Final Presentation of Eng Aly Salah
Final Presentation of Eng Aly Salah
M-36 GL Badri
Shoab Ali Helal
M-1
CURRENT FLOW
26 MMSCFD
U-103
MAX. U-102
8’’ BSUL MAX.
54 MMSCFD
T.G 60 MMSCFD
16’’
U-104 8’’
CURRENT 80-100
MAX. 170 MMSCFD
SUCO
SALES GAS TO GASCO MAX.
CURRENT FLOW 16’’ 70 MMSCFD
EBGDCO 16’’ NEW TIE-IN 20 MMSCFD
Min.
50 MMSCFD
Proposed mode of
operation in RED color
C/F 30 MMSCFD
U108
Max. 144 MMSCFD
8``
AMAL Feed Gas Inlet Separator Main Compression Area
C/F 70 MMSCFD 16`` Drying & Sweetening Area
4 Units, Max. Capacity 220 MMSCFD
6 Molecular Sieves beds, Type 5A
plant pressure 49 kg/cm2
Diethanolamine Unit
C/F 60 MMSCFD
SUCO REMOVE H2S & H2O
Max. 70 MMSCFD
Condensates Tanks
2 Floating Roof Tanks
Fractionation Area
U104 Flow Diagram
FOR SPLITING CONDENSATE
Capacity 38,000 bbl AND LPG
Plant Design Data:
Amal 8”
SDV1955A
Amal 16”
U-108
U-101
8-ESD 711
Header pipe
SDV 1952 U-102+SUCO
U-103
SDV1950
CURRENT Measured
16’’ P/L
FLOW GASCO 16”
U-102 by Suco is 70 MMSCFD U-104
MAX. CURRENT
80 MMSCFD MAX. 170 MMSCFD
14’’ P/L
CURRENT FLOW
160 MMSCFD
FT
10’’ P/L
10’’ P/L
Flow computer FT-200
@ U104 Site
100 mmscfd GASCO
JULY 10 FUEL GAS
( SALES Gas for T/G 3 MMSCFD
0.8 mmscfd ( U103 Fuel Gas) )
For U-104 & EBGDCO NGL 2.5 mmscfd Morgan water flood
190Ton/d propane
Sales To EBGDCO
U-102 FUEL GAS 1MMSCFD Gas Plant ( U-104 ) 160 MMSCFD EBGDCO 5 Ton/d Butane
170 MMSCFD
U-103 TO T/G 5 MMSCFD
SUCO 60
MMSCFD
SHRINKAGE GAS : 10 MMSCFD
Amal 70 MMSCFD 190 MMSCFD
Gupco 60 MMSCFD
2PIC 301
LIC 701 and 702: a liquid level controller indicates the height of liquid
level inside the vessel and controls it according to the operating variables.
Flare Line
From V109
Suc.Booster
LPG Tanks
2pv301
4-HV1104
HV 1108
V109 liquid 4v-102A
PSV
1903A
From T.c.u
ESD-1901 4V-102B
1903B
2SDV 1902 fl
Mist Extractor
Baffle 4
4v1
TO Main ph 1
weir
4V-101
OIL Start up fuel
condensate
H2O
Water
2lv-701
2lic 702
Lablare tank
CD Suction 8-v80
Flare Line
Suc.Booster 1960B
tcu
HIC 1102
V-109 1961B
OFF SPEC LPG
-
PSV 4-W1A
PSV
ESD-1954
PV301
1960A
ESD-1953 4-W1B
1961A
To Main
ph 2
Man Hole
Mist Extractor 4-V101
Baffle
T.C.U
From 4-V15
weir
4V1 FLARE
Condensate
condensate Start up fuel
H2O
U-108
4-T I Water
flare
2LV-4001
Lv-700
Flare
C.D
O.D
T.C.U 4V201
U-108
P kg/cm2 6 18 18 46
T C0 20 103 32 129
Process
P kg/cm2 6 18 18 50
4 - E2 A
SDV 1963A
Gas to Dehydration
Phase I
4 - E1 A Flare
Train A
SDV 1962A Gas from
4-W1A 4-C1A 4-C1B
FIC
101A Condensate from 4-V2B
LV 732A
To 4-P57 Discharge
CD 4- V 3A
4- V4A
4- V2A Set at59 Kg/Cm2
Set at 6.8 Kg/Cm2 Set at 20 Kg/Cm2 To 4-V3B liq. Outlet line
Gas from 4-V4 A/B
2SDV 1905A
2SDV 1942A 4-A102A
Flare
Gas to Dehydration
Phase II 2SDV 1906A
Train A 4-A101A 4-E102A Gas from 4-C101B
Flare
4-W101A 4-C101A
Condensate from 4-V102B
2FV
103A
From 4-P57 Discharge
2-LV
703A
4-V102
4-V103
To 4-P57 Discharge
4-V104
2SDV 1903A
2SDV 1941
2-LV 706A
2FV 181A 2-LV 703B To T.C.U
CD 4-V104A
4-V102A 4-V103A
Set at 20 Kg/Cm2 To 4-V103B Set at59 Kg/Cm2
Set at 8 Kg/Cm2
liq. Outlet line
• Drying Area
Drying Area
• N.G comes from main compression area (V4,V104
A/B) into inlet separators V43,V143 in every
phase from which condensed H.Cs leave from
bottom back to V1,V101, from the top N.Gas leaves
to a three beds of molecular sieve in every
phase(D1 , D101 - A,B,C ) - In parallel .
• N .Gas inter the beds from the top against its
nature-down stream the beds- for more contact
with M.S beds .
Drying Area
• After adsorption of H2O,H2S on M. Sieve sweet
gas leaves the bottom of beds to dust filter
(F17,F117) which filter it molecular sieve dusts
resulted from corrosion .
• Apart of sweet gas taken for regeneration of beds,
the other go to chilling area .
Regeneration
• This stage is done by a fraction of dried, sweetened
gas
( 23-26 MMSCFD ) taken from F17,F117 to C5A/B ( to
drive the Reg. Gas in the Reg. cycle )after that to M.S bed
under cooling.
Regeneration Gas Conditions
• Heating Reg. Gas inter M.S beds from its bottom
at about 300C and leaves at less than 240 C.
MDV4001
4-C1A\B
4003
4005
4-V43
4-E3 RDV4007
FV-108 4009 4011
Lv-4001
flare
4-D1A 4-D1B 4-D1C
FV-4003
FV-4011
MDV4002
Amine
4012
4004
4006
4-f17
4008
4010
unit 4C3
FV-4006
FV-4015
FV-4017
4005
4009
4003
4007
fl
4001
4011
BDV4001
2FV-4012
4-H1D
2FV-217
4-V143 4-D101B C103
D101A D101B D101C
FV-4018
FL
4002
ESD1907
4004
4008
4006
4012 2F117
CD DBB
Amine Unit
Process Description
• Cooled and scrubbed gas from 4-V15 enters the
amine contactor and also lean amine is
pumped from the top tray to remove sour
components.
.
Acid fla
flare PV-4027
4-E23
4-E24
Fv-4002
4-P46A/B To acid flare
Lv-4008
4-V37
Re Amine
V39
Lv-4005 4-v40
Skimmer 4-v38
4-f18 water
4-P47A/B
4-p49
LV-4006 4-E25
SOUR GAS
Lv-4004 4-f19
TO FLARE LIQUID HC
4-H9
FV-4007
INLET DRYERS
Fv-4009
4-P48A/B
Lv 4003
t.c.u
Fv-4008 To Sump Tank
• Gas Cooling and Expansion
• Gas Cooling and Expansion
• The sweet gas from molecular sieve unit are chilled in heat
exchangers and turbo expanders to separate the butane
component in the H.C liquid.
• At Phase II:
• Plant feed gas is lean: Low pressure gas from 4-V108A/B is
increased; Increase flow rate to 4-E104 A/B by closing
2HV-1102 A/B.
• Plant feed gas is Rich: High pressure gas from 4-V107A/B
is increased; Increase flow rate into 4-E105A/B by opening
2HV-1102 A/B.
• It is important to maintain minimum temp. at 4-V107A/B
and 4-V7 A/B to obtain a good butane recovery rate.
Control of Chilling Area:
• Flow controller in the expander bypass line (J.T valve) is
activated automatically in case the expander is shut down
by one of its safe guard's circuits; and also 2SDV valve on
the recompressor by-pass line and the PCV on the outlet
line of the L.P separator are opened automatically to flow
the lean gas toward booster compressor.
• Anti-Surge recycle control system is provided on
expander/compressor. If the compressor operation point
approaches the surge limit, the discharge gas will be
recycled to the suction.
Gas Cooling and Expansion
The Difference between PH-I I& PH-II:
• Cooling gas in phase I takes place through Heat
Exchangers in series while in phase II cooling gas
takes place in Heat Exchangers in parallel.
Recomp.bypass
4-E104A1
4-E104A2 4-E106
4-V-107A/B
HV 1101A/B
FV-109A/B
4-
4-V109
SDV 1915A/B
HV-1103A/B
fv114A/B
CF
FL
SDV-1917
SDV-1913
E105A1/B1 SDV-1918
SDV-1914
SDV-1912
4-V108A/B
HV1102A/B
E105A2/B2
.
Main Feed to Depropanizer
FV-112A/B
Booster Suction
4-T101
LV-712A/B
4-P112A/B/C
• FRACTIONATION AREA
FRACTIONATION AREA
Propane Refrigeration
FL
4
4-E105A/B-HI PRES.
A
4
4-E5 A/B.HI PRESS.
4-V109
PI-316C
57.2 kg/cm2
FUEL GAS
E8A
TI-24C 2TI-25C
98 C 53 C
M
PZ-317C PZ-317C
81 % 4-C4A
TI-23C
FI-106A 39 C
48 mmscfd
TI-22C FV-106A
PI-315C 100 C
30.2 kg/cm2
LEAN GAS
C3A/B CW CW C4C
DSCHRG
C104A/B
SUC
E7A
V16A LV-733A
BD