproofing coating on roof


Providing and laying waterproofing coating on roof all
complete as per design, drawing, specification and
instruction of site engineer. sqm 43.24
43.24 43.24 500.00 21620.00
24 Cement punning finish on roof
3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth
surface on roof as per design, drawing, specification
and instruction of site engineer. sqm 43.24
43.24 43.24 400.00 17296.00
Timber plank on bench:- Providing and laying timber
25 plank on bench all complete as per
design,drawing,specification and instruction of site
engineer sqm 0.90
0.90 0.90 12000.00 10800.00

Contractor Prepared By Checked By Approved By


Pages -262 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
PAVILION I I-
26 Earthwork

Earthwork in excavation for foundation along with


dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
1.00 5.60 0.90 0.60 cum. 3.02
1.00 2.35 0.83 1.00 cum. 1.94
1.00 5.75 1.10 1.00 cum. 6.33
1.00 2.20 0.85 1.00 cum. 1.87
Total= 13.16 13.16 1000.00 13157.75

Filling with earth or mixed soil stacked at site in


150mm thick layer on retaining walls including
27 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
1.00 5.60 0.90 0.30 cum. 1.51
1.00 2.35 0.83 0.30 cum. 0.58
1.00 5.75 1.10 0.30 cum. 1.90
1.00 2.20 0.85 0.30 cum. 0.56
Total= Cum 4.55 4.55 300.00 1365.63

28 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

1.00 5.60 0.90 0.15 cum 0.76


1.00 2.35 0.83 0.15 cum 0.29

Contractor Prepared By Checked By Approved By


Pages -263 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 5.75 1.10 0.15 cum 0.95
1.00 2.20 0.85 0.15 cum 0.28
Total= Cum 2.28 2.28 3000.00 6828.18
29 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

1.00 5.60 0.90 0.075 cum 0.38


1.00 2.35 0.83 0.075 cum 0.15
1.00 5.75 1.10 0.075 cum 0.47
1.00 2.20 0.85 0.075 cum 0.14
Total= Cum 1.14 1.14 10000.00 11389.12

30 RCC Works
Concrete Works for RCC (1:1.5:3) M20 on landscape
and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer.
Grid 3-4 footing 2.000 0.900 0.900 0.300 cum 0.49
Wall footing 1.000 5.000 1.150 0.250 cum 1.44
concrete pedestal-single post 8.000 0.300 0.300 0.750 cum 0.54
concrete pedestal-double post 2.000 0.300 0.600 1.100 cum 0.40
RCC SLAB 1.000 36.180 0.100 cum 3.62
Concrete band 2.000 4.196 0.450 0.100 cum 0.38
Total= cum 6.86 6.86 16000.00 109682.24

31 Steel reinforcement works


Fe500 Reinforcement in PCC including cutting,
bending and placing in position all complete as per
design, drawing, specification and satisfaction to site
engineer.
Total= kgs 1.08 1.08 120000.00 129120.00
32 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing.

Grid 3-4 footing 2.000 3.600 0.300 sqm 2.16


Wall footing 1.000 12.300 0.250 sqm 3.08
concrete pedestal-single post 8.000 1.200 0.750 sqm 7.20
concrete pedestal-double post 2.000 1.800 1.100 sqm 3.96
RCC SLAB 1.000 36.180 0.100 sqm 3.62
Concrete band 4.000 4.196 0.100 sqm 1.68
Total= sqm 21.69 21.69 600.00 13014.84

Contractor Prepared By Checked By Approved By


Pages -264 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
33 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Small Stone 2.00 0.40 0.40 0.55 cum. 0.18
5.00 0.40 0.40 1.15 cum. 0.92
Total= Cum 1.10 1.10 7000.00 7672.00

Contractor Prepared By Checked By Approved By


Pages -265 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
34 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
brick wall 1.000 4.196 0.450 4.110 cum 7.76
Deduction 0.00
brick wall -1.000 0.390 0.450 2.800 cum -0.49

Total= cum 7.27 7.27 15000.00 109036.53


35 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
150mmx150mm 2.00 0.15 0.15 3.60 cum. 0.16
150mmx150mm 7.00 0.15 0.15 2.80 cum. 0.44
wooden casing 7.00 1.10 0.13 0.60 cum. 0.60
50mm wooden pole 28.00 2.03 0.0020 cum. 0.11
25mm wooden pole 56.00 2.03 0.00049 cum. 0.06
wooden plates 14.00 0.40 0.40 0.03 cum. 0.06
Total= Cum 1.43 1.43 250000.00 356661.40

Engraving designs on wooden pillars properly finished


36.0 along with all necessary accessories along with wood
primer all complete as per design, drawing,
specification and instruction of the Engineer..
0.00 Nos 7.000
Total= 7.000 7.00 25000.00 175000.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
37 polished and finished in perfect line, level along with all
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
WB beam 5.000 6.375 0.100 0.100 cum. 0.319
WB beam 5.000 3.962 0.100 0.100 cum. 0.198

Contractor Prepared By Checked By Approved By


Pages -266 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
meth 28.000 0.052 0.075 cum. 0.109
Total= Cum 0.63 0.63 250000.00 156512.50

38 MS STEEL WORKS
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work including
transportation, cutting, connecting and placing in
position,treated with two coat of anticorrosive paints,
all complete as per drawings, specifications and
instruction. Kg/m
100mmx100mmx 4mm post 12.000 2.775 11.730 kg 390.61
100mmx100mmx 4mm beam 1.000 15.764 11.730 kg 184.91
100mmx100mmx 4mm beam 6.000 1.987 11.730 kg 139.85
100mmx100mmx 4mm beam 4.000 1.363 11.730 kg 63.95
75mmx75mmx 4mm bench 1.000 7.650 8.590 kg 65.71
50mmx50mmx 3.6mm bench 2.000 2.100 4.930 kg 20.71
7% for nuts, bolts, plates 60.6016 kg 60.60
Total= Kg 926.34 926.34 250.00 231584.71

Providing and placing decking sheet for concrete deck


39 slab including transportation, cutting, connecting and
placing in position with welds and studs all complete
as per drawings, specifications and instruction.
1.000 36.180 Sqm 36.18 36.18 6000.00 217080.00
40 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. sqm. 0.0
brick wall 1.000 10.485 3.175 33.28
brick wall 2.000 0.450 2.800 2.52
column pedestal 2.000 1.800 0.400 1.44
Deduction 0.00
brick wall -2.000 0.390 2.800 -2.18
35.06 35.06 600.00 21036.00

Contractor Prepared By Checked By Approved By


Pages -267 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
41 specifications to the surface of wall, ceiling, beams
columns, canopies, staircase, lobbies etc., all complete
as per drawings, specifications and instruction. The
rates shall include for scraping, washing the surface
with water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer. sqm. 35.1
35.1 35.06 300.00 10518.00
42 False ceiling works
Providing and placing false ceiling with plyboard(one
side veneer) including the channels to drop false 90500.00
ceiling all complete as per design, drawing,
specification and instruction of site engineer. sqm. - 36.2 36.20 2500.00
Providing and applying PU paint of approved
manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
the surface of false ceiling all complete as per
43 10860.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. sqm. - 36.2 36.20 300.00

44 Fibre cement board cladding for fascia


Providing and laying fibre cement board cladding on
fascia all complete as per design, drawing, 105750.00
specification and instruction of site engineer. sqm. 42.3 42.30 2500.00

45 Waterproofing coating on roof


Providing and laying waterproofing coating on roof all
complete as per design, drawing, specification and 18100.00
instruction of site engineer. sqm. 36.2 36.20 500.00

46 Cement punning finish on roof


3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth 4200.00
surface on roof as per design, drawing, specification
and instruction of site engineer. sqm. 10.5 10.50 400.00

Contractor Prepared By Checked By Approved By


Pages -268 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
PAVILION III-
47 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
Pavilion 3A 1.00 9.20 1.00 0.60 cum 5.52
1.00 9.30 0.90 0.60 cum 5.02
1.00 0.90 1.00 0.60 cum 0.54
1.00 0.90 1.05 0.60 cum 0.57

Pavilion 3B 1.00 8.20 1.00 0.60 cum 4.92


1.00 8.00 0.90 0.60 cum 4.32
1.00 2.00 0.70 0.60 cum 0.84
1.00 2.00 0.70 0.60 cum 0.84
Total 22.57 22.57 1000.00 22569.00
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
48 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
Pavilion 3A 1.00 8.30 1.00 0.75 cum 6.23
Pavilion 3B 1.00 8.30 1.00 0.75 cum 6.23
Total 12.45 12.45 300.00 3735.00

49 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

Pavilion 3A 1.00 9.20 1.00 0.15 cum 1.38


1.00 9.30 0.90 0.15 cum 1.26

Contractor Prepared By Checked By Approved By


Pages -269 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 0.90 1.00 0.15 cum 0.14
1.00 0.90 1.05 0.15 cum 0.14
Pavilion 3B 1.00 8.20 1.00 0.15 cum 1.23
1.00 8.00 0.90 0.15 cum 1.08
1.00 2.00 0.70 0.15 cum 0.21
1.00 2.00 0.70 0.15 cum 0.21
Total 5.64 5.64 3000.00 16926.75
Brick soling works
Providing and laying a single layer flat brick soling on
floor for preparation of P.C.C. in which joints should be
packed by sand to the required levels all complete as
per drawings, specifications and the instructions of the
Engineer.
Pavilion 3A 1.00 8.30 1.00 sqm 8.30
Pavilion 3B 1.00 8.30 1.00 sqm 8.30
Total 16.60 16.60 700.00 11620.00
51 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

Pavilion 3A 1.00 9.20 1.00 0.08 cum 0.69


1.00 9.30 0.90 0.08 cum 0.63
1.00 0.90 1.00 0.08 cum 0.07
1.00 0.90 1.05 0.08 cum 0.07
seating area 1.00 8.80 1.50 0.08 cum 0.99
Pavilion 3B 1.00 8.20 1.00 0.08 cum 0.61
1.00 8.00 0.90 0.08 cum 0.54
1.00 2.00 0.70 0.08 cum 0.11
1.00 2.00 0.70 0.08 cum 0.11
seating area 1.00 8.80 1.50 0.08 cum 0.99
Total 4.80 4.80 10000.00 48011.25

Contractor Prepared By Checked By Approved By


Pages -270 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
52 RCC Works
Concrete Works for RCC (1:1.5:3) M20 on landscape
and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer.
LOWER SLAB 2.000 56.330 0.075 8.449
UPPER SLAB 2.000 21.290 0.075 3.194
11.64 11.64 16000.00 186288.00
53 Steel reinforcement works
Fe500 Reinforcement in PCC including cutting,
bending and placing in position all complete as per
design, drawing, specification and satisfaction to site
engineer. 0.00 kgs 1.80
1.80 1.80 120000.00 216000.00
54 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging 93144.00
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing. sqm. 155.24 155.24 600.00
LOWER SLAB 2.000 56.330 112.660
UPPER SLAB 2.000 21.290 42.580
55 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in 19110.00


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer. cum. 2.73 2.73 7000.00
for wooden post 28.000 0.400 0.400 0.610 2.730

Contractor Prepared By Checked By Approved By


Pages -271 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
56 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
Pavilion 3A 2.00 8.80 0.25 0.85 cum 3.74
2.00 1.00 0.25 0.85 cum 0.43
Pavilion 3B 2.00 8.80 0.25 0.90 cum 3.96
2.00 1.00 0.25 0.90 cum 0.45
Total 8.58 8.58 15000.00 128625.00
57 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories 1133435.63
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
cum. 4.534 4.53 250000.00
150mmx150mm 28.000 0.150 0.150 3.452 2.175
wooden casing 28.000 1.100 0.130 0.350 1.401
50mm wooden pole 112.000 2.225 0.002 0.489
25mm wooden pole 224.000 2.225 0.0005 0.245
wooden plates 56.000 0.400 0.400 0.0250 0.224
Engraving designs on wooden pillars properly finished
along with all necessary accessories along with wood
58 350000.00
primer all complete as per design, drawing,
specification and instruction of the Engineer..
Nos 14.0 14.00 25000.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
polished and finished in perfect line, level along with all
59
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction 0.0 0.0
MB beam 4.000 5.600 0.100 0.200 0.448
MB beam 20.000 2.275 0.100 0.200 0.910
MB beam 4.000 11.400 0.100 0.200 0.912
IB beam 4.000 5.600 0.100 0.150 0.336
IB beam 4.000 11.400 0.100 0.150 0.684
CB beam 6.000 8.350 0.100 0.100 0.501
CB beam 14.000 2.550 0.100 0.100 0.357
meth 112.000 0.052 0.075 0.437
Total cum. 4.6 4.58 250000.00 1146200.00

60 Waterproof plywood works

Contractor Prepared By Checked By Approved By


Pages -272 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Providing and placing waterproof plywood for concrete
deck slab including transportation, cutting, connecting
and placing in position with nails, hooks, etc. all 108668.00
complete as per drawings, specifications and
instruction. sqm. 155.2 155.24 700.00

Contractor Prepared By Checked By Approved By


Pages -273 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
61 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting 4896.00
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. sqm. 8.16 8.16 600.00
Base Plaster of two pavilion 4.00 8.70 0.2 sqm. 7.0
4.00 1.50 0.2 sqm. 1.2

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
62 specifications to the surface of wall, ceiling, beams 2448.00
columns, canopies, staircase, lobbies etc., all complete
as per drawings, specifications and instruction. The
rates shall include for scraping, washing the surface
with water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer. sqm. 8.2 8.16 300.00

63 False ceiling works


Providing and placing false ceiling with plyboard(one
side veneer) including the channels to drop false 106450.00
ceiling all complete as per design, drawing,
specification and instruction of site engineer. sqm. 42.6 42.58 2500.00
Providing and applying PU paint of approved
manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
the surface of false ceiling all complete as per
64 12774.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. sqm. 42.6 42.58 300.00

Contractor Prepared By Checked By Approved By


Pages -274 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

65 WPC board for fascia


Providing and laying WPC board cladding on fascia all
complete as per design, drawing, specification and 279000.00
instruction of site engineer. sqm. 111.6 111.60 2500.00

66 Waterproofing membrane on roof


Providing and laying waterproofing membrane on roof
all complete as per design, drawing, specification and 108668.00
instruction of site engineer. sqm. 155.2 155.24 700.00

67 Panipatti
Providing and laying 20mm. thick Cement Water Bead
(Pani Patti) finished perfectly smooth including
44640.00
necessary scaffolding, raking the joint, wetting the
surface and curing all complete work rm 111.6 111.60 400.00

68 Flooring works

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance,
124192.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative.
sqm. 155.2 155.24 800.00
3mm cement punning in 1:1 c/s mortar in perfect line
69 and level including trowelling and finishing in smooth 62096.00
surface on roof as per design, drawing, specification
and instruction of site engineer. sqm. 155.2 155.24 400.00
Providing and laying of 25 mm thick Telia tile paving
work in (1:2) surki mortar and pointing the joints with
70 1:1 C/S mortar including curing on floor in perfect line 62832.00
and level all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. 18.5 18.48 3400.00
Providing and laying of stone slab of approved
thickness and color on floor in perfect line and level
71 including joint sealing of joint, grinding, polishing all 55440.00
complete as per design, drawing, specification and the
instrution of the site engineer. sqm. 7.9 7.92 7000.00

Contractor Prepared By Checked By Approved By


Pages -275 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
PAVILION IV-
72 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
2.00 4.10 0.80 0.80 cum 5.25
2.00 2.30 0.80 0.80 cum 2.94
2.00 6.20 0.45 0.65 cum 3.63
2.00 5.30 0.45 0.65 cum 3.10
For stone pillar 4.00 0.75 0.75 0.75 cum 1.69
Total= Cum 16.61 16.61 1000.00 16607.00
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
73 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
1.00 2.87 2.87 1.00 cum 8.24
4.00 5.50 0.40 0.30 cum 2.64
4.00 4.55 0.30 0.15 cum 0.82
4.00 3.45 0.30 0.15 cum 0.62
Total= Cum 12.32 12.32 300.00 3695.07

Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
74 quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

4.00 0.70 0.70 0.15 cum. 0.29


Total= Cum 0.29 0.29 3000.00 882.00

Contractor Prepared By Checked By Approved By


Pages -276 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
75 Brick soling works
Providing and laying a single layer flat brick soling on
floor for preparation of P.C.C. in which joints should be
packed by sand to the required levels all complete as
per drawings, specifications and the instructions of the
Engineer.
2.00 4.10 0.50 sqm 4.10
2.00 2.30 0.50 sqm 2.30
2.00 3.95 0.25 sqm 1.98
2.00 3.45 0.25 sqm 1.73
2.00 4.55 0.30 sqm 2.73
2.00 3.95 0.30 sqm 2.37
2.00 5.15 0.30 sqm 3.09
2.00 4.55 0.30 sqm 2.73
2.00 6.00 0.40 sqm 4.80
2.00 5.15 0.40 sqm 4.12
Area 4.00 2.90 sqm 11.60
Total= sqm 41.54 41.54 700.00 29078.00
76 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

Steps 1.000 24.000 0.460 0.075 cum 0.83


Steps 1.000 20.480 0.734 0.075 cum 1.13
Steps 1.000 18.080 0.600 0.075 cum 0.81
Steps 1.000 15.680 0.600 0.075 cum 0.71
Steps 1.000 13.280 0.300 0.075 cum 0.30
stone 4.000 0.660 0.660 0.075 cum 0.13
FLOOR 1.000 3.320 3.320 0.075 cum 0.83
Total= Cum 4.73 4.73 10000.00 47307.84
77 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Column 16.00 0.20 0.20 0.91 cum. 0.58
Total= Cum 0.58 0.58 25000.00 14560.00

Contractor Prepared By Checked By Approved By


Pages -277 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
78 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
1st Step 2.00 3.40 0.25 1.50 cum 2.55
1st Step 2.00 2.85 0.25 1.50 cum 2.14
2nd step 2.00 3.95 0.25 0.10 cum 0.20
2nd step 2.00 3.45 0.25 0.10 cum 0.17
3rd Step 2.00 4.55 0.25 0.55 cum 1.25
3rd Step 2.00 3.95 0.25 0.55 cum 1.09
4th Step 2.00 5.15 0.25 0.10 cum 0.26
4th Step 2.00 4.55 0.25 0.10 cum 0.23
5th Step 2.00 6.00 0.25 0.10 cum 0.30
5th Step 2.00 5.15 0.25 0.10 cum 0.26
Total= Cum 8.44 8.44 15000.00 126562.50
79 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer..
75mmx75mm 16.000 0.075 0.075 2.253 cum. 0.20
wooden casing 16.000 0.400 0.069 0.250 cum. 0.11
50mm wooden pole 64.000 2.225 0.002 cum. 0.28
25mm wooden pole 128.000 2.225 0.0005 cum. 0.14
wooden plates 32.000 0.400 0.400 0.0250 cum. 0.13
Total= Cum 0.86 0.86 250000.00 215090.00

Engraving designs on wooden pillars properly finished


80.0 along with all necessary accessories along with wood
primer all complete as per design, drawing,
specification and instruction of the Engineer..
0.000 Nos 0.00
Total= Nos 0.00 0.00 25000.00 0.00

Contractor Prepared By Checked By Approved By


Pages -278 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing, fabricating & fixing salwood(agrath) wooden


beams, meths, etc. fixing in pillar with joint properly
81 polished and finished in perfect line, level along with all
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
MB beam 10.000 4.000 0.075 0.100 cum. 0.30
IB beam 24.000 0.576 0.075 0.075 cum. 0.08
IB1 beam 4.000 4.000 0.075 0.075 cum. 0.09
CB beam 10.000 5.153 0.075 0.075 cum. 0.29
diagonal struts 4.000 2.300 0.050 0.050 cum. 0.02
truss 4.000 6.435 0.050 0.050 cum. 0.06
truss 4.000 4.092 0.075 0.075 cum. 0.09
purlin 4.000 13.084 0.075 0.075 cum. 0.29
Total= Cum 1.23 1.23 250000.00 307856.56

82 Roofing works
Providing and placing waterproof plywood for roofing
including transportation, cutting, connecting and
placing in position with nails, hooks, etc. all complete
as per drawings, specifications and instruction.
4.000 6.932 27.73
sqm. 27.73 27.73 700.00 19410.03

Providing and placing ikotile for roofing including


83 transportation, cutting, connecting and placing in 97050.19
position with nails all complete as per drawings,
specifications and instruction. sqm. 27.73 27.73 3500.00
4.000 6.932 27.73
84 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting 4116.00
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. sqm. 13.720 13.72 300.00
Steps 1.000 24.000 0.150 3.600
Steps 1.000 20.480 0.150 3.070
Steps 1.000 18.080 0.150 2.710
Steps 1.000 15.680 0.150 2.350
Steps 1.000 13.280 0.150 1.990

Contractor Prepared By Checked By Approved By


Pages -279 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
85 False ceiling works
Providing and placing false ceiling with cement board
including the channels to drop false ceiling all 40000.00
complete as per design, drawing, specification and
instruction of site engineer. sqm. 16 16.00 2500.00

Providing and applying fire retardant paint of approved


manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
86 the surface of false ceiling all complete as per 240000.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. sqm. 16.00 15000.00
87 WPC Panel for ceiling
Providing and laying WPC Panel for ceiling all
complete as per design, drawing, specification and 30557.62
instruction of site engineer. sqm. 12.73 2400.00
perimeter 4.000 3.183 12.732
88 Waterproofing membrane on roof
Providing and laying waterproofing membrane on roof
all complete as per design, drawing, specification and 13864.31
instruction of site engineer. sqm. 27.73 500.00
area 1.000 4.000 6.932 27.729
89 Flooring works

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance,
8816.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative.
sqm. 11.02 800.00
area 1.000 11.020 11.020
3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth
90 5488.00
surface on roof as per design, drawing, specification
and instruction of site engineer. sqm. 13.72 400.00
steps 1.000 13.720 13.720
Providing and laying of 25 mm thick Telia tile paving
work in (1:2) surki mortar and pointing the joints with
91 1:1 C/S mortar including curing on floor in perfect line 27880.00
and level all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. 8.20 3400.00
area 1.000 8.200 8.200
Providing and laying of 50mm thick stone slab of
approved thickness and color on floor in perfect line
92 and level including joint sealing of joint, grinding, 19880.00
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. 2.84 7000.00
area 1.000 2.840 2.840

Contractor Prepared By Checked By Approved By


Pages -280 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Providing and laying of flagstone of approved
thickness and color on floor in perfect line and level
93 including joint sealing of joint, grinding, polishing all 41818.00
complete as per design, drawing, specification and the
instrution of the site engineer. sqm. 29.87 1400.00
Steps 1.000 24.000 0.440 10.560
Steps 1.000 20.480 0.300 6.140
Steps 1.000 18.080 0.300 5.420
Steps 1.000 15.680 0.300 4.700
Steps 1.000 13.280 0.230 3.050
Bells on roof:- Providing and fixing design, drawing,
94 216000.00
specification and instruction of site engineer Nos 36 36.00 6000.00
MANDAP
95 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
2.00 3.70 0.80 0.60 cum 3.55
2.00 3.45 0.80 0.60 cum 3.31
2.00 5.50 0.60 0.45 cum 2.97
2.00 3.30 0.60 0.45 cum 1.78
Inside Mandap 4.00 0.70 0.70 0.20 cum 0.39
Total= Cum 12.01 12.01 1000.00 12008.00
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
96 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
2.00 3.70 0.80 0.30 cum 1.78
2.00 3.40 0.80 0.30 cum 1.63
2.00 5.50 0.60 0.30 cum 1.98
2.00 3.30 0.60 0.30 cum 1.19
1.00 2.90 0.60 cum 1.74
Total= Cum 8.32 8.32 300.00 2494.80

Contractor Prepared By Checked By Approved By


Pages -281 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
97 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

4.00 0.70 0.70 0.15 cum. 0.29


Total= Cum 0.29 0.29 3000.00 882.00
98 Brick soling works
Providing and laying a single layer flat brick soling on
floor for preparation of P.C.C. in which joints should be
packed by sand to the required levels all complete as
per drawings, specifications and the instructions of the
Engineer.

2.00 3.40 0.50 sqm 3.40


2.00 5.50 0.60 sqm 6.60
2.00 3.30 0.60 sqm 3.96
2.00 2.70 0.25 sqm 1.35
2.00 3.70 0.25 sqm 1.85
Area 4.00 2.90 sqm 11.60
Total= Sqm 28.76 28.76 700.00 20132.00
99 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

2.00 3.70 0.50 0.075 cum. 0.28


2.00 3.40 0.50 0.075 cum. 0.26
1 step soiling 2.00 5.50 0.60 0.075 cum. 0.49
2.00 3.30 0.60 0.075 cum. 0.30
1st step top PCC 2.00 5.50 0.60 0.075 cum. 0.49
2.00 4.90 0.60 0.075 cum. 0.44
2nd step 2.00 4.90 0.60 0.075 cum. 0.44
2.00 4.30 0.60 0.075 cum. 0.39

Contractor Prepared By Checked By Approved By


Pages -282 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
3rd step 2.00 4.30 0.30 0.075 cum. 0.19
Area 1.00 3.20 3.20 0.075 cum. 0.77
4.00 0.75 0.75 0.075 cum. 0.17
Total= Cum 4.22 4.22 10000.00 42187.50
100 STONE PILLAR WORKS

Providing and placing stone pillar above PCC in


cement mortar (1:4) all complete as per drawings,
specifications and instruction of the engineer.
Column 16.00 0.20 0.20 0.91 cum. 0.58
Total= Cum 0.58 0.58 7000.00 4076.80
Brick Masonry Works in Superstructure ( 1 : 4
c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
cement : 4coarse sand) in landscape works in all
101
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
Steps 1.000 20.480 0.300 0.561 cum 3.440
Steps 1.000 18.080 0.300 0.075 cum 0.400
Steps 1.000 15.680 0.300 0.075 cum 0.350
Steps 1.000 13.280 0.230 1.164 3.550
Total= Cum 7.74 7.74 15000.00 116100.00
102 WOODEN WORKS

Providing, fabricating & fixing salwood(agrath) wooden


pillars fixing in stone pillar with joint properly finished in
perfect line, level along with all necessary accessories
along with wood primer all complete as per design,
drawing, specification and instruction of the Engineer.. -
75mmx75mm 16.000 0.075 0.075 2.253 cum. 0.20
wooden casing 16.000 0.400 0.069 0.250 cum. 0.11
50mm wooden pole 64.000 2.225 0.002 cum. 0.28
25mm wooden pole 128.000 2.225 0.0005 cum. 0.14
wooden plates 32.000 0.400 0.400 0.0250 cum. 0.13
Total= Cum 0.86 0.86 250000.00 215090.00

Contractor Prepared By Checked By Approved By


Pages -283 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Engraving designs on wooden pillars properly finished


along with all necessary accessories along with wood
103.0
primer all complete as per design, drawing,
specification and instruction of the Engineer..

-
Total= 7.00 7.00 7.00 25000.00 175000.00
Providing, fabricating & fixing salwood(agrath) wooden
beams, meths, etc. fixing in pillar with joint properly
polished and finished in perfect line, level along with all
104
necessary accessories along with wood primer all
complete as per design, drawing, specification and
instruction
MB beam 10.000 4.000 0.075 0.100 cum. 0.30
IB beam 24.000 0.576 0.075 0.075 cum. 0.08
IB1 beam 4.000 4.000 0.075 0.075 cum. 0.09
CB beam 10.000 5.153 0.075 0.075 cum. 0.29
diagonal struts 4.000 2.300 0.050 0.050 cum. 0.02
truss 4.000 6.435 0.050 0.050 cum. 0.06
truss 4.000 4.092 0.075 0.075 cum. 0.09
purlin 4.000 13.084 0.075 0.075 cum. 0.29
Total= Cum 1.23 1.23 250000.00 307856.56
105 Roofing works
Providing and placing waterproof plywood for roofing
including transportation, cutting, connecting and
placing in position with nails, hooks, etc. all complete
as per drawings, specifications and instruction.
4.000 6.932 27.73
- 27.73 27.73 700.00 19410.03
Providing and placing ikotile for roofing including
106 transportation, cutting, connecting and placing in 69321.56
position with nails all complete as per drawings,
specifications and instruction. sqm. - 27.73 27.73 2500.00
4.000 6.932 27.73
107 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on brick walls
including necessary scaffolding , cleaning & wetting 8232.00
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete. sqm. - Sqm 13.72 600.00
Steps 1.000 24.000 0.150 3.600
Steps 1.000 20.480 0.150 3.070
Steps 1.000 18.080 0.150 2.710
Steps 1.000 15.680 0.150 2.350
Steps 1.000 13.280 0.150 1.990

Contractor Prepared By Checked By Approved By


Pages -284 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

108 False ceiling works


Providing and placing false ceiling with cement board
including the channels to drop false ceiling all 22500.00
complete as per design, drawing, specification and
instruction of site engineer. sqm. - 9 9.00 2500.00

Providing and applying fire retardant paint of approved


manufacturer and shade over primer of approved
manufacturer as per manufacturer's specifications to
109 the surface of false ceiling all complete as per 135000.00
drawings, specifications and instruction. The rates
shall include for surface preparation, scaffolding etc.,
all complete as per the manufacturer's
recommendations and as approved by the Engineer. sqm. - 9 9.00 15000.00
110 WPC Panel for ceiling
Providing and laying WPC Panel for ceiling all
complete as per design, drawing, specification and 26994.42
instruction of site engineer. sqm. - 17.996 18.00 1500.00
perimeter 4.000 4.499 17.996
111 Waterproofing membrane on roof
Providing and laying waterproofing membrane on roof
all complete as per design, drawing, specification and 16637.17
instruction of site engineer. sqm. - 27.73 600.00
area 4.000 6.932 27.729
112 Flooring works

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance, 8816.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative. sqm. - 11.020 11.02 800.00
area 1.000 11.020 11.020
3mm cement punning in 1:1 c/s mortar in perfect line
113 and level including trowelling and finishing in smooth 5488.00
surface on roof as per design, drawing, specification
and instruction of site engineer. sqm. - 13.720 13.72 400.00
steps 1.000 13.720 13.720
Providing and laying of 25 mm thick Telia tile paving
work in (1:2) surki mortar and pointing the joints with
114 1:1 C/S mortar including curing on floor in perfect line 28700.00
and level all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 8.200 8.20 3500.00
area 1.000 8.200 8.200
Providing and laying of 50mm thick stone slab of
approved thickness and color on floor in perfect line
115 and level including joint sealing of joint, grinding, 19880.00
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 2.840 2.84 7000.00
area 1.000 2.840 2.840

Contractor Prepared By Checked By Approved By


Pages -285 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Providing and laying of flagstone of approved
thickness and color on floor in perfect line and level
116 including joint sealing of joint, grinding, polishing all 22764.00
complete as per design, drawing, specification and the
instrution of the site engineer. sqm. - 16.260 16.26 1400.00
Steps 1.000 20.480 0.300 6.140
Steps 1.000 18.080 0.300 5.420
Steps 1.000 15.680 0.300 4.700
117 Bells on roof:- Providing and fixing design, drawing, 360000.00
specification and instruction of site engineer Nos - 36 36.00 10000.00
Landscape, drainage and Boundary wall works
118 Site Clearance Work
Clearing and grubbing the site for construction by
removing 150mm thick top soil including bushes, small
trees, levelling of undulated ground, shorting and
stacking/storing selected top soil for reuse in
landscaping works, disposing unsuitable materials
from site, etc., all complete as per drawings,
specifications and instructions of the Engineer.
1.00 80.00 50.00 sqm 4000.00
1.00 20.00 50.00 sqm 1000.00
1.00 50.00 15.00 Sqm 750.00
Total= sqm 5750.00 5750.00 60.00 345000.00
119 Dismantling
Dismantling of existing structures by manual means
comprising of cement concrete works including
scaffolding wherever necessary, sorting the dismantled
material, disposal and stacking materials with all lifts
and leads of 1000meters
5.00 0.25 0.25 1.70 cum 0.53
14.00 0.25 0.25 1.60 cum 1.40
8.00 0.25 0.25 2.10 cum 1.05
1.00 1.10 1.00 0.15 cum 0.17
1.00 3.70 1.30 0.15 cum 0.72
1.00 6.20 3.20 0.15 cum 2.98
1.00 1.00 3.20 0.15 cum 0.48
1.00 4.90 5.20 0.13 cum 3.19
Total= Cum 10.51 10.51 1000.00 10508.75

Contractor Prepared By Checked By Approved By


Pages -286 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Dismantling of existing blocks by manual means
comprising of brick works including scaffolding
120 wherever necessary, sorting the dismantled material,
disposal and stacking materials with all lifts and leads
of 1000meters
2.00 5.50 3.00 sqm 10.50
1.00 6.50 3.00 sqm 10.50
1.00 30.00 1.50 sqm 32.50
1.00 20.00 6.00 sqm 27.00
1.00 15.00 5.75 sqm 21.75
1.00 195.00 Sqm 195.00
Total= sqm 297.25 297.25 1000.00 297250.00
Dismantling of barbed wire fencing includong posts,
foundation concrete, backfilling of pit by manual means
121
including disposal and stacking materials with all lifts
and leads of 1000meters
4.00 29.50 Rm 118.00
6.00 50.00 Rm 300.00
Total= Rm 418.00 418.00 1000.00 418000.00

Dismantling of steel including dismembering by


122
manual means
Exterior wall 1.00 23.50 1.20 kg 423.00 15.00
Gate 1.00 2.70 2.10 kg 198.45 35.00
Small gate 1.00 1.80 2.00 kg 126.00 35.00
Gate 1.00 4.50 3.50 kg 551.25 35.00
Total= Kg 1298.70 1298.70 120.00 155844.00
Dismantling of granular courses pavements and
123 disposal of dismantled materials upto a lead of 1000
m, stacking materials all by manual means
existing pathways and pavement surfaces 1.00 200.00 0.15 cum. 30.00
existing pathways and pavement surfaces 1.00 324.54 0.15 cum. 48.68
Total= Cum 78.68 78.68 1000.00 78681.00

Contractor Prepared By Checked By Approved By


Pages -287 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
124 Earthwork
Earthwork in excavation for foundation along with
dewatering water simultaneously till completion of
foundation in all types of soil including existing debris
& brick bats of old structure if any up to 25 ft.depth
below as per the design, drawing, specification &
instructions of consultant and his authorized
representative.
for RT Walls (From North To South) 1.00 3.70 0.30 1.20 cum. 1.33
1.00 2.00 0.30 0.90 cum. 0.54
1.00 6.85 0.30 1.20 cum. 2.47
1.00 4.00 1.00 1.50 cum. 6.00
1.00 3.90 1.00 1.50 cum. 5.85
1.00 8.80 1.00 1.50 cum. 13.20
1.00 4.75 1.10 1.50 cum. 7.84
1.00 1.10 1.00 1.50 cum. 1.65
1.00 11.30 1.00 1.50 cum. 16.95
2.00 1.00 1.00 1.50 cum. 3.00
1.00 4.45 1.00 1.50 cum. 6.68
1.00 3.40 1.00 1.50 cum. 5.10
1.00 4.75 1.00 1.50 cum. 7.13
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.45 cum. 1.45
1.00 5.50 0.85 0.45 cum. 2.10
1.00 5.20 0.85 0.65 cum. 2.87
1.00 5.90 0.85 1.20 cum. 6.02
1.00 3.00 0.60 0.95 cum. 1.71
1.00 1.50 0.60 0.95 cum. 0.85
1.00 1.30 0.60 0.95 cum. 0.74
1.00 2.50 0.60 0.95 cum. 1.42
1.00 1.20 0.60 0.95 cum. 0.68
1.00 2.10 0.60 0.95 cum. 1.20
1.00 5.40 0.60 0.95 cum. 3.08
1.00 4.60 0.60 0.95 cum. 2.62

Contractor Prepared By Checked By Approved By


Pages -288 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.95 cum. 1.31
1.00 1.65 0.60 0.95 cum. 0.94
1.00 2.10 0.60 0.45 cum. 0.57
1.00 1.30 0.60 0.30 cum. 0.23
1.00 3.00 0.60 0.90 cum. 1.62
1.00 13.50 0.60 0.90 cum. 7.29
for RS Walls (From North to South) -4th step 1.00 15.10 0.60 0.90 cum. 8.15
Whole Kund of Radius 3.15m 1.00 31.16 0.80 cum. 24.93
Outer wall extra depth 0.15m 1.00 17.20 0.50 0.15 cum. 1.29
First step extra 0.15m depth 1.00 10.40 0.60 0.15 cum. 0.94
French Drain 1.00 120.00 0.60 0.60 cum. 43.20
Retaining Wall 1.00 2.90 0.75 1.20 cum. 2.61
East side 1.00 9.40 0.75 1.20 cum. 8.46
East side 1.00 6.80 0.75 1.20 cum. 6.12
East side 1.00 6.90 0.75 0.45 cum. 2.33
East side 1.00 8.40 0.75 1.10 cum. 6.93
East side 1.00 5.20 0.75 1.10 cum. 4.29
East side 1.00 7.10 0.75 1.10 cum. 5.86
East side 1.00 8.80 0.75 1.10 cum. 7.26
East side 1.00 6.50 1.00 2.00 cum. 13.00
South east side 1.00 2.20 1.00 2.00 cum. 4.40
South side 1.00 28.50 0.90 2.00 cum. 51.30
Brick wall south side 1.00 20.50 0.90 1.00 cum. 18.45
Brick wall west side 1.00 4.00 0.90 1.00 cum. 3.60
River bank wall 1.00 8.50 2.00 2.00 cum. 34.00
1.00 9.50 2.00 2.00 cum. 38.00
1.00 6.50 1.75 1.20 cum. 13.65
1.00 4.45 1.75 1.20 cum. 9.35
1.00 6.43 1.75 1.20 cum. 13.50
1.00 0.80 1.75 1.20 cum. 1.68
1.00 5.10 1.75 1.20 cum. 10.71
1.00 2.32 1.75 1.20 cum. 4.87
1.00 3.30 1.75 1.20 cum. 6.93
1.00 11.10 1.75 1.20 cum. 23.31
1.00 1.45 1.75 1.20 cum. 3.05
1.00 3.95 1.75 1.20 cum. 8.30
1.00 7.50 1.75 1.20 cum. 15.75
1.00 1.80 1.75 1.20 cum. 3.78
Concrete Drain 1.00 12.68 0.60 0.50 cum. 3.80
1.00 10.90 0.60 0.50 cum. 3.27
1.00 2.00 0.60 0.50 cum. 0.60
1.00 1.65 0.60 0.50 cum. 0.49
1.00 1.28 0.60 0.50 cum. 0.38
1.00 4.40 0.60 0.50 cum. 1.32
1.00 7.25 0.60 0.50 cum. 2.18
1.00 7.40 0.60 0.50 cum. 2.22
1.00 1.00 0.60 0.50 cum. 0.30
1.00 6.90 0.60 0.50 cum. 2.07
1.00 7.30 0.60 0.50 cum. 2.19
Contractor Prepared By Checked By Approved By
Pages -289 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 3.50 0.60 0.50 cum. 1.05
1.00 9.90 0.60 0.50 cum. 2.97
1.00 9.50 0.60 0.50 cum. 2.85
1.00 5.10 0.60 0.50 cum. 1.53
1.00 6.00 0.60 0.50 cum. 1.80
1.00 11.20 0.60 0.50 cum. 3.36
1.00 1.50 0.60 0.50 cum. 0.45
1.00 8.35 0.60 0.50 cum. 2.51
1.00 3.10 0.60 0.50 cum. 0.93
1.00 1.80 0.60 0.50 cum. 0.54
1.00 7.50 0.60 0.50 cum. 2.25
1.00 2.40 0.60 0.50 cum. 0.72
1.00 3.60 0.60 0.50 cum. 1.08
1.00 3.00 0.60 0.50 cum. 0.90
1.00 1.30 0.60 0.50 cum. 0.39
1.00 6.00 0.60 0.75 cum. 2.70
1.00 22.00 0.60 0.75 cum. 9.90
Shiv mandir east 1.00 13.00 0.60 0.50 cum. 3.90
Shiv mandir north 1.00 9.20 0.60 0.50 cum. 2.76
Catch Basin 3.00 1.00 1.00 1.05 cum. 3.15
RO Base 1.00 31.00 1.50 1.50 cum. 69.75
RE 1.00 33.80 1.50 1.50 cum. 76.05
RE 1.00 13.00 1.50 1.50 cum. 29.25
RE 1.00 4.30 1.00 2.00 cum. 8.60
RE 1.00 9.00 1.00 1.70 cum. 15.30
RC 3.00 3.50 5.30 3.30 cum. 183.65
RS1 1.00 20.00 0.75 1.00 cum. 15.00
RS2 1.00 19.50 0.75 1.40 cum. 20.47
RS3 1.00 19.50 0.75 2.10 cum. 30.71
RS4 1.00 23.90 0.75 1.00 cum. 17.92
RE 1.00 13.00 0.40 0.45 cum. 2.34
1.00 29.70 0.40 0.45 cum. 5.35
1.00 24.70 0.40 0.45 cum. 4.45
1.00 11.50 0.40 0.45 cum. 2.07
1.00 10.40 0.40 0.45 cum. 1.87
1.00 13.90 0.40 0.45 cum. 2.50
1.00 10.90 0.40 0.45 cum. 1.96
1.00 11.50 0.40 0.45 cum. 2.07
1.00 5.50 0.40 0.45 cum. 0.99
1.00 28.00 0.40 0.45 cum. 5.04
1.00 24.70 0.40 0.45 cum. 4.45
1.00 11.90 0.40 0.45 cum. 2.14
For Soling & PCC
PCC P2 1.00 6.10 6.90 0.15 cum. 6.31
1.00 5.80 6.80 0.15 cum. 5.92
Deduction (1.00) 4.40 0.55 0.15 cum. (0.36)
Stone Pillar (10.00) 0.40 0.40 0.15 cum. (0.24)
1.00 7.50 4.20 0.15 cum. 4.73
1.00 7.30 4.20 0.15 cum. 4.60
(1.00) 1.77 0.05 0.15 cum. (0.01)

Contractor Prepared By Checked By Approved By


Pages -290 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
(1.00) 0.60 0.30 0.15 cum. (0.03)
(1.00) 4.10 0.50 0.15 cum. (0.31)
(1.00) 0.70 0.37 0.15 cum. (0.04)
1.00 6.60 1.25 0.15 cum. 1.24
RCC 1.00 6.30 1.15 0.22 cum. 1.63
RCC 1.00 4.45 1.00 0.22 cum. 1.00
RCC 1.00 3.10 1.10 0.22 cum. 0.77
RCC 1.00 1.20 2.50 0.22 cum. 0.67
P3 1.00 11.30 4.95 0.15 cum. 8.39
1.00 11.05 5.20 0.15 cum. 8.62
PCC At Aarati Side 1.00 5.40 4.80 0.25 cum. 6.48
1.00 4.55 1.95 0.25 cum. 2.22
1.00 2.10 3.47 0.25 cum. 1.82
1.00 7.20 3.03 0.25 cum. 5.45
1.00 9.45 3.93 0.25 cum. 9.27
1.00 2.00 3.22 0.25 cum. 1.61
1.00 1.70 1.50 0.25 cum. 0.64
1.00 1.20 9.00 0.22 cum. 2.43
1.00 6.00 0.07 0.22 cum. 0.09
1.00 14.50 0.70 0.22 cum. 2.28
1.00 0.70 5.40 0.22 cum. 0.85
1.00 1.12 4.40 0.22 cum. 1.10
1.00 1.65 3.80 0.22 cum. 1.41
1.00 1.05 3.90 0.22 cum. 0.92
1.00 1.70 2.18 0.22 cum. 0.83
1.00 2.63 4.83 0.22 cum. 2.85
1.00 0.90 9.70 0.22 cum. 1.96
1.00 1.00 9.55 0.22 cum. 2.15
Stone masonry 1.00 31.00 1.86 0.30 cum. 17.30
1.00 10.40 1.73 0.30 cum. 5.40
1.00 9.90 1.38 0.30 cum. 4.10
1.00 9.50 1.76 0.30 cum. 5.02
1.00 9.90 1.05 0.30 cum. 3.12
1.00 8.90 1.05 0.30 cum. 2.80
1.00 7.30 0.92 0.30 cum. 2.01
1.00 6.60 0.45 0.75 cum. 2.23
1.00 15.00 1.50 2.20 cum. 49.50
Soling Exv
N. RS 8& RS 9 1.00 2.16 2.23 0.525 cum. 2.53
RS 9 RS 10 1.00 22.70 1.36 0.525 cum. 16.21
N .RS 8 WALL 1.00 4.25 0.40 0.525 cum. 0.89
N.RC 1.00 3.20 3.80 0.525 cum. 6.38
rs 1 ganesh mandir 1.00 5.00 0.45 0.525 cum. 1.18
RS 1 & RS 2 PIPAL S 1.00 3.70 2.50 0.525 cum. 4.86
RS 1 & RS 2 TREE 1.00 4.40 1.98 0.525 cum. 4.57
RS 1 & RS 2 TREE 1.00 5.30 2.35 0.525 cum. 6.54
last step 1.00 20.00 0.80 0.525 cum. 8.40
1.00 18.90 0.80 0.525 cum. 7.94
1.00 13.80 0.80 0.525 cum. 5.80
1.00 4.10 0.80 0.525 cum. 1.72

Contractor Prepared By Checked By Approved By


Pages -291 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 2.98 0.55 0.525 cum. 0.86
For Cutting at bed Retaining wall 1.00 20 2.32 0.6 cum. 27.84
1.00 16 0.8 0.5 cum. 6.40
1.00 8.4 0.48 0.5 cum. 2.02
Drain Exv 1.00 89.90 0.60 0.75 cum. 40.46
Water Reserve 1.00 5.10 1.50 Area cum. 7.66
1.00 0.50 0.65 0.625 cum. 0.20
1.00 2.55 0.30 0.625 cum. 0.48
Ramp Brick Wall 1.00 12.20 0.45 1 cum. 5.49
Ramp Brick Wall 1.00 12.20 0.45 0.50 cum. 2.75
For Main Gate
Foundation 4.00 1.20 1.20 1.50 cum 8.64
For Beam 2.00 3.75 0.30 0.75 cum 1.69
2.00 1.80 0.30 0.75 cum 0.81
For Boundary Wall 1.00 1.70 0.50 0.90 cum 0.77
Power House 1.00 1.80 1.80 0.60 cum 1.94
Ramp Excavation 1.00 20.30 2.83 0.30 cum 17.26
Steps near Water reserve 1.00 4.85 1.20 1.00 cum 5.82
1.00 2.65 1.05 0.75 cum 2.09
Total= Cum 1,459.84 1459.84 250.00 364959.22
Filling with earth or mixed soil stacked at site in
150mm thick layer on retaining walls including
125 watering, ramming, consolidation and dressing as per
drawing, specifications and satisfaction to site
engineer all complete.
for RT Walls (From North To South) 1.00 3.70 1.00 0.30 cum. 1.11
1.00 2.00 1.00 0.30 cum. 0.60
1.00 6.85 1.00 0.30 cum. 2.05
1.00 4.00 1.00 0.30 cum. 1.20
1.00 3.90 1.00 0.30 cum. 1.17
1.00 8.80 1.00 0.30 cum. 2.64
1.00 4.75 1.10 0.30 cum. 1.57
1.00 1.10 1.00 0.30 cum. 0.33
1.00 11.30 1.00 0.30 cum. 3.39
2.00 1.00 1.00 0.30 cum. 0.60
1.00 4.45 1.00 0.30 cum. 1.34
1.00 3.40 1.00 0.30 cum. 1.02
1.00 4.75 1.00 0.30 cum. 1.43

Contractor Prepared By Checked By Approved By


Pages -292 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.30 cum. 0.97
1.00 5.50 0.85 0.30 cum. 1.40
1.00 5.20 0.85 0.30 cum. 1.33
1.00 5.90 0.85 0.30 cum. 1.50
1.00 3.00 0.60 0.30 cum. 0.54
1.00 1.50 0.60 0.30 cum. 0.27
1.00 1.30 0.60 0.30 cum. 0.23
1.00 2.50 0.60 0.30 cum. 0.45
1.00 1.20 0.60 0.30 cum. 0.22
1.00 2.10 0.60 0.30 cum. 0.38
1.00 5.40 0.60 0.30 cum. 0.97
1.00 4.60 0.60 0.30 cum. 0.83
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.30 cum. 0.41
1.00 1.65 0.60 0.30 cum. 0.30
1.00 2.10 0.60 0.30 cum. 0.38
1.00 1.30 0.60 0.30 cum. 0.23
1.00 3.00 0.60 0.30 cum. 0.54
1.00 13.50 0.60 0.30 cum. 2.43
for RS Walls (From North to South) -4th step 1.00 15.10 0.60 0.30 cum. 2.72
Outer wall 1.00 17.20 0.50 0.30 cum. 2.58
First step 1.00 10.40 0.60 0.30 cum. 1.87
French Drain 1.00 120.00 0.60 0.30 cum. 21.60
East side 1.00 6.50 0.50 1.00 cum. 3.25
South east side 1.00 2.20 0.50 1.00 cum. 1.10
South side 1.00 28.50 0.50 1.00 cum. 14.25
Brick wall south side 1.00 20.50 0.50 1.00 cum. 10.25
Brick wall west side 1.00 4.00 0.50 1.00 cum. 2.00
River bank wall 1.00 8.50 0.50 1.00 cum. 4.25
1.00 9.50 0.50 1.00 cum. 4.75
1.00 6.50 0.50 1.20 cum. 3.90

Contractor Prepared By Checked By Approved By


Pages -293 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 4.45 0.50 1.20 cum. 2.67
1.00 6.43 0.50 1.20 cum. 3.86
1.00 0.80 0.50 1.20 cum. 0.48
1.00 5.10 0.50 1.20 cum. 3.06
1.00 2.32 0.50 1.20 cum. 1.39
1.00 3.30 0.50 1.20 cum. 1.98
1.00 11.10 0.50 1.20 cum. 6.66
1.00 1.45 0.50 1.20 cum. 0.87
1.00 3.95 0.50 1.20 cum. 2.37
1.00 7.50 0.50 1.20 cum. 4.50
1.00 1.80 0.50 1.20 cum. 1.08
1.00 2.90 0.50 0.90 cum. 1.31
1.00 9.40 0.50 0.90 cum. 4.23
1.00 6.80 0.50 0.90 cum. 3.06
1.00 6.90 0.50 0.90 cum. 3.11
1.00 8.40 0.50 0.90 cum. 3.78
1.00 5.20 0.50 0.90 cum. 2.34
1.00 7.10 0.50 0.90 cum. 3.20
1.00 8.80 0.50 0.90 cum. 3.96
Mandap Area 1.00 5.00 4.50 1.00 cum. 22.50
Between P3 and Mandap 1.00 5.00 4.00 0.50 cum. 10.00
Mandap east slope area (from cad) 1.00 15.00 1.00 cum. 15.00
Catch Basain 12.00 0.20 0.70 0.90 cum. 1.51
RO Base 1.00 31.00 0.50 0.90 cum. 13.95
RE 1.00 33.80 0.50 0.90 cum. 15.21
RE 1.00 13.00 0.50 0.90 cum. 5.85
RE 1.00 4.30 0.50 0.90 cum. 1.94
RE 1.00 9.00 0.50 0.90 cum. 4.05
RC 3.00 3.50 5.30 0.90 cum. 50.09
RS1 1.00 20.00 0.75 0.90 cum. 13.50
RS2 1.00 19.50 0.75 0.90 cum. 13.16
RS3 1.00 19.50 0.75 0.90 cum. 13.16
RS4 1.00 23.90 0.75 0.90 cum. 16.13
1.00 15.00 0.75 1.50 cum. 16.88
Total= Cum 371.17 371.17 300.00 111349.50

Contractor Prepared By Checked By Approved By


Pages -294 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
126 Stone soling works

Providing and laying uncoursed hand packed Dry


Rubble Stone soling of 150mm on landscape works
with out any special dressing of stone including filling
interstices with suitable quarry waste or stone chips or
quarry sand, watering, compacting using appropriate
mechanical compaction means with all contractors
materials, handling, placing etc. all complete as per
drawings, specifications and instruction of the
Engineer. The complete item including all lead & lift.

for RT Walls (From North To South) 1.00 3.70 0.90 0.15 cum. 0.50
1.00 2.00 0.90 0.15 cum. 0.27
1.00 6.75 0.90 0.15 cum. 0.91
1.00 4.00 0.90 0.15 cum. 0.54
1.00 3.80 0.90 0.15 cum. 0.51
1.00 8.80 0.90 0.15 cum. 1.19
1.00 4.75 0.90 0.15 cum. 0.64
1.00 1.10 0.90 0.15 cum. 0.15
1.00 11.30 0.90 0.15 cum. 1.53
2.00 1.00 0.90 0.15 cum. 0.14
1.00 4.45 0.90 0.15 cum. 0.60
1.00 3.40 0.90 0.15 cum. 0.46
1.00 4.75 0.90 0.15 cum. 0.64
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.15 cum. 0.48
1.00 5.50 0.85 0.15 cum. 0.70
1.00 5.20 0.85 0.15 cum. 0.66
1.00 5.90 0.85 0.15 cum. 0.75
1.00 3.00 0.60 0.15 cum. 0.27
1.00 1.50 0.60 0.15 cum. 0.13
1.00 1.30 0.60 0.15 cum. 0.12
1.00 2.50 0.60 0.15 cum. 0.22
1.00 1.20 0.60 0.15 cum. 0.11
1.00 2.10 0.60 0.15 cum. 0.19
1.00 5.30 0.60 0.15 cum. 0.48
1.00 4.60 0.60 0.15 cum. 0.41
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.15 cum. 0.21
1.00 1.65 0.60 0.15 cum. 0.15
1.00 2.10 0.60 0.15 cum. 0.19
1.00 1.30 0.60 0.15 cum. 0.12
1.00 3.00 0.60 0.15 cum. 0.27
1.00 13.50 0.60 0.15 cum. 1.21
for RS Walls (From North to South) -4th step 1.00 15.00 0.60 0.15 cum. 1.35
Outer wall 1.00 17.10 0.60 0.15 cum. 1.54
First step 1.00 10.40 0.60 0.15 cum. 0.94
center 1.00 8.04 0.60 0.15 cum. 0.72
for RT Walls (From North To South) 1.00 2.90 0.75 0.15 cum. 0.33
1.00 9.40 0.75 0.15 cum. 1.06
1.00 6.80 0.75 0.15 cum. 0.76
1.00 6.90 0.75 0.15 cum. 0.78
Contractor Prepared By Checked By Approved By
Pages -295 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 8.40 0.75 0.15 cum. 0.95
1.00 5.20 0.75 0.15 cum. 0.59
1.00 7.10 0.75 0.15 cum. 0.80
1.00 8.80 0.75 0.15 cum. 0.99
East side 1.00 6.50 0.90 0.15 cum. 0.88
South east side 1.00 2.20 0.90 0.15 cum. 0.30
South side 1.00 28.50 0.90 0.15 cum. 3.85
River bank wall 1.00 8.50 2.00 0.15 cum. 2.55
1.00 9.50 2.00 0.15 cum. 2.85
1.00 6.50 1.75 0.15 cum. 1.71
1.00 4.45 1.75 0.15 cum. 1.17
1.00 6.43 1.75 0.15 cum. 1.69
1.00 0.80 1.75 0.15 cum. 0.21
1.00 5.10 1.75 0.15 cum. 1.34
1.00 2.32 1.75 0.15 cum. 0.61
1.00 3.30 1.75 0.15 cum. 0.87
1.00 11.10 1.75 0.15 cum. 2.91
1.00 1.45 1.75 0.15 cum. 0.38
1.00 3.95 1.75 0.15 cum. 1.04
1.00 7.50 1.75 0.15 cum. 1.97
1.00 1.80 1.75 0.15 cum. 0.47
RO Base 1.00 31.00 1.50 0.20 cum. 9.30
RE 1.00 33.80 1.50 0.20 cum. 10.14
RE 1.00 13.00 1.50 0.20 cum. 3.90
RE 1.00 4.30 1.00 0.20 cum. 0.86
RE 1.00 9.00 1.00 0.20 cum. 1.80
RC 3.00 3.50 5.30 0.20 cum. 11.13
RS1 1.00 20.00 0.75 0.20 cum. 3.00
RS2 1.00 19.50 0.75 0.20 cum. 2.93
RS3 1.00 19.50 0.75 0.20 cum. 2.93
RS4 1.00 23.90 0.75 0.20 cum. 3.58
RE 1.00 13.00 0.40 0.20 cum. 1.04
1.00 29.70 0.40 0.20 cum. 2.38
1.00 24.70 0.40 0.20 cum. 1.98
1.00 11.50 0.40 0.20 cum. 0.92
1.00 10.40 0.40 0.20 cum. 0.83
1.00 13.90 0.40 0.20 cum. 1.11
1.00 10.90 0.40 0.20 cum. 0.87
1.00 11.50 0.40 0.20 cum. 0.92
1.00 5.50 0.40 0.20 cum. 0.44
1.00 28.00 0.40 0.20 cum. 2.24
1.00 24.70 0.40 0.20 cum. 1.98
1.00 11.90 0.40 0.20 cum. 0.95
RCC 1.00 6.30 1.15 0.20 cum. 1.45
RCC 1.00 4.45 1.00 0.20 cum. 0.89
RCC 1.00 3.10 1.10 0.20 cum. 0.68
RCC 1.00 1.20 2.50 0.20 cum. 0.60
PCC At Aarati Side 1.00 5.40 4.80 0.20 cum. 5.18
1.00 4.55 1.95 0.20 cum. 1.77
1.00 2.10 3.47 0.20 cum. 1.46

Contractor Prepared By Checked By Approved By


Pages -296 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 7.20 3.03 0.20 cum. 4.36
1.00 9.45 3.93 0.20 cum. 7.42
1.00 2.00 3.22 0.20 cum. 1.29
1.00 1.70 1.50 0.20 cum. 0.51
1.00 1.20 9.00 0.20 cum. 2.16
1.00 6.00 0.07 0.20 cum. 0.08
1.00 14.50 0.70 0.20 cum. 2.03
1.00 0.70 5.40 0.20 cum. 0.76
1.00 1.12 4.40 0.20 cum. 0.98
1.00 1.65 3.80 0.20 cum. 1.25
1.00 1.05 3.90 0.20 cum. 0.82
1.00 1.70 2.18 0.20 cum. 0.74
1.00 2.63 4.83 0.20 cum. 2.53
1.00 0.90 9.70 0.20 cum. 1.75
1.00 1.00 9.55 0.20 cum. 1.91
1.00 14.42 9.55 0.20 cum. 27.54
1.00 2.30 9.55 0.20 cum. 4.39
1.00 1.24 9.55 0.20 cum. 2.37
1.00 1.23 9.55 0.20 cum. 2.35
1.00 10.11 9.55 0.20 cum. 19.31
1.00 11.12 9.55 0.20 cum. 21.24
soling 1.00 31 1.86 0.15 cum. 8.65
1.00 9.6 0.83 0.15 cum. 1.20
1.00 9.8 0.95 0.15 cum. 1.40
1.00 10.3 0.86 0.15 cum. 1.33
1.00 9.3 0.95 0.15 cum. 1.33
1.00 10.4 1.73 0.15 cum. 2.70
1.00 9.9 1.38 0.15 cum. 2.05
1.00 9.5 1.76 0.15 cum. 2.51
1.00 9.9 1.05 0.15 cum. 1.56
1.00 8.9 1.05 0.15 cum. 1.40
1.00 7.3 0.92 0.15 cum. 1.01
1.00 6.6 0.45 0.15 cum. 0.45
1.00 10 1.24 0.15 cum. 1.86
1.00 4.4 0.45 0.15 cum. 0.30
1.00 4.4 2.4 0.15 cum. 1.58
1.00 3.5 1.5 0.15 cum. 0.79
1.00 4 2.4 0.15 cum. 1.44
1.00 4.4 2.4 0.15 cum. 1.58
1.00 3.4 1.8 0.15 cum. 0.92
N. RS 8& RS 9 1.00 2.16 2.23 0.15 cum. 0.72
RS 9 RS 10 1.00 22.70 1.36 0.15 cum. 4.63
N .RS 8 WALL 1.00 4.25 0.40 0.15 cum. 0.26
N.RC 1.00 3.20 3.80 0.15 cum. 1.82
rs 1 ganesh mandir 1.00 5.00 0.45 0.15 cum. 0.34
RS 1 & RS 2 PIPAL S 1.00 3.70 2.50 0.15 cum. 1.39
RS 1 & RS 2 TREE 1.00 4.40 1.98 0.15 cum. 1.31
RS 1 & RS 2 TREE 1.00 5.30 2.35 0.15 cum. 1.87

Contractor Prepared By Checked By Approved By


Pages -297 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
last step 1.00 20.00 0.80 0.15 cum. 2.40
1.00 18.90 0.80 0.15 cum. 2.27
1.00 13.80 0.80 0.15 cum. 1.66
1.00 4.10 0.80 0.15 cum. 0.49
1.00 2.98 0.55 0.15 cum. 0.25
Ramp Soling 1.00 20.30 2.83 0.15 Cum 8.63
Ramp Excavation 1.00 20.30 2.83 0.15 cum 8.63
Steps near Water reserve 1.00 4.85 1.20 0.15 cum 0.87
1.00 2.65 1.05 0.15 cum 0.42
1.00 15.00 0.75 0.15 cum. 1.69
1.00 15.00 0.75 0.15 cum. 1.69
Total= Cum 308.73 308.73 3000.00 926182.86
127 Brick soling work
Providing and laying a single layer flat brick soling on
drainage works on lanscape for preparation of P.C.C.
in which joints should be packed by sand to the
required levels all complete as per drawings,
specifications and the instructions of the Engineer.
From kund to Mandap 1.00 16.50 1.25 sqm. 20.63
From tree to shiv mandir 1.00 30.30 1.50 sqm. 45.45
north of P3-A 1.00 4.32 1.25 sqm. 5.40
South of P3-A 1.00 4.00 1.25 sqm. 5.00
Towards baba ramdev temple 1.00 6.50 1.50 sqm. 9.75
towards bishwokarma temple 2.00 7.00 1.25 sqm. 17.50
Towards P4 1.00 6.20 1.25 sqm. 7.75
For P4 1.00 3.00 1.50 sqm. 4.50
For P4 1.00 4.50 1.50 sqm. 6.75
Near P2 1.00 3.50 1.25 sqm. 4.38
Infront of ram mandir (Dia-4.9m outer and 2.1m inner) 1.00 15.39 sqm. 15.39
Around Kund 1.00 33.34 sqm. 33.34
From kund to p1 1.00 1.50 2.00 sqm. 3.00
Near Mandap 1.00 2.50 1.50 sqm. 3.75
1.00 4.00 1.50 sqm. 6.00
1.00 1.00 1.50 sqm. 1.50
To Ramdev Baba temple 1.00 7.00 1.50 sqm. 10.50
Concrete Drainage 1.00 12.68 0.60 sqm. 7.61
1.00 10.90 0.60 sqm. 6.54
1.00 2.00 0.60 sqm. 1.20
1.00 1.65 0.60 sqm. 0.99
1.00 1.28 0.60 sqm. 0.77
1.00 4.40 0.60 sqm. 2.64
1.00 7.25 0.60 sqm. 4.35
1.00 7.40 0.60 sqm. 4.44
1.00 1.00 0.60 sqm. 0.60
1.00 6.90 0.60 sqm. 4.14
1.00 7.30 0.60 sqm. 4.38
1.00 3.50 0.60 sqm. 2.10
1.00 9.90 0.60 sqm. 5.94
1.00 9.50 0.60 sqm. 5.70
Contractor Prepared By Checked By Approved By
Pages -298 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 5.10 0.60 sqm. 3.06
1.00 6.00 0.60 sqm. 3.60
1.00 11.20 0.60 sqm. 6.72

Contractor Prepared By Checked By Approved By


Pages -299 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 1.50 0.60 sqm. 0.90
1.00 8.35 0.60 sqm. 5.01
1.00 3.10 0.60 sqm. 1.86
1.00 1.80 0.60 sqm. 1.08
1.00 7.50 0.60 sqm. 4.50
1.00 2.40 0.60 sqm. 1.44
1.00 3.60 0.60 sqm. 2.16
1.00 3.00 0.60 sqm. 1.80
1.00 1.30 0.60 sqm. 0.78
1.00 6.00 0.60 sqm. 3.60
1.00 22.00 0.60 sqm. 13.20
Shiv mandir east 1.00 13.00 0.60 sqm. 7.80
Shiv mandir north 1.00 9.20 0.60 sqm. 5.52
Catch Basin 3.00 1.00 1.00 sqm. 3.00
1.00 20.50 0.75 sqm. 15.38
1.00 4.00 0.75 sqm. 3.00
Parking 1.00 4.00 20.50 sqm. 82.00
PCC P2 1.00 6.10 6.90 sqm. 42.09
1.00 5.80 6.80 sqm. 39.44
Deduction (1.00) 4.40 0.55 sqm. (2.42)
Stone Pillar (10.00) 0.40 0.40 sqm. (1.60)
1.00 7.50 4.20 sqm. 31.50
1.00 7.30 4.20 sqm. 30.66
(1.00) 1.77 0.05 sqm. (0.09)
(1.00) 0.60 0.30 sqm. (0.18)
(1.00) 4.10 0.50 sqm. (2.05)
(1.00) 0.70 0.37 sqm. (0.26)
1.00 6.60 1.25 sqm. 8.25
Drain Exv 1.00 89.90 0.50 sqm. 44.95
Water Reserve 1.00 7.90 0.38 sqm. 2.96
1.00 0.50 0.65 sqm. 0.33
1.00 2.55 0.30 sqm. 0.76
Ramp Brick Wall 1.00 12.20 0.45 sqm. 5.49
Ramp Brick Wall 1.00 12.20 0.45 sqm. 5.49
For Main Gate -
Foundation 4.00 1.20 1.20 sqm. 5.76
For Beam 2.00 3.75 0.30 sqm. 2.25
2.00 1.80 0.30 sqm. 1.08
For Boundary Wall 1.00 1.70 0.50 sqm. 0.85
Power House 1.00 1.80 1.80 sqm. 3.24
Ramp Excavation 1.00 12.20 3.00 sqm. 36.60
P2 west 1.00 3.3 1.25 sqm. 4.13
Total= Sqm 677.61 677.61 700.00 474324.16

Contractor Prepared By Checked By Approved By


Pages -300 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
128 PCC Works

PCC (1:3:6) M10 for flooring on landscape and


drainage works in perfect line and level with proper
compaction and curing at least 15 days including
supply of materials all complete as per design,
drawing, specification and satisfaction to site engineer.

Bottom of Kunda 1.00 8.06 0.10 cum. 0.81


1st Step Wall 1.00 17.10 0.75 0.08 cum. 0.96
2nd Step 1.00 13.75 0.75 0.08 cum. 0.77
3rd Step 1.00 10.40 0.60 0.08 cum. 0.47
Tree Protection Wall 1.00 1.50 0.35 0.08 cum. 0.04
Tree Protection Wall 1.00 1.40 0.35 0.08 cum. 0.04
2nd Step 1.00 13.75 0.19 0.08 cum. 0.20
1.00 13.75 0.42 0.08 cum. 0.43
3rd Step 1.00 10.40 0.70 0.08 cum. 0.55
for RT Walls (From North To South) 1.00 3.70 0.90 0.08 cum. 0.25
1.00 2.00 0.90 0.08 cum. 0.14
1.00 6.75 0.90 0.08 cum. 0.46
1.00 4.00 0.90 0.08 cum. 0.27
1.00 3.80 0.90 0.08 cum. 0.26
1.00 8.80 0.90 0.08 cum. 0.59
1.00 4.75 0.90 0.08 cum. 0.32
1.00 1.10 0.90 0.08 cum. 0.07
1.00 11.30 0.90 0.08 cum. 0.76
2.00 1.00 0.90 0.08 cum. 0.14
1.00 4.45 0.90 0.08 cum. 0.30
1.00 3.40 0.90 0.08 cum. 0.23
1.00 4.75 0.90 0.08 cum. 0.32
for RS Walls (From North To South) -2nd step 1.00 3.80 0.85 0.08 cum. 0.24
1.00 5.50 0.85 0.08 cum. 0.35
1.00 5.20 0.85 0.08 cum. 0.33
1.00 5.90 0.85 0.08 cum. 0.38
1.00 3.00 0.60 0.08 cum. 0.13
1.00 1.50 0.60 0.08 cum. 0.07
1.00 1.30 0.60 0.08 cum. 0.06
1.00 2.50 0.60 0.08 cum. 0.11
1.00 1.20 0.60 0.08 cum. 0.05
1.00 2.10 0.60 0.08 cum. 0.09
1.00 5.30 0.60 0.08 cum. 0.24
1.00 4.60 0.60 0.08 cum. 0.21
for RS Walls (From North to South) -3rd step 1.00 2.30 0.60 0.08 cum. 0.10
1.00 1.65 0.60 0.08 cum. 0.07
1.00 2.10 0.60 0.08 cum. 0.09
1.00 1.30 0.60 0.08 cum. 0.06
1.00 3.00 0.60 0.08 cum. 0.13
1.00 13.50 0.60 0.08 cum. 0.61
for RS Walls (From North to South) -4th step 1.00 15.00 0.60 0.08 cum. 0.67
Outer wall 1.00 17.10 0.60 0.08 cum. 0.77

Contractor Prepared By Checked By Approved By


Pages -301 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
First step 1.00 10.40 0.60 0.08 cum. 0.47
center 1.00 8.04 0.60 0.08 cum. 0.36
From kund to Mandap 1.00 16.50 1.25 0.10 cum. 2.06
From tree to shiv mandir 1.00 30.30 1.50 0.10 cum. 4.55
north of P3-A 1.00 4.32 1.25 0.10 cum. 0.54
South of P3-A 1.00 4.00 1.25 0.10 cum. 0.50
Towards baba ramdev temple 1.00 6.50 1.50 0.10 cum. 0.98
towards bishwokarma temple 2.00 7.00 1.25 0.10 cum. 0.88
Towards P4 1.00 6.20 1.25 0.10 cum. 0.78
For P4 1.00 3.00 1.50 0.10 cum. 0.45
For P4 1.00 4.50 1.50 0.10 cum. 0.68
Near P2 1.00 3.50 1.25 0.10 cum. 0.44
Infront of ram mandir (Dia-4.9m outer and 2.1m inner) 1.00 15.49 0.10 cum. 1.55
Around Kund 1.00 34.35 0.10 cum. 3.44
From kund to p1 1.00 1.50 2.00 0.10 cum. 0.30
Near Mandap 1.00 2.50 1.50 0.10 cum. 0.38
1.00 4.00 1.50 0.10 cum. 0.60
1.00 1.00 1.50 0.10 cum. 0.15
To Ramdev Baba temple 1.00 7.00 1.50 0.10 cum. 1.05
Concrete Drainage 1.00 12.68 0.60 0.10 cum. 0.76
1.00 10.90 0.60 0.10 cum. 0.65
1.00 2.00 0.60 0.10 cum. 0.12
1.00 1.65 0.60 0.10 cum. 0.10
1.00 1.28 0.60 0.10 cum. 0.08
1.00 4.40 0.60 0.10 cum. 0.26
1.00 7.25 0.60 0.10 cum. 0.44
1.00 7.40 0.60 0.10 cum. 0.44
1.00 1.00 0.60 0.10 cum. 0.06
1.00 6.90 0.60 0.10 cum. 0.41
1.00 7.30 0.60 0.10 cum. 0.44
1.00 3.50 0.60 0.10 cum. 0.21
1.00 9.90 0.60 0.10 cum. 0.59
1.00 9.50 0.60 0.10 cum. 0.57
1.00 5.10 0.60 0.10 cum. 0.31
1.00 6.00 0.60 0.10 cum. 0.36
1.00 11.20 0.60 0.10 cum. 0.67
1.00 1.50 0.60 0.10 cum. 0.09
1.00 8.35 0.60 0.10 cum. 0.50
1.00 3.10 0.60 0.10 cum. 0.19
1.00 1.80 0.60 0.10 cum. 0.11
1.00 7.50 0.60 0.10 cum. 0.45
1.00 2.40 0.60 0.10 cum. 0.14
1.00 3.60 0.60 0.10 cum. 0.22
1.00 3.00 0.60 0.10 cum. 0.18
1.00 1.30 0.60 0.10 cum. 0.08
1.00 6.00 0.60 0.10 cum. 0.36
1.00 22.00 0.60 0.10 cum. 1.32
Shiv mandir east 1.00 13.00 0.60 0.10 cum. 0.78
Shiv mandir north 1.00 9.20 0.60 0.10 cum. 0.55
Contractor Prepared By Checked By Approved By
Pages -302 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Catch Basin 3.00 1.00 1.00 0.10 cum. 0.10
1.00 20.50 0.75 0.10 cum. 1.54
1.00 4.00 0.75 0.10 cum. 0.30
Parking 1.00 4.00 20.50 0.10 cum. 8.20
Concrete Drainage 2.00 12.68 0.10 0.35 cum. 0.44
2.00 10.90 0.10 0.35 cum. 0.38
2.00 2.00 0.10 0.35 cum. 0.07
2.00 1.65 0.10 0.35 cum. 0.06
2.00 1.28 0.10 0.35 cum. 0.04
2.00 4.40 0.10 0.35 cum. 0.15
2.00 7.25 0.10 0.35 cum. 0.25
2.00 7.40 0.10 0.35 cum. 0.26
2.00 1.00 0.10 0.35 cum. 0.03
2.00 6.90 0.10 0.35 cum. 0.24
2.00 7.30 0.10 0.35 cum. 0.26
2.00 3.50 0.10 0.35 cum. 0.12
2.00 9.90 0.10 0.35 cum. 0.35
2.00 9.50 0.10 0.35 cum. 0.33
2.00 5.10 0.10 0.35 cum. 0.18
2.00 6.00 0.10 0.35 cum. 0.21
2.00 11.20 0.10 0.35 cum. 0.39
2.00 1.50 0.10 0.35 cum. 0.05
2.00 8.35 0.10 0.35 cum. 0.29
2.00 3.10 0.10 0.35 cum. 0.11
2.00 1.80 0.10 0.35 cum. 0.06
2.00 7.50 0.10 0.35 cum. 0.26
2.00 2.40 0.10 0.35 cum. 0.08
2.00 3.60 0.10 0.35 cum. 0.13
2.00 3.00 0.10 0.35 cum. 0.11
2.00 1.30 0.10 0.35 cum. 0.05
2.00 6.00 0.10 0.50 cum. 0.30
2.00 22.00 0.10 0.50 cum. 1.10
Shiv mandir east 2.00 13.00 0.10 0.40 cum. 0.52
Shiv mandir north 2.00 9.20 0.10 0.40 cum. 0.37
1.00 4.40 0.50 0.08 cum. 0.17
1.00 20.00 0.50 0.08 cum. 0.75
1.00 37.00 0.45 0.08 cum. 1.25
Base PCC cum.
RO 1.00 31.00 1.50 0.10 cum. 4.65
RE 1.00 33.80 1.50 0.10 cum. 5.07
RE 1.00 13.00 1.50 0.10 cum. 1.95
RE 1.00 4.30 1.00 0.10 cum. 0.43
RE 1.00 9.00 1.00 0.10 cum. 0.90
RC 3.00 3.50 5.30 0.10 cum. 5.57
RS1 1.00 20.00 0.75 0.08 cum. 1.13
RS2 1.00 19.50 0.75 0.08 cum. 1.10
RS3 1.00 19.50 0.75 0.08 cum. 1.10
RS4 1.00 23.90 0.75 0.08 cum. 1.34
GL cum.

Contractor Prepared By Checked By Approved By


Pages -303 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RO 1.00 31.00 1.50 0.08 cum. 3.49
RE 1.00 33.80 1.50 0.08 cum. 3.80
RE 1.00 13.00 1.50 0.08 cum. 1.46
RE 1.00 4.30 1.00 0.075 cum. 0.32
RE 1.00 9.00 1.00 0.075 cum. 0.67
Top cum.
RO 1.00 31.00 0.60 0.10 cum. 1.86
RE 1.00 33.80 1.00 0.10 cum. 3.38
RE 1.00 13.00 1.00 0.10 cum. 1.30
RE 1.00 4.30 1.00 0.10 cum. 0.43
RE 1.00 9.00 1.00 0.10 cum. 0.90
RC 3.00 3.50 0.50 0.10 cum. 0.53
RS1 1.00 20.00 0.35 0.10 cum. 0.70

Contractor Prepared By Checked By Approved By


Pages -304 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RS2 1.00 19.50 0.35 0.10 cum. 0.68
RS3 1.00 19.50 0.35 0.10 cum. 0.68
RS4 1.00 23.90 0.35 0.10 cum. 0.84
RE 1.00 13.00 0.40 0.08 cum. 0.39
1.00 29.70 0.40 0.08 cum. 0.89
1.00 24.70 0.40 0.08 cum. 0.74
1.00 11.50 0.40 0.08 cum. 0.35
1.00 10.40 0.40 0.08 cum. 0.31
1.00 13.90 0.40 0.08 cum. 0.42
1.00 10.90 0.40 0.08 cum. 0.33
1.00 11.50 0.40 0.08 cum. 0.35
1.00 5.50 0.40 0.08 cum. 0.17
1.00 28.00 0.40 0.08 cum. 0.84
1.00 24.70 0.40 0.08 cum. 0.74
1.00 11.90 0.40 0.08 cum. 0.36
For Soling & PCC
PCC P2 1.00 6.10 6.90 0.08 cum. 3.16
1.00 5.80 6.80 0.08 cum. 2.96
Deduction (1.00) 4.40 0.55 0.08 cum. (0.18)
Stone Pillar (10.00) 0.40 0.40 0.08 cum. (0.12)
1.00 7.50 4.20 0.08 cum. 2.36
1.00 7.30 4.20 0.08 cum. 2.30
(1.00) 1.77 0.05 0.08 cum. (0.01)
(1.00) 0.60 0.30 0.08 cum. (0.01)
(1.00) 4.10 0.50 0.08 cum. (0.15)
(1.00) 0.70 0.37 0.08 cum. (0.02)
1.00 6.60 1.25 0.08 cum. 0.62
RCC 1.00 6.30 1.15 0.08 cum. 0.54
RCC 1.00 4.45 1.00 0.08 cum. 0.33
RCC 1.00 3.10 1.10 0.08 cum. 0.26
RCC 1.00 1.20 2.50 0.08 cum. 0.22
P3 1.00 11.30 4.95 0.08 cum. 4.20
1.00 11.05 5.20 0.08 cum. 4.31
PCC At Aarati Side 1.00 5.40 4.80 0.10 cum. 2.59
1.00 4.55 1.95 0.10 cum. 0.89
1.00 2.10 3.47 0.10 cum. 0.73
1.00 7.20 3.03 0.10 cum. 2.18
1.00 9.45 3.93 0.10 cum. 3.71
1.00 2.00 3.22 0.10 cum. 0.65
1.00 1.70 1.50 0.10 cum. 0.26
1.00 1.20 9.00 0.10 cum. 1.08
1.00 6.00 0.07 0.10 cum. 0.04
1.00 14.50 0.70 0.10 cum. 1.02
1.00 0.70 5.40 0.10 cum. 0.38
1.00 1.12 4.40 0.10 cum. 0.49
1.00 1.65 3.80 0.10 cum. 0.63
1.00 1.05 3.90 0.10 cum. 0.41
1.00 1.70 2.18 0.10 cum. 0.37
1.00 2.63 4.83 0.10 cum. 1.27
1.00 0.90 9.70 0.10 cum. 0.87
1.00 1.00 9.55 0.10 cum. 0.96
1.00 0.90 9.70 0.10 cum. 0.87
Contractor Prepared By Checked By Approved By
Pages -305 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 1.00 9.55 0.10 cum. 0.96
1.00 14.42 9.55 0.10 cum. 13.77
1.00 2.30 9.55 0.10 cum. 2.20
1.00 1.24 9.55 0.10 cum. 1.18
1.00 1.23 9.55 0.10 cum. 1.17
1.00 10.11 9.55 0.10 cum. 9.66
1.00 11.12 9.55 0.10 cum. 10.62
pcc 1.000 31.000 1.86 0.075 cum. 4.32
1.000 9.600 0.83 0.075 cum. 0.60
1.000 9.800 0.95 0.075 cum. 0.70
1.000 10.300 0.86 0.075 cum. 0.66
1.000 9.300 0.95 0.075 cum. 0.66
1.000 10.400 1.73 0.075 cum. 1.35
1.000 9.900 1.38 0.075 cum. 1.02
1.000 9.500 1.76 0.075 cum. 1.25
1.000 9.900 1.05 0.075 cum. 0.78
1.000 8.900 1.05 0.075 cum. 0.70
1.000 7.300 0.92 0.075 cum. 0.50
1.000 6.600 0.45 0.075 cum. 0.22
1.000 4.400 0.45 0.075 cum. 0.15
pcc for rcc 1.000 3.4 2.2 0.1 cum. 0.75
1.000 4.5 3.8 0.1 cum. 1.71
1.000 26.1 1.14 0.1 cum. 2.98
1.000 24.8 1.16 0.1 cum. 2.88
1.000 23.6 1.2 0.1 cum. 2.83
1.000 23 2.2 0.1 cum. 5.06
1.000 10 2.13 0.1 cum. 2.13
1.000 11.1 2.61 0.1 cum. 2.90
1.000 9.9 0.85 0.1 cum. 0.84
1.000 9.7 0.75 0.1 cum. 0.73
1.000 9.7 0.75 0.1 cum. 0.73
1.000 9.65 0.75 0.1 cum. 0.72
1.000 9.6 0.75 0.1 cum. 0.72
1.000 9.5 0.75 0.1 cum. 0.71
1.000 9.5 0.75 0.1 cum. 0.71
1.000 9.5 0.75 0.1 cum. 0.71

Contractor Prepared By Checked By Approved By


Pages -306 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.000 9.6 0.75 0.1 cum. 0.72
1.000 10 0.95 0.1 cum. 0.95
This Bill
N. RS 8& RS 9 1.00 2.16 2.23 0.075 cum. 0.36
RS 9 RS 10 1.00 22.70 1.36 0.075 cum. 2.32
N .RS 8 WALL 1.00 4.25 0.40 0.075 cum. 0.13
N.RC 1.00 3.20 3.80 0.075 cum. 0.91
rs 1 ganesh mandir 1.00 5.00 0.45 0.075 cum. 0.17
RS 1 & RS 2 PIPAL S 1.00 3.70 2.50 0.075 cum. 0.69
RS 1 & RS 2 TREE 1.00 4.40 1.98 0.075 cum. 0.65
RS 1 & RS 2 TREE 1.00 5.30 2.35 0.075 cum. 0.93
last step 1.00 20.00 0.80 0.075 cum. 1.20
1.00 18.90 0.80 0.075 cum. 1.13
1.00 13.80 0.80 0.075 cum. 0.83
1.00 4.10 0.80 0.075 cum. 0.25
1.00 2.98 0.55 0.075 cum. 0.12
Drain Base 1.00 89.90 0.50 0.1 cum. 4.50
Drain Wall 2.00 89.90 0.50 0.1 cum. 8.99
Water Reserve 1.00 7.90 0.38 0.075 cum. 0.22
1.00 0.50 0.65 0.075 cum. 0.02
1.00 2.55 0.30 0.075 cum. 0.06
Ramp Brick Wall 1.00 12.20 0.45 0.075 cum. 0.41
Ramp Brick Wall 1.00 12.20 0.45 0.075 cum. 0.41
For Main Gate -
Foundation 4.00 1.20 1.20 0.075 cum. 0.43
For Beam 2.00 3.75 0.30 0.075 cum. 0.17
2.00 1.80 0.30 0.075 cum. 0.08
For Boundary Wall Base 1.00 1.70 0.50 0.075 cum. 0.06
for Boundary Wall Band 1.00 1.70 0.50 0.1 Cum 0.09
Power House 1.00 1.80 1.80 0.075 cum. 0.24
Steps near Water reserve 1.00 4.85 1.20 0.15 cum 0.87
1.00 2.65 1.05 0.15 cum 0.42

p2 west 1.00 3.3 1.25 0.075 cum. 0.31


PCC For RCC
p1and p2 east 1.00 5.35 1.03 0.10 cum. 0.55
p1and p2 east 1.00 1.25 0.90 0.10 cum. 0.11
p1and p2 east 1.00 5.80 2.47 0.10 cum. 1.43
p1and p2 east 1.00 3.20 1.85 0.10 cum. 0.59
p1and p2 east 1.00 2.50 2.30 0.10 cum. 0.58
1.00 11.00 1.00 0.10 cum. 1.10
p2 east step 1.00 1.85 1.60 0.10 cum. 0.30
p2 east step 1.00 5.95 0.47 0.10 cum. 0.28
RC .S . STEP1 1.00 9.73 0.83 0.10 cum. 0.81
RC .S . STEP2 1.00 9.16 0.46 0.10 cum. 0.42
RC .S . STEP3 1.00 8.50 0.44 0.10 cum. 0.37

Contractor Prepared By Checked By Approved By


Pages -307 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RC .S . STEP4 1.00 8.70 0.40 0.10 cum. 0.35
RC .S . STEP5 1.00 8.60 0.44 0.10 cum. 0.38
RC .S . STEP6 1.00 8.50 0.44 0.10 cum. 0.37
RC .S . STEP7 1.00 8.32 0.43 0.10 cum. 0.36
RC .S . STEP8 1.00 8.06 0.42 0.10 cum. 0.34
RC .S . STEP9 1.00 7.42 0.43 0.10 cum. 0.32
RC .S . STEP10 1.00 6.36 0.72 0.10 cum. 0.46
RS 8 & RS9 1.00 15.90 2.36 0.10 cum. 3.75
TREE S STEP 1 1.00 4.60 0.73 0.10 cum. 0.34
TREE S STEP 2 1.00 5.90 0.60 0.10 cum. 0.35
TREE S STEP 3 1.00 6.80 0.43 0.10 cum. 0.29
STEP 4 1.00 17.00 0.75 0.10 cum. 1.28
RS 1 & RS 2 PIPAL S 1.00 3.70 2.60 0.10 cum. 0.96
RS 1 & RS 2 TREE 1.00 4.40 2.08 0.10 cum. 0.92
RS 1 & RS 2 TREE 1.00 5.30 2.45 0.10 cum. 1.30
RC M 1.00 3.50 4.70 0.10 cum. 1.64
RC N 1.00 3.50 4.60 0.10 cum. 1.61
N. RS 4& RS 5 1.00 16.90 2.49 0.10 cum. 4.21
-
RC M& RCN steps 1 1.00 9.70 0.83 0.10 cum. 0.81
RC M& RCN steps 2 1.00 9.70 0.45 0.10 cum. 0.44
RC M& RCN steps 3 1.00 9.70 0.45 0.10 cum. 0.44
RC M& RCN steps 4 1.00 9.80 0.45 0.10 cum. 0.44
RC M& RCN steps 5 1.00 9.80 0.45 0.10 cum. 0.44
RC M& RCN steps 6 1.00 9.90 0.45 0.10 cum. 0.45
RC M& RCN steps 7 1.00 10.00 0.45 0.10 cum. 0.45
RC M& RCN steps 8 1.00 10.15 0.45 0.10 cum. 0.46
RC M& RCN steps 9 1.00 10.40 0.43 0.10 cum. 0.45
RC M& RCN steps 10 1.00 11.00 0.92 0.10 cum. 1.01
RS 8 & RS9 N. 1.00 15.90 1.98 0.10 cum. 3.15
RS 9 & RS10 1ST STEPS 1.00 12.50 0.58 0.10 cum. 0.73
RS 9 & RS10 2ST STEPS 1.00 10.67 0.89 0.10 cum. 0.95
last step 1.00 20.00 0.80 0.10 cum. 1.60
1.00 18.90 0.80 0.10 cum. 1.51
1.00 13.80 0.80 0.10 cum. 1.10
1.00 4.10 0.80 0.10 cum. 0.33
1.00 2.98 0.55 0.10 cum. 0.16
Steps near Water reserve 1.00 4.85 1.20 0.10 cum 0.58
1.00 2.65 1.05 0.10 cum 0.28
1.00 2.20 2.10 0.10 cum 0.46
1.00 15.00 0.75 0.25 cum. 2.81
Total= cum. 307.56 307.56 10,000.00 3075557.12
129 RCC Works

Contractor Prepared By Checked By Approved By


Pages -308 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Concrete Works for RCC (1:1.5:3) M20 on landscape


and drainage works in perfect line and level with
proper compaction and curing for at least 15 days
including supply of materials all complete as per
design, drawing, specification and satisfaction to site
engineer. 25.72 25.72 16000.00 411532.00
At Ramp 1.00 32.50 2.83 0.15 cum. 13.81
Gate Footing 4.00 1.20 1.20 0.3 cum 1.73
Beam 2.00 4.60 0.25 0.25 cum 0.58
2.00 2.70 0.25 0.25 cum 0.34
Pillar 4.00 0.30 0.30 4.4 cum 1.58
Slab Near Shiva Mandir 1.00 3.40 0.75 0.075 cum 0.19
Gate Top Bem 2.00 4.60 0.25 0.25 cum 0.58
2.00 2.70 0.25 0.25 cum 0.34
Gate Slab 1.00 5.20 3.20 0.125 cum 2.08
Ganesh mandir infront drain cover 1.00 45.00 1.00 0.1 cum 4.50
Fe500 Reinforcement in PCC including cutting,
131 bending and placing in position all complete as per 981000.00
design, drawing, specification and satisfaction to site
engineer. tonne 8.18 8.18 120000.00
130 Centering and Shuttering Work

Centering and shuttering with approved 19mm


waterproofing plywood for drain works at any level with
necessary mild steel propping, scaffolding, staging
supporting. Cutting holes for utilization works and
removal of formwork and lead upto 30 m etc all
complete as per instruction, specification and drawing.
Concrete Drainage 4.00 12.68 0.35 sqm. 17.75
4.00 10.90 0.35 sqm. 15.26
4.00 2.00 0.35 sqm. 2.80
4.00 1.65 0.35 sqm. 2.31
4.00 1.28 0.35 sqm. 1.79
4.00 4.40 0.35 sqm. 6.16
4.00 7.25 0.35 sqm. 10.15
4.00 7.40 0.35 sqm. 10.36
4.00 1.00 0.35 sqm. 1.40
4.00 6.90 0.35 sqm. 9.66
4.00 7.30 0.35 sqm. 10.22
4.00 3.50 0.35 sqm. 4.90
4.00 9.90 0.35 sqm. 13.86
4.00 9.50 0.35 sqm. 13.30
4.00 5.10 0.35 sqm. 7.14
4.00 6.00 0.35 sqm. 8.40
4.00 11.20 0.35 sqm. 15.68
4.00 1.50 0.35 sqm. 2.10
4.00 8.35 0.35 sqm. 11.69
4.00 3.10 0.35 sqm. 4.34
4.00 1.80 0.35 sqm. 2.52
4.00 7.50 0.35 sqm. 10.50
4.00 2.40 0.35 sqm. 3.36
Contractor Prepared By Checked By Approved By
Pages -309 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
4.00 3.60 0.35 sqm. 5.04
4.00 3.00 0.35 sqm. 4.20
4.00 1.30 0.35 sqm. 1.82
4.00 6.00 0.50 sqm. 12.00
4.00 22.00 0.50 sqm. 44.00
Shiv mandir east 4.00 13.00 0.40 sqm. 20.80
Shiv mandir north 4.00 9.20 0.40 sqm. 14.72
Base PCC Sides
RO 1.00 31.00 2.00 0.10 sqm. 6.20
RE 1.00 33.80 2.00 0.10 sqm. 6.76
RE 1.00 13.00 2.00 0.10 sqm. 2.60
RE 1.00 4.30 2.00 0.10 sqm. 0.86
RE 1.00 9.00 2.00 0.10 sqm. 1.80
RC 3.00 3.50 2.00 0.10 sqm. 2.10
RS1 1.00 20.00 2.00 0.075 sqm. 3.00
RS2 1.00 19.50 2.00 0.075 sqm. 2.93
RS3 1.00 19.50 2.00 0.075 sqm. 2.93
RS4 1.00 23.90 2.00 0.075 sqm. 3.58
GL
RO 1.00 31.00 2.00 0.075 sqm. 4.65
RE 1.00 33.80 2.00 0.075 sqm. 5.07
RE 1.00 13.00 2.00 0.075 sqm. 1.95
RE 1.00 4.30 2.00 0.075 sqm. 0.64
RE 1.00 9.00 2.00 0.075 sqm. 1.35
Top
RO 1.00 31.00 2.00 0.10 sqm. 6.20
RE 1.00 33.80 2.00 0.10 sqm. 6.76
RE 1.00 13.00 2.00 0.10 sqm. 2.60
RE 1.00 4.30 2.00 0.10 sqm. 0.86
RE 1.00 9.00 2.00 0.10 sqm. 1.80
RC 3.00 3.50 2.00 0.10 sqm. 2.10
RS1 1.00 20.00 2.00 0.10 sqm. 4.00
RS2 1.00 19.50 2.00 0.10 sqm. 3.90
RS3 1.00 19.50 2.00 0.10 sqm. 3.90
RS4 1.00 23.90 2.00 0.10 sqm. 4.78
This Bill Sides
Drain Wall 2.00 89.90 2.00 0.5 sqm. 179.80
p1and p2 east 1.00 5.35 1.00 0.15 sqm. 0.80
p1and p2 east 1.00 1.25 1.00 0.15 sqm. 0.19
p1and p2 east 1.00 5.8 1.00 0.15 sqm. 0.87
p1and p2 east 1.00 3.2 1.00 0.15 sqm. 0.48
p1and p2 east 1.00 2.5 1.00 0.15 sqm. 0.38
11
p2 east step 1.00 1.85 1.00 0.15 sqm. 0.28
p2 east step 1.00 5.95 1.00 0.15 sqm. 0.89
RC .S . STEP1 1.00 9.73 1.00 0.15 sqm. 1.46
RC .S . STEP2 1.00 9.16 1.00 0.15 sqm. 1.37
RC .S . STEP3 1.00 8.5 1.00 0.15 sqm. 1.28
RC .S . STEP4 1.00 8.7 1.00 0.15 sqm. 1.31
RC .S . STEP5 1.00 8.6 1.00 0.15 sqm. 1.29
Contractor Prepared By Checked By Approved By
Pages -310 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RC .S . STEP6 1.00 8.5 1.00 0.15 sqm. 1.28
RC .S . STEP7 1.00 8.32 1.00 0.15 sqm. 1.25
RC .S . STEP8 1.00 8.06 1.00 0.15 sqm. 1.21
RC .S . STEP9 1.00 7.42 1.00 0.15 sqm. 1.11
RC .S . STEP10 1.00 6.36 1.00 0.15 sqm. 0.95
RS 8 & RS9 1.00 15.9 1.00 0.15 sqm. 2.39
TREE S STEP 1 1.00 4.6 1.00 0.15 sqm. 0.69
TREE S STEP 2 1.00 5.9 1.00 0.15 sqm. 0.89
TREE S STEP 3 1.00 6.8 1.00 0.15 sqm. 1.02
STEP 4 1.00 17 1.00 0.15 sqm. 2.55
RS 1 & RS 2 PIPAL S 1.00 3.7 1.00 0.15 sqm. 0.56
RS 1 & RS 2 TREE 1.00 4.4 1.00 0.15 sqm. 0.66
RS 1 & RS 2 TREE 1.00 5.3 1.00 0.15 sqm. 0.79
RC M 1.00 3.5 1.00 0.15 sqm. 0.53
RC N 1.00 3.5 1.00 0.15 sqm. 0.53
N. RS 4& RS 5 1.00 16.9 1.00 0.15 sqm. 2.53
-
RC M& RCN steps 1 1.00 9.7 1.00 0.15 sqm. 1.45
RC M& RCN steps 2 1.00 9.7 1.00 0.15 sqm. 1.45
RC M& RCN steps 3 1.00 9.7 1.00 0.15 sqm. 1.45
RC M& RCN steps 4 1.00 9.8 1.00 0.15 sqm. 1.47
RC M& RCN steps 5 1.00 9.8 1.00 0.15 sqm. 1.47
RC M& RCN steps 6 1.00 9.9 1.00 0.15 sqm. 1.49
RC M& RCN steps 7 1.00 10 1.00 0.15 sqm. 1.50
RC M& RCN steps 8 1.00 10.15 1.00 0.15 sqm. 1.52
RC M& RCN steps 9 1.00 10.4 1.00 0.15 sqm. 1.56
RC M& RCN steps 10 1.00 11 1.00 0.15 sqm. 1.65
RS 8 & RS9 N. 1.00 15.9 1.00 0.15 sqm. 2.39
RS 9 & RS10 1ST STEPS 1.00 12.5 1.00 0.15 sqm. 1.88
RS 9 & RS10 2ST STEPS 1.00 10.67 1.00 0.15 sqm. 1.60
At Ramp 2.00 32.50 1.00 0.15 sqm. 9.75
Gate Footing 4.00 1.20 4.00 0.3 sqm. 5.76
Beam 2.00 4.60 2.00 0.25 sqm. 4.60
2.00 2.70 2.00 0.25 sqm. 2.70
Pillar 4.00 0.30 4.00 0.9 sqm. 4.32
For Boundary Wall Base 1.00 1.70 2.00 0.075 sqm. 0.26
for Boundary Wall Band 1.00 1.70 2.00 0.1 sqm. 0.34
For Gate Formwork sqm. 85.00
Total= Sqm 714.47 714.47 600.00 428684.70
STONE MASONRY WORKS IN CEMENT MORTAR
Providing and laying Random Rubble stone masonry
works on retaining walls in cement mortar (1:4)
including providing through/bond stone at required
132
interval including providing required scaffolding,
preparing mortar and construction of wall to any height
and shape all complete as per drawings, specifications
and instruction of the engineer.
for RT Walls (From North To South) 1.00 3.70 0.68 2.00 cum 5.00
Contractor Prepared By Checked By Approved By
Pages -311 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 2.00 0.68 2.00 cum 2.70
1.00 6.85 0.68 2.00 cum 9.25
1.00 4.00 0.68 2.00 cum 5.40
1.00 3.90 0.68 2.00 cum 5.27
1.00 8.80 0.68 2.00 cum 11.88
1.00 4.75 0.68 2.00 cum 6.41
1.00 1.10 0.68 2.00 cum 1.49
1.00 11.30 0.68 2.00 cum 15.26
2.00 1.00 0.68 2.00 cum 2.70
1.00 4.45 0.68 2.00 cum 6.01
1.00 3.40 0.68 2.00 cum 4.59
1.00 4.75 0.68 2.00 cum 6.41
for RS Walls (From North To South) -2nd step 1.00 3.80 0.60 1.15 cum 2.62
1.00 5.50 0.60 1.15 cum 3.79
1.00 5.20 0.60 1.15 cum 3.59
1.00 5.90 0.60 1.15 cum 4.07
1.00 3.00 0.43 1.00 cum 1.28
1.00 1.50 0.43 1.00 cum 0.64
1.00 1.30 0.43 1.00 cum 0.55
1.00 2.50 0.43 1.00 cum 1.06
1.00 1.20 0.43 1.00 cum 0.51
1.00 2.10 0.43 1.00 cum 0.89
1.00 5.40 0.43 1.00 cum 2.30
1.00 4.60 0.43 1.00 cum 1.95
for RS Walls (From North to South) -3rd step 1.00 2.30 0.43 1.00 cum 0.98
1.00 1.65 0.43 1.00 cum 0.70
1.00 2.10 0.43 1.00 cum 0.89
1.00 1.30 0.43 1.00 cum 0.55
1.00 3.00 0.43 1.00 cum 1.28
1.00 13.50 0.43 1.00 cum 5.74
for RS Walls (From North to South) -4th step 1.00 15.10 0.43 1.00 cum 6.42
1st Step Wall 1.00 17.10 0.43 0.80 cum 5.81
2nd Step 1.00 13.75 0.50 0.30 cum 2.06
3rd Step 1.00 10.40 0.60 0.30 cum 1.87
Tree Protection Wall 2.00 1.50 0.35 0.80 cum 0.84
Tree Protection Wall 1.00 1.40 0.35 0.80 cum 0.39
for RT Walls (From North To South) 1.00 2.90 0.60 1.00 cum 1.74
1.00 9.40 0.60 1.20 cum 6.77
1.00 6.80 0.60 1.10 cum 4.49
1.00 6.90 0.60 1.10 cum 4.55
1.00 8.40 0.60 1.10 cum 5.54
1.00 5.20 0.60 1.10 cum 3.43
1.00 7.10 0.60 1.10 cum 4.69
1.00 8.80 0.60 1.10 cum 5.81
1.00 6.50 0.68 1.90 cum 8.40
1.00 2.20 0.68 1.90 cum 2.84
1.00 28.50 0.68 1.90 cum 36.82
1.00 8.50 0.98 3.77 cum 31.40
1.00 9.50 0.98 3.77 cum 35.10
1.00 6.50 0.98 3.00 cum 19.11
1.00 4.45 0.98 3.00 cum 13.08
1.00 6.43 0.98 3.00 cum 18.90
Contractor Prepared By Checked By Approved By
Pages -312 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 0.80 0.98 3.00 cum 2.35
1.00 5.10 0.98 3.00 cum 14.99
1.00 2.32 0.98 3.00 cum 6.82
1.00 3.30 0.98 3.00 cum 9.70
1.00 11.10 0.98 3.00 cum 32.63
1.00 1.45 0.98 3.00 cum 4.26
1.00 3.95 0.98 3.00 cum 11.61
for RS Walls (From North to South) -3rd step 1.00 7.50 0.98 3.00 cum 22.05
1.00 1.80 0.98 3.00 cum 5.29
Base cum
RO 1.00 31.00 1.50 1.20 cum 55.80
RE 1.00 33.80 1.50 1.20 cum 60.84
RE 1.00 13.00 1.50 1.20 cum 23.40
RE 1.00 4.30 1.00 0.90 cum 3.87
Above PCC cum
RO 1.00 31.00 1.05 2.30 cum 74.87
RE 1.00 33.80 1.25 1.10 cum 46.48
RE 1.00 13.00 1.25 1.10 cum 17.88
RE 1.00 4.30 0.75 1.10 cum 3.55
RE 1.00 9.00 0.75 2.00 cum 13.50
cum -
RC1 1.00 10.70 1.08 3.00 cum 34.51
RC2 1.00 11.20 1.08 3.00 cum 36.12
RC3 1.00 10.20 1.08 3.00 cum 32.89
RS1 1.00 20.00 0.40 0.750 cum 6.00
RS2 1.00 19.50 0.40 0.750 cum 5.85
RS3 1.00 19.50 0.40 0.750 cum 5.85
RS4 1.00 23.90 0.40 0.750 cum 7.17
RE 1.00 13.00 0.40 1.00 cum 5.20
1.00 29.70 0.40 0.75 cum 8.91
1.00 24.70 0.40 0.75 cum 7.41
1.00 11.50 0.40 0.75 cum 3.45
1.00 10.40 0.40 0.75 cum 3.12
1.00 13.90 0.40 0.75 cum 4.17
1.00 10.90 0.40 0.75 cum 3.27
1.00 11.50 0.40 0.75 cum 3.45
1.00 5.50 0.40 0.75 cum 1.65
1.00 28.00 0.40 0.75 cum 8.40
1.00 24.70 0.40 0.75 cum 7.41
1.00 11.90 0.40 0.75 cum 3.57
Stone Masonry work 1.00 31.00 1.86 0.30 cum 17.30
1.00 10.40 1.73 0.30 cum 5.40
1.00 9.90 1.38 0.30 cum 4.10
1.00 9.50 1.76 0.30 cum 5.02
1.00 9.90 1.05 0.30 cum 3.12
1.00 8.90 1.05 0.30 cum 2.80
1.00 7.30 0.92 0.30 cum 2.01
1.00 6.60 0.45 0.75 cum 2.23
1.00 9.80 1.15 0.30 cum 3.38
1.00 10.30 1.03 0.30 cum 3.18
1.00 9.30 1.10 0.30 cum 3.07
1.00 15.00 1.25 2.75 cum. 51.56
Contractor Prepared By Checked By Approved By
Pages -313 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Total= Cum 1037.29 1037.29 7000.00 7261017.05

Contractor Prepared By Checked By Approved By


Pages -314 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Brick Masonry Works in Superstructure ( 1 : 4


c/s )
Providing and laying first class chimney fired brick of
one or more brick thick wall in cement mortar 1:4 (1
133 cement : 4coarse sand) in landscape works in all
heights and level including the cost of single or multi
stage scaffolding, soaking bricks, curing, raking joints,
provision for recesses, openings, toothing etc., all
complete as per drawing, specifications and
instructions of the Engineer..
1.00 20.50 0.50 0.90 cum. 9.23
2.00 4.00 0.50 0.90 cum. 1.80
west 1.00 1.40 0.25 1.20 cum. 0.42
west 1.00 1.00 0.25 0.90 cum. 0.23
west 1.00 1.00 0.25 0.90 cum. 0.23
South 1.00 8.00 0.25 0.90 cum. 1.80
South 1.00 9.00 0.25 0.90 cum. 2.03
1.00 5.00 0.25 0.70 cum. 0.88
1.00 5.10 0.25 0.70 cum. 0.89
1.00 2.00 0.25 0.70 cum. 0.35
This Bill
Boundary Wall 1.00 1.70 0.50 0.90 Cum 0.77
1.00 1.70 0.25 1.20 Cum 0.51
At Ramp Support Wall 1.00 12.20 0.38 1.00 Cum 4.57
1.00 12.20 0.38 0.30 Cum 1.37
Water Reserve area 1.00 7.90 0.25 1.35 Cum 2.67
1.00 4.00 0.25 0.45 Cum 0.45
At Step 1.00 2.80 0.30 0.20 Cum 0.17
Infront of Ganesh Mandir Drain 2.00 45.00 0.25 1.00 Cum 11.25
Total= cum. 39.59 39.59 15000.00 593913.75
PIPEWORKS FOR WEEPHOLE AND GEOTEXTILE
134
WORKS FOR RETAINING WALLS
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work including
transportation,cutting,connecting and placing in
position, treated with two coat of anticorrosive paints,
all complete as per drawings,specifications and
instruction.(80mmdi GI medium duty)
From Previous Bill 1.00 120.00 rm 120.00
1.00 105.00 rm 105.00

1.00 19.32 rm 19.32

Total= Rm 244.32 244.32 700.00 171024.00


135 GEO TEXTILE FOR RETAINING WALLS
Providing and placing of Geo Textile on retaining wall
and french drain as per the instruction of engineer
From Previous Bill
1.0 120.00 1.50 sqm 180.00
river bank 1.0 72.40 3.00 sqm 217.20
upper retaining wall 1.0 105.00 1.50 sqm 157.50
-
Contractor Prepared By Checked By Approved By
Pages -315 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.0 197.10 3.00 sqm 591.30

Contractor Prepared By Checked By Approved By


Pages -316 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.0 195.00 2.00 Sqm 390.00
Total= Sqm 1,536.00 1536.00 80.00 122880.00
136 Plastering and Painting Works
Providing and laying 12.5mm thick plaster upto
required line and perfect smooth level as per site
condition in 1:4 cement sand mortar on internal walls
including necessary scaffolding , cleaning & wetting
the surface, packing of joints and proper curing for 15
days as per drawing, specification and instruction all
complete.
Road Side Wall Parking
2.00 5.20 0.80 8.32
2.00 5.10 0.80 8.16
1.00 7.90 1.50 11.85
1.00 7.90 1.10 8.69
1.00 9.90 1.20 11.88
1.00 9.00 1.10 9.90
1.00 1.15 1.45 1.67
1.00 1.80 1.80 3.24
1.00 1.15 1.55 1.78
1.00 1.80 1.90 3.42
1.00 1.20 1.55 1.86
Upper Side Walls 1.00 111.40 0.66 73.65
At Brick Wall 2.00 45.00 1.00 90.00
Circular pond 1.00 10.90 0.10 1.09
circular reserve 1.00 4.92 0.60 2.95
water container 1.00 1.95 1.95
water container 1.00 7.30 0.50 3.65
riser of steps 2.00 150.00 300.00
riser of steps 2.00 150.00 0.20 60.00
catch basin 11.00 2.40 0.90 23.76
sqm. - 627.82 627.82 600.00 376690.42

Flushing pointing on the exterior Brick wall of gate


structure by cement sand mortar of ratio 1:2 all
complete as per drawings, specificatios and
137 instruction. The rates shall include for scraping, 66284.00
washing the surface with water, surface preparation,
scaffolding,etc.,all complete as per the manufacturer's
recommendations and as approved by the Engineer.
sqm. - 165.71 400.00
River Side Wall R0 1.00 31.00 2.75 85.25
RE 1.00 33.80 1.50 50.70
RC 3.00 9.60 1.03 29.76

Contractor Prepared By Checked By Approved By


Pages -317 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Providing and applying two or more coats of exterior


plastic emulsion paint of approved manufacturer and
shade over a coat of alkali resistant cement primer of
approved manufacturer as per manufacturer's
specifications on exterior plaster all complete as per
138 238058.21
drawings, specifications and instruction. The rates
shall include for scraping, washing the surface with
water, surface preparation, scaffolding etc., all
complete as per the manufacturer's recommendations
and as approved by the Engineer.
sqm. - 793.53 300.00

Contractor Prepared By Checked By Approved By


Pages -318 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Providing and laying 20mm. thick Cement Water Bead
(Pani Patti) finished perfectly smooth including
139 0.00
necessary scaffolding, raking the joint, wetting the
surface and curing all complete work sqm. - 0.00 400.00

140 Flooring Work

Providing and laying minimum of 25mm and in


average of 40 mm thick Screed of 1:3:3 (Cement Sand
Chip) on thoroughly chipped floor (to remove laitance, 80000.00
caked mortar, loose sand, dirt etc.) all complete as per
design, drawing, specification and instruction of
consultant and his authorized representative. sqm. 100.00 100.00 100.00 800.00
3mm cement punning in 1:1 c/s mortar in perfect line
and level including trowelling and finishing in smooth
141 surface on risers of steps on landscape works as per 271259.84
design, drawing, specification and instruction of site
engineer. sqm. - 678.15 678.15 400.00
Circular pond 1.00 10.90 0.10 1.09
circular reserve 1.00 4.92 0.60 2.95
water container 1.00 1.95 1.95
water container 1.00 7.30 0.50 3.65
concrete drain 1.00 257.00 0.75 192.75
catch basin 11.00 2.40 0.90 23.76
riser of steps 1.00 321.00 321.00
riser of steps 1.00 655.00 0.20 131.00
Providing and laying of flagstone of approved
thickness and color on landscape works in perfect line
142 and level including joint sealing of joint, grinding, 1764166.46
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 1,260.12 1260.12 1400.00
RC S 1.00 3.4 1.8 6.12
RC S 1.00 4.5 3.4 15.30
STEP 1 1.00 26.1 0.74 19.31
STEP 2 1.00 24.8 0.76 18.85
STEP 3 1.00 23.6 0.8 18.88
STEP 4 1.00 23 1.8 41.40
M RS 4 &B RS 5 1.00 10 1.73 17.30
S RS 4 & RS 5 1.00 11.1 2.21 24.53
RC .M STEP 1 1.00 9.9 0.45 4.46
RC .M STEP 2 1.00 9.7 0.35 3.39
RC .M STEP 3 1.00 9.7 0.35 3.39
RC .M STEP 4 1.00 9.65 0.35 3.38
RC .M STEP 5 1.00 9.6 0.35 3.36
RC .M STEP 6 1.00 9.5 0.35 3.32
RC .M STEP 7 1.00 9.5 0.35 3.32
RC .M STEP 8 1.00 9.5 0.35 3.32
RC .M STEP 9 1.00 9.6 0.35 3.36
RC .M STEP 10 1.00 10 0.55 5.50

Contractor Prepared By Checked By Approved By


Pages -319 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
RC .S . STEP1 1.00 9.73 0.73 7.10
RC .S . STEP2 1.00 9.16 0.36 3.30
RC .S . STEP3 1.00 8.5 0.34 2.89
RC .S . STEP4 1.00 8.7 0.3 2.61
RC .S . STEP5 1.00 8.6 0.34 2.92
RC .S . STEP6 1.00 8.5 0.34 2.89
RC .S . STEP7 1.00 8.32 0.33 2.75
RC .S . STEP8 1.00 8.06 0.32 2.58
RC .S . STEP9 1.00 7.42 0.33 2.45
RC .S . STEP10 1.00 6.36 0.62 3.94
RS 8 & RS9 1.00 15.9 2.26 35.93
TREE S STEP 1 1.00 4.6 0.63 2.90
TREE S STEP 2 1.00 5.9 0.5 2.95
TREE S STEP 3 1.00 6.8 0.33 2.24
STEP 4 1.00 17 0.65 11.05
RS 1 & RS 2 PIPAL S 1.00 3.7 2.5 9.25
RS 1 & RS 2 TREE 1.00 4.4 1.98 8.71
RS 1 & RS 2 TREE 1.00 5.3 2.35 12.46
RC M 1.00 3.5 4.6 16.10
RC N 1.00 3.5 4.5 15.75
N. RS 4& RS 5 1.00 16.9 2.39 40.39
RC M& RCN steps 1 1.00 9.7 0.73 7.08
RC M& RCN steps 2 1.00 9.7 0.35 3.39
RC M& RCN steps 3 1.00 9.7 0.35 3.39
RC M& RCN steps 4 1.00 9.8 0.35 3.43
RC M& RCN steps 5 1.00 9.8 0.35 3.43
RC M& RCN steps 6 1.00 9.9 0.35 3.47
RC M& RCN steps 7 1.00 10 0.35 3.50
RC M& RCN steps 8 1.00 10.15 0.35 3.55
RC M& RCN steps 9 1.00 10.4 0.33 3.43
RC M& RCN steps 10 1.00 11 0.82 9.02
RS 8 & RS9 N. 1.00 15.9 1.88 29.89
RS 9 & RS10 1ST STEPS 1.00 12.5 0.48 6.00
RS 9 & RS10 2ST STEPS 1.00 10.67 0.79 8.43
p1and p2 east 1.00 5.35 0.93 4.98
p1and p2 east 1.00 1.25 0.8 1.00
p1and p2 east 1.00 5.8 2.37 13.75
p1and p2 east 1.00 3.2 1.75 5.60
p1and p2 east 1.00 2.5 2.2 5.50
p2 west 1.00 9 1.5 13.50
1.00 33 4 132.00
p2 east step 1.00 20 3 60.00
p2 east step 1.00 13 4 52.00
last step 1.00 9 4 36.00
last step 1.00 9 4 36.00
1.00 10 4 40.00

Contractor Prepared By Checked By Approved By


Pages -320 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
1.00 16 6 96.00
1.00 12 1.3 15.60
1.00 20 1.3 26.00
1.00 13 1.3 16.90
1.00 11 1.3 14.30
1.00 19 4 76.00
1.00 36 1.3 46.80
1.00 34 1.25 42.50
1.00 3 5 15.00
RE 33.00
Providing and laying of 25 mm thick Telia brick paving
work in (1:2) surki mortar and pointing the joints with
143 1:1 C/S mortar including curing on landscape works in 174012.00
perfect line and level all complete as per design,
drawing, specification and the instrution of the site
engineer. sqm. - 51.18 51.18 3400.00
At Landscaping 1.00 2.3 4 9.20
1.00 2.5 2 5.00
1.00 2 1 2.00
1.00 7 1.5 10.50
1.00 2 2 4.00
1.00 3.2 3.2 10.24
1.00 3.2 3.2 10.24

Providing and laying stone slab of approved quality


and color over PCC on pavements including cement
mortar of 1:3(cement sand) in perfect line, level
144 finished with necessary pointing in joints sloped 93520.00
towards drain line all complete as per design,
drawing, specification and the instrution of consultant
and his authorized representative. Samples should be
approves by consultant. sqm. 13.36 13.36 13.36 7000.00

Providing and laying of brick pavement of approved


thickness and color on landscape works in perfect line
145 and level including joint sealing of joint, grinding, 0.00
polishing all complete as per design, drawing,
specification and the instrution of the site engineer. sqm. - 0.00 700.00

Contractor Prepared By Checked By Approved By


Pages -321 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Cement skirting works:-Providing and laying cement
punning skirting on rammed earth walls inside rooms
146 in perfect line and level with grouting all complete as 0.00
per design, drawing , specification and instruction of
consultant and his authorized representative sqm. - 0.00 600.00
Waterproofing works:- Providing and applying water
proof coating work necessary on cement punning area
147 after preparing the surface all complete work as per 0.00
design, drawing , specification and instruction of
consultant and his authorized representative sqm. - 0.00 500.00

Providing and laying subsurface drain with perforated


pipe of 100mm internal diameter of PVC, closely joined
148 perforations ranging from 3mm to 6mm depending
upon size of material surrounding the pipe with 150mm
bedding below the pipe and 300mm cushion above
pipe, as per drawing and specification.
1 120.00 rm 120.00
Total= rm 120.00 120.00 800.00 96000.00

149 PEBBLES FOR COVERED DRAIN AND TAP


Providing and laying pebbles for drain cover and stone
tap on landscape works as per design, drawing, 0.00
specification and instruction of site engineer. 0.0 m2 0.0 0.0 0.00 10000.00

150 STEEL GRATING FOR DRAINS


Providing and laying light duty iron channel grates on
drains in perfect line and level including finishing in
smooth surface on landscape as per design, drawing,
specification and instruction of site engineer. kg
concrete drain grate 1.000 257.00 0.36 5 kgs 462.6
Total= kgs 462.6 0.00 250.00 0.00
Supplying and fitting of railing with 50mm vertical MS
circular pipe of 500mm height at 2m interval and
151 50mm black pipe handrail including welding, joints, 189800.00
and prmer painting asper drawing and instructions all
complete. 1.0 m2 29.20 29.20 29.20 6500.00

Contractor Prepared By Checked By Approved By


Pages -322 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
GAMALA POTS ON LANDSCAPE
Providing, molding and placing gamala pots on
landscape as per design, drawing, specification and
instruction of site engineer.
152 gamala 1 8.00 nos 8.00 8.00 1000.00 8000.00
153 gamala 2 5.00 nos 5.00 5.00 1000.00 5000.00
154 gamala 3 2.00 nos 2.00 2.00 1000.00 2000.00
155 gamala 4 1.00 nos 1.00 1.00 1000.00 1000.00
156 gamala 5 3.00 nos 3.00 3.00 1000.00 3000.00
157 gamala 6 10.00 nos 10.00 10.00 1000.00 10000.00
158 gamala 7 6.00 nos 6.00 6.00 1000.00 6000.00
159 Wooden railing works
Providing and placing seasoned laminated timber rail
on openings of gates including transportation, cutting,
connecting and placing in position with wood primer 0.00 0.00
and paint, all complete as per drawings, specifications
and instruction. 0.00 cum 0.00 2500.00

160 Wooden fascia works


Providing and placing 25mm thk. Treated hardwood
fascia board on roof including transportation, cutting,
connecting and placing in position with wood primer 6.90 82800.00
and paint, all complete as per drawings, specifications
and instruction. 0.00 sqm 6.90 12000.00

161 Waterproof plyboard on roof


Providing and laying 10mm waterproof plywood with
one side veneer in perfect line and level above adobe
insulation all complete as per design, drawing, 30.70 21490.00
specification and instruction of consultant and his
authorized representative. Samples should be
approved by consultant. 0.00 sqm 30.70 700.00

162 Iko-tile roofing works


Providing and laying iko-tile nailed and stacked over
plyboard on sloped roofs in perfect line and level all
complete as per design, drawing, specification and 0.00 107450.00
instruction of consultant and his authorized
representative. 0.00 sqm 30.70 3500.00

Contractor Prepared By Checked By Approved By


Pages -323 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
163 Structural steel Works
Providing and placing structural steel tested grade Fe-
250 equivalent NS, for structural work on gate roof
including transportation, cutting, connecting and 0.00 0.00
placing in position,treated with two coat of
anticorrosive paints, all complete as per drawings,
specifications and instruction. 0.00 kgs 0.00 250.00

Providing and fabricating MS steel gate and fixing in


164 entrance polished and finished in perfect line, level as 300.00 75000.00
per design, drawing, specification and instruction all
complete. 0.00 kgs 300.00 250.00

Supplying and fitting of railing with M.S. pipe including


165 welding, joints and primer painting as per drawing and
instructions all complete
Boundary wall A 1.00 1.40 0.35 m2 0.49
2.00 1.00 0.65 m2 1.30
1.00 1.00 1.60 m2 1.60
Boundary wall B 1.00 9.00 0.65 m2 5.85
1.00 3.00 2.10 m2 6.30
1.00 8.00 0.65 m2 5.20
Boundary wall E 1.00 2.00 0.65 m2 1.30
1.00 1.00 1.60 m2 1.60
1.00 1.98 0.88 m2 1.74
1.00 3.03 0.53 m2 1.60
1.00 5.00 1.60 m2 8.00
1.00 5.10 0.53 m2 2.70
1.00 6.50 1.60 m2 10.40
1.00 2.14 0.53 m2 1.13
1.00 14.25 1.60 m2 22.80
North Side 1.00 20.00 1.50 m2 30.00

Contractor Prepared By Checked By Approved By


Pages -324 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Total= m2 102.02 102.02 5000.00 510092.25

166 Shera board works


Providing, fabricating & fixing shera board works on
gate finished in perfect line, level along with all 0.00
necessary accessories all complete as per design,
drawing, specification and instruction 0.00 m2 0.00 0.00 0.00 2500.00
STONE TAP FIXTURES AND FITTINGS
167 Supplying and Fixing Indian pattern C.P. valves with 12000.00
wall flange Including c.p. nipple all complete set. 6.00 nos 6.00 6.00 6.00 2000.00
Supplying and Fixing CP Bib Cock with wall flange,cp 12000.00
168 nipple all complete set 3.00 nos 3.00 3.00 3.00 4000.00
Supplying and Fixing 20 mm CPVC pipe with pipe
Jointing materials (Tee, Elbow, Union), making holes,
169 clips and vent cowl all complete set as per 100720.00
specification and instruction. (Mangalam,
Panchakanya , Prince,Supreme or Equivalent. ) 125.90 rm 125.90 125.90 125.90 800.00
Providing and fixing PVC water tank- brand
Nepatop/Hilltake/ Panchakanya or equivalent, of
capacity 2000 ltrs. finished in perfect line, level along 70000.00
with all necessary accessories all complete as per
170 design, drawing, specification and instruction 2.00 nos 2.00 2.00 2.00 35000.00
PLANTATION WORKS
Planting dubo grass on site including digging, planting
hole 10-20 cm depth using a metal rod or hardwood 480000.00
171 peg. sqm 800.00 800.00 600.00

Planting rooted tree stump cutting and bare root


seedlings, including pitting, transplanting, composting
and mulching, pit size 10cm diameterx depth compost
volume of pit mix with original soil.

Specifications for trees(3-4ft):-


Sami (Ficus benjamina)
Bougainvillea (Bougainvillea glabra)
Mango (Magnifera Indica) 50000.00
Neem (Azadirachta indica)
Parijat ((Nyctanthes arbor tristis)
Jasmine (Jasminum polyanthum)
Ashoka (Saraca asoca)
Supari (Areca catechu)
Bamboo (Bambusa vulgaris)
Gulmohar (Delonix regia)
Banana (Musa paradiscata)
Willow (Salix babylonica)
172 no 50.00 50.00 1000.00
Planting shrubs including digging, planting hole, etc. all 2000.00
173 complete. ls 1.00 1.00 2000.00
Electrical 0.00

Contractor Prepared By Checked By Approved By


Pages -325 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
LED strip light warm white 220V with soft bending
diffuser, philips equivalent, 72 LED per meter or
equivalent for bright and uniform lighting, complete set 90000.00
with fitting components and installation, with junction
174 box if necessary rm 45.00 45.00 2000.00

LUMINAIRES ( FIXTURES) Outdoor LED based


Luminaries set all complete. LEGERO, GE, Philips or
equivalent
7W Garden Spike, Anthracite, Warm White,Floor 27000.00
Lamp, 220V, warm white, IP 65 or above, complete set
with fitting components and installation, with junction
175 box if necessary set 18.00 18.00 1500.00
30W LED outdoor wall washer (Tubelight for indirect
lighting), 3000K, IP 65 and above, 220 V, complete set 24000.00
176 with fitting components and installation set 16.00 16.00 1500.00
LUMINAIRES ( FIXTURES) Outdoor LED based
Luminaries set all complete. LEGERO, GE, Philips or
equivalent,
6W 800lm Sleek small LED Track Lighting, 220V, 36000.00
warm white, IP 65 or above, complete set with fitting
components and installation, with junction box if
177 necessary set 24.00 24.00 1500.00
Up down Sconce light 10W equivalent IP 65 and
above,2700K/3000K warm white, complete set with
6000.00
fitting components and installation, with junction box if
178 necessary set 4.00 4.00 1500.00
Wall recessed 12 inch to 24 inch length, 10W
equivalent (600-800lm) LED warm white light, 220V, IP
122000.00
65 or above, complete set with fitting components and
179 installation, with junction box if necessary set 61.00 61.00 2000.00
Street Light / Flood Light Philips BGP704 equivalent
220V, 10000 lumens, warm white luminaires with
mount and all other components complete set with 4000.00
fitting components and installation, with junction box if
180 necessary set 2.00 2.00 2000.00
12W ceiling recessed Warm white luminaire set, 220V,
complete set with fitting components and installation, 3500.00
181 with junction box if necessary set 1.00 1.00 3500.00
9W directional LED ceiling recessed light track light, all
7000.00
182 complete,with junction box if necessary set 2.00 2.00 3500.00
Floor recessed (ground well) LED luminaire 12 W,
Warm white 220V, IP 65 or above, complete set with 21000.00
183 fitting components and installation set 14.00 14.00 1500.00

Post top LED warm white luminaire 30W, 220V with


heritage style cast iron lamp post of minimum 7 feet
height from ground level (to be bought in consultation 28000.00
with architecture), complete set with fitting components
and installation, with junction box if necessary
184 set 14.00 14.00 2000.00
Street Light Philips BGP704 equivalent 220V, 10000
lumens, warm white luminaires with mount and all
6000.00
other components complete set with fitting
185 components and installation set 2.00 2.00 3000.00
Contractor Prepared By Checked By Approved By
Pages -326 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११

Installation, testing and commissioning of 10 sq mm


2C, armored copper cable from existing point to
48000.00
distribution board, underground via 32 mm HDPE pipe,
complete set with fitting components and installation
186 Rm 40.00 40.00 1200.00

Electrical Outdoor distribution box, Waterproof sealed


with IP rating of IP66 or above, made with stainless
steel with stand kept 2 feet above ground level, 60000.00
embedded door with required copper bush, installation
and fitting cost of MCB ans switches all included
187 set 1.00 1.00 60000.00
Installation, testing and comissioning of 16 way SPN
5000.00
188 DB set 1.00 1.00 5000.00
Installation testing and commissioning of 6 A SP MCB,
7200.00
189 all complete set 12.00 12.00 600.00

Contractor Prepared By Checked By Approved By


Pages -327 of 333
MEASUREMENT SHEET
यस हालसम्म
काम/सेवाको विवरण यस नापीको मापनको आयाम नापीबाट अध्यावधिक परिमाण सूची
क्र.सं. कायम काम भएको (BoQ) मा जम्मा रकम
भएको उल्लिखित दर
क्रियाकलाप संख्या लम्बाइ चौडाइ उचाइ ईकाई परिमाण परिमाण
१ २ ४ ५ ६ ७ ८ ९ १० ११ १२=१०*११
Installation testing and commissioning of 16 A SP
1200.00
190 MCB, all complete set 2.00 2.00 600.00
Installation testing and commissioning of 32 A DP
600.00
191 MCB, all complete set 1.00 1.00 600.00
Installation testing and comissioning of 32 A DP
2000.00
192 Switch, all complete set 1.00 1.00 2000.00
Weatherproof Outdoor Junction Box, IP 68 or above
rated, JB with option for sealing the incoming and 60000.00
193 outgoing 2c wire set 30.00 30.00 2000.00
3*3 metal (Stainless Steel) junction box with rubber
35000.00
194 gasket for weather proofing set 10.00 10.00 3500.00
195 9m Pole for electric lighting single arm set 2.00 2.00 75000.00 150000.00
196 9m double arm pole for electrc lighting set 1.00 1.00 15000.00 15000.00
Installation, testing, and commissioning of 2.5 sq mm
2C, armored copper cable from the distribution board
976000.00
to, light points underground via 32 mm HDPE pipe, all
197 complete Rm 1220.00 1220.00 800.00
Chemical Earthing
Supply, Installation, testing and commissioning of
50000.00
Chemical Earthing System with including all material
198 and accessories to all complete the works nos 1.00 1.00 50000.00
Supply , installation & testing of 8 SWG bare copper
8000.00
199 conductor from Main panel to earth test pit Rm 10.00 10.00 800.00
Sub-Total 33997702.56
Price Adjustment 0.00
VAT @ 13% 4419701.33
Net Total with VAT only 38417403.89
Provisonal Sum Amount 120000.00
Grand Total with Vat and PS 38537403.89

Contractor Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with Remark


SN Norms No. Description of work Nos Length Breadth Height Unit Quantity Amount
Quantity OH s
General
A
works
Provide Insurance of works,
materials,construction
1 equipments against accident to 1 PS 1.00 1.00 30000.00 30,000.00
workforce including
third party

Provide & Maintain protective safety


Equipments including Hats, Gloves,
2 Googles, Dust mask, First Aid Kit
1 PS 1.00 1.00 10000.00 10,000.00
with medicine for work force

Lab test of the construction


3 materials as rebar cement, brick, as 1 PS 1.00 1.00 15000.00 15,000.00
per specified by site incharge
Provide & Installation of Project
Information Board1.
4 2*.90 m Size as to Complete the
1 LS 1.00 1.00 5000.00 5,000.00
Work as Specified

B Road works
Dimantling of existing
1 DoR-2.4 (ii) B
structures
brick masonry works
drain inner portion 2 350.00 0.25 0.50 cum. 87.50
cum. 87.50 87.50 1853.57 162,187.37
2 DoR-10.8 Stone soling
Providing and laying of hand pack
Stone soling with 150 to 200 mm
thick stones and packing with
smaller stone on prepared surface
as per Drawing and Technical
Specifications.
Unit = cum [For 5 cum]
trench filling 2 350.00 0.60 0.50 cum. 210.00
drain bed 2 350.00 1.00 0.10 cum. 70.00
cum. 280.00 280.00 7689.92 2,153,178.58
3 DoR - 20.2 A Concreting work.
PCCM15with screen river aggregate
and approved level, lines abd
dimension and curing all complete
as per specification and instruction
of engineer
(A) Bed PCC M15 2 350.00 1.00 0.100 cum. 70.00
(B) Wall top PCC M15
drain wall-inner 2 350.00 0.38 0.050 m3 13.30
drain wall-outer 2 350.00 0.25 0.050 m3 8.75
tick drain 2 350.00 0.20 0.075 m3 10.50
cum. 102.55 102.55 10669.15 1,094,121.13
4 DoR-25.1D Brick masonry works
Brick work (1:6) in with approved
quality of first class bricks in perfct
line and level, finished including
wetting the bricks packing the joints
and curing the complete in all types
and thickness of walls as per
specification and instruction of
engineer
drain wall-inner 2 350.00 0.38 0.80 m3 212.80
drain wall-outer 2 350.00 0.25 0.40 m3 70.00
m3 282.8000 282.80 14298.82 4043706.13

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with Remark


SN Norms No. Description of work Nos Length Breadth Height Unit Quantity Amount
Quantity OH s
12mm thick plaster (1:4) cement
sand plaster on wall of good finish,
including raking the joints, cleaning
5 DoR-25.4C
and wetting the surface and curing
the works all the complete as per
instruction of engineer.
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 324.29 272404.75
Punning work: Cement punning of
6 DUDBC:(11-20) 3mm thick cement slurry on
plastered surface
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 276.08 231907.62
7 DOR - 10.2 B Grader work
Sub-grade ( Existing pitch, gravel &
side shoulder cutting ), preparation
for designed road formation level
with grader machine.
road stretch 1 350.00 8.00 m2 2,800.00
350.00 m2 2,800.00 2,800.00 16.86 47220.23
8 DoR-12.1 A Preparation of Sub Base Work
Supplying and constrcution of sub-
base with watering and rolling by 8-
10 ton roller in layersnot exceeding
15cm at a time and with adequate
watering til full consolidation as per
instruction of engineer
road stretch 1 350.00 8.00 0.150 m3 420.00
portion 1 150.00 6.00 0.300 m3 270.00
m3 690.00 690.00 3,357.97 2316996.67
9 DoR-12.7 A Preparation of base course

Supplying, Laying & grading of


crusher run material base course of
mentioned thickness and watering,
proper levelling and cambering of
road including compaction with
roller & haulling up to 10 m
distance , as per the instruction of
Engineer's all complete
road stretch 1 350.00 7.00 0.10 m3 245.00
350.00 m3 245.00 245.00 4341.62 1063696.28
10 DOR-13.1A Prime Coat
Providing and spraying bituminious
prime coat of 60:40 including
cleaning the road surface using wire
brushes, broom etc. on base course
before applying prime coat
including supply of materials all
complete.
road stretch 1 350.00 7.00 m2 2,450.00
350.00 lit 2,450.00 2450.00 191.16 468333.55
11 DoR-13.2A Tack coat
Providing and spraying bituminious
tack coat including cleaning the
road surface using wire brushes,
broom etc. on the surface before
applying tack coat including supply
of materials all complete.
road stretch 1 350.00 7.00 m2 2,450.00

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total Rate with Remark


SN Norms No. Description of work Nos Length Breadth Height Unit Quantity Amount
Quantity OH s
350.00 lit 1,225.00 1225.00 178.99 219262.76

12 DoR 13.6 Asphalt concreting work


Providing, mixing, laying of asphalt
concrete using machine crushed
aggregate of specified grading
premixed with bituminous binder
and filter as per drawing and
technical specifications.
road stretch 1 350.00 7.00 0.040 m3 98.00
350.00 m3 98.00 98.00 28280.51 2771490.18
13 DoR-20.5 Steel Reinforcement Work
Steel reinforcement bar including
stringtening,cutting, bending,
binding with 20 SWG wire and fixing
in positions as per drawings,
specifications, and complete work
as per instruction of engineer.
for cover slab :
10mm dia main bar @ 5" c/c 8760 1.00 0.617 kgs 5407.41 1752
No. of
15768 0.40 0.395 kgs 2491.73 cover
8mm dia distribution bar @ 6" c/c slabs
kgs 7899.14 7899.14 135.70 1071878.52
14 DoR-18.1a Form work
Centering and shuttering with
wooden/plywood formworks for RCC
works including all necessary
propping, scaffolding, staging
supporting etc. all complete as per
specification and instruction of
engineer.
for cover slab : 1752 2.80 0.10 m2 490.56
m2 490.56 122.64 1046.98 128402.14
15 DoR - 20.2 B P.C.C for R.C.C M20
PCC M20 for R.C.C work including
mixing, laying, finishing to
approved level, lines and dimension
and curing all complete as per
specification and instruction of
engineer.
for cover slab : 1752 1.00 0.40 0.10 m3 70.08
m3 70.08 70.08 11697.42 819755.12
16 Site Clearance
Clearing of exisitng drain free from
debris, mud , stone , waste and
Depositing of outcasted debris to
site and dumping yard and site LS 15000.00
clearance after completion of work,
with all work complete
Sub-Total 16884541.04
VAT @ 13% 2194990.33
Sub-Total 19134531.37
Contingencies @ 3% 574035.94
Grand Total 19708567.31

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total
SN Description of work Nos Length Breadth Height Unit Quantity Rate Amount Remarks
Quantity
Dimantling of existing
1
structures
brick masonry wrks
drain inner portion 2 350.00 0.25 0.50 cum. 87.50
cum. 87.50 87.50 1015.00 88,812.50
2 Gravelling filling
Gravel filling in bed of excavated
material trench with approved
quality in layers not exceeding
15cm at a time and with adequate
watering till full consolidation as per
instruction of engineer
trench filling 2 350.00 0.60 0.80 cum. 336.00
drain bed 2 350.00 1.00 0.10 cum. 70.00
cum. 406.00 406.00 2534.25 1,028,905.50
3 Concreting work.
PCC(1:3:6) with screen river
aggregate and approved level, lines
abd dimension and curing all
complete as per specification and
instruction of engineer
(A) Bed PCC (1:3:6) 2 350.00 1.00 0.100 cum. 70.00
cum. 70.00 70.00 8183.01 572,810.70
Brick work (1:6) in with approved
quality of first class bricks in perfct
line and level, finished including
wetting the bricks packing the joints
4
and curing the complete in all types
and thickness of walls as per
specification and instruction of
engineer
drain wall-inner 2 350.00 0.38 0.80 m3 212.80
drain wall-outer 2 350.00 0.25 0.40 m3 70.00
m3 282.80 282.80 11580.15 3274866.42
12mm thick plaster (1:4) cement
sand plaster on wall of good finish,
including raking the joints, cleaning
5
and wetting the surface and curing
the works all the complete as per
instruction of engineer.
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 269.27 226186.80
Punning work: Cement punning of
6 3mm thick cement slurry on
plastered surface
drain wall-inner 2 350.00 0.80 m2 560.00
drain wall-outer 2 350.00 0.40 m2 280.00
m2 840.00 840.00 252.59 212175.60
7 PCC 1:2:4 works
wall
drain wall-inner 2 350.00 0.38 0.050 m3 13.30
drain wall-outer 2 350.00 0.25 0.050 m3 8.75
tick drain 2 350.00 0.20 0.075 m3 10.50
m3 32.55 32.55 9,354.71 304495.81

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total
SN Description of work Nos Length Breadth Height Unit Quantity Rate Amount Remarks
Quantity
8 Grader work
Sub-grade ( Existing pitch, gravel &
side shoulder cutting ), preparation
for designed road formation level
with grader machine.
road stretch 1 350.00 8.00 m2 2,800.00
350.00 m2 2,800.00 2,800.00 16.51 46228.00
9 Preparation of Sub Base Work
Supplying and constrcution of sub-
base with watering and rolling by 8-
10 ton roller in layersnot exceeding
15cm at a time and with adequate
watering til full consolidation as per
instruction of engineer
road stretch 1 350.00 8.00 0.150 m3 420.00
portion 1 150.00 6.00 0.300 m3 270.00
m3 690.00 690.00 2,534.25 1748632.50
10 Preparation of base course
Supplying, Laying & grading of
crusher run material base course of
mentioned thickness and watering,
proper levelling and cambering of
road including compaction with
roller & haulling up to 10 m
distance , as per the instruction of
Engineer's all complete
road stretch 1 350.00 7.00 0.10 m3 245.00
350.00 m3 245.00 245.00 3665.81 898123.45
11 Prime Coat
Providing and spraying bituminious
prime coat of 60:40 including
cleaning the road surface using wire
brushes, broom etc. on base course
before applying prime coat
including supply of materials all
complete.
road stretch 1 350.00 7.00 m2 2,450.00
350.00 lit 2,450.00 2450.00 127.69 312840.50
12 Tack coat
Providing and spraying bituminious
tack coat including cleaning the
road surface using wire brushes,
broom etc. on the surface before
applying tack coat including supply
of materials all complete.
road stretch 1 350.00 7.00 m2 2,450.00
350.00 lit 1,225.00 1225.00 119.27 146105.75

13 Asphalt concreting work


Providing, mixing, laying of asphalt
concrete using machine crushed
aggregate of specified grading
premixed with bituminous binder
and filter as per drawing and
technical specifications.
road stretch 1 350.00 7.00 0.040 m3 98.00
350.00 m3 98.00 98.00 19289.93 1890413.14

Prepared By Checked By Approved By


BIRATNAGAR METROPOLITAN
OFFICE OF THE MUNICIPAL EXECUTIVE
1 No. Province, Nepal

Detailed Estimate & Abstract Of Cost


Name Of Project : Construction of Storm water Drain and Asphalt Concreting works
Location :- Uday marga Ward no- 03

Total
SN Description of work Nos Length Breadth Height Unit Quantity Rate Amount Remarks
Quantity
14 Steel Reinforcement Work
Steel reinforcement bar including
stringtening,cutting, bending,
binding with 20 SWG wire and fixing
in positions as per drawings,
specifications, and complete work
as per instruction of engineer.
for cover slab :
10mm dia main bar @ 5" c/c 8760 1.00 0.617 kgs 5407.41 1752
No. of
15768 0.40 0.395 kgs 2491.73 cover
8mm dia distribution bar @ 6" c/c slabs
kgs 7899.14 7899.14 108.20 854687.03
15 Form work
Centering and shuttering with
wooden/plywood formworks for RCC
works including all necessary
propping, scaffolding, staging
supporting etc. all complete as per
specification and instruction of
engineer.
for cover slab : 1752 2.80 0.10 m2 490.56
m2 490.56 122.64 782.51 95967.03
16 P.C.C for R.C.C (1:2:4)
PCC (1:2:4) for R.C.C work
including mixing, laying, finishing to
approved level, lines and dimension
and curing all complete as per
specification and instruction of
engineer.
for cover slab : 1752 1.00 0.40 0.10 m3 70.08
m3 70.08 70.08 9354.71 655578.08
17 Site Clearance
Clearing of exisitng drain free from
debris, mud , stone , waste and
Depositing of outcasted debris to
site and dumping yard and site LS 15000.00
clearance after completion of work,
with all work complete
Sub-Total 10681300.10
Overhead @ 15% 1602195.02
Sub-Total 12283495.12
VAT @ 13% 1596854.37
Sub-Total 13880349.48
Contingencies @ 3% 416410.48
Grand Total 14296759.97

Prepared By Checked By Approved By

You might also like