Foe Kjo Ond3 Mos Demo 001 Rev A
Foe Kjo Ond3 Mos Demo 001 Rev A
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
REVISION HISTORY
Rev.
Company Position Date Signature Remarks
No. Name
CONTRACTOR REPRESENTATIVE
Prepared By:
FOE Project Engineer 15-June-2025
Syed Maqsood
A Checked By:
FOE Safety Officer 15-June-2025
Prakash R
Approve By:
FOE Project Manager 15-June-2025
Avinash
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
TABLE OF CONTENTS
1 Scope 1
2 Responsibilities 2
3 Equipment’s Tools 5
5 PROCEDURE 5
7 Reference Drawings 12
8 Attachments: Drawings 13
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
1. SCOPE
The purpose of this statement is to define the rules and conditions designed to ensure that demolition
work is planned to enable personnel to be aware of all the procedures and dangers involved and to decide
on the safest method of work, including the following:
2. INSTALLATION OF LEVEL INDICATOR ON OILY WATER SUMP PIT – POWER PLANT AREA
• Demolition of the existing Level Switch PP-LS-01 located at Oily Water Sump PP-TK-832
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
2. RESPONSIBILITIES
2.1 Project Manager is responsible:
▪ For overall implementation of this method statement and supervision of all activities.
▪ For submittals and approvals of Drawings, Plans, Method Statements including Inspection and
Test Plans and Risk/Impact Assessments.
▪ Liaison with the client and all other parties for approval permits for the smooth operations.
▪ Overall supervision of Quality Management System.
▪ Overall Supervision of OHS & E Management System.
▪ Project execution and handing over of site to client and to obtain completion certificates.
▪ To coordinate with client for any changes to design and or project requirements.
▪ Controlling the progress work and ensuring final approval is obtained at least 3 days before start
of work.
2.2 Project Engineer is responsible:
▪ Arranging human and material resources and scheduling activities.
▪ For carrying out works as per approved drawings, method statements, and QHSE Procedures.
▪ For getting client/client representative’s approvals for works done, wherever applicable.
▪ Notifying QC engineer and issuing WIR (Works Inspection Request) in sufficient time (normally 24
hours in advance) when work is ready for inspection as detailed hereunder.
▪ Facilitate the inspection by engineer and obtain approval.
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
A detailed survey shall be conducted to ensure the identification of any structural problems and risks
associated with flammable substances and hazardous. The survey shall take into account any adjoining
properties likely to be affected by the demolition works.
Consideration shall be given to the location of premises containing trees, cars, etc. so that restrictions
shall be made for the falling of materials, vibrations, and dust protection during demolition.
5. PROCEDURE
General:
• Adequate protection and preservation shall be given to existing lights and walkways.
• In case of any obstructions or fall of debris on roads, the area shall be cleaned.
• During demolition of concrete structures, suitable temporary supports shall be made to the
existing structure. All the demolished materials shall be separately stored and disposed of at the
approved dumping location.
• In case of observations of any unidentified services or cables during the process, it shall be
reported to the company.
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
• A sequence of operations shall be established that allows the clearance of debris regularly,
such that unnecessary overloads to the existing structures shall be avoided, and to maintain
good housekeeping.
• Upon completion of demolition work, the site shall be kept tidy, and the surrounding area shall
be cleaned to avoid the accumulation of any dust and debris.
• All steel & waste will be removed from the site in suitable skips that will be transported from the
site for disposal.
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
• Transport the demolished light and other accessories to a designated area assigned by the
KJO Representative.
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
VI. Construct Shelter at the Demulsifier Chemical Injection System (South Area)
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
➢ Dismantling
• Unbolt the crane and lift using a hoist/crane/Boom Truck.
• Break the foundation using a breaker.
3. Cable Rerouting
➢ Demolish Cable Run
• Isolate electrical circuits.
• Cut and remove existing cables.
➢ Cable Laying & Termination
• Reroute to new pole location as per drawing K-180121 sheet 001.
4. Curbstone & Ramp Area at Shelter #2
➢ Demolition
• Remove curbstone with crowbar or jackhammer.
• Cut and break the ramp portions as needed.
➢ Area Preparation
• Clean and level the ground for new construction.
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
• At all times, the appointed demolition contractor will ensure a high standard of Health and
Safety is always carried out on site.
• Adequate segregation of pedestrians and vehicular traffic will always be maintained. Reversing
vehicles and plants will always be minimized.
• Permit to Work: All demolition and modification work must be conducted under an approved
permit from KJO. This includes relevant permits such as Hot Work, Excavation, and Electrical
Isolation.
• Job Safety Analysis (JSA): Conduct JSA or Risk Assessment before starting any job to identify
site-specific hazards and mitigation actions.
• Daily Toolbox Talk (TBT): Held at the start of each shift to discuss the job scope, hazards, control
measures, and emergency protocols.
• Dust Suppression: Use water sprays or dust collectors to minimize airborne particles, especially
in enclosed or active process areas.
• Barricading and Signage: Demolition zones must be physically barricaded with clear signage to
prevent unauthorized access.
• Before removal or rerouting of any electrical components (like lighting poles or level switches),
ensure Lock-Out/Tag-Out procedures are followed.
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
4. Environmental Protection
• Dispose of oily rags, contaminated concrete, or insulation as per site Aramco environmental
guidelines.
• Use low-noise tools where feasible. Work during permitted hours if within noise-sensitive
zones.
• For cutting, welding, or grinding operations a Hot Work Permit must be obtained.
• Near-miss, incident, or unsafe condition reporting must be encouraged and tracked for
corrective action.
• HSE officers must be assigned to monitor high-risk tasks like elevated work, excavation,
electrical demolition, and hot work.
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
METHOD STATEMENT
FOR DEMOLITION
DOC. NO: FOE-KJO-OND3- WORK REV.A DATE: June 15, 2025
MOS-DEMO-001
LOCATION AL KHAFJI JOINT OPERATIONS
PROJECT COMBINED OND PROJECTS_ PACKAGE-03
CONTRACT NO GT832PC23
8. ATTACHMENTS: DRAWINGS
E
NOTES:
LE
ShT. No. Rev. N0. DWG.NO. INDEX PLANT No. PROJECT No.
1. ALL DIMENSIONS ARE IN MILLIMETERS AND ELEVATIONS ARE IN METERS UNLESS
C
NOTED OTHERWISE.
TH
TR
2. ALL WORK SHALL BE IN ACCORDANCE WITH APPLICABLE SAUDI ARAMCO
R
NO
STANDARD (SAES) AND NATIONAL ELECTRICAL CODE (NEC) LATEST EDITION.
2348
IC
3. EXISTING LIGHTING POLE SHALL BE RELOCATED.
AL
4. EXISTING CABLE SHALL BE DEMOLISHED AND REPLACE AS SHOWN IN DRAWING
NUMBER KA-180121 SHT.001 REV.00.
TR
5. CLOUDED PORTION WITH DOUBLE HATCHED SHALL BE DEMOLISHED/RELOCATED.
E
N
C
.6°
39
H
AH
KK
MA
300
11412
1800-8B-LG-035
SEE NOTE 3
3293
2656
M16 EXISTING STREET LIGHT
ON BRANCHES SUITABLE FOR INSTALLATION
ON METTALIC STRUCTURE
1 X 70W HIGH PRESSURE SODIUM VAPOR
8.250
P-071A/B
P-072A
P-072C
2810
540
REFERENCE DRAWINGS
1800-8B-LG-030 P-072D DRAWING CONTROL LIST (EWO# PCD/FP/SO-01/18) DCL-001
°
1834
45
1800-8B-LG-029
350
1800-8B-LG-033
M08 M07
350
METERS
1:50M
SCALE:
17728
7.800 REVISION VALIDATION
THIS REVISION NO. 00IS COVERED, FOR ALL APPROVAL AND CERTIFICATION
REQUIREMENTS, PER KJOEP-3412, UNDER DRAWING COMPLETION CERTIFICATE NO:
PCD/FP/SO-01/18-001
1800-8B-LG-027
7.900
ALKHAFJI JOINT OPERATIONS
KGOC / AGOC
AL-KHAFJI, SAUDI ARABIA
1800-8B-LG-028
DRAWING TYPE
3885
LTG