GIS - I & D - Final Fesiblity Report - Augast .2021 - V0
GIS - I & D - Final Fesiblity Report - Augast .2021 - V0
VOLUME IV – ENGINEERING
AUGUST, 2021
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
August, 2021
Issue and Revision Record
Descriptio
Rev Date Originator Checker Approver
n
This document has been prepared for the titled project or named part thereof and should not be relied upon or
used for any other project without an independent check being carried out as to its suitability and prior written
authority of Ethiopian Construction Design and Supervision Works Corporation (ECDSWC) being obtained. The
corporation accepts no responsibility or liability for the consequence of this document being used for a purpose
other than the purposes for which it was commissioned. Any person using or relying on the document for such
other purpose agrees, and will by such use or reliance be taken to confirm his agreement to indemnify ECDSWC
for all loss or damage resulting there from.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
TABLE OF CONTENT
TABLE OF CONTENT................................................................................................iii
LIST OF TABLES....................................................................................................... vi
LIST OF FIGURES.................................................................................................... vii
ABREVATIONS AND ACRONYMS..........................................................................viii
EXECUTIVE SUMMARY.............................................................................................x
1.0 INTRODUCTION.................................................................................................13
1.1 Objective..........................................................................................................13
1.2 Scope of Work.................................................................................................13
1.3 Project Location...............................................................................................14
1.4 Climate............................................................................................................ 16
1.5 Topography of the area...................................................................................16
1.6 Methods and Approaches................................................................................19
2.0 REVIEW OF THE PREVIOUS STUDIES............................................................20
3.0 INTERPRETATION AND USE OF OTHER SECTORAL STUDIES AS DATA
SOURCES................................................................................................................ 22
3.1 Summary of Soil and Land Evaluation Study..................................................22
3.1.1 Soil Texture..............................................................................................
3.1.2 Soil Structure...........................................................................................
3.1.3 Bulk Density.............................................................................................
3.1.4 Infiltration Rate and Hydraulic Conductivity...........................................
3.2 Land Suitability Evaluation...............................................................................24
3.3 Water Resources.............................................................................................27
3.3.1 Water Quality...........................................................................................
3.2 Depth of Groundwater and Chemical Characteristics......................................33
3.4 GEOTECHNICAL INVESTIGATIONS.............................................................38
3.4.1. Geotechnical investigation result on Main Canal route (MC)....................39
3.4.2. Geotechnical investigation result on primary canal route (PC-1)..............40
3.4.3. Geotechnical investigation result on primary canal route (PC-2)..............40
4.0 CROP WATER REQUIREMENTS......................................................................41
4.1 Reference Crop Evapotranspiration (ETo)......................................................41
4.2 Crop Coefficient (Kc).......................................................................................42
4.3 Crop Evapotranspiration (Etc).........................................................................43
4.4 Effective Rainfall (Pe)......................................................................................44
4.5 Net Irrigation Water Requirement (IWRN).......................................................45
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
LIST OF TABLES
Table 1.1 Summary of the climatic condition of the project.......................................16
Table 3.1 Extent of the soil mapping units in the survey area...................................22
Table 3.2 Physical properties of the soil mapping units............................................24
Table 3.3 Summary of Land Capability Classes of the Survey Area........................25
Table 3.4 Suggested criteria for irrigation water use based upon electric conductivity
(Salinity classification based on United States Salinity Laboratory guide (USSL,
1954).).......................................................................................................................30
Table 3.5 General classification of water sodium hazard based on SAR values......31
Table 3.6 Chloride classification of irrigation water...................................................32
Table 3.7 Water quality status of Gongola River.......................................................33
Table 3.8 Summary of investigated locations of ground water potentials, aquifer
depths, yields and levels...........................................................................................34
Table 3.9 Summary of Groundwater Depths and Physio-chemical Parameters within
the GIS Command Area............................................................................................37
Table 4.1 Guyuk - Climatic Data and Refence Crop Evapotranspiration (ET0) 42
Table 4.2 Length Growing periods (LPG) and Crop Coefficient (kc) for seasonal
crops......................................................................................................................... 43
Table 4.3 Guyuk Irrigation Scheme -Crop Water and Irrigation Requirement...........48
Table 5.1 Recommended furrow lengths for different soil types, and depth of
irrigation 48
Table 5.2 Range of available water holding capacity of soils....................................50
Table 5.3 effective root zone depths of some common crops...................................51
Table 5.4 TAW values for different soil textures and root zones..............................52
Table 5.5 Possible Irrigation Intervals for Effective Root Zone of 60 cm...................53
Table 5.6 Possible Irrigation Intervals for Effective Root Zone of 90 cm..................53
Table 5.7 Possible Irrigation Intervals for Effective Root Zone of 120 cm................53
Table 5.8 Possible Irrigation Intervals for Effective Root Zone of 180 cm................54
Table 5.9 Summary of Irrigation Interval and Irrigation depth..................................54
LIST OF FIGURES
Figure 3.1 Land Capability Classification map of Guyuk Irrigation Scheme survey
area 26
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
EXECUTIVE SUMMARY
This draft detail design report of irrigation and drainage systems is
prepared and compiled as part of the sectorial feasibility and detail
reports studied for Guyuk Irrigation Scheme. The report is prepared in
accordance with the terms of reference given particularly to the irrigation
and drainage system study and design. The study has been conducted
with consideration of the previous studies and the present relevant
sectorial studies of the scheme.
The previous study, prefeasibility study for GIS, 2014/15, proposed the
extent of gravity and pumping command areas; recommended site for
diversion head work, determined length of the main canal and the point at
which it ends and bifurcated in to left & right sides of Gongola River,
crossing is required for the left canal to cross Gongola River. But the
proposals of the previous study have been revised depending on the
planning of irrigation and drainage infrastructures’ layout, which has been
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
produced using data obtained from topographic map, frequent field visits,
and the assessment of different sectoral studies.
GIS irrigation and drainage system layout has been prepared from a contour map
of 0.5m 0.75m,1.0m and1.25m intervals produced from a detailed topographic
survey of the scheme area. The layout comprises canals to provide and
distribute the irrigation water; drains to collect and remove excess
irrigation water and surface runoff; roads to facilitate mobilization within
the farm area by the farming community, to supply inputs and collect
harvests and to facilitate the implementation and supervision of the
structures. Naming and numbering of canals according to their locations
and sizes has been made, which is assumed to be helpful for identification
during construction, operation and maintenance stages of the system.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The capacities of canals to convey and deliver the required water from the
source to the field have been calculated depending on net irrigable area,
the maximum duty water requirement, flexibility is considered for only
main and primary canals, due to shortage of water resource. The net
command area of the scheme area for gravity irrigation system is
8163.24ha.
The main canal at its end bifurcated in to two primary canals, the one run
to the left & the other to the right side of Gongola River.
To protect the command area from damaging internal and external floods,
proper drainage facilities have been arranged. The infield drainage
systems collect excess irrigation water and runoff from the command area
and dispose them in to the natural gullies used as collector drains. The
interceptor drains protect the external flood coming from the catchment
area. There are thirteen interceptor drains, which are aligned nearly
parallel to the primary canals to divert the external flood to the natural
drains. The interceptor drains are made of dikes and/or excavated
channels depending on the topography of the respective alignments. The
intensity – duration – frequency curve of GIS has been used to estimate
the drain duty while the flood catchment area has been estimated from
topo-map of the scheme area.
The hydraulic structures are designed for irrigation and drainage system
to effectively and efficiently convey, regulate and to protect the system
from storm runoff damage. Cross drainage structures: - syphon, aqueduct
and drain culverts are designed based on topography and stream sizes to
pass the storm water runoff either under the canal or over the canal. The
regulating structures are cross regulators, head regulators, pond intake
for regulating and dividing flow. In addition, fall structures to dissipate
energy wherever necessary, road culverts, bifurcation, escape & sluice
structures are also designed as part of the system.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
1.0 INTRODUCTION
The Federal Government of Nigeria has given greater emphasis on the
proper use and development of available land and water resources for
irrigation, power and other water related activities and thereby improves
performance of agriculture, energy and other relevant sectors. By the
principle of Integrated Water Resources Management (IWRM), the Federal
Ministry of Water Resource (FMWR) has identified and selected some pilot
schemes to be considered for support in the rehabilitation, expansion, and
development of irrigation. For the proper management and
accomplishment of the selected pilot schemes, the FMWR has established
a project dubbed “Transforming Irrigation Management in Nigeria
(TRIMING)”.
Guyuk irrigation scheme is one of the areas selected for the purpose and
hence TRIMING has assigned ENVIPLAN International Limited in
association with formerly WWDSE present (ECWDSC- Water and Energy
Sector) to undertake detail design for Guyuk irrigation scheme.
Therefore, this detail design report of Guyuk irrigation scheme has been
prepared as part of the assignment given by TRIMING to ENVIPLAN
International Limited in association with WATER WORKS DESIGN AND
SUPERVISION ENTERPRISE (WWDSE), the present ECDSWC (Water and
Energy Sector).
1.1 Objective
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
1.4 Climate
The climatic condition of the project area has been presented in detail
under hydrology report. Which is located within the Gongola River Basin,
one of the major west bank tributaries of River Benue, North-Eastern
Nigeria. The basin has a tropical climate characterized by two distinct
rainy and dry seasons, which is governed by the movement of the Inter
Tropical Convergent Zone or ITCZ north, and south of the equator. The
winter (November to March) is the dry season; under the influence of a
Saharan high-pressure zone, the northeastward harmattan wind brings
hot, dry air and high temperatures on to the basin. Temperature data
from NiMET and CHRS Rain sphere (2019) shows that March is the
warmest month of the year in the Gongola River basin with maximum
temperature ranging from 36oC in Jos, 43oC in Bauchi, 41oC in Gombe,
43oC in DadinKowa and 45.2oC at Yola.
Rain
Min Max Humidit Wind Sunshin Solar fall
Month Temp. Temp y speed e Rad (mm)
(0C) . (0C) (%) (km/d) (Hours) (MJ/m2/d)
January 16 34 29 59 8 19.2 0
February 18 37 26 69 7.6 19.8 0
March 22 39 34 81 7 20 0.4
April 23 39 44 94 7.3 20.8 22.9
May 23 36 59 90 7.4 20.5 59.9
June 22 34 69 73 6.7 19.1 86.5
July 21 32 73 56 6.1 18.3 114
August 21 31 76 50 5.2 17.3 166
September 21 31 77 51 6.1 18.6 165.2
October 21 33 68 48 7.6 20 64
November 18 35 41 50 9.1 20.9 0.8
December 16 34 39 51 9 20 0
Average 20.2 34.6 53 64 7.3 19.5 679.3
Source: GIS Hydrology report,
1.5 Topography of the area
The Guyuk irrigation scheme area is relatively a flat terrain along with
some rolling hills and undulating landforms. Spots of rough and hilly areas
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
affected by erosion are also observed in some parts of the project area.
The proposed irrigation area having a slope of less than 3 per cent in most
places can be described as flat and quite favorable for the development of
gravity irrigation schemes. However, spots here and there, because of
reasons related to degradation and topography might not be considered
for surface irrigation.
The elevation of the command area ranges from 228.48 m.a.s.l. at the
head of storage reservoir-3 supplied by the pump station-1 to 172.92
m.a.s.l at tail end of pc-1 command area.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The methods followed to undertaking the full feasibility study and detail
design of Guyuk Irrigation scheme include:
Review of the previous pre-feasibility and feasibility studies related
to irrigation and drainage works;
Discussions with different concerned experts of Upper Benue River
Basin Development Authority regarding the existing irrigation
structures, previous designs, and future interest of the client;
Preparation of planning and preliminary design criteria;
Preparation of the general layout of the project by generating
contour map of the command area with an interval of 0.5, 0.75m,
1.0m and 1.25 from detailed topographic survey output
Collection of primary and secondary data from different sectoral
studies of the project related to irrigation and drainage activities to
determine the suitable part of the areas for gravity irrigation;
Identify suitable alignments and locations for irrigation canals and
structures, storage facilities, drainage and flood control structures;
Preparation of detail designs, drawings, and quantities.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The study proposed the irrigation method for the scheme to be surface
irrigation (by gravity and use of pumps) with estimated command area as
indicated in Table 2.1.
Total
Savanna gross
Right Left Bank Gross area (ha)
h Sugar area
Comman Bank
(ha)
d Gross
Not covered
area(ha) Covered by
by soils
Soil Study
study
From this previous study, the following facts are summarized: - two sites
were selected for Diversion head works / weir/ locations; furthermore, the
length of the Main Canals from site1 and 2 are said to be 55km and
72.8km respectively.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The previous study facts, which are presented above were understood and
considered in the current study and design of the scheme as follows: -
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
command area and minimize loss/ to serve the left bank command
areas.
Eleven pumping stations with respective night storage reservoirs
were considered, for command areas above the headwork contour
line.
The present study gross IWR at headwork to be 1.1 litters/sec./ha for
24hours’, the estimates of this study comply with previous study.
Soils of the command area have been grouped into seven major soil
mapping units were identified at Guyuk Irrigation Scheme soils survey
area namely GK 1, GK 2, GK 3, GK 4, GK5, GK 6 and GK 7. Soil mapping
Unit GK 4 was further divided into GK 4a, GK 4b, GK 4c and GK 4d, given
rise to total of ten (10) soil-mapping units. The names of soil mapping
units and extent of the survey area are presented (Table 3.1).
Table 3.1 Extent of the soil mapping units in the survey area
Soil Mapping Unit Area (ha.) Proportion of Area (%)
Symbol
GK 1 330.65 1.00
GK 2 6304.65 19.12
GK 3 2991.38 9.07
GK 4a 5598.21 16.98
GK 4b 2830.65 8.58
GK 4c 3643.95 11.05
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
GK 4d 1428.46 4.33
GK 5 5073.90 15.39
GK 6 3753.80 11.38
GK 7 1023.44 3.10
Total 32,979.10 100.00
Gully 19.5
Pond 80.2
RBS 144.5
River 2266.2
Settl 212.2
Grand Total 35,701.6
Source: GIS Soils study report, Annex D, Volume III, April 2020
3.1.1 Soil Texture
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
soils, through incorporation crops residues into the soils and practice crop
rotation.
The bulk density of the project area soils ranges from 1.14 to 1.83 g/cm 3
(averaging about 1.485 g/cm3), which is the characteristic of sandy clay
loam, sand, loamy sand and sandy loam soils. This implies that the soils
of the project have low capacity for retaining soil moisture and plant
nutrients.
The infiltration rate of the command area generally varies from 0.96
cm/hr. in clay soils to 24 cm/hr. in sandy loam soils; whereas the hydraulic
conductivity (K) in the project area soils varies from 0.29 cm/hr. to 4.88
cm/hr. The very high infiltration rate in some test pits namely GK5
requires attention in taking necessary soils management strategy to
overcome the expected irrigation water loss.
Table 3.2 summarizes the physical properties of the soil of the respective
mapping units.
Table 3.2 Physical properties of the soil mapping units
Soil Textur Saturated Availab
Bulk Infiltrati Moisture Bar
Mappi Dep Sa Cla al Porosi hydraulic le
Silt densi on rate Suctions, g
ng th nd y class ty conductiv moistu
ty g -1
Unit USDA ity re
cm cm/hr.
g g g/cm 3
% cm/hr. 0.33 0.15 g g-1
g kg- kg-
kg-1 1 1
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
42 10 0.19 0.04
80- 35.35
0- 0- 0- SL, CL, 1.44- 3.60 0.664- 8- 5- 0.125-
GK4a 28 8-
200 78 30 SCL 1.607 2.014 0.38 0.09 0.333
0 45.66
0 0 7 8
30 36.79 0.03
20- 40- 1.426 0.2-
0- 0- S, SL, 2- 24.00 0.542- 8- 0.144-
GK 4b 48 28 - 0.39
215 92 L, CL 46.18 1.99 0.09 0.319
0 0 1.595 6
0 9 6
40 12 39.39 0.19 0.05
40- 1.489
0- 0- 0- SCL, 6- 3.90 0.573- 9- 2- 0.107-
GK 5 26 -
200 76 34 SL, CL 43.81 0.823 0.25 0.12 0.192
0 1.606
0 0 1 9 4
34 38.18 0.18 0.02
40- 60- 1.195
0- 0- SCL, 9- 19.62 0.212- 4- 6- 0.143-
GK 6 32 34 -
200 90 SL, CL 54.90 1.708 0.27 0.10 0.208
0 0 1.638
0 6 4 1
56 0.20 0.03
40- 80-
0- 0- 9- 5- 0.146-
GK 7 28 16 LS, SL
100 78 0.31 0.07 0.237
0 0
0 5 8
Source: Detailed soils survey for agricultural development studies,
Annex D Soils study, GIS report,
Land suitability is the potential of land for use in either specified ways or
management practices for the selected method of irrigation system. The
suitability classification has been made based on a rating of a set of
permanent soil characteristics as regards to risks of soil damage.
Limitation to use, soil management requirement, slope, soil texture,
drainage conditions, soil depth, effects of past erosion, water holding
capacities and stoniness which are considered permanent land qualities
and characteristics.
Table 3.3 Summary of Land Capability Classes of the Survey Area
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The following analysis has been taken from hydrology study report of
Guyuk irrigation scheme accordingly Gongola River was identified as a
source of irrigation water for Guyuk irrigation scheme, which is regulated
by an upstream dam constructed across it at DadinKowa. Inflows from
lateral tributaries between DadinKowa and Guyuk also provides additional
flows to be harvested for the Guyuk irrigation water use, however,
majority of these tributaries are seasonal rivers and their flows are not
available during the dry season, lasting between November to April. Thus,
the only guaranteed flow is the flow released from the DadinKowa dam
particularly the 150m3/sec released through the two turbines.
Consequently, operation of the DadinKowa hydropower scheme is critical
to the availability of irrigation water requirement for the Guyuk irrigation
project.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The suitability of water for irrigation is determined not only by the total
amount of salt present but also by the kind of salt. Various soil and
cropping problems develop as the total salt content increases, and
special management practices may be required to maintain acceptable
crop yields. Water quality or suitability for use is judged on the potential
severity of problems that can be expected to develop during long-term
use.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The principal factors that contribute to soil salinity are: (i) high water
table, (ii) inadequate irrigation, (iii) hot and dry climate. In the first case,
due to irrigation the water table rises near the surface level which causes
significant evaporation from soil water leaving salt accumulation in the
root zone (Ghosh, 1999). Soil water salinity can affect soil physical
properties by causing fine particles to bind together into aggregates. This
process is known as flocculation and is beneficial in terms of soil
aeration, root penetration, and root growth.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Table 3.4 Suggested criteria for irrigation water use based upon
electric conductivity (Salinity classification based on
United States Salinity Laboratory guide (USSL, 1954).)
TDS EC Class Effect
(mg/l) (µS/cm)
<200 <250 C1 Low-salinity water –can be used for
irrigation with most crops on most soils, with
little likelihood that a salinity problem will
develop. Some leaching is required, but this
occurs under normal irrigation practice,
except in soils of extremely low permeability.
200–500 250–750 C2 Medium-salinity water – can be used if a
moderate amount of leaching occurs. Plants
with moderate salt tolerance can be grown in
most instances without special practices for
salinity control.
500– 750– C3 High-salinity water – cannot be used on
1,500 2,250 soils with restricted drainage, special
management for salinity control may be
required and plants with good salt tolerance
should be selected.
1,500– 2,250– C4 Very-high-salinity water – is not suitable for
3,000 5,000 irrigation under ordinary condition but may be
used occasionally under very special
circumstances. The soil must be permeable,
drainage must be adequate, irrigation water
must be applied in excess to provide
considerable leaching and very salt-tolerant
corps should be selected.
Sodium has the opposite effect of salinity on soils. The primary physical
processes associated with high sodium concentrations are soil
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
dispersion and clay platelet and aggregate swelling. The forces that
bind clay particles together are disrupted when too many large sodium
ions come between them. When this separation occurs, the clay
particles expand, causing swelling and soil dispersion. Soil dispersion
hardens soil and blocks water infiltration, making it difficult for plants
to establish and grow. The major implications associated with
decreased infiltration due to sodium-induced dispersion include
reduced plant available water and increased runoff and soil erosion.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
ppm
Note that meq /¿=
equi. wt .
The quality of irrigation water for GIS regarding the suitability and
toxicity hazards has been analyzed and the laboratory analysis results
of the samples are presented in Table 3.7.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Source: Detailed soils survey for agricultural development studies, GIS report,
April, 2020.
From the evaluation of water quality (Table 3.7), it can be concluded that
the irrigation water from different places of the Gongola River is suitable
for irrigation.
3.2 Depth of Groundwater and Chemical Characteristics
Depth to groundwater table varies according to the geological and
geomorphologic conditions. Hence, 26 profiles were investigated within
the GIS command area, and the output of the analysis obtained from the
samples is presented in Table 3.8.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
Table 3.8 Summary of investigated locations of ground water potentials, aquifer depths, yields and
levels
UTM, Location
Profil Groundwat Aquifer Depth (Recommended depth
Aquifer Levels Field Numbers
e No. er Potential to be drilled)
Easting Northing
1083817
824244 a)5-10m @pnt 12
.1
Out of Command, at
1 824219 1083816 Good Shallow to Moderate
b) 60 - 130m @pnts 5,6 tail end of TC12-2-3
.6 .9
c) 210 - 240m @ pnts 9,10
827247 1086992
a) 80-140m @ pnts 11,12,13,15
.9 .8 Several Shallow and
2 Very Good TC1-27-3, FC7
827226 1086986 Deep aquifers
b) 90 - 180 m @ pnts 4,5,6,7
.6 .4
823468 1087401
a) 5-130m @pnt2 2
.3 .9
Few shallow and
3 823468 1087423 Fair TC11-2-4, FC2
b) 130 - 230 m @ pnt 4 Deep aquifers
.1 .7
c) 240 - 270 m @ pnts 11, 13
824731 1088397
.4 .4
4 Fair 10 – 90 m @ all pnts except pnt 8 Shallow aquifers TC11-2-7, FC6
824743 1088366
.8 .8
824086 1091362
.1 .5 SC10a-4 & 5,
5 Poor 60-90m @ pnt 14 Moderate aquifer
824088 CH.760m
1091384
.9
823134 1091406
a)10-60m @ pnt 5
6 .2 .3 Fair Shallow aquifers TC10a-4-1, FC1
823109 1091403 b) 30 – 85 m @ pnt 9
ENVIPLAN IN ASSOCIATION with ECDSWC
.8
c) 25 – 70 m @ pnt 13
824804 1093576
.5 .9
7 Fair 260- 300 m @ pnts 2,3,5,8 Deep aquifers TC10a-3-7, FC2
824813 1093601
.4 .6
824007 1094421
.4 .7
8 Poor More than 300 m @ pnts 2, 11 Very Deep TC10a-2-4, FC4
824028 1094409
.6 .6
823829 1095868
a)35- 80 m @pnt 8
.7 .6
9 Fair Shallow TC10a-1-3, FC2
823808 1095871
b) 40 – 60 m @ 11
.3 .5
823316 1100455
.3 .4
10 Good 10- 150 m @ all pnts except pnt 11 Shallow to Moderate TC9-2-4, FC2
823325
1100434
.6
1101164
823499 a)30-120 m @pnt 7
.4
11 823502 1101139 Good Shallow to Moderate TC1-2-2, FC2
b) 60 – 90 m @ pnt 11
.3 .8
170 - 190 m @ 8
820759
1104163 a)250 -270 m @ pnt 2
.1
12 Fair Deep Near to TC8-2-3
820734 1104165
b) 280 – 290 m @ pnt 5
.6 .9
1105189
819997 a)25 – 40 m @ pnt 10
.6
13 Fair Shallow Near to PC-8
820012 1105208
b) 35 – 80 m @ pnt 9
.1 .2
Page | 42
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
819383 1105971
.5 .4 out of Command,
14 Good 190 – 290 m @ pnts 1, 3, 6, 11, 13 Moderate to deep
819383 1105946 around NSR-8
.7 .8
817389
1108740
.9 20 – 180 m @ all pnts except pnts 5
15 Good Shallow to Modrate TC1-3-1, FC5
817365 1108730 and 7
.6 .5
814263 1111138
.1 .8 15 – 240 m @ all pnts except pnts 2
16 Good Shallow to modrate TC6-3-2, FC10
814257 1111114 &4
.2 .2
814038 1110278
.9 .9
17 Good 10 – 180 m @ all pnts except pnt 11 Shallow to modrate TC6-3-1, FC1
814036 1110251
.1 .2
808974 1112612
a)260 – 300m @ pnt 2
.8 .1 out of command
18 Fair Deep
808953 area/s of MC
1112615 b) 220 – 289 @ pnt 11
.4
808279 1110884
.5 .2 190 – 300 m @ pnts 3, 4, 7, 9, 10, out of Command
19 Good Deep
808270 1110862 13, 14 Area/s ofTC4a-2-4
.6 .6
803587 1113937
.9 .6
20 Good 10 – 130 m @ pnts 1, 2, 7, 8, 13 Shallow to Deep TC3-2-1, FC4
803566 1113949
.4 .7
805339 1114044
out of command at
21 .2 .7 Very Good 25 – 150 m @ all pnts Shallow to moderate
tail end of TC3-3-2
805317 1114044
Page | 43
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
.8 .5
807713 1115719
a)20 – 120 m @ 6
.9 .3
22 Fair Shallow Tc0-0-1, FC2
807710 1115743
b) 80 – 100 m @ pnt 11
.7 .8
823642
1113713 a)10 – 40 m @ pnts 9, 10
.7
23 823618 1113709 Fair Shallow to Deep TC2-6-5, FC1
b) 30 – 150 m @ pnts 13, 14
.3 .7
c) 100 – 240 m @ pnt 12
824985 1105695
.9 .3 Near to SC1-12
24 Good 30 – 180 m @ pnts3, 5, 6, 8 & 13 Shallow to moderate
825013 1105698 command
.3 .6
824158 1109562
.6 .8 Near to SC1-8
25 Very Good 60 – 130 m @ all pnts Shallow to moderate
824161 1109584 command
.4 .4
826190 1116786 the first point is out
.2 .8 of Command, u/s of
60 – 140 m @ all pnts with excellent
26 Very Good Shallow to moderate SC2-8, & the second
826216 1114932 pnts @ 4, 5, 12, 13 & 14
point is TC2-8-2,
.2 .6 FC2
Page | 44
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
From above table, it can be noticed that profile no. 2, 10, 11, 15, 16, 17,
20, 26 (second point at TC2-8-2, FC2) and 3, 4, 6, 7,9,22, 23 with
respective field number have good to fair potential for irrigation with
aquifer depths as indicated. In addition, two profile points named as 5 and
8 have poor potential. It is also identified that profile no.1, 12, 13,
14,18,19,21, 24, 25 and 26 (first point) lie outside the command area.
The laboratory test result of the ground water sample in table 3.10 shows
that, there is no problem with respect to the quality of the groundwater.
(Refer section 3-3-1 of this report).
However, at this level of study, the water balance of the ground water was
not computed.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The materials proved are predominantly sand, clay, laterite, black cotton
soil (USCS: silty sand, clayey sand, silt, clay) along the route. These were
proved within total explored depth of 3.0m in all the trial pits and between
0.6 – 3.6m in the standard penetration test.
The materials encountered in the proposed borrow pit close to this
location were predominantly borderline clayey/silty sands and lean clay
(USCS designation: SC-SM & CL). Details of laboratory results can be found
in Appendix A.
The allowable bearing pressures for proposed structures where SPT was
carried out are within the range of 136- 991kN/m3. The bearing capacity
are >101kN/m2 (Factor of safety 3.0) for the trial pit location (along the
irrigation canal)
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
According to FAO 1977 revised, Paper No.24, the effect of climate on crop
water requirements is given by the reference crop evapotranspiration
(ETo), which is defined as "the rate of evapotranspiration from an
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Climatic data, wind speed, relative humidity, sun shine hours, maximum &
minimum temperature are used for calculating ETo using FAOCROPWAT
software version 8.0. Hence, the calculated ETo values for Guyuk irrigation
scheme are presented in Table 4.1 below.
Sunshi Solar
Max Min Humidi Wind ET0
ne Rad
Month Temp. Temp. ty speed (mm/
(Hours (MJ/
0
( C) 0
( C) (%) (km/d) d)
) m2/d)
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The values of ETc and CWR (Crop Water Requirements) are identical,
whereby ETc refers to the amount of water lost through
evapotranspiration and CWR refers to the amount of water that is
needed to compensate for the loss. ETc can be calculated from climatic
data by directly integrating the effect of crop characteristics into ETo.
ETc = ETo x Kc
Where:
ETc = Crop evapotranspiration (mm/day)
ETo = Reference crop evapotranspiration (mm/day)
Kc = Crop coefficient
Effective rainfall is that part of the total dependable rainfall during the
growing period that is available to plants to meet the evapotranspiration
and miscellaneous requirements. No all rainfall is effective, because its
part may be lost by surface runoff, deep percolation, and Evaporation,
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
only a portion of total rain can enter and be stored in the root zone. In this
study, FAO CropWat software has been used to determine the effective
rainfall amounts for the Scheme.
225
175
125
75
25
Janu- Febru- March April May June July August Sep- Octo- No- De-
ary ary tember ber vember cember
Rain mm NaN 0.3 0.2 6.5 47.2 115.2 139.7 163.9 197.9 186.4 64.5 2.4 0.3
Eff rain mm NaN 0 0 0 18.3 68.2 87.7 107.2 134.3 125.1 28.7 0 0
The dependable rainfall of the area is 781.5 mm/year while the effective
rainfall of the respective rainfall is 595. 2 mm/year, which shows around
186.0 mm, is lost due to different pre-stated factors.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
If irrigation is the sole source of water supply for the plant, the irrigation
requirement will always be greater than the crop water requirement to
allow for inefficiencies in the irrigation system. If the crop receives some
of its water from other sources (rainfall, water stored in the ground,
underground seepage, etc.), then the irrigation requirement can be
considerably less than the crop water requirement. For determining the
net irrigation requirement for Guyuk irrigation schemes, values of Ge, Wb
and LR have been neglected.
Thus; IWRn = Etc – Pe
Irrigation water is wasted along the irrigation system in various ways i.e.
not all water diverted at head works is available to the crops at field.
Water could be lost from canals in the conveyance, distribution systems
and during field applications due to evaporation, seepage and deep
percolations. The overall project efficiency is a product of the conveyance,
distribution and field application efficiencies.
Field application efficiency (ea): Takes into account water that is lost
in field canals and the actual irrigated field. In view of the local
farmers’ poor skill of irrigation, the present study has considered
(ea) value of 60% for surface irrigation method for Guyuk irrigation
scheme.
Distribution efficiency (ed): Takes account of water lost in the
secondary and tertiary canals. For unlined canals, (ed) value of 85%
has been considered,
Conveyance efficiency: Considers water lost in the Main Canal and
primary canals. As main canal and primary canals are usually lined,
(ec) value of 95% has been taken in this study. Thus, the overall
project efficiency (ep) for surface irrigation would be (ea) x (ed) x
(ec), which is equal to 48.45%.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
4.6.1 Pre-Irrigation
IWRg = IWRn/Ep
Where:
IWRg: Gross irrigation water requirements (mm)
IWRn: Net irrigation water requirements (mm)
Ep: Overall project efficiency (%)
The gross and net irrigation requirements estimated for the proposed
cropping pattern of Guyuk Scheme are summarized on Table 4.3. The
peak Gross IWR at headwork for Guyuk 100% surface irrigation, occurs in
January and amounts to 1.11litters/sec./ha, for 24 hours’ irrigation and
2.22 litters/sec./ha for 12 hours’ irrigation.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
The previous studies i.e. (Pre – Feasibility Study DadinKowa (Part A) and
Reconnaissance Study of Guyuk (Part B) in 2014 & 2015) have estimated the
gross IWR at headwork to be 1.1 litters/sec./ha for 24hours’ irrigation for
Guyuk Irrigation Scheme, which is similar to the present estimates.
Therefore, the present study has used long-term climatic data from
stations close to the project sites, the estimates of this study could be
considered as more reasonable.
Page |
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Table 4.3 Guyuk Irrigation Scheme -Crop Water and Irrigation Requirement
Total Total NIR
Ma No
Crops Jan Feb Mar Apr Jun Jul Aug Sep Oct Dec NIR
y v in mm3
(mm)
86. 108. 113. 108.
Rice 0 0 0 0 0 9.5 0 0 426.7 4267
6 6 8 2
17.
Maize 0 0 0 0 0 88.5 90.1 9.4 0 0 0 205.9 2059
9
15. 112.
Groundnut 0 0 0 0 0 68.5 68.3 0 0 0 264.3 2643
1 4
22. 117.
Cotton 0 0 0 0 0 90.7 105 3.7 0 0 339.7 3397
9 4
15. 101.
Soybean 0 0 0 0 0 62 112 4.6 0 0 295.1 2951
1 4
100.
Sorghum 0 0 0 0 0 8.7 43.6 92.6 15.9 0 0 261.2 2612
4
137. 29.
Cow Pea 0 0 0 0 0 0 0 17.1 95.6 0 279.3 2793
1 5
138. 135.
Peppers 120 20 0 0 0 0 0 0 0 82 496 4960
6 4
142. 31. 120.
Okra 49.9 0 0 0 0 0 0 0 0 344.1 3441
1 2 9
137. 65.
Onion 29.7 0 0 0 0 0 0 0 0 138 370.9 3709
5 7
129.
Cabbage 139 77.7 0 0 0 0 0 0 0 0 72.1 418 4180
2
138. 105.
Maize rain fed 0 0 0 0 0 0 0 0 11 66.2 321.7 3217
6 9
154. 154. 136. 138.
Rice wet season 4.2 0 0 0 0 0 0 0 588.4 5884
4 3 9 6
142. 112. 44. 123.
Tomato N 0 0 0 0 0 0 0 0 422.7 4227
3 1 7 6
Net scheme irr.req
in mm/day 4.7 4.2 2.3 0.1 0 1.2 2.5 3.2 2.9 0.6 0.6 3.7
in l/s/ha 0.54 0.49 0.27 0.0 0 0.1 0.29 0.37 0.34 0.07 0.0 0.43
Page | 58
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
1 4 7
Irrigated area (% of total
100 100 55 50 0 90 90 100 100 80 55 100
area)
Irr.req. for actual area 0.0 0.1 0.1
0.54 0.49 0.49 0 0.32 0.37 0.34 0.09 0.43
(l/s/ha) 2 6 2
Gross Irrigation
0.0 0.2
Requirement L/s/ha at field 0.9 0.82 0.82 0 0.53 0.62 0.57 0.15 0.2 0.72
3 7
canals for 24 hrs
Tota Total
l NIR
Crops Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec NIR
in
(mm
mm3
)
Gross Irrigation
Requirement
1.8 1.63 1.63 0.07 0 0.53 1.07 1.23 1.13 0.3 0.4 1.43
L/s/ha at in field
canals for 12 hrs
Gross Irrigation
Requirement
L/s/ha at 1.06 0.96 0.96 0.04 0 0.31 0.63 0.73 0.67 0.18 0.24 0.84
secondary canals
24 hrs
Gross Irrigation
Requirement
L/s/ha at 2.12 1.92 1.92 0.08 0 0.63 1.25 1.45 1.33 0.35 0.47 1.69
secondary canals
12hrs
Gross Irrigation
Requirement
1.11 1.01 1.01 0.04 0 0.33 0.66 0.76 0.7 0.19 0.25 0.89
L/s/ha at head
works 24 hrs
Page | 59
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Gross Irrigation
Requirement
2.22 2 2 0.1 0 0.7 1.3 1.5 1.4 0.4 0.5 1.8
L/s/ha at head
works 12 hrs
Month Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Irr.req. for actual area (l/s/h) 0.54 0.49 0.15 0.01 0.00 0.13 0.26 0.37 0.34 0.06 0.04 0.43
Efficiency (0.95*0.85*0.6) 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48 0.48
Gross duty @PC 1.11 1.01 0.31 0.01 0.00 0.26 0.54 0.76 0.70 0.12 0.08 0.89
Number of days 31 28 31 30 31 30 31 31 30 31 30 31
Gross duty @Head work with 1. 1.1 0.3 0 0 0
10% flexibility 29 7 5 0.01 - .30 0.62 0.88 0.81 .13 .09 1.03
Number of days 31 28 31 30 31 30 31 31 30 31 30 31
Gross Irrigation water 3,456. 2,832. 950.5 30.9 78 1,67 2,3 2,10 35 23 2,75 17,
Requirement 24hrs (m3/ha) 56 98 5 7 - 0.51 0.67 68.39 6.15 8.46 8.49 2.45 546.19
Page | 60
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION with ECDSWC
Chart 4-3 Guyuk Irrigation Scheme –Monthly Gross Irrigation Water requirement
1,000.00
864.14
709.56
500.00
325.87216.81
- 28.16 -
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Page | 61
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The contour map of the command area was produced with an interval of
0.5m 0.75m, 1.0m and 1.25m, using LiDar survey for preparation of the
layout of GIS, drainage & infrastructures. Features of existing
infrastructures, gullies and important spots have been verified at site
through actual ground truthing and data collections.
The irrigation and drainage system layout comprises road and drainage
systems inside the command area and along the conveyance system. To
cross the canals and to continue mobilization of the community, to supply
inputs and collect harvests and to facilitate the implementation and
supervision of the canal structures. Furthermore, the system is provided
with bridges and culverts at appropriate locations. Interceptor drains are
provided at the upper side of primary canals adjacent to the road to protect
the incoming runoff from scattered places around the foot of the
escarpments and safely dispose the runoff to existing natural gullies and
the whole bench marks was used during topographic survey are listed on
the following table
Table 5.1 List of Bench marks of GIS
List of BMs of GIS
No Name- Easting Northing Elevation No Name Easting Northing Elevation
1 EIL000GYK 806778.33 1119494.76 208.67 23 EIL011PC1 826212.99 1108657.73 205.99
2 EIL001GYK 806707.19 1119061.23 213.64 24 EIL012PC1 825047.70 1106726.97 198.45
3 EIL002GYK 806392.86 1117330.52 209.46 25 EIL013PC1 824896.29 1105418.23 195.31
4 EIL003GYK 807365.62 1116512.72 216.75 26 EIL014PC1 824559.67 1103531.58 194.34
5 EIL004GYK 806332.16 1115252.04 208.16 27 EIL015PC1 823927.09 1102278.39 188.43
6 EIL005GYK 807462.48 1113823.47 212.11 28 EIL016PC1 823826.44 1100597.58 193.67
7 EIL006GYK 807911.14 1112356.90 204.30 29 EIL017PC1 823919.37 1099191.10 200.19
8 EIL007GYK 808283.04 1111281.51 202.82 30 EIL018PC1 825083.21 1099197.67 194.31
9 EIL008GYK 808829.41 1109978.15 203.92 31 EIL019PC1 826359.09 1098179.45 189.45
10 EIL009GYK 811347.14 1109741.76 205.54 32 EIL020PC1 825839.20 1096707.37 189.44
11 EIL010GYK 812811.08 1110059.09 205.15 33 EIL021PC1 825007.96 1094618.85 188.29
12 EIL011GYK 814311.69 1111775.54 210.82 34 EIL022PC1 825095.25 1093189.45 187.50
13 EIL012GYK 815036.27 1111611.51 212.71 35 EIL023PC1 825061.09 1091948.66 187.27
14 EIL001PC1 814967.07 1109932.79 236.60 36 EIL024PC1 825399.55 1090543.40 186.27
15 EIL003PC1 818053.87 1106724.58 201.78 37 EIL025PC1 824459.16 1089097.95 188.13
16 EIL004PC1 820100.21 1107128.59 212.43 38 EIL026PC1 825488.62 1087937.90 186.27
17 EIL005PC1 821358.62 1108816.71 207.46 39 EIL027PC1 825467.29 1085387.40 191.40
18 EIL006PC1 823298.62 1107298.40 209.36 40 EIL028PC1 826743.88 1085131.91 185.17
Page | 62
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 63
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 64
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The canal system layout, channel alignments and capacities to supply the
maximum area that is economically commanded have been established
with consideration of the design criteria.
Main Canal
Its designed length is 22.749 Km, which conveys a discharge of 21.24m 3/s
of irrigation water from Gongola River at the point of diversion weir and
supplies to five tertiaries, five secondary canals and to sumps from where
the lift system command areas of PCs are to be supplied. Finally, the main
canal is bifurcated in to two primary canals named as PC-1 and PC-2.
The canal is designed for 12hrs duty, but it conveys for 24hrs continuous
supply for future development of irrigable land up stream of main canal
alignment using lift irrigation system and it expected to feed the night
storage during 12hrs night period, and its detail designed doesn’t
conducted at this stage due to contractual restriction.
The main canal designed concert lined canal for its full-length. It is a
contour canal running at slope of 1/5000, side slope 1:1.5, Bed width
varying from 8.6to 11.30m, full supply depth from 1.77m to 1.89m and
structure losses are provided at cross regulating and gully/river crossings.
Primary Canals
Page | 65
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Gongola River with a total length of 56.762km, 12.16m 3/sec capacity at the
binging. And its Bed width varying from 0.75m to 4.75m, full supply depth
from 0.52m to 1.83m and structure losses are provided at cross regulating
and gully/river crossings. This primary canal supplies irrigation water to the
distributary canal systems of the gravity command area, which directly
offtake to twenty-nine secondary and to five tertiary canals.
Page | 66
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
4.0 m wide surfaced farm access road and tertiary drain is provided along
the tertiary canal alignment where necessary.
Field Canals
The field canals will be unlined fill canals that off-take from secondary or
tertiary canals. These canals are planned to supply irrigation water to an
area of about 10ha having a uniform canal sections and capacity, 100lt/sec.
The fields would have a maximum 100m furrow length and 500m long field
canal with some exceptions.
All of the field canals are aligned down the major gradient and so will have
frequent small check structures to control bed erosion and water level for
easy delivery of water to adjacent furrows. Field canal has a bed slope of
1/1000, side slope of 1:1, Bed width of 0.3m and full supply depth of 0.
35m. A 3.0 m wide farm access road with side ditches as field drains would
be provided at the end of the furrows parallel to the field canal alignment.
Field Drains
Field drains run parallel to field canals, collect excess water from furrows
and field channel escapes, and dispose into a higher order drain or into a
natural/artificial depression on the border of the command area. Most of the
field drains are aligned with the field roads so the drain ditches for the field
roads are proposed to replace the field drains to minimize construction cost.
Tertiary Drains
Tertiary drains collect water from lower order drains (field drains). Disposal
can be into secondary drains or a natural gully or into a natural depression on
the border of the command area.
Secondary Drains
Secondary drains collect water from lower order drains (tertiary drains or
field drains). Disposal can be into interceptor drain or a natural gully or into
a natural depression on the border of the command area.
Page | 67
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Interceptor Drains
Main Canal: The scheme has one main canal, denoted as MC and the
network as explained below.
Primary Canals: There are fourteen primary canals numbered from PC-1
to PC-13 (PC-1 and 2 off-taking from the Main Canal, and PC-3 to PC-13 off-
taking from the respective sumps provided) and the network, which
connects the canals, is presented as below.
Page | 68
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Secondary Canals: Secondary canals are named in the order of their off
taking chainages from the main canal and primary canals, for example the
secondary canal off-taking directly from the main canal is named SC0-1up
to SC0-5, the primary canal one command is named SC 1-1 up to SC1-29,
and the primary canal two command is named SC 2-1 up to SC2-9, and etc.
Tertiary Canals: Tertiary canals are labelled sequentially in the order from
where they off-take from the main and secondary canals, using the three-
letter abbreviations. For example, the first tertiary canal directly off-taking
from the main canal is named TC0-0-1 and from the first Secondary Canal of
Page | 69
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
the main canal is named TC0-1-1, and from the primary canal one, (PC1),
will be named TC 1-1-1 and with similar naming for other.
Field Canal: A similar numbering system is adopted for the field canals.
They are also labelled sequentially in the order from where they off-take
from the tertiary canals. An example would be FC 1-1-1-1. Generally, it can
be understood that the first number stands for MC or PC; the second
number represents a secondary canal; the third number stands for tertiary
canal and the fourth number represents a field canal.
Drain Canals: The drainage channel categories will be identified using the
following codes:
Interceptor Drain, ID: there are about 13 interceptor drains in the right
side of Gongola River named as ID-1, ID-2, to ID-13
Secondary Drain, SD: is numbered with the same number with the
secondary canal. For example, secondary drain for secondary canal SC 1-1
is named as SD 1-1
Tertiary Drain, TD: coded for each secondary canal as TD-1, TD-2, etc. for
instance if SC 1-1 has three tertiary drains, the drains will be named as TD-
1, TD-2 and TD-3. Besides the flow, the arrow in the drain layout indicates
direction of the drains.
Page | 70
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Based on the past experience of GIS area with irrigation, required labour
inputs, prevailing topography, soils condition, cost and irrigation skill of the
local farmers, the previous study report (Preliminary Studies to Develop
25,000 Ha of Irrigation Scheme Downstream of the DadinKowa Dam,
Gombe State) proposed irrigation method to be surface irrigation (by
gravity and use of pumps). The surface irrigation method is proposed as it is
less expensive, simple to implement and easy to operate. As a traditional
method, it would be more readily accepted by farmers and would not create
conflicts and inequitable water supply. It is also in accordance with the
quantity of available water for irrigation. Though, other methods like
sprinkler irrigation have efficient water utilization and gives higher yields, it
Page | 71
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The smallest irrigation unit size is the area irrigated at a time by a field
canal during an irrigation turn. The irrigation unit size depends on several
factors. Most importantly, the following are basic criteria used to fix the size
of the smallest irrigation unit:
The flow rate of the field canal is taken as 100 l/s for the scheme. This
is because the farm sizes that each farmer holds are varying, and it is
difficult to fix the discharge as per the requirement of individuals’ land
size. Hence with uniform supply of irrigation water to the field, the time
of irrigation for a given area could be managed i.e., smaller area can be
irrigated in a shorter period while larger area requires relatively longer
period;
The length of the field canal is about 500m; so that the maximum area
for a two-side irrigation is 10ha;
Page | 72
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 73
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Furrow irrigation is one of several surface methods used for applying water
to crops and are most commonly made down the slope but when land slope
exceeds the safe limit of soil erosion, they are constructed nearly on
contour or obliquely. Similarly, when rainwater is to be conserved, furrows
act as an effective means to catch and conserve the rainfall water. Efficient
irrigation by the furrow method is obtained by selecting proper
combinations of spacing, length, and slope, suitable size of the irrigation
stream and duration of the water application.
The spacing between furrows depends on the water movement in the soil,
which is texture related, on the crop agronomic requirements as well as on
the type of equipment used in the construction of furrows. In practice, a
compromise often has to be reached between these factors.
Page | 74
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Table 5.2 Recommended furrow lengths for different soil types, and
depth of irrigation
Furrow length, metres
Soil type
Furrow
slope % Clays Loams Sands
Net depth of water application
7.5cm 15cm 5cm 10cm 5cm 7.5cm 10cm
0.05 300 400 120 270 60 90 150
0.1 350 440 180 330 90 120 190
0.2 370 470 220 370 120 190 250
0.3 390 500 280 400 150 225 280
0.5 380 500 280 370 120 190 250
1.0 270 400 250 300 90 150 220
Source: irrigation theory and practice, A M Michael, 1978
The size of the furrow stream is the one factor, which can be varied after
the furrow irrigation system has been installed. Its purpose is to wet the
Page | 75
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
entire length of each furrow as quick as possible, thus enabling the soil to
absorb water evenly through the entire furrow length. After the water
reaches the lower end of a furrow, the stream is reduced or cut back so that
it will just keep the furrow wet throughout its length with minimum waste at
the end.
The size of the furrow stream usually varies from 0.5lt/sec to 2.5lt/sec. To
obtain the most uniform irrigation, the maximum size of the irrigation
stream that can be used at the start of the irrigation is limited by
considerations of erosion in furrows, overtopping of the furrows and
prevention of runoff at the downstream end.
0.6
q m= ;
S
For a furrow slope of 0.3%, the flow rate, q m will be 2.0l/s while for furrow
slope of 0.5%, the flow rate becomes 1.2 l/s and hence the maximum non-
erosive furrow stream flow for the scheme is limited to 2 l/s.
The average depth of water applied during irrigation can be calculated from
the following relationship (A M Michael, 1978):
d= ( q m∗360∗t
w∗L )
Where: d = average depth of water applied (cm)
qm = stream size (l/s)
t = duration of irrigation (elapsed time (hr)
w = furrow spacing (m)
L = furrow length (m)
Page | 76
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Advance time is the number of hours needed to travel from the delivery
point to the lower end of the field. Water is applied at a faster rate at the
beginning of the irrigation period and then reduced or cutback to a lesser
rate, usually one-half the initial rate.
Page | 77
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The soil moisture between field capacity and permanent wilting point and is
referred to as readily available moisture. Table 5.2 below presents the
range of available water holding capacity of different soil textural groups.
Table 5.3 Range of available water holding capacity of soils
%moisture based on dry wt. of soil Depth of available
Soil type water per unit of soil
FC PWP Cm per m depth of soil
Fine sand 3–5 1-3 2-4
Sandy loam 5-15 3-8 4-11
Silt loam 12-18 6-10 6-13
Clay loam 15-30 7-16 10-18
Clay 25-40 12-20 16-30
(Adopted from A M Michael, 1978)
Effective root zone is the depth from which the roots of an average mature
plant are capable of reducing soil moisture to the extent that it should be
replaced by irrigation. It is not necessarily the maximum root depth for any
given plant. The approximate values of effective root zone depth of some
common crops are presented below:
Where: TAW (m) = Total available water for one-meter soil profile
(mm/m)
FC = Moisture content at field capacity (% by weight)
WP =Moisture content at wilting point (% by weight)
BD = Bulk density (gr/cm3), The bulk density of the project area
soils ranges from 1.14 to 1.83 g/cm 3 (averaging about
1.485 g/cm3)
Page | 78
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The dominant soil textures of the command area are sandy loam, clay loam
and clay, so that from Table 5.4, the respective average values of the
available water are 75mm/m, 140mm/m and 160mm/m.
The total available water (TAW) for the effective root zone depth is
determined by:
TAW = TAW(m) × RZ
Where: TAW = Total available water for the soil depth of the effective root zone
(mm)
RZ = Effective root zone (m)
Hence, the TAW values for different root zones at different soil texture is
calculated and presented in the table below (Table 5.4).
For optimal yields, the soil moisture content should be well above the
critical point. This means that the consumption of water by the crop must
be less than the total available water in the effective root zone depth.
Table 5.5 TAW values for different soil textures and root zones
TAW, mm
TAW(m),
Soil texture RZ, m
mm/m
0.6 0.9 1.2 1.8
Sandy loam 75 45 67.5 90 135
Clay loam 140 84 126 168 252
Page | 79
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
T = MWD/NIWR
Where: T = Interval between irrigations (days)
NIWR = Irrigation water requirement (mm/day)
Page | 80
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 81
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
It can be observed from Tables 5.5 to 5.8 that interval for crops with
effective root depths of 60cm, 90cm, 120cm and 180cm is 4days, 6days,
7days and 11days respectively. But the actual irrigation interval, which is
calculated by the agronomist as shown in Table 5.9 is 6 days, which is to be
best suited for the conditions of the Guyuk irrigation scheme. Accordingly,
the area that a single field canal with a capacity of 100l/s can irrigate is
computed as:
Page | 82
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
A shorter irrigation interval with surface irrigation is not possible once the
system is designed for a 6-day operation cycle. However, during irrigation
times of lower water demand, the Water Users Association can coordinate
the farmers to use irrigation intervals shorter than 6 days.
Page | 83
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 84
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The canal capacity reduces from the head reach towards the tail
according to the command area it covers. Therefore, design discharge
and net irrigable area for each off taking canals are summarized on table
6.2 for Guyuk gravity irrigation scheme.
Table 6.2 Design Discharge and net irrigable area of Main Canals
Conveyance Off taking Q(m3/
Parent canal Net IA, ha
system canals s)
0.0
MC TC0-0-1 18.18
5
0.1
,, TC0-0-2 54.10
5
0.2
,, TC0-0-3 87.34
4
0.1
,, TC0-0-4 56.52
6
0.1
,, TC0-0-5 49.21
4
0.2
,, Gravity SC 0-1 91.87
5
0.5
,, SC 0-2 179.10
0
0.1
,, SC 0-3 56.70
6
0.2
,, SC 0-4 87.15
4
0.5
,, SC 0-5 184.98
1
sub-total 2.4
,, 865.16
gravity 0
Table 6.2 cont’d: Design Discharge and net irrigable area of PC-1
parent canal
Off
Q(m3/
taking Net IA, ha Off taking canals Net IA, ha Q(m3/s)
s)
canals
132. 0.3 45.6
SC 1-1 SC 1-16 0.11
13 2 4
86. 0.2 157.4
SC 1-2 SC 1-17 0.39
25 1 1
274. 0.6 47.1
SC 1-3 TC1-0-3 0.12
27 7 3
282. 0.6 132.1
SC 1-4 SC 1-18 0.32
49 9 9
SC 1-5 199. 0.4 SC 1-19 169.7 0.42
Page | 85
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
74 9 7
231. 0.5 123.
SC 1-6 SC 1-20 0.30
45 7 56
247. 0.6 68.
SC 1-7 SC 1-21 0.17
65 1 56
153. 0.3 181.
SC 1-8 SC 1-22 0.44
12 7 69
49. 0.1 233.
SC 1-9 SC 1-23 0.57
56 2 12
TC1-0- 30. 0.0 177.
SC 1-24 0.43
1 87 8 48
SC 1- 68. 0.1 286.
SC 1-25 0.70
10 38 7 38
SC 1- 78. 0.1 376.
SC 1-26 0.92
11 78 9 98
SC 1- 126. 0.3 245.
SC 1-27 0.60
12 11 1 35
SC 1- 173. 0.4 66.
TC1-0-4 0.16
13 92 3 93
SC 1- 121. 0.3 29.
TC1-0-5 0.07
14 10 0 63
TC1-0- 11. 0.0 183.
SC 1-28 0.45
2 75 3 29
SC 1- 72. 0.1 116.
SC 1-29 0.28
15 88 8 17
Sub- total PC-1
4,981.73 12.19
gravity
Table 6.2 Cont’d: Design Discharge and net irrigable area of PC-2
parent canal
Conveyance Off taking Q(m3/
Parent canals Net IA, ha
system canals s)
Gravity 0.9
PC-2 SC 2-1 378.247
3
0.4
,, SC 2-2 194.583
2
0.9
,, SC 2-3 374.399
1
0.9
,, SC 2-4 399.555
0
0.7
,, SC 2-5 325.276
9
1.0
,, SC 2-6 415.193
1
0.1
,, SC 2-7 42.025
0
0.3
,, SC 2-8 151.579
7
,, SC 2-9 65.137 0.1
6
Page | 86
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
5.5
,, total 2316.356
6
The delineation of GIS command area is made by considering many factors.
Some of the factors considered included but not limited to; topographic
conditions of the scheme area, the availability of resources (water and
soils/land suitability), involvement of canal structures (type, size, quantity
etc.) total cost involvement to develop the scheme, power requirement to
lift the irrigation water, etc. Accordingly, the total GIS command are
determined to be about 8,163.24ha gravity irrigation system.
During the planning process for the irrigation system, canal layout involves
the determination of an important parameter called full supply levels (FSL)
at various points of the canal system and preparation of a complete working
head at the different reach of the entire canal system from main canal up to
field canals. The following points have been taken into consideration for
preparing the command statement.
Critical point: It is the spot, which requires highest water level due to the
combined impact of spot level in terms of elevation and its distance from
the irrigation channel /outlet. Thus, the critical point has been identified.
Head over the field: – It has been assumed that the depth of water should
be a minimum of 0.15m over the critical spot level.
Canal head losses: - In order not to lose any command area all, the canal
head losses in the canal system should be identified and the minimum
practical structure losses should be added on the calculated Critical Ground
Level and the adopted minimum head over the field, which is 0.15m. The
minimum canal and structure head loses used are given here below (Table
6.3).
Table 6.3 Canal Head Losses
S/N Description Head Loss, M Remark
Page | 87
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Working Head: It is required to provide working head at the head of the off
taking channel, which is the difference in the FSL of the parent channel and
that of the off taking channel, in order to facilitate the flow of the design
discharge. To overcome such problems, the following working head has
been adopted:
All the canals have been considered as a trapezoidal shape and are
designed using Manning’s formula as defined below:
A×R2/3 ×s 1/2
Q=
n
Page | 88
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
:
R = hydraulic radius
s = hydraulic gradient
n = Manning’s roughness coefficient
Page | 89
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The type material on the side and bed of the canal as well as the Channel
alignment (sinuosity) has an influence on the value of roughness coefficient.
The selected manning roughness coefficient, n, of 0.025 for unlined canals
and 0.018 for concrete lined main and primary canals has been used for the
project.
Table 6.5 Recommended values of Manning roughness coefficient
for lined and unlined canals
Manning’s roughness coefficient
Type of canal surface
“n”
Masonry 0.025-0.035
No vegetation 0.023-0.030
Page | 90
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The side slopes of a canal depend upon the stability of the material in
which it is constructed. Accordingly, the side slopes that has been used for
the design of canals are listed in the following table 6.6
Canal Name Side Slope (1V: m H)
τ = CWRs, where:
C = Coefficient depending on the shape of the channel and the
part of the canal considered.
W = Specific weight of water (9 810 N/m3).
R = Hydraulic radius (flow area / wetted perimeter).
S = Hydraulic gradient.
The unit tractive force is not uniformly distributed along the wetted
perimeter and the value of C on the sides and bottom of a trapezoidal
channel is different. However, the tractive force on the bed is greater than
that on the sides; hence the bed value is used in comparison with the
permissible tractive force. The permissible tractive force of up to 3.0
Page | 91
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
N/m2was taken for the design of canals. A trial-and-error process has been
followed to establish the maximum allowable slope of canals for a particular
discharge to ensure that the tractive force does not exceed the permissible
limit. Accordingly, the permissible velocity of 0.30m/s to 0.90m/s has been
adapted. The recommended C values are given in Table 6.7.
For unlined canals in non-cohesive material the minimum stable b/d ratio
can be determine by Lacey water surface width formula
The USBR recommends two types of canal freeboard. Canal lining and
canal banks should be extended above the normal full supply level as a
safety measure to protect the conveyance system from overtopping. The
Page | 92
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
free board values adapted for design of secondary canals are presented in
Table 6.8.
For the tertiary and quaternary canals, the freeboard has been set to be
0.2m and 0.15m, respectively.
Bank back slopes are chosen to maintain the seepage phreatic surface at
least 0.3 m within the toe of the embankment for canals in fill. The seepage
(hydraulic) gradient adopted generally varies from 1 in 3 (for heavy soils) to
1 in 7 (for light soils). To fulfill these criterion counter-berms (i.e., berms on
the outer bank) may be cost effective.
Page | 93
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Whenever the topography permits, the radius is set to a value greater than
the minimum defined in Table 6.10.
Table 6.2 Minimum canal radii for canals under sub-critical flow
Unlined 7T – 10T
Lined 3T
a) The ground level profiles along the final alignment of the canal
have been taken.
b) The canal Full Supply Level at the head of each canal has been
fixed and longitudinal profile of each canal computed by using
the canal cross section parameters. The head losses at canal
regulators, siphons, etc. has been determined from their
designs and incorporated in on L-section design.
c) Checking whether or not the full supply level of the off-taking
channel has the required working head, if not revise the up-
stream water surface profile until it attains the working head
requirement.
For construction use the canal setting out data and parameter table showing the canal
centerline and structure location, as well as the canal cross and longitudinal section
parameter are prepared.
Page | 94
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 95
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
9 1
1.7 4.8
21270 7347.29 8.60 0.953 19.1 20.00 55.556 1.50 20.053 15.016 1.335
8 3
1.7 6.3
TC0-0-5 21340.07 7347.29 11.20 0.959 19.1 20.00 55.556 0.00 19.913 14.756 1.349
8 0
1.7 6.3
PC1 & 2 22775.8 7298.08 11.20 0.957 19.0 20.00 55.556 0.00 19.823 14.740 1.345
7 3
Page | 96
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 97
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 98
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
0 8 6
3.0 1.4 2.0
PC-10 42726.19 1715.32 0.958 7.26 33.33 55.556 1.50 7.586 8.268 0.917
0 6 5
3.0 1.1 2.7
SC 1-23 43504.25 1715.32 0.824 4.20 33.33 55.556 1.50 5.092 6.953 0.732
0 0 4
2.4 1.1 2.2
SC 1-24 47100.39 1482.21 0.802 3.63 33.33 55.556 1.50 4.523 6.434 0.703
8 0 6
2.3 1.1 2.1
SC 1-25 48557.72 1304.73 0.795 3.47 33.33 55.556 1.50 4.369 6.294 0.694
4 0 3
2.3 1.1 2.1
SC 1-26 48571.82 1018.35 0.795 3.47 33.33 55.556 1.50 4.369 6.294 0.694
4 0 3
3.2 1.1 2.9
SC 1-27 51734.89 641.37 0.646 3.47 20.00 55.556 1.50 5.377 7.209 0.746
5 0 6
3.2 1.1 2.9
TC1-0-4 53064.87 396.02 0.646 3.47 20.00 55.556 1.50 5.377 7.209 0.746
5 0 6
3.2 1.1 2.9
TC1-0-5 53549.03 329.09 0.646 3.47 20.00 55.556 1.50 5.377 7.209 0.746
5 0 6
3.2 1.1 2.9
PC-11, 12 54176 299.46 0.646 3.47 20.00 55.556 1.50 5.377 7.209 0.746
5 0 6
1.5 0.7 2.0
PC-13 56628.04 299.46 0.463 1.15 20.00 55.556 2.50 2.480 5.487 0.452
0 4 3
1.5 0.6 2.2
SC 1-28 56730.26 299.46 0.444 0.73 20.00 55.556 1.50 1.652 3.888 0.425
0 6 6
0.7 0.5 1.4
SC 1-29 56741.38 116.17 0.355 0.28 20.00 55.556 1.50 0.800 2.632 0.304
5 2 4
Page | 99
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Table 6.14 Summarized GIS command area and length of canals for gravity system
Page | 100
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
(m) (m) s s
Page | 101
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The drain discharge or duty from the smaller catchments of up to 12km 2 can
be estimated from the Rational Formula Method given by the following
equation:
Page | 102
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Q = 0.278 x C x I x A
Where;
Q = flood peak at drainage (m3/s)
C = runoff coefficient that is the ratio between the runoff volume from an
area and the average rate of rainfall depth over a given duration for that
area.
I = rainfall intensity from intensity-duration-frequency curve (mm/hr) for a
duration equal to the time of concentration, tc.
A = catchment area (km2)
Where the catchment area is more than 12km 2, adjustments are applied to
prevent over estimation of the design flood. The Nigerian Highway Manual
recommended a conversion factor given in equation:
1
Reductionfactor= 12
(1− )
A
e
Where, A is the catchment area in km2.
(The following analysis has been taken from hydrology study report, February 2020)
Kn
I =
( t + a )b
Where I = Rainfall Intensity inches / hour.
Page | 103
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
K n = A + B log 10 N
a, b, A & B = Station Constants.
N is the Storm frequency
The values of the Station Constant are presented in Table 7.1. Federal
Ministry of Works Highway Manual Part 1: Design Volume IV: Drainage
Design (2013) recommended that the same station constants can be
assumed for areas of the country having similar rainfall regime but to
proportion the rainfall intensity to the total rainfall. In areas of similar
regimes, the rainfall intensities would be proportional to the total rainfall as
those already established in proportion to the total rainfall i.e., ratio of AAR
of 917mm for Yola to AAR of 926mm for Kano. The conversion factor of
917mm/926mm or 0.9902801is applied.
Constants
Station
a b A B
Guyuk near Yola rainfall pattern is considered similar to Kano, therefore, the
rainfall intensity at Guyuk can be estimated by equation: -
Page | 104
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
250.00
Rainfall Intensity (mm/hr)
200.00
150.00
100.00
50.00
0.00
0 10 20 30 40 50 60 70 80 90 100
Return Period (Years)
30.00
Rainfall Intensity (mm/hr)
25.00
20.00
15.00
10.00
5.00
0.00
0 10 20 30 40 50 60 70 80 90 100
Return Period (Years)
Page | 105
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The drains are designed to dispose the volume of runoff from a 1 in 5 years,
24hrs storm, in the same day. Hence, from Table 7.3, the value of I is
3.97mm/hr. the value of the coefficient, C, is given according to the type of
the soil. Summary of the calculated drain discharge for four different soil
types is presented below:
There are 13 interceptor drains (ID-1, ID-2… ID-13), which are generally
aligned parallel to the primary canals i.e., the primary canals, which
serves pumped command areas, to intercept and convey local sheet
runoff arising from areas upstream of the command area and dispose the
flood in to natural drainage channels. They are usually well-defined
watercourses, which usually require channeling, stabilization measures
and/or bank protection.
Page | 106
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The hydraulic design of the drainage canal is carried out using maximum
discharge flood. The hydraulic parameters are designed based on the
principle that if the velocity is high, scouring will occur, but when the
velocity is low, silting occurs. Such channels should be designed for a
non- scouring and non -silting velocity.
Side slope of 1.5 to 2.0 is used depending in the free board size of the flow.
Page | 107
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 108
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Since the dike is likely to come in contact with high velocity currents, the
waterside should be provided with stone pitching over a layer of filter.
Therefore, a 0.20 m thickness of stone pitching with 0.10 m thickness layer
of gravel and 0.10 m thickness layer of filter material (sand) is provided. In
addition, the d/s face has to be protected from any external load that would
erode the soil and hence grass should be planted on the d/s face.
7.6 Infield drainage systems
The excess water arising, either from irrigation supplies or from excessive
rainfall over the irrigated land will be collected by a network of infield
drainages from field drains up to secondary drains. Field drains collect
excess water from the field area of about 5 ha which is half of the basic
irrigation unit and their FSL will be fixed at least 0.15 below the ground
level. Tertiary Drains will collect excess surface water directly from field
drains and the design water level should be the minimum ground level for
the fields being drained, or 0.2-0.30 m below the average field level or at
least about 0.05 - 0.10 m below the FSL of the field drains. The design water
level in secondary Drains is dependent on the water levels required by the
Tertiary Drains where they join.
Similarly, the water levels in the secondary drains are kept below the water
level in tertiary drains. Normally the drop at drain junctions will be minimal,
about 0.05 - 0.10 m. However, the design water level in the drainage
channels should ideally always remain below natural ground level and drain
drops will be allowed up to 1.0 m where required.
Page | 109
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
• Channel Roughness
The channels are designed for a Manning’s n value assuming the channel is
established with some weed growth and not freshly dug. A Manning’s n of
0.025 is likely to be suitable.
The longitudinal slope and prism design should result in suitable flow
velocities. Longitudinal slopes of a drainage channel normally decrease
going downstream as design discharge increases.
Page | 110
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Side slopes for a trapezoidal drain section depend on the type of material in
which the drain is constructed. Recommended side slopes are given in
Table 7.7.
Side Slope
Type of Soil
(1V: H)
Field Drain 0.5
Tertiary Drain 1.0
Secondary Drains 1.5
Interceptor Drain 1.5
• Freeboard
The design discharge and design water level are based on a rainfall event
with a five-year return period. To ensure that floodwater flowing in a
drainage channel will not overtop the channel section at any point and
cause flooding of adjacent land free board should be provided to the
drainage channels (Table 7.8).
Wherever possible the drain alignments should follow a straight line. Where
a curve is unavoidable, it is desirable to ensure that radius is not too small,
to avoid erosion on the outside of the bend in unlined canals. Limits are
Page | 111
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
also advisable for lined canals, to ensure that the head loss is not excessive
and the flow remains uniform.
Page | 112
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
8.0 LANDLEVELING
The most ideal field surface for irrigated agricultural production is a plane
surface on a nearly leveled grade. Like-wise, the least desirable is one with
such surface relief that irrigation can barely be accomplished and that
unusually good management is required to obtain even fair irrigation water
efficiencies. Accordingly, in order to obtain suitable field surface throughout
the command area of the scheme, the application of land leveling practice
might be required. Stages of land leveling include:
Page | 113
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The canal structures include all canal structures like storm water crossing,
canal siphons, falls, and road culverts. The regulating structures are cross
regulators, head regulators, pond intake & escape structures. The
structures dividing the flow in secondary, tertiary and field though regulate
the flow, in a broader term have been termed as flow division structures.
The protective structures, which externally protect the canal from storm
water, have also referred as cross drainage structures and the structures,
which internally safeguard the canal from the excess canal water, have
been named as escape structures. The cross-drainage structures would
direct the storm water runoff either under the canal or over the canal.
For Guyuk project, the hydraulic structures have been categorized as:
Page | 114
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Fall (Drop
CR HR Offtake
Canal structure) FC C Aquedu Sipho Pump Bifurcation
(from
Name M P T S S T Offtake D ct n station structure
PC SC TC FC NSR)
C C C C C C
MC 16 35 4 4 5 5 6 1 1
SC 8 4 125
19 16 2
PC-1 4 7 5 619 8 1
8 1 9
PC-2 1 66 59 4 4 9 4 324 7 1 1
28 25 1 4 1 2
Total 1 0 5 12 4 1 0 8 3 8 1068 0 1 2 2 0 1
Page | 115
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
A head regulator (HR) is provided at the head of off-taking channel, and its
main purpose is control of discharge entering in to the off taking channel. A
Cross regulator (CR) on the other hand is located at the downstream side of
an off taking point on the continuing channel. Its main purpose is to head
up water level so that FSL of the off-taking canal can be met.
The head and cross regulating structures would be equipped with a vertical
gate. The flow under gated structure can be divided into free flow, drowned
orifice flow, and closed conveyance flow. The formula for the free flow is
different from that of the drowned and closed conveyance flow. As a result,
flow condition under the get has to be checked first.
The Cross regulators (CR) on the main canals are provided where the
secondary/tertiary canals off-take from the main canals and are located at
the downstream of the off-taking canal. The Main Canal has four cross
regulators; each will be incorporated with a Vertical lift gates. All of the
cross regulators are designed as ‘Drowned Orifice Flow’ condition which the
driving head is the difference between the upstream and downstream
energy levels. The maximum driving head of 0.2 m has been taken.
Page | 116
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The details of Main Canal Head and Cross regulators parameters & the
typical plan drawing are provided on the soft cope
A head regulator (HR) is provided at the head of off-taking channel, and its
main purpose is control of discharge entering in to the off taking channel. A
gated head regulator has been provided at all points where the primary
canal and secondary canals off take from the Main Canal. All of the head
regulators are designed as ‘Drowned Orifice Flow’ condition with maximum
driving head of 0.3 m or above. The head regulator structure incorporated a
pipe to cross under the canal embankment and the access road. The
maximum length of pipe will be about 6-13 m. The parameters for these
structures are presented in Table 10.2.
Page | 117
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Q=C D Bw √ 2 g y 1
√ 1+
w
y1
Where, y1 is the u/s flow depth in m
w is the gate opening in m
CD is the discharge coefficient, dimensionless
is the contraction coefficient of the jet (usually taken as
0.6
A gated cross regulator has been provided at all secondary canal off takes.
The entire cross regulators are design as ‘Drowned Orifice Flow’ condition in
which the driving head is the difference between the upstream and
downstream energy levels. The maximum driving head of 0.2m has been
taken.
The details of Primary Canal Head and Cross regulators parameters & the
typical plan drawing are provided in the following Table 10.3 and on Figure
10.2.
Page | 118
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
PC2_1-9
PCR 01-9 6860.00 SHR01 6.801 5.822 0.542 1x3 1.4 x 1.4 1x1 0.8 x 0.9
PCR 01-10 9650.00 SHR01 4.926 4.108 0.116 1x3 1.8 x 1.8 1x1 0.5 x 0.6
PCR 01-11 12280.00 SHR01 3.147 3.056 0.160 1x2 1.3 x 1.3 1x1 0.5 x 0.6
PCR 01-12 16500.00 SHR01 2.728 2.566 0.407 1x2 1.2 x 1.2 1x1 0.8 x 0.9
PCR 01-14 23200.00 SHR01 2.365 1.778 0.369 1x2 1.2 x 1.2 1x1 0.8 x 0.9
PCR 01-15 26580.00 SHR01 1.778 1.292 0.291 1x2 0.9 x 0.9 1x1 0.6 x 0.7
PCR 01-17 31800.00 SHR01 1.257 1.027 0.416 1x1 1.5 x 1.5 1x1 0.8 x 0.9
PCR 01-18 36000.00 SHR01 0.751 0.530 0.575 1x1 1.0 x 1.0 1x1 0.9 x 0.9
PCR 01-19 37900.00 SHR01 0.530 0.335 1.320 1x1 0.9 x 0.9 1x2 0.9 x 0.9
PCR 01-20 41521.26 SHR02 0.195 0.195 0.273 1x1 0.5 x 0.6 1x1 0.6 x 0.7
Page | 119
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
A gated head regulator has been provided at all secondary canal off takes
from the main & Primary Canal. All of the head regulators are design as
‘Drowned Orifice Flow’ condition with maximum driving head of 0.3m. The
secondary head regulator structure will incorporate a pipe to cross under
Page | 120
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
the canal embankment and the access road. The maximum length of pipe
will be about 15 m. The details of Secondary Canal Head and Cross
regulators parameters & the typical plan drawing are provided in the
following Table 9.4 and on Figure 9.3.
Cross-regulator Off-taking PC design Offtakin Gate opening size and Number (WxH,
Primary / Discharge(m3/s) g N)
Referenc Chainage( Secondar Up Down Dischar Cross Regulator Head Regulator
e m) y Canals stream stream ge
(m3/s) CRN, Size HRN, size*(w*
GN (W*H) GN H)
MC_SCR
SCR01 29.8 THR01 0.217 0.217 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR02 539.87 THR02 0.121 0.121 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR03 1049.9 THR03 0.062 0.062 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR04 1559.91 THR04 0.018 0.018 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 30.12 THR01 0.143 0.8 x 0.9 1x1 0.5 x 0.6
0.420 0.420 1x1
SCR02 541.12 THR02 0.114 0.7 x 0.8 1x1 0.5 x 0.6
0.281 0.281 1x1
SCR03 1051.15 THR03 0.114 0.5 x 0.6 1x1 0.5 x 0.6
0.166 0.166 1x1
SCR04 1561.46 THR04 0.114 0.3 x 1x1 0.5 x 0.6
0.077 0.077 1x1 0.45
SCR01 52.16 THR01 1x1 0.5 x 0.6 1x1 0.5 x 0.6
0.134 0.134 0.114
SCR02 570.30 THR02 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.058 0.058 0.45
SCR03 1044.95 THR03 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.029 0.029 0.45
SCR01 52.16 THR01 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
0.205 0.205
SCR02 569.36 THR02 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
0.126 0.126
SCR03 1043.97 THR03 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.038 0.038 0.45
SCR01 49.30 THR01 1x1 0.8 x 0.9 1x1 0.5 x 0.6
0.434 0.434 0.131
SCR02 111.20 THR02 1x1 0.7 x 0.8 1x1
0.307 0.307 0.114 0.5 x 0.6
SCR03 837.90 THR03 0.212 0.212 1x1 0.5 x 0.6 1x1
0.114 0.5 x 0.6
SCR04 1595.66 THR04 0.106 0.106 1x1 0.5 x 0.6 1x1
0.114 0.5 x 0.6
Cross-regulator Off-taking PC design Offtakin Gate opening size and Number (WxH,
Primary / Discharge(m3/s) g N)
Referenc Chainage Secondar Up Down Dischar Cross Regulator Head Regulator
e (m) y Canals stream stream ge
(m3/s) CRN, Size HRN, size*(w*
GN (W*H) GN H)
PC1_S
CR
SCR01 50.32 THR01 0.311 0.311 0.134 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR02 327.44 THR02 0.179 0.179 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR03 1138.74 THR03 0.097 0.097 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
Page | 121
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
SCR04 1643.09 THR04 0.032 0.032 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 31.65 THR01 0.201 0.201 0.173 1x1 0.5 x 0.6 1x1 0.6 x 0.7
SCR02 551.76 THR02 0.034 0.034 0.117 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 86.68 THR01 0.647 0.647 0.119 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR02 613.25 THR02 0.530 0.530 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR03 973.37 THR03 0.467 0.467 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR04 1452.46 THR04 0.403 0.403 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR05 2603.53 THR05 0.361 0.361 0.172 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR06 2610.54 THR06 0.189 0.189 0.192 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01& 44.52 THR01&0 0.664 0.664 0.130 1x1 0.5 x 0.6 1x1 0.5 x 0.6
02 2
SCR03 547.64 THR03 0.437 0.437 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR04 1057.73 THR04 0.324 0.324 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR05 1578.74 THR05 0.229 0.229 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR06 2093.57 THR06 0.132 0.132 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR07 2608.40 THR07 0.035 0.035 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 67.34 THR01 0.469 0.469 0.127 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR02 690.16 THR02 0.319 0.319 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR03 1269.55 THR03 0.268 0.268 0.138 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR04 1784.35 THR04 0.131 0.131 0.132 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 42.57 THR01 0.542 0.542 0.197 1x1 0.9 x 0.9 1x1 0.6 x 0.7
SCR02 448.00 THR02 0.345 0.345 0.136 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR03 948.00 THR03 0.210 0.210 0.136 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR04 1448.00 THR04 0.076 0.076 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 79.26 THR01 0.583 0.583 0.138 1x1 0.9 x 0.9 1x1 0.5 x 0.6
SCR02 903.15 THR02 0.445 0.445 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR03 1432.69 THR03 0.356 0.356 0.136 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR04 1932.69 THR04 0.220 0.220 0.136 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR05 2432.69 THR05 0.085 0.085 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01& 32.65 THR01&0 0.358 0.358 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
02 2
SCR03 368.76 THR03 0.239 0.239 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR04 881.12 THR04 0.139 0.139 0.141 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 224.56 THR01 0.116 0.116 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR02 409.73 THR02 0.047 0.047 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 30.30 THR01 0.160 0.160 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR02 428.99 THR02 0.066 0.066 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 100.00 THR01 0.185 0.185 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR02 565.12 THR02 0.081 0.081 0.139 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR03 1065.12 THR03 0.033 0.033 0.147 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 16.85 THR01 0.295 0.295 0.140 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR02 527.16 THR02 0.158 0.158 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR03 939.60 THR03 0.048 0.048 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 34.00 THR01 0.407 0.407 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
Page | 122
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
SCR02 518.90 THR02 0.334 0.334 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR03 692.87 THR03 0.233 0.233 0.128 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR04 1049.15 THR04 0.107 0.107 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 30.00 THR01 0.287 0.287 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR02 963.64 THR02 0.207 0.207 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR03 1267.15 THR03 0.153 0.153 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR04 1772.30 THR04 0.101 0.101 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR05 2300.08 THR05 0.046 0.046 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
0 0.114 1x1 0.5 x 0.6
SCR01& 78.10 THR01&0 0.169 0.169 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
02 2
SCR01 207.66 THR01 0.109 0.109 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR02 660.90 THR02 0.073 0.073 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR03 1113.00 THR03 0.039 0.039 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 69.50 THR01 0.369 0.369 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR02 486.20 THR02 0.303 0.303 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR03 812.23 THR03 0.254 0.254 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR04 1211.57 THR04 0.150 0.150 0.153 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 29.29 THR01 0.308 0.308 0.160 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR02 417.70 THR02 0.151 0.151 0.155 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 34.78 THR01 0.399 0.399 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR02 502.70 THR02 0.330 0.330 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR03 972.40 THR03 0.262 0.262 0.140 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR04 1484.84 THR04 0.124 0.124 0.126 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 34.80 THR01 0.291 0.291 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR02 494.40 THR02 0.216 0.216 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR03 882.20 THR03 0.151 0.151 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR04 1051.55 THR04 0.107 0.107 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR05 1565.43 THR05 0.046 0.046 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 91.41 THR01 0.162 0.162 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR02 591.64 THR02 0.080 0.080 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR03 1105.40 THR03 0.033 0.033 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 77.53 THR01 0.428 0.428 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR02 582.00 THR02 0.369 0.369 0.114 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR03 1100.90 THR03 0.309 0.309 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR04 1628.00 THR04 0.247 0.247 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR05 1981.71 THR05 0.154 0.154 0.155 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 129.54 THR01 0.546 0.546 0.126 1x1 0.9 x 0.9 1x1 0.5 x 0.6
SCR02 576.18 THR02 0.422 0.422 0.148 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR03 900.97 THR03 0.275 0.275 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR04 1305.60 THR04 0.162 0.162 0.164 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 69.27 THR01 0.416 0.416 0.156 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR02 576.30 THR02 0.264 0.264 0.143 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR03 1095.30 THR03 0.123 0.123 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR04 1612.65 THR04 0.052 0.052 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
Page | 123
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
SCR01 108.40 THR01 0.672 0.672 0.158 1x1 1.0 x 1.0 1x1 0.5 x 0.6
SCR02 608.40 THR02 0.517 0.517 0.160 1x1 0.9 x 0.9 1x1 0.5 x 0.6
SCR03 1108.40 THR03 0.358 0.358 0.157 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR04 1608.40 THR04 0.203 0.203 0.152 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR05 2108.41 THR05 0.053 0.053 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
SCR01 115.80 THR01 0.885 0.885 0.132 1x1 1.1 x 1.1 1x1 0.5 x 0.6
SCR02 615.80 THR02 0.756 0.756 0.137 1x1 1.0 x 1.0 1x1 0.5 x 0.6
SCR03 1115.80 THR03 0.620 0.620 0.130 1x1 1.0 x 1.0 1x1 0.5 x 0.6
SCR04 1615.80 THR04 0.491 0.491 0.130 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR05 2115.80 THR05 0.363 0.363 0.208 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR06 2203.83 THR06 0.159 0.159 0.163 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 38.66 THR01 0.575 0.575 0.141 1x1 0.9 x 0.9 1x1 0.5 x 0.6
SCR02 633.70 THR02 0.437 0.437 0.165 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR03 1203.00 THR03 0.274 0.274 0.156 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR04 1698.29 THR04 0.120 0.120 0.121 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 121.30 THR01 0.427 0.427 0.142 1x1 0.8 x 0.9 1x1 0.5 x 0.6
SCR02 644.40 THR02 0.286 0.286 0.150 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR03 1180.23 THR03 0.138 0.138 0.142 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR01 121.90 THR01 0.273 0.273 0.114 1x1 0.7 x 0.8 1x1 0.5 x 0.6
SCR02 621.90 THR02 0.187 0.187 0.114 1x1 0.5 x 0.6 1x1 0.5 x 0.6
SCR03 1121.91 THR03 0.091 0.091 0.114 1x1 0.3 x 1x1 0.5 x 0.6
0.45
Cross-regulator Off-taking PC design Off Gate opening size and Number (WxH, N)
Primary / Discharge(m3/s) taking
Referenc Chainag Secondar Up Down Dischar Cross Regulator Head Regulator
e e (m) y Canals stream stream ge
(m3/s) CRN, GN Size HRN, size*(w*
(W*H) GN H)
PC2_SC
R
SCR01 180 THR 2-1-3 0.856 0.856 0.114 1x1 1.1 x 1x1 0.5 x 0.6
1.1
SCR02 442 THR 2-1-4 0.739 0.739 0.186 1x1 1.0 x 1x1 0.6 x 0.7
1.0
SCR03 943 THR 2-1-5 0.557 0.557 0.180 1x1 0.9 x 1x1 0.6 x 0.7
0.9
SCR04 1276 THR 2-1-6 0.379 0.379 0.198 1x1 0.8 x 1x1 0.6 x 0.7
0.9
SCR05 1821.28 THR 2-1-7 0.189 0.5 x 1x1 0.6 x 0.7
0.186 0.186 1x1 0.6
SCR01 180.00 THR 2-2-3 0.3 x 1x1 0.5 x 0.6
0.061 0.061 0.114 1x1 0.45
SCR01 120.00 THR 2-3-2 0.8 x 1x1 0.5 x 0.6
0.436 0.436 0.114 1x1 0.9
SCR02 230.00 THR 2-3-3 0.8 x 1x1 0.5 x 0.6
0.390 0.390 0.149 1x1 0.9
SCR03 762.00 THR 2-3-4 1x1 0.5 x 1x1 0.5 x 0.6
0.244 0.244 0.114 0.6
SCR04 1262.00 THR 2-3-5 1x1 0.5 x 1x1 0.5 x 0.6
0.137 0.137 0.121 0.6
SCR05 1761.72 THR 2-3-6 1x1 0.3 x 1x1 0.5 x 0.6
0.017 0.017 0.114 0.45
SCR01 200.00 THR2-4-2 0.167 1x1 1.2 x 1x1 0.5 x 0.6
0.924 0.924 1.2
SCR02 580.00 THR2-4-3 0.175 1x1 1.0 x 1x1 0.6 x 0.7
0.759 0.759 1.0
Page | 124
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 125
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 126
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
A gated head regulator has been provided at all tertiary canal off takes and
the gates are simple vertical lift gates that can be operated by an
individual. The tertiary head regulator/field canal off take structure will
incorporate a pipe to cross under the canal embankment and the access
road. A standard tertiary canal field canal off take is prepared for
discharges of 0.9m3/sec and are designed with maximum length of pipe will
be about 4 m for a maximum driving head of 0.1m.
The details of Tertiary Canal Head and Cross regulators parameters & the
typical plan drawing are provided in the following Table 10.5 and on Figure
9.3 below.
Page | 127
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The structure was designed using the same design principles for cross and
head regulator as ‘Drowned Orifice Flow’ condition in which the driving
head is the difference between the upstream and downstream energy
levels.
Page | 128
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The side channel spillway is used for the emergency escape structures &
equated using broad crested weir formula:
Length of spillway channel, Q=CLH3/2
Where, L: Length of weir
C: 1.705 for broad crest weir
H: Head over crest in m
H=h+ (v2/2g)
Escapes allow release of water from a channel and are generally provided
upstream of inverted siphons and other structures protected by trash
screens, in case they become blocked.
Side spillway weirs are used for the emergency escape structures. The
discharge over the weir is obtained from the following formula:
Q = 1.7 L h 3/2
where
:
Q = Discharge (m3/s).
L = Weir crest length (m)
h = Head over the weir (m)
Condition for calculation
Water level at the beginning point of the side spill channel is same
one as the crest level of weir.
Assumed water surface slope is as straight line.
Assumed maximum velocity is as 3m/s and that the water depth is
the same as the height of pipe at the end point.
Sluice Escape
Page | 129
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The discharge over the sluice escape is obtained from the following
formula:
Qe =V * A = =V * ((b + m*h1x2) +m x h) * h
Where, Qe = Escape discharge
V=velocity in main canal
A: flow Area above FSL at the canal
b: Bed width of canal
m: side slop inside of canal
h: Depth over flow the crest
h1: Flow depth canal
Page | 130
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
A vertical drop structure has a vertical wall between the control and the
stilling basin. The small portion of energy loss occurs by impact of the jet on
the floor. The major portion of energy loss occurs by turbulence in the
stilling basin.
Vertical drop is the most common drop structure that has an aerated free-
falling nappe, which hits the downstream basin floor/cistern. The turbulent
flow in the basin is one of the stages of energy dissipation. The most
Page | 131
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
important part of the hydraulic design of the vertical drop structure is the
design of the stilling basin.
Vertical drop stilling basins are characterized by, a free-falling jet into the
basin. The free-falling jet makes an impact with the basin floor and is turned
into the downstream direction. The basin is equipped with an end sill. Up to
50% of the energy may be dissipated by the impact of the jet and by the
turbulent circulation in the pool beneath the jet. The remainder part is
dissipated by the hydraulic jump in the basin. Even if the vertical drop
stilling basin seems easy to construct, but it has to be well checked on uplift
of the floor by groundwater pressure.
Vertical drops become rather massive structures for large drop heights. In
addition, their hydraulic performance may decrease because of variation in
the place where the jet strikes the basin floor where the discharge changes.
Straight drops are not recommended if the change in energy head over the
structure exceeds 1.50m.
The size of the length of basin/cistern has been determined with the
following equation (USBR):
3
dc dc
L=[2.5+1.1 + 0.79( ) ] √h d c
h h
' dc
h=
2
For GIS project a standard drop height of 0.5m, 1.0m, 1.5m, and 2.0m have
been adapted and accordingly a range of standard vertical drop structures
have been designed for discharges from 0.114 to 1.4 m3/s for primary,
secondary tertiary and Field canals. The details of standard vertical drop
structures are provided on Figure 9.5 below.
Page | 132
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
The need for cross drainage structures results from the flow of drainage or
storm runoff water from the high side of the channel to the low side. To
protect the channel from such flows, cross drainage structures will be
provided. While the alignment of a channel usually follows natural ground
contours, it is often necessary to cross natural drainage channels. In
crossing large natural drainage channels, the channel flow is usually
conveyed in an aqueduct over, or in an inverted siphon under, the drainage
channel. For small drainage flows, it may be cheaper for the drainage flow
to be passed under, over or into a channel using one of the following cross
drainage structures:
Page | 133
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Cross drainage structures are provided on the main and Primary Canals on
locations where there are major tributaries of Gongola River. The location
and type of cross drainage structures have been identified and designed
according to the design criteria.
Drainage culverts are suitable for carrying small drainage flows under a
channel which is in fill. Culverts are unsuitable for large cross drainage
flows which could be transporting boulders and other debris which would
block the culvert.
The cross-drainage structures provided on the main and Primary Canals are
categorized as pipe culvert, box culvert, Aqueduct and inverted siphon. For
hydraulic design of the cross-drainage structures, the 1 in 25-year return
period peak discharges have been adopted and the particular configuration
for each is summarized in Table 9.6.
Cross drainage structures are designed with 25-year return period flood
estimation as detail presented in Guyuk Hydrology report
CD Design
Name CH Discharge Q D Total loss
m (㎥/S) bxhxnr
2.5x2.25x
CD-0 MC1-1520 20.000 4 0.66
Syphon 01 MC 6260 202.7 2.5*2.5*2 1.0
2.5x2.25x
CD-2 MC1-10760 24.134 3 0.21
CD-3 MC1-14390 4.460 1.75x2x2 0.9
2.5x2.25x
CD-4 MC1-17230 26.730 4 0.66
2.5x2.25x
CD-5 MC1-18255 22.978 3 0.19
2.5x2.25x
CD-6 MC1-22020 22.685 3 0.18
3.5*1.83*
Syphon 2-1 PC2 (0+040-0+860) 21.8 1 0.60
1.25x1.5x
CD-7 PC2-2540 8.272 2 0.3
1.25x1.5x
CD-8 PC2-3980 7.331 2 0.26
CD-9 PC2-5620 7.266 1.25x1.5x 0.26
Page | 134
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
2
1.25x1.5x
CD-10 PC2-6140 7.266 2 0.25
1.25x1.5x
CD-11 PC2-9580 4.926 2 0.13
1.25x1.5x
CD-12 PC2-12180 3.147 2 0.06
1.25x1.5x
CD-13 PC2-13660 3.056 2 0.06
Aqueduct 4.25*2.0*
01 PC1-26140 26.9 1 0.40
2.5x2.25x
CD-14 PC1-30006 10.180 4 0.24
2.5x2.25x
CD-15 PC1-30247 8.430 4 0.17
2.5x2.25x
CD-16 PC1-31293 15.550 4 0.49
2.5x2.25x
CD-17 PC1-31815 10.590 4 0.26
2.5x2.25x
CD-18 PC1-33948 58.780 4 1.32
2.5x2.25x
CD-19 PC1-42206 41.750 4 0.67
2.5x2.25x
CD-20 PC1-42830 58.530 4 0.7
2.5x2.25x
CD-21 PC1-50310 46.650 4 0.68
2.5x2.25x
CD-22 PC1-54361 21.970 4 0.35
2.5x2.25x
CD-23 PC1-54844 26.490 4 0.47
Page | 135
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Canal Parameters:
Design Discharge of Canal 24 m3/s
Bed Width of Canal 10.0 m
Full Supply Depth 1.86 m
Canal Bed level at D/S 200.76 m
Side Slope of Canal 1.50 :1
Free Board 0.75 m
Drain Parameters:
Design Flood Discharge of Drain 202.7 m3/s
High Flood Level 201 M asl
Bed Level of Drain 197 m
The Designed feature of the Canal Syphon are as follows:
Canal Waterway
Number of tubes 2 No.
Width of Canal tube 2.5 m
Height of Canal tube 2.5 m
Thickness of tube wall 0.25 m
Length of Contraction Transition 5.0 m
Page | 136
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 137
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 138
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
ANNEX
A-1 HYDRULIC DESIGN OF MAJOR CANALS
A-1.1 Hydraulic Design of Main Canal
Page | 139
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
CH Canal Dis. Rou. F.S.D F.B Slope B SS BW A WP Hyd. Expon Chezy V Dis. Diffe B/D
Name Req. Coef. radius ential coef. Des. rence
From To m3/s m m m m m2 m m m0.5/s m/s m3/s m3/s
SC 1-1
- 1,263 12.20 0.02 1.82 0.60 5,350 5.00 1.50 2.00 14.08 11.57 1.22 0.17 57.41 0.87 12.20 (0.00) 2.75
SC 1-2
1,263 1,282 11.87 0.02 1.80 0.60 5,350 5.00 1.50 2.00 13.81 11.47 1.20 0.17 57.30 0.86 11.87 0.00 2.78
PC-
1,282 2,496 7,CR1 11.66 0.02 1.80 0.60 5,350 4.85 1.50 2.00 13.60 11.34 1.20 0.17 57.26 0.86 11.66 (0.00) 2.69
SC1-3
2,496 5,338 11.66 0.02 1.80 0.60 5,350 4.85 1.50 2.00 13.60 11.34 1.20 0.17 57.26 0.86 11.66 (0.00) 2.69
PC-
5,338 6,451 8,CR2 10.99 0.02 1.75 0.60 5,350 4.85 1.50 2.00 13.03 11.14 1.17 0.17 57.03 0.84 10.99 0.00 2.78
SC1-4
6,451 7,471 10.99 0.02 1.75 0.60 5,350 4.80 1.50 2.00 13.02 11.12 1.17 0.17 57.04 0.84 10.99 (0.00) 2.74
SC1-5
7,471 8,956 10.30 0.02 1.74 0.60 5,350 4.50 1.50 2.00 12.37 10.77 1.15 0.17 56.85 0.83 10.30 (0.00) 2.59
SC1-6
8,956 10,378 9.81 0.02 1.74 0.60 5,350 4.22 1.50 2.00 11.89 10.50 1.13 0.17 56.72 0.83 9.81 (0.00) 2.43
SC1-7
10,378 12,767 9.24 0.02 1.72 0.60 5,350 4.00 1.50 2.00 11.35 10.21 1.11 0.17 56.54 0.81 9.24 (0.00) 2.32
SC 1-
12,767 15,633 8,CR3 8.64 0.02 1.66 0.60 5,350 4.00 1.50 2.00 10.80 10.00 1.08 0.17 56.28 0.80 8.64 (0.00) 2.41
SC1-9
15,633 16,845 8.26 0.02 1.62 0.60 5,350 4.00 1.50 2.00 10.46 9.86 1.06 0.17 56.11 0.79 8.26 (0.00) 2.46
TC1-0-1
16,845 17,737 8.14 0.02 1.61 0.60 5,350 4.00 1.50 2.00 10.35 9.81 1.05 0.17 56.05 0.79 8.14 (0.00) 2.48
SC1-10
17,737 18,350 8.07 0.02 1.60 0.60 5,350 4.00 1.50 2.00 10.28 9.78 1.05 0.17 56.01 0.78 8.07 0.00 2.49
SC 1-11
18,350 25,079 7.90 0.02 1.59 0.60 5,350 4.00 1.50 2.00 10.12 9.72 1.04 0.17 55.93 0.78 7.90 0.00 2.52
SC 1-
25,079 25,080 12,CR4 7.82 0.02 1.52 0.60 4,250 3.75 1.50 2.00 9.21 9.25 1.00 0.17 55.51 0.85 7.82 0.00 2.46
SC1-13
25,080 28,901 7.82 0.02 1.52 0.60 4,250 3.75 1.50 2.00 9.21 9.25 1.00 0.17 55.51 0.85 7.82 0.00 2.46
PC-
28,901 31,098 9,CR5 7.82 0.02 1.52 0.60 4,250 3.75 1.50 2.00 9.21 9.25 1.00 0.17 55.51 0.85 7.82 0.00 2.46
SC1-14
31,098 31,171 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
TC1-0-2
31,171 31,357 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
Page | 140
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
SC1-15
31,357 32,811 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
SC1-16
32,811 32,826 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
SC 1-
32,826 33,100 17,CR6 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
TC1-0-3
33,100 36,345 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
SC1-18
36,345 37,499 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
SC1-19
37,499 39,591 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
SC1-20
39,591 39,603 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
SC1-21
39,603 41,959 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
SC1-22
41,959 42,120 7.26 0.02 1.51 0.60 4,250 3.50 1.50 2.00 8.69 8.94 0.97 0.17 55.29 0.84 7.26 0.00 2.32
PC-
42,120 42,596 10,CR7 7.26 0.02 1.50 0.60 3,300 3.00 1.50 2.00 7.85 8.40 0.94 0.17 54.94 0.92 7.26 (0.00) 2.00
SC1-23
42,596 43,374 4.20 0.02 1.12 0.60 3,300 3.00 1.50 2.00 5.27 7.05 0.75 0.17 52.92 0.80 4.20 (0.00) 2.67
SC1-24
43,374 46,865 3.63 0.02 1.12 0.60 3,300 2.48 1.50 2.00 4.69 6.54 0.72 0.17 52.56 0.77 3.63 0.00 2.21
SC1-25
46,865 48,322 3.47 0.02 1.12 0.60 3,300 2.34 1.50 2.00 4.52 6.39 0.71 0.17 52.45 0.77 3.47 (0.00) 2.08
SC1-26
48,322 48,336 3.47 0.02 1.12 0.60 3,300 2.34 1.50 2.00 4.52 6.39 0.71 0.17 52.45 0.77 3.47 (0.00) 2.08
SC 1-
48,336 51,499 27,CR8 3.47 0.02 1.10 0.60 5,000 3.25 1.50 2.00 5.38 7.21 0.75 0.17 52.91 0.65 3.47 - 2.96
TC1-0-4
51,499 52,829 3.47 0.02 1.10 0.60 5,000 3.25 1.50 2.00 5.38 7.21 0.75 0.17 52.91 0.65 3.47 - 2.96
TC1-0-5
52,829 53,313 3.47 0.02 1.10 0.60 5,000 3.25 1.50 2.00 5.38 7.21 0.75 0.17 52.91 0.65 3.47 - 2.96
PC-11 &
53,313 53,540 12,CR9 3.47 0.02 1.10 0.60 5,000 3.25 1.50 2.00 5.38 7.21 0.75 0.17 52.91 0.65 3.47 - 2.96
PC-13
53,540 55,720 1.15 0.02 0.74 0.60 5,000 1.50 2.50 2.00 2.48 5.49 0.45 0.17 48.67 0.46 1.15 - 2.03
SC 1-28
55,720 55,822 0.73 0.02 0.66 0.60 5,000 1.50 1.50 2.00 1.65 3.89 0.42 0.17 48.17 0.44 0.73 - 2.26
SC 1-29
55,822 55,833 &CR10 0.28 0.02 0.52 0.60 5,000 0.75 1.50 2.00 0.80 2.63 0.30 0.17 45.56 0.36 0.28 - 1.44
Page | 141
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Canal Dis. Rou. F.S.D F.B Slope Bed Side BW A WP Hyd. Expon Chezy V Dis. Diffe B/D
Name Req Coef. width slope radius ential coef. Des. rence
.
From To m m m m m2 m m m0.5/s m/s m3/s m3/s
m3/
s
SC- 5,000
3,038 1,CR1 0.02 1.41 0.50 3.30 1.50 2.00 7.66 8.40 0.91 0.17 54.71 0.74 5.66 0.00 2.33
- 5.66
SC-2 5,000
3,038 6,792 0.02 1.30 0.50 3.20 1.50 2.00 6.72 7.90 0.85 0.17 54.08 0.71 4.74 0.00 2.46
4.74
SC-3 5,000
6,792 6,812 0.02 1.25 0.50 3.10 1.50 2.00 6.21 7.60 0.82 0.17 53.71 0.69 4.26 0.00 2.48
4.26
SC- 5,000
6,812 8,220 4,CR2 0.02 1.20 0.50 2.50 1.50 2.00 5.14 6.82 0.75 0.17 53.01 0.65 3.35 0.00 2.09
3.35
SC-5 5,300
8,220 9,517 0.02 1.11 0.50 2.05 1.50 2.00 4.13 6.06 0.68 0.17 52.12 0.59 2.44 (0.00) 1.84
2.44
SC- 5,300
9,517 10,973 6,CR3 0.02 1.01 0.50 1.50 1.50 2.00 3.06 5.15 0.59 0.17 50.93 0.54 1.65 0.00 1.48
1.65
SC-7 5,300
10,973 12,436 0.02 0.72 0.50 1.00 1.50 2.00 1.49 3.59 0.42 0.17 48.00 0.43 0.64 0.00 1.39
0.64
SC-8
12,436 14,602 0.02 0.70 0.50 5,300. 0.80 1.50 2.00 1.30 3.33 0.39 0.17 47.50 0.41 0.53 0.00 1.14
0.53
SC- 5,300
14,602 16,277 9,CR4 0.02 0.45 0.50 0.50 1.50 2.00 0.53 2.13 0.25 0.17 44.08 0.30 0.16 0.00 1.11
0.16
Page | 142
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 143
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 144
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 145
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
REFERENCES
1) A M Michael, 1978. Irrigation theory and practice, Delhi
2) Andreas P. S, and Karen F., 2002. Irrigation manual: Planning,
development, monitoring and evaluation of irrigated agriculture with
farmers’ participation; Vol. II, Module 7; FAO, Harare
3) Chow, V.T, 1973. Open - Channel Hydraulic, McGraw – Hill Book
Company Ltd.
4) Guyuk Irrigation Scheme Feasibility Study and Detail Design, Irrigation
Agronomy Draft Report, July, 2020, Gombe
5) Guyuk Irrigation Scheme Feasibility Study and Detail Design,
Hydrogeology Study Draft Report, February, 2020, Gombe
6) Guyuk Irrigation Scheme Feasibility Study and Detail Design, Soil
Study Draft Report, July, 2020, Gombe
7) Guyuk Irrigation Scheme Feasibility Study and Detail Design,
Hydrogeology Study Draft Report, July, 2020, Gombe
8) Food and Agriculture Organization of the United Nations. 1977 rev.
Crop Water Requirements, FAO Irrigation and Drainage paper 24,
Rome, Italy.
9) FAO. (1994). IRRIGATION AND DRAINAGE PAPER, 29 Rev. 1. Rome.
10) H. PRitzema (Ed.), Drainage Principles and Applications.
International Institute for Land Reclamation and Improvement (ILRI),
Publication 16, second revised edition, 1994, Wageningen, The
Netherlands. ISBN 90 70754 3 39
11) Preliminary Studies to Develop 25,000 Ha of Irrigation Scheme
Downstream of the DadinKowa Dam, Gombe State
12) Pre-feasibility of DadinKowa and Reconnaissance study of
Guyuk, Draft report,March, 2014, Upper Benue River Basin, Nigeria.
13) S.N. GHOSH (1996) “Flood Control and Drainage Engineering”,
professor, Department of Civil Engineering Indian Institute of
Technology, Kharagpur.
Page | 146
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector
ENVIPLAN IN ASSOCIATION WITH ECDSWC
Page | 147
Ethiopian Construction Design and Supervision Works
Corporation (ECDSWC), Water and Energy
Design and Supervision Works Sector