MCF Design Guidelines For Distributed Antenna Systems 060525 FINAL
MCF Design Guidelines For Distributed Antenna Systems 060525 FINAL
2025 EDITION
Implementation Approval
Name: Chris Coughlan
Position: Head of Spectrum and Network
Infrastructure
Note for MCF readers: The contents of this publication are subject to change without notice.
All efforts have been made to ensure the accuracy of this publication. Notwithstanding, AMTA
and the MCF does not assume responsibility for any errors nor for any consequences arising
from any errors in this publication.
This document replaces and supersedes any previous versions of the ‘Design Specification
for Distributed Antenna Systems (DAS)’ and applies to DAS designs that commence after the
publication date.
1 DEFINITIONS ................................................................................................................................................................8
3 PURPOSE ...................................................................................................................................................................10
4 PLANNING ..................................................................................................................................................................19
5 DESIGN .......................................................................................................................................................................24
7 DELIVERABLES .........................................................................................................................................................45
Table 1 Sub 6GHz Bands designated for use by mobile network operators --------------------------------------------------------- 22
Table 2 Reference Technologies and 3GPP Standards ----------------------------------------------------------------------------------- 22
Table 3 DAS site type Minimum Solution Recommendations ---------------------------------------------------------------------------- 25
Table 4 Maximum Input Power ------------------------------------------------------------------------------------------------------------------ 34
Table 5 Example power share calculation ---------------------------------------------------------------------------------------------------- 35
Table 6 Signal, Dominance, and Quality Performance Levels for DAS ---------------------------------------------------------------- 37
Table 7 Installation/Test Report ----------------------------------------------------------------------------------------------------------------- 49
Table 8 MNC Input PIM Test Parameters ----------------------------------------------------------------------------------------------------- 52
Table 9 Passive Branch PIM Test Parameters ---------------------------------------------------------------------------------------------- 52
FIGURES
Carrier means a member of the Mobile Carriers Forum who is the owner and operator of a
public mobile telecommunications network in Australia, currently Optus, Telstra and TPG
Telecom and their related body corporates.
Category 1 IBC means an In Building Coverage or DAS where none of the antennas exceed
the ARPANSA Radiation Protection Series S-1 General Public reference levels at 20cm from
the antenna.
Category 2 IBC means an In Building Coverage or DAS where one or more of the antennas
exceed the ARPANSA Radiation Protection Series – S1 General Public reference levels at
20cm from the antenna.
DAS Contractor means an organisation that designs, installs and implements a DAS.
DAS Equipment means the equipment used to distribute the mobile signal from the Carrier
base stations over either an Active, Hybrid or Passive DAS.
DAS Infrastructure Operator means a third party that can perform the functions of a ‘Lead
Carrier’. The DAS Infrastructure Operator may, or not, provide a turnkey service to a building
owner providing a service facilitating inbuilding coverage from some, or all, mobile network
providers. A DAS Infrastructure Operator would need to satisfy regulatory requirements to
operate and maintain infrastructure used to provide carriage services.
Distributed Antenna System (DAS) means the distributed antenna system for mobile
telecommunications coverage installed in the building comprising a constellation of antenna
and interconnecting equipment which has been installed throughout the building.
Exemption Zone(s) means areas within a building environment which have been agreed by
the Lead Carrier/DAS infrastructure Operator and Building Owner to be exempt from
achieving the Coverage and/or Capacity KPIs as defined in this guideline.
Lead Carrier means a Carrier engaged contractually by a Building Owner to provide Carrier
base station connection and ongoing maintenance/fault management. If for any project or
building, a Lead Carrier is not appointed, then in this guideline the words “Lead Carrier’ are to
be interpreted as referring to all Carriers that are intended to use the DAS which may include
a third-party DAS Infrastructure Operator.
Target Coverage Area means the coverage area of a building or property which the Lead
Carrier endorses as the zone which KPI thresholds should be met.
RF – Radiofrequency
UE – User Equipment
3.1 CONTEXT
A Distributed Antenna System (DAS), when connected to Carrier networks, provides mobile
coverage and capacity solutions in situations where the external mobile network may not
provide reliable services to all areas within a building or structure.
When a DAS is properly designed and installed it can provide the mobile user with an optimal
quality experience. Conversely, a poorly designed or installed system will see users
encounter unreliable experiences such as dropped calls, clipped speech, slow data speed,
etc.
The purpose of these DAS Design Guidelines is to provide guidance for the installation of
network equipment in buildings and other infrastructure so that by compliance with these
DAS Design Guidelines, the building owners and occupiers can be confident that mobile
carriers will be capable of connecting their equipment and providing high quality coverage
within the facility. These DAS Design Guidelines provide a series of recommended technical
standards and procedures to facilitate multi-carrier access to a DAS.
3.2 SCOPE
These DAS Design Guidelines outline the recommended design, engineering, operational
aspects and performance criteria for a DAS that in most circumstances will be considered to
be sufficient to ensure that end-users receive a carrier-grade service in locations where
terrestrial mobile network coverage may be affected by the built environment or may
otherwise be insufficient to meet capacity demands. These DAS Design Guidelines should
be read and interpreted within the framework of the Scope set out in this section 3.2.
These DAS Design Guidelines provide a source of information for stakeholders (including
building owners and developers) interested in installing a DAS that meets the regulatory and
network requirements of each Carrier. These DAS Design Guidelines include guidance on
designing and installing DAS to accommodate new spectrum and technology changes, and
specifically to support the deployment of 5G capable network infrastructure.
The design, specification, and performance guidelines set out in this document are
recommendations to assist with meeting regulatory requirements and to reduce deployment
costs in circumstances where all Carriers are likely to share access to a DAS in a multi-
carrier environment. These recommendations suggest standards for a properly designed
DAS which, if adopted, are intended to:
These DAS Design Guidelines do not address nor cover any commercial arrangements
(including tenure) that may be negotiated or agreed between Carriers and stakeholders.
The building of a DAS involves three key stakeholders who will typically have the following
responsibilities and interactions with one another (note reference to Lead Carrier also refers
to a DAS Infrastructure Operator):
• initiate the DAS requirement and engage the DAS Contractor to provide a solution;
• provide equipment room/s to house DAS and Carrier equipment (e.g. Floor Space,
Secure Rooms, Wall Space);
• provide power supply for the DAS and Carrier equipment (e.g. AC lead in and
outlets);
• provide environmental management for DAS and Carrier equipment (e.g.
Airconditioning);
• provide cable path access and amenities (e.g. risers, cable trays, conduit, floor
penetrations);
• engage a Lead Carrier to provide Carrier connection and maintenance (e.g. Carrier
base station and ancillary equipment) through commercial agreements that typically
specify service level agreements on repair and maintenance timing, fault monitoring,
and managing DAS adjustments resulting from fit-outs and refurbishments; and
• may engage a third party to provide and own the DAS.
Typically, a building owner appoints a Lead Carrier who will provide a compliance
assessment of designs and installations to ensure that the DAS installation meets all
regulatory, operational, security, and health and safety standard requirements. Engagement
of a Lead Carrier is usually on terms that its assessment may then be shared with other
Carriers to avoid duplication of effort regarding assessment of compliance.
The appointment of a Lead Carrier is at the discretion of the building owner and is intended to
reduce costs and increase efficiency but is not mandatory. There is no formal requirement for
a building owner to appoint a Lead Carrier and a building owner may adopt alternative
arrangements.
This Guideline anticipates that the key stakeholders will each be responsible for discrete
elements in the solution delivery and interact with one another in various stages and
manners.
Figure 2 depicts the typical process flow and interactions of the key stakeholders from DAS
inception to completion of a DAS ready for Carrier connection.
By law, the combined DAS and Carrier equipment solution can only be operated by an entity
that is registered with the ACMA as a licenced carrier.
A Carrier chosen by the building owner to licence or own the DAS is typically considered a
Lead Carrier. Early engagement of a Lead Carrier by the Building Owner will generally
facilitate effective collaboration between the DAS Contractor and all Carriers which can
optimise the DAS design, delivery, and Carrier connection process.
Where a Building Owner chooses to engage a Lead Carrier or DAS Infrastructure Operator,
that entity is generally able to provide the following design advice:
Appointment of a Lead Carrier assessing DAS compliance does not constitute or imply that
the Lead Carrier acts for, or on behalf of, other Carriers in connection with the appointment.
Appointment of a Lead Carrier assessing DAS compliance does not of itself signify or imply
that the Lead Carrier has any liability to the other Carriers in relation to the appointment.
Other Carriers remain free to determine whether the DAS meets their individual
requirements.
A DAS constructed to comply with this design guidance will enable connection by all Carriers.
There is no obligation on a building owner to allow all Carriers to connect. Conversely there
is no obligation on any Carrier to use a DAS.
This document replaces and supersedes any previous versions of the ‘Design Specification
for Distributed Antenna Systems (DAS)’ and applies to DAS designs that commence after the
publication date.
https://amta.org.au/in-building-coverage-information-for-property-owners-managers/
This document provides information required to ensure a DAS can be designed and installed
to meet the relevant workplace safety standards. However, this document should be
considered subordinate to any general or project specific HS&W requirements, laws or
regulations.
The DAS design process must address EME levels in line with mandatory ARPANSA
standards. It should be noted that a significant modification of the EME guidelines has
occurred in this revision around the antenna classification compliance categories and EME
design methodologies.
In the development of a DAS solution, it is recommended that the designer consider the
following solution principles and aspects.
• Incorporate any additional requirements and DAS objectives from the building owner
that the design target to provide above and beyond what the DAS guideline
recommends.
• Provide enhanced coverage, and a consistent user experience within the Target
Coverage Area.
• Provide dominant coverage within the Target Coverage Area to avoid unnecessary
hand-off and/or interference to/from the rest of the network. The design should ideally
evaluate the coverage levels (in consultation with the Lead Carrier) provided by the
surrounding cells, considering any proposed network changes that are likely to cause
an impact. Refer to HANDOVER ZONE AND CONTROLLED LEAKAGE.
• The design should ideally consider any technical, structural, and/or architectural
constraints.
• To avoid any risk of service disruption between different types of users all fibre optic
and electrical cables associated with a DAS are ideally physically separate and
clearly distinguishable from any other cable which may be installed within or
throughout the premises.
• To meet best practice, it is not appropriate for conduits containing DAS Coax Cable to
be ‘sunk’ into the concrete during the slab pour. Ideally all DAS Coax Cable should
be installed surface mounted to allow for ease of fault finding and maintenance.
• When a chosen DAS topology requires fibre connectivity, Carriers may agree to the
use of existing in-building optical dark fibre where access and identification is possible
however dedicated fibre connectivity is preferred.
• comply with any applicable regulatory conditions and standards (building codes,
electrical safety, etc.);
• ensure that appropriate RF signage is used to achieve EME compliance in
accordance with industry standards; and/or
• be able to operate in accordance with each Carrier’s ACMA licence conditions and be
and compliant with Australian Federal Government advice around security of network
operations (e.g. CISC TSSR).
• be designed and deployed for bands as outlined in Section 4.3. The design should
assume that all channels in every frequency band applicable are in operation
simultaneously;
• provide enough capacity for the size of the building and expected occupancy, with
reasonable allowance for network traffic growth. It is recommended that the DAS is
designed so that it can be easily expanded and upgraded for capacity reasons by way
of sectorisation or similar, without compromising the DAS performance;
• be sensitive to the building functions, structure properties and environments to reduce
risk of DAS performance issues such as Passive Inter-modulation (PIM) and external
interferers; and/or
• include filtering requirements to resolve uplink/downlink channel interference issues to
be addressed with Carrier advice.
The DAS designer is typically responsible for selecting a suitable propagation model for the
DAS environment to ensure that the minimum signal levels recommended in this document
are delivered by the systems once it is in operation. The details of the propagation model
used should be based in sound engineering principles and should be traceable via
calculation to a solid empirical or theoretical base including sufficient design margins.
4.2 ARCHITECTURE
The DAS architecture type selection should consider the complexity, components, cost (total
DAS infrastructure and Building Owner expenses), and the final performance KPI. When
determining the most appropriate architecture, the DAS designer should consider the
complete solution including the carrier equipment requirements and building owner
equipment housing and environmental conditioning requirements.
A DAS design may consist of a combination of DAS architectures however, for any single RF
sector it is recommended that there should be no mixture of passive and other DAS
architecture segments. See Figure 5 for a simplified schematic of example DAS
architectures.
Distributed Antenna System (DAS) solutions can be provided using architecture that may be
described as:
Where the base station RF signal is distributed to antennas via a passive network of coaxial
cables, splitters, and couplers. A passive DAS is typically divided into the backbone feed
system, which forms the distribution to each floor area, and the floor/area cabling and
antenna system.
• The backbone is generally comprised of cables, splitters, and couplers.
• The equipment can be a combination of cable, radiating cable, antennas, and
terminations.
Where the base station RF signal is converted to digital and distributed via a digital network
to remote radio units that then feeds an RF passive network of coaxial cables, splitters, and
couplers.
• A hybrid DAS typically has a backbone feed system of digital equipment which
provides the distribution to each floor area via optical fibre cables or electrical cabling.
• The floor/area equipment can be a combination of passive equipment including cable,
radiating cable, antennas, and terminations fed from remote radio equipment.
Where the base station RF signal is converted to digital and distributed to active antenna
units.
• An Active DAS typically has a backbone network of Master/Slave Units feeding floor
area antenna systems via a network of either optical fibre cables or electrical cabling.
• The floor/area antenna systems can convert digital inputs to RF and are typically
referred to as Access Points.
Where the base station digital signal is distributed to active antenna units.
• A Digital DAS typically has a backbone network of Master/Slave Units feeding floor
area antenna systems via a network of either optical fibre cables or electrical cabling.
• The floor/area antenna systems can convert digital inputs to RF and are typically
referred to as Access Points.
In Australia, the following bands are currently designated for use by the mobile carriers under
both Spectrum and Apparatus Licences (PTS) which are administered by the ACMA.
Table 1 Sub 6GHz Bands designated for use by mobile network operators
For maximum flexibility, the passive components of the DAS should be selected to allow
operation on all available bands (703-3800 MHz).
Best practice is that DAS should be designed to operate with base station and repeater
equipment that is compliant with the corresponding ACMA licence conditions, as well as the
relevant 3GPP standards.
Carriers will regularly undertake testing and compliance certification of materials and
equipment prior to inclusion into network infrastructure to ensure compliance with network
security, performance, and regulatory requirements.
Certified materials and equipment may be listed in an approved material list that DAS
Contractors can access when designing a DAS. Refer to the AMTA website for the latest
version:
https://amta.org.au/in-building-coverage-information-for-property-owners-managers/
Approved material and equipment selection also contributes to the long-term reliable
performance of the DAS and enables a Carrier to provide the necessary ongoing
management, maintenance, and support.
A DAS that is designed and constructed with only approved materials and equipment will
ensure Carriers will be capable of connecting their equipment to a compliant system.
The DAS required to deliver the necessary network performance capability will depend on the
specific areas and characteristics of the building and Target Coverage Area.
A DAS should be designed to provide appropriate network performance capability within the
Target Coverage Area. Carriers can accommodate reasonable flexibility in a DAS design to
meet the different in-building connectivity needs of building developers and owners.
However, while some designs may initially provide sufficient network performance, they may
limit the system capabilities. For example, a decision to not incorporate MIMO and/or
sufficient capacity into a DAS may result in Carriers being unable to supply 5G features and
performance within that building and potentially the need for upgrades in the future.
Early Lead Carrier engagement is an option available to Building Owners and DAS
Contractors to assist in design considerations.
Best practice is that the Target Coverage Area should encompass the entire building floor
area to provide continuous connectivity.
Exemption zones that are incorporated into the Target Coverage Area need to be agreed
between stakeholders.
Network performance of a DAS may depend on a variety of factors, including the structure of
the building or specific site, and the number of users of the network at any given time. The
design should ideally take into consideration these factors when selecting the appropriate
solution architecture to achieve an acceptable performance in Target Coverage Areas.
Carriers may be engaged to assist with determining appropriate DAS solution architecture for
a site or alternatively the Solution Categories in Table 3 can be used to assist Building
Owners and DAS designers with this architectural determination, by associating typical
building types with recommended solution types.
Typical candidates for a higher order MIMO DAS configuration are locations which cater for
large numbers of users e.g. stadiums, entertainment/exhibition/convention centres,
auditoriums, transport/railway stations and tunnels, underground platforms, and airports.
Carriers can assist DAS designers and Building Owners with determining the order of MIMO
best suited to the required performance attributes for a DAS.
The DAS design should ideally include well-defined handover zones to minimise unwanted
handovers to maximise customer experience. This is applicable for both internal sectors of
the DAS and handovers to and from the external mobile network at entry/egress points.
DAS sector boundaries should avoid high traffic, KPI exemption zones or dwell areas, and
make use of natural separation areas of the building design e.g. horizontal floor levels where
possible.
Where defined separation cannot be used as a handover boundary (e.g. large open atriums),
the expected handover zones should be annotated in the DAS design sectorisation plan.
As best practice, handovers to/from external fast-moving mobiles need to be avoided except
for DAS applications being installed specifically for transport infrastructure (tunnels, railway
stations etc.). In those specific installations, coverage should be extended to ensure
seamless handover to the macro network.
In addition to the general design requirements for all DAS solutions, it is best practice that
there are additional design aspects that relate to specific building types and applications.
The design solution considered appropriate for a specific DAS varies depending on the
application. Specifically, a DAS for a mine or railway tunnel will not apply the same design
approach as the design for a stadium. Likewise, a residential apartment building DAS should
address requirements differently to a commercial office environment.
This section identifies specific design considerations for typical building type categories.
All residential layouts are unique and the extent of Targeted Coverage Areas within
apartments will depend on size, apartment layout, and even building exclusivity.
In small apartments the Target Coverage Area requirement inside an apartment may possibly
be met with antennas and infrastructure placed outside the apartments (i.e. in corridors and
common areas). Larger apartments will typically require antennas inside to meet the KPIs for
performance and quality – particularly at the higher frequency bands.
Where antennas are required inside apartments, ideally it is important for all stakeholders to
acknowledge that access to private residential apartments for maintenance and fault finding
may be difficult and will inevitably lead to delays in rectifying faults. To mitigate this risk, it is
best practice that the DAS should be configured so each apartment has a unique feed
accessible from common areas of the building which can be physically isolated from the
remainder of the DAS to assist with fault finding and help mitigate PIM contamination
affecting other parts of the DAS. It is not recommended that any branch of the DAS service
multiple apartments without the ability to inspect and isolate each individual apartment being
serviced by that branch from common areas.
With respect to antenna positioning, residential apartments typically have very confined false
ceiling space due to the number of services being run inside ceiling cavities, such as plumbing,
air- conditioning and electrical. The confinement and density of these services is regularly
identified as a significant cause of PIM and therefore careful consideration of this is
recommended at the design stage and during installation.
5.2.2 HOTELS
With respect to addressing coverage requirements inside Hotel rooms the design
considerations for residential and serviced Apartments can be applied. However, experience
suggests that typically corridor mounted cabling and antennas should provide sufficient
coverage to most hotel rooms. Where antennas in Hotel rooms are required, ideally the DAS
should be configured so each room has a unique feed accessible from common areas of the
building which can be physically isolated from the remainder of the DAS. However, as
access to Hotel rooms do not have the same restrictions as residential apartments, branch
cabling design has more flexibility and where it is more cost-effective, branch cabling for
antennas can be run through partition walls between hotel suites rather than through
A commercial building that is not tenanted will usually require the DAS designer to use
appropriate prediction modelling that will represent the expected RF environment. Where
possible the design should include the capability for adding spare RF for future changes to
floor layouts – such as subdivision of floors, addition of meeting rooms, offices.
Due to the complexity of convention centre DAS design, it is recommended a Lead Carrier is
engaged to facilitate Carrier consultation and design guidance.
5.2.5 STADIUMS
Due to the complexity of stadium DAS design, it is recommended a Lead Carrier is engaged
to facilitate Carrier consultation and design guidance. Capacity, sectorisation, and interaction
with macro network are site specific and need to be treated carefully. MIMO is strongly
recommended for stadiums. Pitch/On-Field criteria will usually be defined by stadium
owner’s intended usage of the space and guided by the Lead Carrier.
5.2.6 AIRPORTS
Design input criteria from each Carrier may differ from general specification requirements
outlined in this document and direct consultation with a Lead Carrier is recommended to
provide direction and advice with respect to the DAS design and interaction characteristics
with external macro networks.
MIMO is strongly recommended for all metropolitan rail tunnels. Handover between sectors
should be carefully considered for continuity of service. The size of sectors will also be a
particular area of interest to ensure the Carriers can provide adequate capacity. Contiguous
performance is typically required through the length of a tunnel measured or simulated at the
centre of a train carriage filled with commuters. Appropriate modelling should be undertaken
to simulate expected RF characteristics to exceed the required performance KPIs.
It is recommended that capacity should be designed to cater for network traffic peaks which
arise due to delays caused by traffic congestion within the tunnels.
It is important to consider external macro coverage areas immediately adjacent to the tunnel
5.2.9 HOSPITALS
All hospital layouts are unique and the extent of Targeted Coverage Areas within rooms may
depend on size, layout, and construction. Access to some Hospital rooms for fault finding
and maintenance (i.e. theatres, radiology rooms, etc.) may be restricted and as such,
wherever possible, the DAS should ideally be designed to meet the Target Coverage Area
requirements inside these rooms with antennas and infrastructure placed outside (i.e. in
common areas).
Certain medical equipment may generate RF noise that impacts DAS performance and the
DAS installer may be required to relocate antennas to minimise the impact.
Providing a DAS for a building that is completed as a cold shell presents design and
installation challenges. An RF design completed without considering losses presented when
partitions, ceilings, and furnishings are later constructed may well fail Target Coverage Area
performance and quality KPIs after fit-out. To mitigate this risk the DAS designer should use
appropriate prediction modelling that will represent the expected RF environment.
Where there are lifts within the Target Coverage Area, it is recommended that antennas be
placed in the lift foyer adjacent to the lift core (with a recommended minimum of one antenna
per every three adjacent lifts). Placement of the antennas may be designed in consultation
with a Lead Carrier. RF power levels to each antenna should ideally:
High speed lifts (typically defined as a lift that travels 8m/s or two floors per second) may
require dedicated inside lift solutions to provide coverage and seamless network performance
and handover. The solution to be implemented may be designed with Lead Carrier input. It is
important for stakeholders to acknowledge that difficulty in accessing lifts and lift infrastructure
when required for maintenance may well lead to delays in rectifying faults of dedicated inside
lift solutions.
To avoid triggering undue hand-offs, sector design for the DAS should consider the impact of
lifts rapidly travelling through different sectors and the abrupt closure of lift doors.
Where there are fire stairs in the Target Coverage Area and antennas cannot be located
This section outlines the typical accommodation and provisioning requirements for carrier
equipment which should be provided by the Building Owner and DAS Contractor as part of the
design proposal.
The equipment room will usually contain the carrier’s base station and peripheral equipment
racks that will be installed and connected to the DAS. The equipment footprint per carrier will
vary based on the DAS architecture and capacity requirements of the site.
Dimensioning of the room should be undertaken in conjunction with the Lead Carrier to
ensure that sufficient space requirements have been factored into the design. Rack allocation
should also be considered for any active DAS equipment based on the design.
Rack allocations for all Carriers should be clearly shown in equipment room floor plan in the
design documentation.
For planning purposes, it is recommended that 32m² of floor area be considered a typical
requirement to cater for all carriers based on 4 Racks per carrier and 2 additional racks for
shared requirements. Carrier racks may be installed rear to wall. Standard carrier
equipment rack dimensions are as follows:
As best practice, a minimum a 300mm cable tray is required leading up to the communications
room with a 300mm wide by 100mm high penetration for COAX and Fibre access into the
communications room and continue inside the equipment room across all racks to provide
access to from above. All works should be mechanically treated to comply with building and
environmental requirements and should utilise proper edging protection/caps.
Where cabling is required externally to the communications room a tray size should be
agreed upon with the Lead Carrier.
Main Carrier accommodation will usually house sensitive telecommunications equipment and
Active or Hybrid DAS, which typically utilise remote equipment locations throughout a
property, typically require sufficient space to house several remote equipment units and
associated ancillary equipment.
Locations should be easily accessible by each Carrier with appropriate consideration for
access security, power availability per Carrier, fibre provisioning, environmental heat
management and should be undertaken in conjunction with the Lead Carrier advice.
For planning purposes, it is recommended that 3m² of wall space be considered a typical
requirement for a single sector of remote equipment.
Hybrid and Active DAS architecture equipment is usually located remotely from the carrier
equipment room. To preserve operational integrity of the DAS and mitigate risk due to
deliberate tampering or inadvertent disconnection (unplugging equipment to use a GPO,
fibres being cutover to another user etc.). It is best practice that the remote equipment is
adequately protected in the context of its installed environment.
The use of locked enclosures, captive GPO, or hard wiring for remote equipment with a key
operated power isolation switches held by the Lead Carrier may be appropriate solutions.
The most appropriate solution will depend on the environment and the circumstance and
Lead Carrier consultation can assist with this determination.
Where existing cooling or building ventilation systems are not sufficient to cater for the added
heat loading requirements of DAS and Carrier equipment, additional air-conditioning systems
may need to be provided. Where required, Active DAS Equipment and/or Carrier radio unit
equipment locations should be provisioned with air-conditioning that meets heat loading
dissipation requirements.
Heat load may vary depend on both the DAS configuration and the equipment deployed by
the Carriers and as such advice should be sought from Carriers on the anticipated loads. For
planning purposes, 12kW of cooling can be considered a typical requirement in a
main/secondary equipment room.
AC power requirements for a DAS and associated Carrier equipment will typically depend on
the type and location of equipment. As a guideline, for an installation that has all DAS and
Where DAS equipment (Hybrid and Active architecture components) and Carrier equipment
are housed in remote locations, each location will typically require individual assessment for
AC Power requirements. One Single phase captive outlet per remote unit is typically
required.
Essential Power is typically not required in the main DAS equipment room or any remote
location however, it is preferred to underpin continuity of service.
Any remote active DAS Equipment or Carrier radio unit equipment which is not connected to
auxiliary power will not be available during power outages unless the requirement is factored
into DAS design.
In cases where more robust communications service levels may be specified or required
(such as tunnels, hospitals, or other critical infrastructure environments), the Lead Carriers
should be engaged to co-ordinate auxiliary power solutions. These solutions may involve
shared use of building generators or in some cases more battery strings (which will have floor
loading implications).
As indicated above, special consideration for provision of backup power to remote active
DAS Equipment or Carrier radio equipment should also be addressed where there may be an
expectation of continued mobile communication during power interruptions.
Essential power, components, and cables (both communications and power) should be
connected to a compliant earthing system as per AS/NZS 3015.
Any essential power installation that includes batteries should provision the environmental
requirements set out in AS/NZS 3015 (i.e. ventilation). This should be considered for all
Carriers reserve technology choice.
Electrical engineering designed solutions may be required for larger installations such as
stadiums.
Building “lead-in” optical fibre conduit access should be provided from the carrier equipment
room to the nearest fibre access point (FAP) outside the premises for mobile carriers to
connect their radio base station equipment to their respective networks.
The conduits should be sufficient to support independent fibre for each carrier.
The designer ideally should consult with the Carriers to confirm the requirement for a
standalone GPS installation.
Where required, the DAS design should incorporate a direct cable path from the equipment
room to a viable, unobstructed, GPS antenna position outside the building. The design
should clearly articulate the length of the cable run and identify those which are >180m as this
poses a risk for local GPS synchronisation issues.
In some cases, it may be more appropriate for the DAS Contractor to install cables for GPS
antennas and in those circumstances the DAS Contractor should identify the specific cabling
requirements of the Carrier/Carriers. GPS antennas will typically also require the GPS feeder
to be earthed (lightning protection earth).
Cables should be left coiled and protected at both ends with sufficient excess cable available
to allow for termination into carrier base stations and the GPS antenna.
Best practice and the accepted method for combining signals onto a common Passive DAS is
by way of a Multi-Network Combiner (MNC). These combiners are generally available with
four input ports, and four output ports. Output ports connect to DAS segments and each
output port carries a composite signal that is a combination of all the connected Carrier
signals at the input ports.
It is recommended that a single MNC input port should be utilised per operator. The fourth or
spare unused MNC input port should be terminated with a suitable load and utilised for
testing purposes. Unused output ports require termination with an appropriate load.
IP3
MNC OP3
Carrier 3 Segment 3
tttttttt
Maximum composite RF power per MNC input port Within MNC manufacturer’s specification
These levels should ideally be used as the basis of the link power budget, maximum signal
level limits and EME design requirements.
It is typically the responsibility of the Carrier’s to connect their base station equipment to the
MNC and the DAS design should incorporate the accommodation requirements as per
Section MAIN CARRIER EQUIPMENT ROOM REQUIREMENTS 5.4.1.
The MNC and all Carrier base station equipment should be co-located in a main equipment
room that will require appropriate dimensioning to provide a single common location for all
the DAS equipment.
In circumstances where building constraints result in a main equipment room dimension that
cannot accommodate all Carrier equipment, then some of the Sharing Carrier equipment may
be accommodated in a separate room with coaxial tie cables provided (supplied and installed
by the DAS Contractor - typically 7/8inch feeder) between the MNC and the separate Sharing
Carrier equipment location for connectivity. Due to cable loss, the separation between the
MNC and Sharing Carrier equipment is limited to 15m. Secondary equipment rooms will
have the same requirements as the main equipment room as per Section MAIN CARRIER
EQUIPMENT ROOM REQUIREMENTS 5.4.1.
A Lead Carrier can provide recommendations on all Tie Cable/Fibre connection requirements
and advice on alternate solutions if necessary.
It is best practice that the design should provide a duplex input port for each Sharing Carrier
for each frequency band which is being deployed. The combined RF power level at the point
of interconnect should not exceed the DAS Equipment manufacturer’s specification.
Most Hybrid and Active DAS solutions share common radios between all connecting Carriers
to minimise the physical site footprint. It is recommended designers consult with the Lead
Carrier to implement a power sharing approach appropriate for the specific DAS technology
used.
With most technologies it will be optimal to share radio power with an equal power spectral
density (Power Spectral Density, measured in W/MHz) allocation per connected Carrier. A
total composite power based on equal PSD will then be allocated per port, per spectrum band
for each Sharing Carrier. The final power output of the radio should also be adjusted to meet
EME and KPI design constraints.
This ideal approach facilitates the implementation of a single RF design per spectrum band
for all Sharing Carriers and efficiently allocates radio hardware.
Spectrum bandwidth used in the power sharing calculations should be based on current
ACMA licence holdings for the location.
The maximum radio power share per port, per spectrum band is calculated as:
See the table below for an example calculation for a single band.
All DAS must be designed as per requirements in AMTA RF Safety Program Document
“EME Compliance for IBC and DAS” which is located in RFNSA document section as follows:
The onus remains with the DAS Contractor responsible for the design and build of the DAS to
ensure compliance with the latest standards.
It is recommended that designers familiarise themselves with the environment in which the
DAS will be installed, taking note of any potential EMC issues that may arise, or any local
rules imposed on the use of radio transmitters.
Designers are recommended to be aware of the impact that Radio Frequency Interference
may have on various types of equipment, particularly when designing a DAS in hospitals or in
locations where there may be explosive atmospheres or devices.
AMTA has produced a guideline to help designers assess the impact of Radio Frequency
Interference in the above situations titled, “7.11 Interference and ignition hazards from mobile
base stations”.
This is available on the RFNSA Documents section under the RF Safety Program.
5.7.1 RF LEVELS
It is recommended that the DAS should provide dominant coverage within the Target
Coverage Area to avoid unnecessary hand-over and/or interference to/from the external
mobile network and should also deliver high quality signal within the Target Coverage Area.
The external mobile network is typically defined as any mobile network signal
received/measured/identified within the Target Coverage Area which is not part of the DAS
itself.
Table 6 Signal, Dominance, and Quality Performance Levels for DAS, specifies the required
signal, quality, and dominance levels for various technologies. These values should be
reliably achieved and available to >95% of the Target Coverage Area.
RF levels for the DAS design will typically vary according to the location within the building.
For example, the influence of the external macro network is likely to be greatest in proximity
to the perimeter walls and windows. The DAS design should particularly ensure performance
from the DAS meets required criteria in these locations.
4G / 5G LTE / NR 5G NR
700MHz – 2600MHz 3300MHz –3800MHz
Table 6 Notes:
KPI for 95% of Target Coverage Area.
5G NR Reference Power based on 30KHz sub-carrier spacing.
Equal power spectral density (W/MHz)/Equal Coverage per operator across all bands, refer
Section 5.5.4.
DAS signal levels at a distance 6m outside the building at 1.5m above ground level from the
IBC should be low enough to ensure dominance by each Carrier’s macro network.
As per Section 7.5.1 any Target Coverage Area Exemption Zones should be clearly
documented by the DAS Contractor with reasoning on all relevant floor plans.
It is best practice that the return loss of each Passive DAS segment connecting to a multi-
network combiner should be ≥ 16 dB over the operating frequency bands. Where a DAS
segment is comprised of multiple branches connecting to a DAS segment, the connection
points to the branch should each also individually comply with the above performance
requirement.
In its installed operating position, it is recommended that the antenna’s EME compliance
boundary should not extend or encroach into locations normally accessible to the general
public.
For more details, refer to AMTA RF Safety Program Document, “EME Compliance for IBC
and DAS” in Section 5.6 of this document.
It is recommended that Antennas should always be installed as far away as practical from
metallic items that may affect their radiation pattern or cause PIM issues. They should also
be mounted as far away as practical from items that will affect their radiation pattern.
When flexible tails are supplied as part of the antenna, patch leads should not be used to
connect the antenna to the feeder.
It is recommended that concealing antennas for aesthetic reasons inside a ceiling space
should be avoided as the resulting reduction in RF performance will increase antenna
quantity requirements and therefore increase cost and will impact maintenance/fault finding.
Ideally, there should be no objects within 600mm of the antenna. In practice, locate antennas
centrally in or on a ceiling tile to maximise the spacing from the supporting grid and place as
far as from ductwork, cable trays, emergency lighting, door openers, etc.
It is recommended that the metal ground plane of the antenna is insulated from any metal
ceiling tiles, by using an insulating disc, insulated standoffs or in some cases the radome of the
antenna may provide an effective stand-off if it wraps sufficiently over the edge of the ground
plane.
Antennas which have a non-metallic securing nut are preferred in this situation. When screws
are required to secure the antenna to the ceiling, use non-metallic screws, nuts, and washers
(nylon or similar).
When mounting Access Points for Active DAS systems the structural integrity of the mounting
surface needs to be considered in relation to the load bearing capabilities.
To minimise wideband noise, best practice is to identify possible wideband noise sources at
design and during installation and allow the DAS antennas to be located with enough
distance from interference sources to ensure a low noise floor in the cellular bands.
Distances greater than 1m from obstructing or interfering objects such as lighting and cabling
can typically minimise signal noise. The sources of wideband noise can be many and varied.
Fortunately, levels of interference from most of these devices falls away with distance so it
can often be simply managed using separation. In cases where it is not able to be managed it
may be necessary to change the offending device. This may be a LED light incorporating a
SMPS or a better quality of cable.
The components should be installed a position that is accessible for future maintenance.
Both the component and cable should be secured to the riser wall or tray.
Components should not be installed with support only by the attached cables.
It is best practice that adaptors should never be used to connect cables or components
together.
The DAS designer should propose the jumper length and suitable cable type at the design
stage to ensure insertion loss has been considered as well as practicality of installation.
It is recommended to use jumper cables with 4.3-10 Male connectors at both ends that are
from the Carriers approved hardware list.
Normal practice is to put a loop in the jumper cable to minimise stress being placed on the
connectors and to make it easier to disconnect components.
IMPORTANT: If jumper cables have not been specified in the design but they are used
during installation, the as-built configuration should be recalculated and reassessed by the
designer as it may have an adverse impact on the original design due to extra insertion
losses.
It is recommended that all backbone feeder cables should run to the equipment room and be
terminated with connectors that meet the approved equipment requirements.
If it is necessary to stack cables on top of each other, any cables that have connectors on the
end should be installed in a manner that allows future access to the connectors.
The backbone cables should be secured to the cable tray at intervals not exceeding the
manufacturer’s maximum distance between supports and preferably using nylon cable ties.
When running feeders in cable trays, appropriate separation distances from existing services
should be maintained to avoid interference - both physical or otherwise.
Fire-proof sealing should be applied at all penetrations where a cable crosses a boundary
from one fire control region to another, such as from a riser into a floor area. Watertight glands
should also be installed where necessary.
Branch floor feeder cables run in the roof space should be installed in a manner that
minimises the potential for damage if fit-out changes are made. The preference is for coax
cables to be supported on a catenary, secured in cable trays, or mechanically fixed to the
concrete slab.
Fibre optic and electrical network cabling is not as resilient as coaxial cables and therefore
support and management is critical to ensuring functional longevity.
As best practice, fibre optic cables (including hybrid power plus fibre cables) need to be
physically secured and protected, and ideally separated from other cabling. Fibre optic and
hybrid cables should be supported and affixed to cable trays/ladders, or in conduit that is
suitable affixed to building components. Catenary wires do not provide sufficient stability for
fibre cable support and should not be used.
Cables to remote units should be terminated into a small patch panel housed in a termination
box fixed to either the ceiling or another permanent structure that provides suitable support
and protection. Pigtails should be spliced onto the end of the fibre and terminated in the box.
Jumper cables should be used between the termination box and the remote unit. The patch
ports should be labelled as per the corresponding patch panel port in the main equipment
room.
An acceptable alternative to using fibre patch cables is to splice flexible cables directly onto
the end of the fibre. Where this solution has been applied, the splices should be done in a
splice box.
It is best practice that all installed cable and components should be labelled clearly with DAS
identification as follows:
Labels should also be attached on or close to each component. Labelling stickers should not
be placed on the radiating element of the antenna or on the component identification plate.
Labelling stickers should be placed on radiating cable in accordance with the spacing
intervals indicated above.
All feeders should be identified at both feeder entry/exit points with a label containing a
concise identification code uniquely identifying each cable and cross-referenced to the
system drawing. Identification labels should be provided by the contractor.
Typically, interference due to PIM presents as an elevated noise floor on a cellular base
station which can inhibit proper use of the system. Whilst this noise cannot always be “heard”
by end users, the sensitivity of the base station receiver is adversely impacted with the
consequences of reduced coverage, increased call drops and decreased data throughput.
PIM can be generated anywhere in the RF path. The RF path includes not only the antenna
feed system but also includes the antenna itself, as well as objects excited by the antenna.
POOR WORKMANSHIP
During construction, care should be taken to avoid mechanical stresses on RF connections,
so they do not create PIM sources over time. Proper mounting of components to a support
structure and the use of stress relief in the cabling will assist in long term PIM performance.
The following list provides recommended guidelines for minimising PIM in DAS installations:
7 DELIVERABLES
For efficiency, the DAS Contractor should ideally provide the Lead Carrier with all
preliminary/detailed design documentation for review.
Submission of DAS information to the Lead Carrier should be through soft copies of all
drawings, documents, and test results.
It is best practice that all files should be submitted completely unlocked in their original
software production form, so they are editable by the Lead Carrier for future modifications to
the DAS. For example, the power budget spreadsheets can be updated with the addition of
extra technologies or channels in the future using the original file. The Carriers should provide
editable link budgets, but this does not include specific IP. Carriers may decide to share
power budgets.
If a DAS has been designed in specific software (e.g. iBwave™ or equivalent planning tools)
those format files should ideally be provided.
Where CAD has been used for design, the drawings should also be supplied in AutoCAD
format and be made available to the Lead Carrier. In cases where CAD files are not available,
documentation should be provided in high resolution PDF.
The DAS designer may submit preliminary DAS design documentation to the Lead Carrier for
confirmation of design acceptability prior to progression to detailed design. For efficiency, the
preliminary documentation should ideally contain all relevant related information to address
the following:
The DAS designer may engage a Lead Carrier to review a detailed design prior to any
installation works commencing. In order to facilitate the efficiency of the review, it is
recommended that the following information be submitted to the Lead Carrier. The industry
expectation is that this design will be “for construction” and will not deviate substantially from
final as-built design.
These details are a combination of generic installation practice and fabrication drawings and,
where required, will also include structural engineering and details for unique installation
scenarios at a site. Drawings should provide installation related information, enough for
actual installation works to proceed.
Where required include all aspects of civil engineering design work including the following:
• Specification of AC power outlets for all AC powered equipment specified in the DAS;
• Security materials and installation specifications and details in accordance with
requirements of Section 5.4;
• Design and specification of the protective earth systems including lightning finials on
the antenna support structures for all externally installed antennas; and/or
• DAS and EME Signage and Labelling specification, location, and fixing requirements.
It is recommended that the following information be submitted in a final package to the Lead
Carrier to achieve acceptance and handover of the DAS.
It is recommended that the final DAS commissioning report submitted pursuant to Section 7.4
above should provide the following:
Any Target Coverage Area Exemption Zones with CW Walk Test Report
reasoning shown on floor plans
All sweep results (Return Loss – RL and Distance to Certificate of Compliance that all sweeps
Fault – DTF) Pass
Any configuration settings for Active systems As-Built Pack and design files
2. Serial number;
7.5.3 RF SWEEPS
It is recommended that all RF cables used in the DAS should be swept / have a return loss
measurement performed across all frequency bands indicated in Section 4.3.
Where a design tool model has not been utilised, the measurements should also be recorded
in a spreadsheet summarising all measurements made with cross-referencing to the relevant
cable number provided in the result.
The date (DD/MM/YYYY) of all measurements should ideally be included in the supplied
spreadsheet.
It is recommended that all cables should have a distance-to-fault test performed to validate
the installed length of the cable using the distance-to-fault value. The actual installation
values should be utilised to update the design and recalculate in the as-built documentation
to demonstrate it has not adversely impacted the design. The data relating to feeder length
should be updated in the As Built and Link Budget.
• Be recorded in a similar format as per the diagram below and should include the
cable number in the title.
• Be performed on each individual feeder cable, without other passive devices, jumpers
or antennas connected.
• Have a suitable termination load placed on the far end during test.
• Display the date and time the test was performed and the calibration status of the
instrument during the test.
• Return Loss limit line configured to represent the manufacturers specification for the
component under test.
• Instrument be set to measure 2000 data points or higher for resolution.
Testing a Passive DAS should commence with a PIM test of the MNC as an integrity test only
and no results typically need to be provided as part of the test report deliverables.
PIM tests should be provided as part of the handover documentation are conducted on all the
inputs of the multi-network combiner with all segments connected. Unused output ports will
require termination into a precision load. Figure 9 shows the test configuration for Input 1
and Table 8 shows the PIM test parameters that apply. The test should be performed with the
antennas connected to the DAS segment under test and ensure EME precautions are
followed.
For a Hybrid DAS, test results should be provided showing reflected third-order PIM
measurements taken from the input of each Passive Segment of the DAS connected to a
remote unit (at the most forward location from the remote unit and after any filtering/band-
specific componentry). Table 9 shows the PIM test parameter that apply and are based on
per channel power levels.
Where PIM tests are conducted on points in the DAS other than the MNC input these tests
should be conducted at power levels that consider the applicable losses at that point. For
example, if a PIM test is undertaken for trouble shooting purposes into a DAS segment on
the output side of the MNC, then the ~6dB loss through the MNC needs to be accounted for
and the test tone power levels will be as per Table 9.
Equally, where a DAS segment has a lower proposed composite input power the PIM test tone
power should be reduced accordingly and a target ≤ - 140dBc pass achieved.
PIM testing should be conducted with a device that validly calibrated. The measurement
should pass with a duration of 10 seconds or greater (e.g. PIM Vs Time for 10Sec). The DAS
installer should provide the original PIM test result files as part of their handover documents.
Testing PIM at high band is optimal if possible, however testing at 2600MHz while not testing
PIM at 3500MHz is acceptable.
It is recommended that walk survey readings be plotted against final versions of building floor
plans that have DAS antenna locations overlayed.
A scanner and test transmitter (CW signal generator) should be used at the highest
frequency band proposed in the DAS system and using proposed operational power levels.
Walk survey tests of MIMO DAS system elements requires a different methodology to SISO
DAS system tests to ensure validation of both MIMO streams. Typically, this can be
achieved by either using two different test frequency inputs and providing a walk test scans
that captures both, or by testing each MIMO stream in two separate walk tests.
It is recommended that the walk test route cover all trafficable areas of the building and pass
under each antenna to capture antenna transmitting signal levels.
The walk test route should specifically demonstrate DAS performance meets or exceeds the
performance requirements for >95% of the Target Coverage Area (apart from in any agreed
Exemption Zone).
It is best practice for the walk test to ensure that the colour scheme used can clearly highlight
where a DAS passes and fails the required KPI’s.
It is best practice for the results for walk tests to be recorded using a graduated and colour
coded snail trail – as per the example shown in Figure 10.
For efficiency, the log files for these tests should be supplied to the Lead Carrier. This will
typically be uploaded to a web-based file server which is accessible by the Lead Carrier.
Files should be in readable format without the need of any program processing, and they
need to include a summary of the DAS performance.
It is recommended that OTDR/Link Loss measurements be completed on all fibres (used and
spare) to confirm the integrity of the cable link without including the performance of the end
connector/pigtails.
Link Loss (LL) is measured at 1550nm and/or 1310nm and the measured link insertion loss
should be less than or equal to theoretical calculated maximum insertion losses as per
manufacturer’s specifications. Test results for all fibres are to be documented showing
theoretical and achieved levels along with the current calibration date/status of all used.