CEA BESS Safety Regulations 2025 - Draft

The Central Electricity Authority (CEA) of India is proposing the Draft Central Electricity Authority (Measures relating to Safety and Electric Supply) (First Amendment) Regulations, 2025, which includes new definitions and additional safety requirements for Battery Energy Storage Systems (BESS). Stakeholders and the public are invited to provide comments on the draft regulations by July 20, 2025. The regulations aim to enhance safety measures and standards for the operation and management of BESS installations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2K views5 pages

CEA BESS Safety Regulations 2025 - Draft

The Central Electricity Authority (CEA) of India is proposing the Draft Central Electricity Authority (Measures relating to Safety and Electric Supply) (First Amendment) Regulations, 2025, which includes new definitions and additional safety requirements for Battery Energy Storage Systems (BESS). Stakeholders and the public are invited to provide comments on the draft regulations by July 20, 2025. The regulations aim to enhance safety measures and standards for the operation and management of BESS installations.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

GOVERNMENT OF INDIA

CENTRAL ELECTRICITY AUTHORITY


Sewa Bhawan (North Wing), Room No. 622, 6 th Floor,
R. K. Puram, New Delhi-110066
Tel. Fax -011-26103246, email: celegal-cea@gov.in
Website: www.cea.nic.in

PUBLIC NOTICE

In exercise of powers conferred under Section 177 of the


Electricity Act, 2003, the Central Electricity Authority (CEA),
proposes to notify the Draft Central Electricity Authority
(Measures relating to Safety and Electric Supply) (First
Amendment) Regulations, 2025. The proposed draft
regulations are available on the CEA Website www.cea.nic.in for
inviting public comments. The Regulations can also be inspected
in the office of Chief Engineer (Legal), Sewa Bhawan (North
Wing), Room No. 622, 6th Floor, R. K. Puram, New Delhi-
110066 on any working day till 20.07.2025 between 1100 hrs. to
1600 hrs.

2. All the Stakeholders and the public are requested to send


their comments on the draft regulations to Chief Engineer
(Legal), Sewa Bhawan (North Wing), Room No. 622, 6th Floor,
R. K. Puram, New Delhi-110066 by post or through e-mail
(celegal-cea@gov.in) latest by 20.07.2025.

(Rakesh Kumar)
Secretary, CEA
[To be published in the Gazette of India, Extraordinary, Part III, Section 4]

CENTRAL ELECTRICITY AUTHORITY


NOTIFICATION
New Delhi, the …………., 2025

F No. ....................................................— In exercise of the powers conferred by clause


(e) of sub-section (2) of section 177 of the Electricity Act, 2003 read with section 53 of the
Electricity Act, 2003 (36 of 2003), the Central Electricity Authority hereby makes the following
regulations, namely: -

1. Short Title and Commencement- (1) These regulations may be called the Central Electricity
Authority (Measures relating to Safety and Electric Supply) (First Amendment) Regulations,
2025.
(2) They shall come into force on the date of their publication in the Official Gazette.

2. The following definitions shall be added under Chapter I, Regulation 2 as follows:


(ea) “Battery Energy Storage Systems” or “BESS” means a system connected to the Power System
which is used to store electric energy by means of electrochemical materials, typically includes
batteries, power conversion system, and battery management system.
(eb) “Battery Management System” or “BMS”: A system which implements controls on batteries
in order to obtain safe operation, it also balances the energy of batteries and monitors the status
thereof.
(ec) “Power Conversion System” or PCS in a BESS refers to the integrated system of inverters,
rectifiers, controllers, and associated power electronics that convert DC power from the battery to
AC power for the grid (discharging), and vice versa (charging).
3. The following Chapter X-A titled “Additional safety requirements for Battery Energy
Storage System (BESS)” shall be added namely:-
122(A). Additional safety requirements for Battery Energy Storage System (BESS):
The regulations under this chapter shall be applicable to Battery Energy Storage System (BESS)
which shall be in addition to the regulations provided from Chapter I to VII and XIV.

122(B). General Safety considerations


(1) The chargers used for charging the battery energy storage systems shall be designed for the
chemistry of the battery to be charged.
(2) The battery system shall be designed with two-fault tolerance to prevent catastrophic failures
under all conditions, including but not limited to overcharge, over-discharge, short circuit, and
operation outside specified temperature limits. .
Explanation: Two-fault tolerance refers to the system's ability to continue to operate safely or shut
down safely even after two independent faults have occurred
(3) Testing of BESS shall be carried out as per relevant standard
(4) Fire and explosion protection at Cell level, Module level, container level and site specific
installation level shall be as per the relevant standard
(5) (a) BMS shall monitor and record voltage, temperature, current, and thermal runway at cell
level and module level.
Provided that audio visual alarms shall be activated in case the monitored parameter
exceeds the operating range as specified per OEM.
Provided further that BMS shall automatically stop charging and discharging of the battery
when the temperature readings exceeds manufacturer’s recommended values.
(b) PCS shall be capable of fully automatic and unattended operation, including synchronizing
with the grid or electric power system, seamless paralleling and disconnecting from the grid or
electric power system. It shall include self-protective and diagnostic features to protect itself from
damage in the event of component failure and abnormal operating parameters.
(6) Coolant lines shall be routed and secured to mitigate leakage on live electrical parts. A failure
of the dielectric fluid cooling system, including any fault in the cooling lines shall not result in a
leakage that can cause short circuiting of the cells inside the battery pack or lead to a hazardous
condition.
122(C). Battery Container:
(1) The battery container shall be explosion-proof, with a forced ventilation system and automated
louvers for safe release of the flammable gas and maintain internal pressure within safe limits.
(2) Ingress Protection shall be provided as per the relevant standards.
(3) Walk-in System, including Entrances & Exit, of BESS shall be as per the relevant standard.

122(D). Equipment Location

(1) All Battery containers shall be positioned so as to ensure a distance of 7.5 meters from the
nearest exterior wall or roof overhang.
Provided that where prescribed distance cannot be maintained, Large Scale Fire Testing
(LSFT) shall be conducted as per relevant standard to validate the safety of the installation.
Provided further that adequate measure shall be taken for noise reduction in the area where
BESS is installed within densely populated urban area or critical building.
(2) A distance of 3 meters shall be maintained between two Battery containers.
Provided that where prescribed distance cannot be maintained, LSFT shall be conducted as
per relevant standard to validate the safety of the installation.
Provided further that the external wall of container shall have a minimum fire resistance
rating of 2 hours.

122(E). Ventilation:
(1) Adequate ventilation and cooling systems for BESS container shall be installed to prevent
overheating.
(2) A suitable mechanism shall be provided to limit the concentration of flammable materials
inside the enclosure of BESS, in compliance to relevant Indian Standard.
Provided that in the event of the mechanical ventilation system failure, the system shall
initiate a shuts down to maintain the concentration of flammable materials in the battery
container within safe limits.

122(F). Hazard Detection and Suppression System:


(1) BESS shall have hazard detection systems for smoke, gas, heat and flame as per relevant
standard and the same shall be monitored.
(2) Every battery container of 200 kWh and above rating shall be provided with water based
automatic fire suppression system as per relevant standard.
(3) The components of the installed fire suppression system shall be protected from ambient
weather conditions and unauthorized access while ensuring ease of accessibility for inspection and
maintenance.

122 (G) Electrolyte spill: In case of batteries having acidic/basic aqueous electrolytes in liquid
form, the electrolyte spills shall be contained as per relevant standards.

122(H). Lighting and Signage:


(1) A separate emergency source of lighting with automatic initiation shall be provided in enclosed
working spaces as per relevant standard.
(2) Location and specification of lighting and signage shall support safe access and navigation to
the site

122(I). Security Systems:


(1) BESS installations shall be protected by fencing not less than 1.8 m in height so as to prevent
unauthorized entry.
(2) The installation of CCTV, motion or break glass sensors, and alarm sets connected to a
monitoring and response system shall be provided at appropriate locations.

122(J). Emergency Stops:


(1) In case a safety issue or battery anomaly is detected, the affected section of BESS shall shut
down within pre-set period.
(2) Manual emergency stop buttons or switches or mechanisms shall be placed at easily accessible
and visible locations.
122(K) Earthing: BESS equipment earthing shall be as per the relevant standard.

122(L) Other Requirement:


(1) An independent third party fire safety audit of the BESS shall be conducted, as
provided in the Standard Operating Procedure (SOP) to be issued by the Authority
within a period of three months from the date of notification of these Regulations.
(2) BESS owner shall submit the above fire safety audit report to the Electrical Inspector
at the time of inspection.
(3) The appropriate government shall ensure that Fire Safety officials are trained to
address fire risks specific to BESS.
Provided that the Directorate General of Fire Safety (DGFS) shall issue guidelines
for such training within a period of three months from the date of notification of these
Regulations.

4. New Regulation 137 shall be added in Chapter XIV, after Regulation 136 of the Principal
Regulations as under:

137. List of Relevant Standards- The Authority through a separate order shall issue a list of
relevant standards applicable in these regulations, within three month of publication of the
amendment in these regulation ;

(Rakesh Kumar)
Secretary

Note: The principal regulations were published in the Gazette of India, Extraordinary, Part III, Section 4, vide
notification No. CEA-PS-16/1/2021-CEI Division, dated the 8th June 2023.