22EH0141ORIG
22EH0141ORIG
WORK TO BE DONE
ITEM A.1.1(11) Provision of 4X2 Pick up Type Service Vehicle for the
Engineers on Bare Rental Basis
A.1.1(11) = 8.43 LS
PART C Earthworks
Removal of Actual Structures/Obtruction, 0.15m THK.
ITEM 101(3)b1 PCCP (Unreinforced)
PART C Earthworks
Pier/Wharf
0 + 000.000 8.724 0
0 + 010.000 10 9.273 89.985
0 + 015.000 5 8.089 43.405
0 + 000.000 7.6 0
0 + 010.000 10 7.639 76.195
0 + 015.000 5 8.534 40.4325
COMPUTED
161.88 57.72 29.48 0.00 2032.47 370.88 237.00 1084.60 1967.60 102.44
QUANTITY:
Contract ID 21EH0080-R1
Quantity Take-Off
Item 311(1)c1 - Portland Cement Concrete Pavement (Unreinforced), 0.23 m THK.
Computed
= 300.00 sq.m.
Quantity
a. Pier/Wharf
legnth = 20.00 m
width = 15.00 m
area = 300.00 sq.m.
Quantity Take-Off
Item 104(3)a - Foundation Fill
Computed
= 2.56 sq.m.
Quantity
a. Foundation Fill
legnth = 4.27 m
width = 6.00 m
depth = 0.10 m
area = 2.56 sq.m.
Quantity Take-Off
Item - 509(1)b1 - Steel Sheet Pile (Slope Protection)
Computed
= 3937.60 ln.m
Quantity
=
Linear Length (m) 196.88m / 0.40m x 8.00m
Linear Length (m) = 3937.60 ln.m
Quantity Take-Off
Item - 407(8) - Lean Concrete
Computed
= 13.78 cu.m.
Quantity
Quantity Take-Off
Item - 509(1)b1 - Steel Sheet Pile (Slope Protection)
NO. OF STEEL
DRIVEN LENGTH LENGTH IN THICKNESS
DATE SHEET PILES REMARKS
(m) LINEAR METERS (mm)
DRIVEN
Monday,27 September 2021 20 8.00 160.00 15.5
Tuesday,28 September 2021 32 8.00 256.00 15.5
Wednesday,29 September 2021 45 8.00 360.00 15.5
Thursday,30 September 2021 55 8.00 440.00 15.5
Friday,1 October 2021 34 8.00 272.00 15.5
Saturday,2 October 2021 42 8.00 336.00 15.5
Monday,4 October 2021 25 8.00 200.00 15.5
Tuesday,5 October 2021 35 8.00 280.00 15.5
Wednesday,6 October 2021 48 8.00 384.00 15.5
Thursday,7 October 2021 14 8.00 112.00 15.5
Total: 350 2800
Quantity Take-Off
Item - 509(1)b2 - Steel Sheet Pile (Cofferdaming)
NO. OF STEEL
DRIVEN LENGTH LENGTH IN THICKNESS
DATE SHEET PILES REMARKS
(m) LINEAR METERS (mm)
DRIVEN
Monday,11 October 2021 17 3.00 51.00 15.5
Tuesday,12 October 2021 16 3.00 48.00 15.5
Wednesday,13 October 2021 11 3.00 33.00 15.5
Thursday,14 October 2021 30 3.00 90.00 15.5
Friday,15 October 2021 20 3.00 60.00 15.5
Total: 94 282.00
Contract ID 21EH0076
Contract Name: Construction of Coastal Road Along Tan-Agan (Phase II)
Location: San Andres, Romblon
Contractor: HI-TONE CONSTRUCTION AND DEVELOPMENT CORPORATION
Quantity Take-Off
Item - 509(1)b2 - Steel Sheet Pile (Cofferdaming)
NO. OF STEEL
DRIVEN LENGTH LENGTH IN THICKNESS
DATE SHEET PILES REMARKS
(m) LINEAR METERS (mm)
DRIVEN
Monday,11 October 2021 17 3.00 51.00 15.5
Tuesday,12 October 2021 16 3.00 48.00 15.5
Wednesday,13 October 2021 11 3.00 33.00 15.5
Thursday,14 October 2021 30 3.00 90.00 15.5
Friday,15 October 2021 20 3.00 60.00 15.5
Total: 94 282.00
Contract ID 21EH0080-R1
Quantity Take-Off
Item - 405(1)a2 - Structural Concrete Class "A"
Computed
= 341.71 cu.m.
Quantity
a. Pile Cap
base = 0.50 m
depth = 0.50 m
length = 196.88 m
b. Revetment
c. Retaining Wall
thickness = 0.30 m
slant height 1 = 1.99 m
slant height 2 = 0.3 m
length = 5.34 m
slant slant
Area = + x length x 0.5
height 1 height 2
Area = 0.30 + 1.99 x 5.34 x 0.5
Area = 6.11 cu.m.
Units = 2 Beginning and End
Total Area = 12.23 cu.m. b A = 2.435
ca sq.m. d
d. Wave Deflector
a = 0.6 m a
b = 0.65 m d
c = 0.2 m
d = 0.2 m b A = 0.242 sq.m.
Area = 0.242 sq.m.
length = 180.88 m
R0.60
Volume = length x Area
Volume = 180.88 x 0.242
Volume = 43.77 cu.m.
c
a
e. Column Pedestal - Street Light
g. Jogger's Lane
Width (Slab) = 2t + S
Width (Slab) = 2.84 m
Width
Volume = (Slab) x length x thickness
Volume = 3.75 cu.m.
Width (Slab) = 2t + S
Width (Slab) = 1.61 m
Width
Volume = x length x thickness
(Slab)
Volume = 1.74 cu.m.
Quantity Take-Off
Item - 405(1)a2 - Structural Concrete Class "A"
Computed
= 130.01 cu.m.
Quantity
a. Pile Cap
base = 0.50 m
depth = 0.50 m
length = 112.00 m
b. Revetment
c
112.88
Total: 74.90241
a
c. Retaining Wall
d
thickness = 0.30 m A = 0.242 sq.m.
slant height 1 = 1.99 m
b
slant height 2 = 0.3 m
length = 5.34 m R0.60
slant slant
Area = + x length x 0.5
height 1 height 2 c
Area = 0.30 + 1.99 x 5.34 x 0.5
Area = 6.11 cu.m.
Units = 2 Beginning and End
Total Area = 12.23 cu.m. b A = 2.435
ca sq.m. d
a
b A = 0.382 sq.m.
d. Wave Deflector f
g e
c A = 0.741 sq.m.
a = 0.6 m a d
b = 0.65 m d
c = 0.2 m
d = 0.2 m b A = 0.242 sq.m.
Area = 0.242 sq.m.
length = 112 m
R0.60
Volume = length x Area
Volume = 112.00 x 0.242
Volume = 27.10 cu.m.
c
a
e. Column Pedestal - Street Light
Quantity Take-Off
Item - 404(1)a - Reinforcing Steel Bars (Grade 40)
Original
= 19491.69 kgs
Quantity
Computed
= 22285.62 kgs
Quantity
a. Pile Cap
base = 0.50 m
depth = 0.50 m
length = 196.88 m
ties
= 12.00 mm
diameter
spacing of
= 0.15 m
ties
horizontal
bar = 16.00 mm
diameter
No. of H-
= 6.00 pcs
Bar
a.1 Stirrups
Refer NSCP 2015 Table 425.3.2 Minimum Inside Diameter for Stirrups
bending &
= 0.123 m
hook
cut length = 2.40 m
net length = 2.65 m
No. of Ties
= 1314.00 pcs
Needed
Length of
= 6.00 m
RSB used
No. of
Horizontal = 6.00 pcs (direct counting)
Bar
Length of
= 6.00 m
Bar Use
No. of
= 32 pcs
Splicing
Splicing
= 0.64 m
Req.(40d)
Total
Length for = 20.48 m
Splicing
Add. Bars
= 4.00 pcs
for Splicing
thickness = 0.20 m
slant height = 2.2 m
length = 200.88 m
vert. rebar
= 12.00 mm
diameter
vert.
= 0.20 m
spacing
hor. rebar
= 12.00 mm
diameter
bending &
= 0.216 m
hook
cut length = 2.63 m
No. of
Rebar
= 1006.00 pcs
Needed for
Vert.
Length of
= 6.00 m
RSB used
No. of
Horizontal = 12.00 pcs
Bar
Length of
= 6.00 m
Bar Use
No. of Bays = 34 bays
No. of
= 33 pcs
Splicing
Splicing
= 0.48 m
Req.(40d)
Total
Length for = 15.84 m
Splicing
Add. Bars
= 3.00 pcs
for Splicing
Vertical
b.1
Rebar
Quantity Bar Diameter Length
Quantity = 503.00 12 6
Weight = 2679.99 kgs
Horizontal
b.2
Rebar
c. Revetment (ramp)
thickness = 0.20 m
slant height = 5.34 m
length = 8.00 m
vert. rebar
= 12.00 mm
diameter
vert.
= 0.20 m
spacing
hor. rebar
= 12.00 mm
diameter
bending &
= 0.216 m
hook
cut length = 5.77 m
No. of
Rebar
= 41.00 pcs
Needed for
Vert.
Length of
= 6.00 m
RSB used
No. of
Horizontal = 28.00 pcs
Bar
Length of
= 6.00 m
Bar Use
No. of Bays = 2 bays
No. of
= 1 pcs
Splicing
Splicing
= 0.48 m
Req.(40d)
Total
Length for = 0.48 m
Splicing
Add. Bars
= 1.00 pcs
for Splicing
Vertical
c.1
Rebar
Quantity Bar Diameter Length
Quantity = 41.00 12 6
Weight = 218.45 kgs
Horizontal
c.2
Rebar
d. Retaining Wall
thickness = 0.30 m
slant height
= 1.99 m
1
slant height
= 0.3 m
2
length = 5.34 m
Length 11 = 1.254
Length 12 = 1.186
Length 13 = 1.119
Length 14 = 1.051
2 units
Length 15 = 0.984
2 units
Length 16 = 0.916
Length 17 = 0.849
Length 18 = 0.781
Length 19 = 0.714
Length 20 = 0.648
Length 21 = 0.579
Length 22 = 0.512
Length 23 = 0.444
Length 24 = 0.377
Length 25 = 0.309
Length 26 = 0.242
Total = 28.283
Sta. 0+181.00
Beginning Ramp = 83.14 ln.m.
say = 14 pcs of 12mm dia.
Sta. 0+189.00
End Ramp = 83.14 ln.m.
say = 14 pcs of 12mm dia.
e. Wave Deflector
e.1 Stirrups 1
Refer NSCP 2015 Table 425.3.2 Minimum Inside Diameter for Stirrups
bending &
= 0.123 m
hook
Concrete
= 75.000 mm
cover
cut length = 1.36 m
length = 200.88 m
spacing = 0.20 m
No. of Ties
= 1006.00 pcs
Needed
Length of
= 9.50 m
RSB used
No. of
Horizontal = 6.00 pcs (direct counting)
Bar
Length of
= 6.00 m
Bar Use
No. of
= 33 pcs
Splicing
Splicing
= 0.48 m
Req.(40d)
Total
Length for = 15.84 m
Splicing
Add. Bars
= 3.00 pcs
for Splicing
h. Jogger's Lane
thickness = 0.15 m
width = 3 m
length = 141.88 m
vert. rebar
= 12.00 mm
diameter
vert.
= 0.20 m
spacing
hor. rebar
= 12.00 mm
diameter
bending &
= 0.216 m
hook
cut length = 3.43 m
No. of
Rebar
= 711.00 pcs
Needed for
Longi.
Length of
= 10.50 m
RSB used
No. of
= 16.00 pcs
Trans. Bar
Length of
= 6.00 m
Bar Use
No. of
= 23 pcs
Splicing
Splicing
= 0.48 m
Req.(40d)
Total
Length for = 11.04 m
Splicing
Add. Bars
= 2.00 pcs
for Splicing
Vertical
b.1
Rebar
Quantity Bar Diameter Length
Quantity = 237.00 12 10.5
Weight = 2209.79 kgs
Horizontal
b.2
Rebar
BAR - 1 (2 Units)
Rebar Diameter = 16 mm
Spacing = 0.22 m
Quantity = L - 2c / Spacing
Quantity = 26.82
Quantity = 27.00 pcs
Total
= 54.00 pcs
Quantity
BAR - 2 (2 Units)
Rebar Diameter = 16 mm
Spacing = 0.28 m
Quantity = L - 2c / Spacing
Quantity = 21.07
Quantity = 22.00 pcs
Total
= 44.00 pcs
Quantity
BAR - 3 (2 Units)
Rebar Diameter = 16 mm
Spacing = 0.22 m
Quantity = L - 2c / Spacing
Quantity = 26.82
Quantity = 27.00 pcs
Total
= 54.00 pcs
Quantity
Rebar Diameter = 16 mm
Spacing = 0.22 m
Quantity = L - 2c / Spacing
Quantity = 26.82
Quantity = 27.00 pcs
Total
= 54.00 pcs
Quantity
BAR - 5 (2 Units)
Rebar Diameter = 12 mm
Spacing = 0.24 m
Quantity = L - 2c / Spacing
Quantity = 24.58
Quantity = 25.00 pcs
Total
= 50.00 pcs
Quantity
BAR - 6 (4 Units)
Rebar Diameter = 12 mm
Spacing = 0.25 m
Net Length = L
Net Length = 6.00 m
Quantity = L - 2c / Spacing
Quantity = 23.60
Quantity = 24.00 pcs
Total
= 96.00 pcs
Quantity
Total
= 1665.00 kgs
Weight
BAR - 1 (1 Unit)
Rebar Diameter = 16 mm
Spacing = 0.22 m
Quantity = L - 2c / Spacing
Quantity = 26.82
Quantity = 27.00 pcs
BAR - 2 (1 Unit)
Rebar Diameter = 16 mm
Spacing = 0.28 m
Quantity = L - 2c / Spacing
Quantity = 21.07
Quantity = 22.00 pcs
BAR - 3 (1 Unit)
Rebar Diameter = 16 mm
Spacing = 0.22 m
Quantity = L - 2c / Spacing
Quantity = 26.82
Quantity = 27.00 pcs
BAR - 4 (2 Units)
Rebar Diameter = 16 mm
Spacing = 0.22 m
Quantity = L - 2c / Spacing
Quantity = 26.82
Quantity = 27.00 pcs
Total
= 54.00 pcs
Quantity
BAR - 5 (2 Units)
Rebar Diameter = 12 mm
Spacing = 0.24 m
Quantity = L - 2c / Spacing
Quantity = 24.58
Quantity = 25.00 pcs
Total
= 50.00 pcs
Quantity
BAR - 6 (3 Units)
Rebar Diameter = 12 mm
Spacing = 0.25 m
Net Length = L
Net Length = 6.00 m
Quantity = L - 2c / Spacing
Quantity = 23.60
Quantity = 24.00 pcs
Total
= 72.00 pcs
Quantity
Total
= 1028.31 kgs
Weight
Contract ID 21EH0080-R1
Quantity Take-Off
Item - 404(1)a - Reinforcing Steel Bars (Grade 40)
Original
= 19491.69 kgs
Quantity
Computed
= 7756.69 kgs
Quantity
a. Pile Cap
base = 0.50 m
depth = 0.50 m
length = 112.00 m
ties
= 12.00 mm
diameter
spacing of
= 0.15 m
ties
horizontal
bar = 16.00 mm
diameter
No. of H-
= 6.00 pcs
Bar
a.1 Stirrups
Refer NSCP 2015 Table 425.3.2 Minimum Inside Diameter for Stirrups
bending &
= 0.123 m
hook
cut length = 2.40 m
net length = 2.65 m
No. of Ties
= 748.00 pcs
Needed
Length of
= 6.00 m
RSB used
No. of
Horizontal = 6.00 pcs (direct counting)
Bar
Length of
= 6.00 m
Bar Use
No. of
= 18 pcs
Splicing
Splicing
= 0.64 m
Req.(40d)
Total
Length for = 11.52 m
Splicing
Add. Bars
= 2.00 pcs
for Splicing
thickness = 0.20 m
slant height = 2.2 m
length = 112.00 m
vert. rebar
= 12.00 mm
diameter
vert.
= 0.20 m
spacing
hor. rebar
= 12.00 mm
diameter
bending &
= 0.216 m
hook
cut length = 2.63 m
No. of
Rebar
= 561.00 pcs
Needed for
Vert.
Length of
= 6.00 m
RSB used
No. of
Horizontal = 12.00 pcs
Bar
Length of
= 6.00 m
Bar Use
No. of Bays = 19 bays
No. of
= 18 pcs
Splicing
Splicing
= 0.48 m
Req.(40d)
Total
Length for = 8.64 m
Splicing
Add. Bars
= 2.00 pcs
for Splicing
Vertical
b.1
Rebar
Quantity Bar Diameter Length
Quantity = 280.50 12 6
Weight = 1494.51 kgs
Horizontal
b.2
Rebar
b d
c. Revetment (ramp)
thickness = 0.20 m
slant height = 5.34 m c
length = 8.00 m
vert. rebar
= 12.00 mm
diameter
vert.
= 0.20 m
spacing
hor. rebar
= 12.00 mm
diameter
bending &
= 0.216 m
hook
cut length = 5.77 m
No. of
Rebar
= 41.00 pcs
Needed for
Vert.
Length of
= 6.00 m
RSB used
No. of
Horizontal = 28.00 pcs
Bar
Length of
= 6.00 m
Bar Use
No. of Bays = 2 bays
No. of
= 1 pcs
Splicing
Splicing
= 0.48 m
Req.(40d)
Total
Length for = 0.48 m
Splicing
Add. Bars
= 1.00 pcs
for Splicing
Vertical
c.1
Rebar
Quantity Bar Diameter Length
Quantity = 41.00 12 6
Weight = 218.45 kgs
Horizontal
c.2
Rebar
CONTRACTOR : ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1 Annex "1"
MAIN ADDRESS : 209 Arellano Extension Daraga Albay CONTRACT NAME: Payment Certificate No. 01
Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
LOCATION: Odiongan, Romblon
GREATCHEN T. FIRMALO JULIEN MARIE EVANGELIO ALAN T. SALVADOR BOY ALEXIS E. MINANO ELENA M. CASTILAN
DPWH, Project Inspector DPWH, Project Engineer I Chief, Construction Section OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________ Date: __________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As of: December 06, 2021
GREATCHEN T. FIRMALO JULIEN MARIE EVANGELIO ALAN T. SALVADOR BOY ALEXIS E. MINANO ELENA M. CASTILAN
DPWH, Project Inspector DPWH, Project Engineer I Chief, Construction Section OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________ Date: __________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHE
As of: August 06 to December 15, 2021
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - F
Construction/Repair/Rehabilitation/Impr
Local Projects - Construction of Flood
Protection/Causewa
LOCATION: Odiong
Prepared by:
Odiongan, Romblon
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - F
Construction/Repair/Rehabilitation/Impr
Local Projects - Construction of Flood
Protection/Causewa
LOCATION: Odiong
Prepared by:
Odiongan, Romblon
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Fa
Construction/Repair/Rehabilitation/Improvement of Various Infrast
Local Projects - Construction of Flood Mitigation Structure - Cons
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 16,754.85 4.57 4.57
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 43,562.61 0.10 0.10
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 57,362.50 0.160 0.16
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 5,546.54 1.00 1.00
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 568,680.67 0.10 0.10
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 156,598.87 0.10 0.10
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 374,447.28 0.50 0.50
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 125.37 -
PCCP (Unreinforced)
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 287.72 -
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2,017.95 -
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 1,815.25 1,461.66 1,461.66
PART D - SUBBASE AND BASE COURSE 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 1,965.02 -
PART E - SURFACE COURSE 102.67
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 1,377.74 -
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 2,498.11 -
0.28m THK.
PART F - BRIDGE CONSTRUCTION 0.00%
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 68.28 2,525.47 2,525.47
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 11,171.32 9.00 9.00
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 8,675.32 -
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 7,096.66 98.39 98.39
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 4,671.11 1,075.87 1,075.87
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 4,632.52 1,080.00 1,080.00
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 2,087.49 -
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 216,550.75 -
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT:
Prepared by:
GREATCHEN T. FIRMALO JULIEN MARIE EVANGELIO ALAN T. SALVADOR BOY ALEXIS E. MINAN
DPWH, Project Inspector DPWH, Project Engineer I Chief, Construction Section OIC, Assistant District En
Date: ____________________________ Date: ____________________________ Date: ____________________ Date: __________________
EMENT OF WORK ACCOMPLISHED
ust 06 to December 20, 2021
Odiongan, Romblon
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0080-R
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - Flood C
Construction/Repair/Rehabilitation/Improveme
Local Projects - Construction of Flood Mitigati
Protection/Causeway leadin
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 5.50
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A.1.2(4) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 0.00 0.00 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01%
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05%
103(3) Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,895.88
PART D - SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27%
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kg 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 7,756.69
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 130.01
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59
509(1)b1 Steel Sheet Pile (Slope Protection) m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 2,300.00
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT:
NOTE: CLAIMING ONLY THE ORIGINAL CONTRACT AMOUNT OF FORTY EIGHT MILLION TWO HUNDRED SIXTY FIVE THOUSAND ONE HUNDRED TWENTY TH
OF SEVEN HUNDRED THIRTY FOUR THOUSAND EIGHT HUNDRED SEVENTY SIX (75/100) (73
Odiongan, Romblon
- - - - 1,504.44 0.00%
17.00
- 87.19 - - 112,383.43 0.00%
- 2.56 - - 6,780.31 0.00%
1,895.88 136.59 3,441,496.17 3,441,496.17 274,974.07 7.13%
- 0.00%
212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
300.00
FIVE THOUSAND ONE HUNDRED TWENTY THREE PESOS & (25/100) (PHP 48,265,123.25) AND AMOUNT OF SAVINGS
D EIGHT HUNDRED SEVENTY SIX (75/100) (734,876.75)
Recommending Approval:
Approved:
ELENA M. CASTILAN
District Engineer
Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for : January 18 to May 02, 2022
Contract ID : 21EH0080-R1
Contract Name : Flood Control and Drainage - Flood Control Structures/Facilities - Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including Local Projects - Construction of Flood Mitigation Structure - Construction of Shore Protection/Causeway leading to Poctoy Port
Location : Odiongan, Romblon
Contractor : ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION
Page ____ of ____
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory
A1.1(6) and Living Quarters Building for the Engineer mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 5.50 2.43 7.93 0.50 92,151.67 40,714.29 132,865.96 8,377.42 0.27%
(Rental Basis)
Provision of 4X2 Pick up Type Service Vehicle
A.1.2(4) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 7.00 7.10 1.33 4,356.26 304,938.27 309,294.53 57,938.27 0.63%
for the Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS - - 0.00%
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 - 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 - 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 - 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 7.63 7.73 0.70 15,659.88 1,194,849.38 1,210,509.26 109,619.21 2.45%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 - 187,223.64 187,223.64 0.38%
PART C - EARTHWORKS - - 0.00%
Removal of Actual Structures/Obtruction,
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 0.00 0.00 0.00% - - - - - - 0.00%
0.15m THK. PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00 - 4,535.77 0.00%
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% 87.19 87.19 - - 25,086.30 25,086.30 - 0.05%
103(3) Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% 2.56 2.56 - - 5,165.95 5,165.95 - 0.01%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,895.88 136.59 2,032.47 - 3,441,496.17 247,944.99 3,689,441.16 - 7.48%
PART D - SUBBASE AND BASE COURSE - - - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 - 417,900.80 310,885.81 0.85%
PART E - SURFACE COURSE - - 0.00%
Portland Cement Concrete Pavement
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% - 237.00 - - - 326,524.38 0.00%
(Unreinforced), 0.15m THK.
Portland Cement Concrete Pavement
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00 - 624,234.00 0.00%
(Unreinforced), 0.123m THK.
Portland Cement Concrete Pavement
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - - 2,709,450.10 0.00%
(Unreinforced), 0.28m THK.
PART F - BRIDGE CONSTRUCTION - - 0.00%
404(1)a Reinforcing Steel Grade 40 kg 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 7,756.69 14,528.93 22,285.62 - 529,626.79 992,035.34 1,521,662.13 - 3.09%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 130.01 211.70 341.71 - 1,452,383.31 2,364,968.44 3,817,351.75 - 7.74%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84 5.94 13.78 - 68,014.50 51,531.40 119,545.90 - 0.24%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES - - 0.00%
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44 102.44 - 726,981.85 - 726,981.85 - 1.47%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 171.01 1,967.60 - 8,392,069.51 798,806.52 9,190,876.03 - 18.64%
509(1)b1 Steel Sheet Pile (Slope Protection) m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 2,300.00 1,637.60 3,937.60 - 10,654,796.00 7,586,214.75 18,241,010.75 - 36.99%
PART H - MISCELLANEOUS STRUCTURES - - 0.00%
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - - 4,114,464.25 0.00%
Total: 48,265,123.25 100.00% Total: 49,307,920.83 102.16% Amount Due 26,054,252.98 13,612,255.63
Cost to date 39,666,508.61 9,641,412.22
Percentage 80.44%
NOTE: CLAIMING ONLY THE ORIGINAL CONTRACT AMOUNT OF FORTY EIGHT MILLION TWO HUNDRED SIXTY FIVE THOUSAND ONE HUNDRED TWENTY THREE PESOS & (25/100) (PHP 48,265,123.25) AND AMOUNT OF
SAVINGS OF SEVEN HUNDRED THIRTY FOUR THOUSAND EIGHT HUNDRED SEVENTY SIX (75/100) (734,876.75)
Prepared by: Verified by: Checked and Reviewed by: Recommending Approval: APPROVED FOR PAYMENT
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR BOY ALEXIS E. MINANO ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for: February 21, 2022
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1 Annex "1"
: 209 Arellano Extension Daraga Albay CONTRACT NAME: Payment Certificate No. 01
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 5.50 5.50 2.93 92,151.67 92,151.67 49,091.71 0.19%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 4,356.26 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 15,659.88 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 125.37 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% - 87.19 - - 112,383.43 0.00%
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% - 2.56 - - 6,780.31 0.00%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,695.88 1,695.88 336.59 3,078,446.17 3,078,446.17 638,024.07 6.38%
PART D - SUBBASE AND BASE COURSE - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% - 237.00 - - 326,524.38 0.00%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 7,556.69 7,556.69 14,728.93 515,970.79 515,970.79 814,921.80 1.07%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 142.01 142.01 199.70 1,586,439.15 1,586,439.15 2,393,455.31 3.29%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84 7.84 5.94 68,014.50 68,014.50 48,495.04 0.14%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 93.44 93.44 9.00 663,111.91 663,111.91 35,128.46 1.37%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 1,796.59 171.01 8,392,069.51 8,392,069.51 863,594.82 17.39%
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 1,440.00 1,440.00 2,497.60 6,670,828.80 6,670,828.80 11,118,048.00 13.82%
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 21,763,765.68
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 21,763,765.68
Percentage 45.10%
MARIANO P. ADUPE JR. GREATCHEN T. FIRMALO ELMER M. TOLENTINO BOY ALEXIS E. MINANO
Contractor's Projcet Engineer DPWH, Project Inspector Chief, Quality Assurance Section OIC, Assistant District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for: August 06, 2021 to December 31, 2021
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 4.93 4.93 3.50 82,601.41 82,601.41 58,641.97 0.17%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 4,356.26 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 15,659.88 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 125.37 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% - 87.19 - - 112,383.43 0.00%
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% - 2.56 - - 6,780.31 0.00%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,695.88 1,695.88 336.59 3,078,446.17 3,078,446.17 638,024.07 6.38%
PART D - SUBBASE AND BASE COURSE - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% - 237.00 - - 326,524.38 0.00%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 7,556.69 7,556.69 14,728.93 515,970.79 515,970.79 814,921.80 1.07%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 142.01 142.01 199.70 1,586,439.15 1,586,439.15 2,393,455.31 3.29%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84 7.84 5.94 68,014.50 68,014.50 48,495.04 0.14%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 93.44 93.44 9.00 663,111.91 663,111.91 35,128.46 1.37%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,665.05 1,665.05 302.55 7,777,631.70 7,777,631.70 1,478,032.63 16.11%
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 1,200.00 1,200.00 2,737.60 5,559,024.00 5,559,024.00 12,229,852.80 11.52%
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 20,027,972.81
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 20,027,972.81
Percentage 41.50%
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1 Annex "1"
: 209 Arellano Extension Daraga Albay CONTRACT NAME: Payment Certificate No. 01
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 5.50 5.50 2.93 92,151.67 92,151.67 49,091.71 0.19%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 4,356.26 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 15,659.88 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 125.37 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% - 87.19 - - 112,383.43 0.00%
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% - 2.56 - - 6,780.31 0.00%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,695.88 1,695.88 336.59 3,078,446.17 3,078,446.17 638,024.07 6.38%
PART D - SUBBASE AND BASE COURSE - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% - 237.00 - - 326,524.38 0.00%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 7,556.69 7,556.69 14,728.93 515,970.79 515,970.79 814,921.80 1.07%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 176.03 176.03 165.68 1,966,487.45 1,966,487.45 2,013,407.01 4.07%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84 7.84 5.94 68,014.50 68,014.50 48,495.04 0.14%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44 102.44 - 726,981.85 726,981.85 - 28,741.48 1.51%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 1,796.59 171.01 8,392,069.51 8,392,069.51 863,594.82 17.39%
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 1,440.00 1,440.00 2,497.60 6,670,828.80 6,670,828.80 11,118,048.00 13.82%
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 22,207,683.92
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 22,207,683.92
Percentage 46.02%
MARIANO P. ADUPE JR. GREATCHEN T. FIRMALO ELMER M. TOLENTINO BOY ALEXIS E. MINANO
Contractor's Projcet Engineer DPWH, Project Inspector Chief, Quality Assurance Section OIC, Assistant District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
FIRST PROGRESS BILLING - VOLUME COMPUTATION
WORK TO BE DONE
ITEM A.1.1(11) Provision of 4X2 Pick up Type Service Vehicle for the
Engineers on Bare Rental Basis
A.1.1(11) = 0.10 LS
PART C Earthworks
Removal of Actual Structures/Obtruction, 0.15m THK.
ITEM 101(3)b1 PCCP (Unreinforced)
PART C Earthworks
Pier/Wharf
0 + 000.000 8.724 0
0 + 010.000 10 9.273 89.985
0 + 015.000 5 8.089 43.405
0 + 000.000 7.6 0
0 + 010.000 10 7.639 76.195
0 + 015.000 5 8.534 40.4325
COMPUTED
161.88 57.72 29.48 0.00 2032.47 370.88 242.82 1084.60 1967.60
QUANTITY:
ITEM 505(2)a
REMARKS
VOLUME
3.68
12.40
15.74
18.53
14.80
10.35
0.96
6.36
6.73
6.71
2.22
3.97
102.44
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for: March 14, 2022
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 7.37 7.37 1.06 123,483.24 123,483.24 17,760.14 0.26%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 4,356.26 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 15,659.88 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 125.37 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% - 87.19 - - 112,383.43 0.00%
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% - 2.56 - - 6,780.31 0.00%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,695.88 1,695.88 336.59 3,078,446.17 3,078,446.17 638,024.07 6.38%
PART D - SUBBASE AND BASE COURSE - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% - 237.00 - - 326,524.38 0.00%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 10,730.00 10,730.00 11,555.62 732,644.40 732,644.40 598,248.19 1.52%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 182.03 182.03 159.68 2,033,515.37 2,033,515.37 1,946,379.09 4.21%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84 7.84 5.94 68,014.50 68,014.50 48,495.04 0.14%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44 102.44 - 726,981.85 726,981.85 - 28,741.48 1.51%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 1,796.59 171.01 8,392,069.51 8,392,069.51 863,594.82 17.39%
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 2,040.00 2,040.00 1,897.60 9,450,340.80 9,450,340.80 8,338,536.00 19.58%
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 25,302,229.02
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 25,302,229.02
Percentage 52.44%
MARIANO P. ADUPE JR. GREATCHEN T. FIRMALO ELMER M. TOLENTINO BOY ALEXIS E. MINANO
Contractor's Projcet Engineer DPWH, Project Inspector Chief, Quality Assurance Section OIC, Assistant District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for: March 21, 2022
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 7.37 7.37 1.06 123,483.24 123,483.24 17,760.14 0.26%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 4,356.26 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 15,659.88 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 125.37 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% - 87.19 - - 112,383.43 0.00%
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% - 2.56 - - 6,780.31 0.00%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,695.88 1,695.88 336.59 3,078,446.17 3,078,446.17 638,024.07 6.38%
PART D - SUBBASE AND BASE COURSE - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% - 237.00 - - 326,524.38 0.00%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 10,730.00 10,730.00 11,555.62 732,644.40 732,644.40 598,248.19 1.52%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 182.03 182.03 159.68 2,033,515.37 2,033,515.37 1,946,379.09 4.21%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84 7.84 5.94 68,014.50 68,014.50 48,495.04 0.14%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44 102.44 - 726,981.85 726,981.85 - 28,741.48 1.51%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 1,796.59 171.01 8,392,069.51 8,392,069.51 863,594.82 17.39%
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 3,160.00 3,160.00 777.60 14,638,763.20 14,638,763.20 3,150,113.60 30.33%
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 30,490,651.42
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 30,490,651.42
Percentage 63.19%
MARIANO P. ADUPE JR. GREATCHEN T. FIRMALO ELMER M. TOLENTINO BOY ALEXIS E. MINANO
Contractor's Projcet Engineer DPWH, Project Inspector Chief, Quality Assurance Section OIC, Assistant District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for: April 04, 2022
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0081-R1
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 7.37 7.37 1.06 123,483.24 123,483.24 17,760.14 0.26%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 4,356.26 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 15,659.88 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 125.37 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% - 87.19 - - 112,383.43 0.00%
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% - 2.56 - - 6,780.31 0.00%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,695.88 1,695.88 336.59 3,078,446.17 3,078,446.17 638,024.07 6.38%
PART D - SUBBASE AND BASE COURSE - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% - 237.00 - - 326,524.38 0.00%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 12,350.00 12,350.00 9,935.62 843,258.00 843,258.00 487,634.59 1.75%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 194.03 194.03 147.68 2,167,571.21 2,167,571.21 1,812,323.25 4.49%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 9.84 9.84 3.94 85,365.14 85,365.14 31,144.40 0.18%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44 102.44 - 726,981.85 726,981.85 - 28,741.48 1.51%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 1,796.59 171.01 8,392,069.51 8,392,069.51 863,594.82 17.39%
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 3,620.00 3,620.00 317.60 16,769,722.40 16,769,722.40 1,019,154.40 34.75%
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 32,883,630.70
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 32,883,630.70
Percentage 68.16%
MARIANO P. ADUPE JR. GREATCHEN T. FIRMALO ELMER M. TOLENTINO BOY ALEXIS E. MINANO
Contractor's Projcet Engineer DPWH, Project Inspector Chief, Quality Assurance Section OIC, Assistant District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As of: January 18 to April 15, 2022
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0080-R1 Annex "1"
: 209 Arellano Extension Daraga Albay CONTRACT NAME: Payment Certificate No. 01
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 5.50 5.50 2.93 - 92,151.67 49,091.71 0.19%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A.1.2(4) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 - 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS -
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - - 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - - 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 - 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 - 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 - 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS -
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 0.00 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00 17.00 -
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% 87.19 87.19 - 25,086.30 25,086.30 87,297.13 0.05%
103(3) Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% 2.56 2.56 - 5,165.95 5,165.95 1,614.36 0.01%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,895.88 1,895.88 136.59 - 3,441,496.17 274,974.07 7.13%
PART D - SUBBASE AND BASE COURSE - - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 - 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE -
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% 216.00 216.00 21.00 297,591.84 297,591.84 28,932.54 0.62%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% - 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION -
404(1)a Reinforcing Steel Grade 40 kg 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 7,756.69 10,953.31 18,710.00 3,575.62 747,892.00 1,277,518.80 53,373.79 2.65%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 130.01 134.02 264.03 77.68 1,497,180.30 2,949,563.61 1,030,330.85 6.11%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 7.84 5.94 13.78 - 51,531.40 119,545.90 - 3,036.36 0.25%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES -
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44 102.44 - - 726,981.85 - 28,741.48 1.51%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 1,796.59 171.01 - 8,392,069.51 863,594.82 17.39%
509(1)b1 Steel Sheet Pile (Slope Protection) m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 2,300.00 1,637.60 3,937.60 - 7,586,214.75 18,241,010.75 - 452,133.95 37.79%
PART H - MISCELLANEOUS STRUCTURES -
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 10,210,662.54
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 36,264,915.53
Percentage 75.15%
NOTE: CLAIMING ONLY THE ORIGINAL CONTRACT AMOUNT OF FORTY EIGHT MILLION TWO HUNDRED SIXTY FIVE THOUSAND ONE HUNDRED TWENTY THREE PESOS & (25/100) (PHP 48,265,123.25) AND AMOUNT OF SAVINGS
OF SEVEN HUNDRED THIRTY FOUR THOUSAND EIGHT HUNDRED SEVENTY SIX (75/100) (734,876.75)
MARIANO P. ADUPE JR. GREATCHEN T. FIRMALO ELMER M. TOLENTINO BOY ALEXIS E. MINANO
Contractor's Projcet Engineer DPWH, Project Inspector Chief, Quality Assurance Section OIC, Assistant District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for: May 02, 2022
CONTRACTOR
: ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION CONTRACT ID: 21EH0080-R1
: 209 Arellano Extension Daraga Albay CONTRACT NAME:
MAIN ADDRESS Flood Control and Drainage - Flood Control Structures/Facilities -
Construction/Repair/Rehabilitation/Improvement of Various Infrastructure including
Local Projects - Construction of Flood Mitigation Structure - Construction of Shore
Protection/Causeway leading to Poctoy Port
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
1 2 3 4a 4b 4c 5 4a 4b 4c 5 6a 6b 6c 6d 7a 7b 7c 7d 8
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 8.43 16,754.85 141,243.38 0.29% 8.43 16,754.85 141,243.38 0.29% 7.37 7.37 1.06 123,483.24 123,483.24 17,760.14 0.26%
Basis)
Provision of 4X2 Pick up Type Service Vehicle for the
A1.1(2) mos. 8.43 43,562.61 367,232.80 0.76% 8.43 43,562.61 367,232.80 0.74% 0.10 0.10 8.33 4,356.26 4,356.26 362,876.54 0.01%
Engineers on Bare Rental Basis
PART B - OTHER GENERAL REQUIREMENTS
B.4(1) Construction Survey and Staking km. 0.16 57,362.50 9,178.00 0.02% 0.16 57,362.50 9,178.00 0.02% 0.160 0.16 - 9,178.00 9,178.00 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,546.54 5,546.54 0.01% 1.00 5,546.54 5,546.54 0.01% 1.00 1.00 - 5,546.54 5,546.54 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 568,680.67 568,680.67 1.18% 1.00 568,680.67 568,680.67 1.15% 0.10 0.10 0.90 56,868.06 56,868.06 511,812.61 0.12%
B.8(1) Traffic Management mos. 8.43 156,598.87 1,320,128.47 2.74% 8.43 156,598.87 1,320,128.47 2.68% 0.10 0.10 8.33 15,659.88 15,659.88 1,304,468.59 0.03%
B.9 Mobilization and Demobilization l.s. 1.00 374,447.28 374,447.28 0.78% 1.00 374,447.28 374,447.28 0.76% 0.50 0.50 0.50 187,223.64 187,223.64 187,223.64 0.39%
PART C - EARTHWORKS
Removal of Actual Structures/Obtruction, 0.15m THK.
101(3)b1 sq.m. 12.00 125.37 1,504.44 0.00% 0.00 125.37 0.00 0.00% - - - - 1,504.44 0.00%
PCCP (Unreinforced)
101(8) Removal of Existing Guardrails ln.m. 17.00 266.81 4,535.77 0.01% 17.00
103(1)a Structure Excavation cu.m. 390.60 287.72 112,383.43 0.23% 87.19 287.72 25,086.30 0.05% - 87.19 - - 112,383.43 0.00%
104(3)a Foundation Fill cu.m. 3.36 2,017.95 6,780.31 0.01% 2.56 2,017.95 5,165.95 0.01% - 2.56 - - 6,780.31 0.00%
104(3)a Embankment from Borrow cu.m. 2,047.36 1,815.25 3,716,470.24 7.70% 2,032.47 1,815.25 3,689,441.16 7.48% 1,695.88 1,695.88 336.59 3,078,446.17 3,078,446.17 638,024.07 6.38%
PART D - SUBBASE AND BASE COURSE - 0.00%
200(1) Aggregate Subbase Course cu.m. 328.07 1,965.02 644,664.11 1.34% 370.88 1,965.02 728,786.61 1.48% 212.67 212.67 158.21 417,900.80 417,900.80 226,763.31 0.87%
PART E - SURFACE COURSE
Portland Cement Concrete Pavement (Unreinforced),
311(1)a sq.m. 237.00 1,377.74 326,524.38 0.68% 237.00 1,377.74 326,524.38 0.66% 216.00 216.00 21.00 297,591.84 297,591.84 28,932.54 0.62%
0.15m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)c1 sq.m. 300.00 2,080.78 624,234.00 1.27% 300.00
0.123m THK.
Portland Cement Concrete Pavement (Unreinforced),
311(1)e1 sq.m. 1,084.60 2,498.11 2,709,450.10 5.61% 1,084.60 2,498.11 2,709,450.10 5.49% - 1,084.60 - - 2,709,450.10 0.00%
0.28m THK.
PART F - BRIDGE CONSTRUCTION
404(1)a Reinforcing Steel Grade 40 kgs. 19,491.69 68.28 1,330,892.59 2.76% 22,285.62 68.28 1,521,662.13 3.09% 16,590.00 16,590.00 5,695.62 1,132,765.20 1,132,765.20 198,127.39 2.35%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 356.26 11,171.32 3,979,894.46 8.25% 341.71 11,171.32 3,817,351.75 7.74% 212.03 212.03 129.68 2,368,654.97 2,368,654.97 1,611,239.49 4.91%
407(8) Lean Concrete cu.m. 13.43 8,675.32 116,509.54 0.24% 13.78 8,675.32 119,545.90 0.24% 11.84 11.84 1.94 102,715.78 102,715.78 13,793.76 0.21%
PART G - DRAINAGE AND SLOPE PROTECTION STRUCTURES
505(2)a Grouted Riprap (Class A) cu.m. 98.39 7,096.66 698,240.37 1.45% 102.44 7,096.66 726,981.85 1.47% 102.44 102.44 - 726,981.85 726,981.85 - 28,741.48 1.51%
508(1) Hand-Laid Rock Embankment cu.m. 1,981.47 4,671.11 9,255,664.33 19.18% 1,967.60 4,671.11 9,190,876.03 18.64% 1,796.59 1,796.59 171.01 8,392,069.51 8,392,069.51 863,594.82 17.39%
509(1)b1 Steel Sheet Pile (Slope Protection) ln.m. 3,840.00 4,632.52 17,788,876.80 36.86% 3,937.60 4,632.52 18,241,010.75 36.99% 3,840.00 3,840.00 97.60 17,788,876.80 17,788,876.80 - 36.86%
PART H - MISCELLANEOUS STRUCTURES
600(7) Concrete Curb and Gutter Precast pc 324.00 2,087.49 676,346.76 1.40% 324.00 2,087.49 676,346.76 1.37% - 324.00 - - 676,346.76 0.00%
624(8) Solar LED Street Lights ea. 19.00 216,550.75 4,114,464.25 8.52% 19.00 216,550.75 4,114,464.25 8.34% - 19.00 - - 4,114,464.25 0.00%
WE HEREBY CERTIFY THAT THIS STATEMENT OF WORK Amount Due 34,708,318.54
ACCOMPLISHED ON THIS PAGE IS TRUE AND CORRECT: Cost to date 34,708,318.54
Percentage 71.94%
MARIANO P. ADUPE JR. GREATCHEN T. FIRMALO ELMER M. TOLENTINO BOY ALEXIS E. MINANO
Contractor's Projcet Engineer DPWH, Project Inspector Chief, Quality Assurance Section OIC, Assistant District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
MANUEL L. URQUICO, JR. JULIEN MARIE M. EVANGELIO ALAN T. SALVADOR ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construction Section District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
STATEMENT OF WORK ACCOMPLISHED
for the period of March 29, 2022 to July 15, 2022
Contract ID : 22EH015-R1
Contract
: Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Batiano Boulevard Flood Mitigating Structure
Name
Location : Odiongan, Romblon
Contractor : ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION
Page ____ of ____
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
PART A - FACILITIES FOR THE ENGINEER
Provision of Combined Field Office Laboratory and
A1.1(6) Living Quarters Building for the Engineer (Rental mos. 10.13 16,567.75 167,831.30 0.18% 10.13 16,567.75 167,831.30 0.18% 3.62 3.62 6.51 59,975.25 59,975.25 107,856.05 0.06%
Basis)
B.4(1) Construction Survey and Staking km. 0.41 56,683.00 23,240.03 0.02% 0.41 56,683.00 23,240.03 0.02% 0.410 0.41 - 23,240.03 23,240.03 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,383.00 5,383.00 0.01% 1.00 5,383.00 5,383.00 0.01% 1.00 1.00 - 5,383.00 5,383.00 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 697,398.00 697,398.00 0.74% 1.00 697,398.00 697,398.00 0.74% 0.10 0.10 0.90 69,739.80 69,739.80 627,658.20 0.07%
B.9 Mobilization and Demobilization l.s. 1.00 79,040.00 79,040.00 0.08% 1.00 79,040.00 79,040.00 0.08% 0.50 0.50 0.50 39,520.00 39,520.00 39,520.00 0.04%
103(3) Foundation Fill cu.m. 3.60 1,556.80 5,604.48 0.01% 3.60 1,556.80 5,604.48 0.01% - 3.60 - - 5,604.48 0.00%
104(2)a Embankment from Borrow cu.m. 3,124.33 1,624.80 5,076,411.38 5.40% 2,739.65 1,624.80 4,451,383.32 4.74% 953.98 953.98 1,785.67 1,550,026.70 1,550,026.70 2,901,356.62 1.61%
200(1) Aggregate Subbase Course cu.m. 581.03 1,504.10 873,927.22 0.93% 598.43 1,504.10 900,098.56 0.96% - 598.43 - - 900,098.56 0.00%
404(1)a Reinforcing Steel Grade 40 kg 44,053.16 74.10 3,264,339.15 3.47% 36,197.14 74.10 2,682,208.07 2.85% 4,487.51 4,487.51 31,709.63 332,524.49 332,524.49 2,349,683.58 0.34%
404(1)b Reinforcing Steel Grade 60 kg 4,131.16 76.60 316,446.85 0.34% 5,139.26 76.60 393,667.31 0.42% 947.20 947.20 4,192.06 72,555.52 72,555.52 321,111.79 0.08%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 769.53 11,030.50 8,488,300.66 9.03% 845.52 11,030.50 9,326,508.35 9.92% 197.54 197.54 647.98 2,178,964.97 2,178,964.97 7,147,543.38 2.26%
407(8) Lean Concrete cu.m. 31.86 7,434.75 236,871.13 0.25% 33.41 7,434.75 248,394.99 0.26% 7.54 7.54 25.87 56,058.01 56,058.01 192,336.98 0.06%
500(1)c Pipe Culverts, 910mm dia. (36" Ø) m 0.00 0.00% 15.00 7,273.31 109,099.65 0.12% - 15.00 - - 109,099.65 0.00%
505(2)a Grouted Riprap (Class A) cu.m. 316.89 3,382.30 1,071,817.04 1.14% 320.20 3,382.30 1,083,012.45 1.15% 107.98 107.98 212.22 365,220.75 365,220.75 717,791.70 0.38%
508(1) Hand-Laid Rock Embankment cu.m. 4,759.21 1,311.90 6,243,607.59 6.64% 4,410.22 1,311.90 5,785,767.61 6.16% 1,464.77 1,464.77 2,945.45 1,921,631.76 1,921,631.76 3,864,135.85 1.99%
509(1)b1 Steel Sheet Pile (Slope Protection) m. 9,104.00 6,795.00 61,861,680.00 65.81% 9,544.00 6,795.00 64,851,480.00 68.99% 3,280.00 3,280.00 6,264.00 22,287,600.00 22,287,600.00 42,563,880.00 23.10%
600(7) Concrete Curb and Gutter Precast pc 425.00 2,030.15 862,813.75 0.92% 425.00 2,030.15 862,813.75 0.92% - 425.00 - - 862,813.75 0.00%
Percentage 30.02%
Prepared by: Verified by: Checked and Reviewed by: Recommending Approval: APPROVED FOR PAYMENT
MANUEL L. URQUICO, JR. DANTE F. FETALVERO ELMER M. TOLENTINO BOY ALEXIS E. MINANO ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer III Chief, Construction Section OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for : September 05, 2022
Contract ID : 22EH015-R1
Contract Name : Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Batiano Boulevard Flood Mitigating Structure
Location : Odiongan, Romblon
Contractor : ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION
Page ____ of ____
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
B.4(1) Construction Survey and Staking km. 0.41 56,683.00 23,240.03 0.02% 0.41 56,683.00 23,240.03 0.02% 0.410 0.41 - 23,240.03 23,240.03 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,383.00 5,383.00 0.01% 1.00 5,383.00 5,383.00 0.01% 1.00 1.00 - 5,383.00 5,383.00 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 697,398.00 697,398.00 0.74% 1.00 697,398.00 697,398.00 0.74% 0.10 0.10 0.90 69,739.80 69,739.80 627,658.20 0.07%
B.9 Mobilization and Demobilization l.s. 1.00 79,040.00 79,040.00 0.08% 1.00 79,040.00 79,040.00 0.08% 0.50 0.50 0.50 39,520.00 39,520.00 39,520.00 0.04%
103(3) Foundation Fill cu.m. 3.60 1,556.80 5,604.48 0.01% 3.60 1,556.80 5,604.48 0.01% - 3.60 - - 5,604.48 0.00%
104(2)a Embankment from Borrow cu.m. 3,124.33 1,624.80 5,076,411.38 5.40% 2,739.65 1,624.80 4,451,383.32 4.74% 991.70 991.70 1,747.95 1,611,314.16 1,611,314.16 2,840,069.16 1.67%
200(1) Aggregate Subbase Course cu.m. 581.03 1,504.10 873,927.22 0.93% 598.43 1,504.10 900,098.56 0.96% - 598.43 - - 900,098.56 0.00%
404(1)a Reinforcing Steel Grade 40 kg 44,053.16 74.10 3,264,339.15 3.47% 36,197.14 74.10 2,682,208.07 2.85% 4,487.51 4,487.51 31,709.63 332,524.50 332,524.49 2,349,683.58 0.34%
404(1)b Reinforcing Steel Grade 60 kg 4,131.16 76.60 316,446.85 0.34% 5,139.26 76.60 393,667.31 0.42% 947.20 947.20 4,192.06 72,555.52 72,555.52 321,111.79 0.08%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 769.53 11,030.50 8,488,300.66 9.03% 845.52 11,030.50 9,326,508.35 9.92% 204.74 204.74 640.78 2,258,384.57 2,258,384.57 7,068,123.78 2.34%
407(8) Lean Concrete cu.m. 31.86 7,434.75 236,871.13 0.25% 33.41 7,434.75 248,394.99 0.26% 7.89 7.89 25.52 58,660.18 58,660.17 189,734.82 0.06%
500(1)c Pipe Culverts, 910mm dia. (36" Ø) m 0.00 0.00% 15.00 7,273.31 109,099.65 0.12% - 15.00 - - 109,099.65 0.00%
505(2)a Grouted Riprap (Class A) cu.m. 316.89 3,382.30 1,071,817.04 1.14% 320.20 3,382.30 1,083,012.45 1.15% 44.05 44.05 276.15 148,990.32 148,990.31 934,022.14 0.15%
508(1) Hand-Laid Rock Embankment cu.m. 4,759.21 1,311.90 6,243,607.59 6.64% 4,410.22 1,311.90 5,785,767.61 6.16% 1,521.70 1,521.70 2,888.52 1,996,318.23 1,996,318.23 3,789,449.38 2.07%
509(1)b1 Steel Sheet Pile (Slope Protection) m. 9,104.00 6,795.00 61,861,680.00 65.81% 9,544.00 6,795.00 64,851,480.00 68.99% 2,000.00 2,000.00 7,544.00 13,590,000.00 13,590,000.00 51,261,480.00 14.09%
600(7) Concrete Curb and Gutter Precast pc 425.00 2,030.15 862,813.75 0.92% 425.00 2,030.15 862,813.75 0.92% - 425.00 - - 862,813.75 0.00%
Percentage 21.03%
Prepared by: Verified by: Checked and Reviewed by: Recommending Approval: APPROVED FOR PAYMENT
MANUEL L. URQUICO, JR. DANTE F. FETALVERO ELMER M. TOLENTINO BOY ALEXIS E. MINANO ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer III Chief, Construction Section OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for : September 05, 2022
Contract ID : 22EH015-R1
Contract Name : Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Batiano Boulevard Flood Mitigating Structure
Location : Odiongan, Romblon
Contractor : ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION
Page ____ of ____
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
B.4(1) Construction Survey and Staking km. 0.41 56,683.00 23,240.03 0.02% 0.41 56,683.00 23,240.03 0.02% 0.410 0.41 - 23,240.03 23,240.03 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,383.00 5,383.00 0.01% 1.00 5,383.00 5,383.00 0.01% 1.00 1.00 - 5,383.00 5,383.00 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 697,398.00 697,398.00 0.74% 1.00 697,398.00 697,398.00 0.74% 0.67 0.67 0.33 467,256.66 467,256.66 230,141.34 0.48%
B.9 Mobilization and Demobilization l.s. 1.00 79,040.00 79,040.00 0.08% 1.00 79,040.00 79,040.00 0.08% 0.50 0.50 0.50 39,520.00 39,520.00 39,520.00 0.04%
103(3) Foundation Fill cu.m. 3.60 1,556.80 5,604.48 0.01% 3.60 1,556.80 5,604.48 0.01% - 3.60 - - 5,604.48 0.00%
104(2)a Embankment from Borrow cu.m. 3,124.33 1,624.80 5,076,411.38 5.40% 2,739.65 1,624.80 4,451,383.32 4.74% 1,010.00 1,010.00 1,729.65 1,641,048.00 1,641,048.00 2,810,335.32 1.70%
200(1) Aggregate Subbase Course cu.m. 581.03 1,504.10 873,927.22 0.93% 598.43 1,504.10 900,098.56 0.96% - 598.43 - - 900,098.56 0.00%
404(1)a Reinforcing Steel Grade 40 kg 44,053.16 74.10 3,264,339.15 3.47% 36,197.14 74.10 2,682,208.07 2.85% 4,487.51 4,487.51 31,709.63 332,524.50 332,524.49 2,349,683.58 0.34%
404(1)b Reinforcing Steel Grade 60 kg 4,131.16 76.60 316,446.85 0.34% 5,139.26 76.60 393,667.31 0.42% 947.20 947.20 4,192.06 72,555.52 72,555.52 321,111.79 0.08%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 769.53 11,030.50 8,488,300.66 9.03% 845.52 11,030.50 9,326,508.35 9.92% 176.04 176.04 669.48 1,941,809.22 1,941,809.22 7,384,699.13 2.01%
407(8) Lean Concrete cu.m. 31.86 7,434.75 236,871.13 0.25% 33.41 7,434.75 248,394.99 0.26% 7.89 7.89 25.52 58,660.18 58,660.17 189,734.82 0.06%
500(1)c Pipe Culverts, 910mm dia. (36" Ø) m 0.00 0.00% 15.00 7,273.31 109,099.65 0.12% - 15.00 - - 109,099.65 0.00%
505(2)a Grouted Riprap (Class A) cu.m. 316.89 3,382.30 1,071,817.04 1.14% 320.20 3,382.30 1,083,012.45 1.15% 44.05 44.05 276.15 148,990.32 148,990.31 934,022.14 0.15%
508(1) Hand-Laid Rock Embankment cu.m. 4,759.21 1,311.90 6,243,607.59 6.64% 4,410.22 1,311.90 5,785,767.61 6.16% 1,521.70 1,521.70 2,888.52 1,996,318.23 1,996,318.23 3,789,449.38 2.07%
509(1)b1 Steel Sheet Pile (Slope Protection) m. 9,104.00 6,795.00 61,861,680.00 65.81% 9,544.00 6,795.00 64,851,480.00 68.99% 3,360.00 3,360.00 6,184.00 22,831,200.00 22,831,200.00 42,020,280.00 23.66%
600(7) Concrete Curb and Gutter Precast pc 425.00 2,030.15 862,813.75 0.92% 425.00 2,030.15 862,813.75 0.92% - 425.00 - - 862,813.75 0.00%
Percentage 31.36%
Prepared by: Verified by: Checked and Reviewed by: Recommending Approval: APPROVED FOR PAYMENT
MANUEL L. URQUICO, JR. DANTE F. FETALVERO ELMER M. TOLENTINO BOY ALEXIS E. MINANO ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer III Chief, Construction Section OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for : September 05, 2022
Contract ID : 22EH015-R1
Contract Name : Construction/Maintenance of Flood Mitigation Structures and Drainage Systems - Construction of Batiano Boulevard Flood Mitigating Structure
Location : Odiongan, Romblon
Contractor : ROLCO CONSTRUCTION AND DEVELOPMENT CORPORATION
Page ____ of ____
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
B.4(1) Construction Survey and Staking km. 0.41 56,683.00 23,240.03 0.02% 0.41 56,683.00 23,240.03 0.02% 0.410 0.41 - 23,240.03 23,240.03 - 0.02%
B.5 Project Billboard/Sign Board each 1.00 5,383.00 5,383.00 0.01% 1.00 5,383.00 5,383.00 0.01% 1.00 1.00 - 5,383.00 5,383.00 - 0.01%
B.7(1) Occupational Safety and Health Program l.s. 1.00 697,398.00 697,398.00 0.74% 1.00 697,398.00 697,398.00 0.74% 0.67 0.67 0.33 467,256.66 467,256.66 230,141.34 0.48%
B.9 Mobilization and Demobilization l.s. 1.00 79,040.00 79,040.00 0.08% 1.00 79,040.00 79,040.00 0.08% 0.50 0.50 0.50 39,520.00 39,520.00 39,520.00 0.04%
103(3) Foundation Fill cu.m. 3.60 1,556.80 5,604.48 0.01% 3.60 1,556.80 5,604.48 0.01% - 3.60 - - 5,604.48 0.00%
104(2)a Embankment from Borrow cu.m. 3,124.33 1,624.80 5,076,411.38 5.40% 2,739.65 1,624.80 4,451,383.32 4.74% 1,010.00 1,010.00 1,729.65 1,641,048.00 1,641,048.00 2,810,335.32 1.70%
200(1) Aggregate Subbase Course cu.m. 581.03 1,504.10 873,927.22 0.93% 598.43 1,504.10 900,098.56 0.96% - 598.43 - - 900,098.56 0.00%
404(1)a Reinforcing Steel Grade 40 kg 44,053.16 74.10 3,264,339.15 3.47% 36,197.14 74.10 2,682,208.07 2.85% 4,487.51 4,487.51 31,709.63 332,524.50 332,524.49 2,349,683.58 0.34%
404(1)b Reinforcing Steel Grade 60 kg 4,131.16 76.60 316,446.85 0.34% 5,139.26 76.60 393,667.31 0.42% 947.20 947.20 4,192.06 72,555.52 72,555.52 321,111.79 0.08%
405(1)a2 Structural Concrete Class A (20.68MPa) cu.m. 769.53 11,030.50 8,488,300.66 9.03% 845.52 11,030.50 9,326,508.35 9.92% 176.04 176.04 669.48 1,941,809.22 1,941,809.22 7,384,699.13 2.01%
407(8) Lean Concrete cu.m. 31.86 7,434.75 236,871.13 0.25% 33.41 7,434.75 248,394.99 0.26% 7.89 7.89 25.52 58,660.18 58,660.17 189,734.82 0.06%
500(1)c Pipe Culverts, 910mm dia. (36" Ø) m 0.00 0.00% 15.00 7,273.31 109,099.65 0.12% - 15.00 - - 109,099.65 0.00%
505(2)a Grouted Riprap (Class A) cu.m. 316.89 3,382.30 1,071,817.04 1.14% 320.20 3,382.30 1,083,012.45 1.15% 44.05 44.05 276.15 148,990.32 148,990.31 934,022.14 0.15%
508(1) Hand-Laid Rock Embankment cu.m. 4,759.21 1,311.90 6,243,607.59 6.64% 4,410.22 1,311.90 5,785,767.61 6.16% 1,521.70 1,521.70 2,888.52 1,996,318.23 1,996,318.23 3,789,449.38 2.07%
509(1)b1 Steel Sheet Pile (Slope Protection) m. 9,104.00 6,795.00 61,861,680.00 65.81% 9,544.00 6,795.00 64,851,480.00 68.99% 3,360.00 3,360.00 6,184.00 22,831,200.00 22,831,200.00 42,020,280.00 23.66%
600(7) Concrete Curb and Gutter Precast pc 425.00 2,030.15 862,813.75 0.92% 425.00 2,030.15 862,813.75 0.92% - 425.00 - - 862,813.75 0.00%
Percentage 31.36%
Prepared by: Verified by: Checked and Reviewed by: Recommending Approval: APPROVED FOR PAYMENT
MANUEL L. URQUICO, JR. DANTE F. FETALVERO ELMER M. TOLENTINO BOY ALEXIS E. MINANO ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer III Chief, Construction Section OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for : July 06, 2022
Contract ID : 22EH0141
Contract Name : Construction/Rehabilitation of Water Supply/Septage and Sewerage/Rain Water Collector System- Construction of Level III Public Water Supply System
Location : Canduyong, Odiongan, Romblon
Contractor : B. VICENCIO BUILDERS (BVB), INC.
Page ____ of ____
B.5 Project Billboard/Sign Board each 1.00 8,602.73 8,602.73 0.09% 1.00 1.00 - 8,602.73 8,602.73 - 0.09%
B.7(2) Occupational Safety and Health Program l.s. 1.00 185,949.79 185,949.79 1.94% 0.10 0.10 0.90 18,594.98 18,594.97 167,354.82 0.19%
B.9 Mobilization and Demobilization l.s. 1.00 86,136.32 86,136.32 0.90% 0.50 0.50 0.50 43,068.16 43,068.16 43,068.16 0.45%
803(1) Structure Excavation (Common Soil) cu.m. 50.37 292.17 14,716.60 0.15% 32.56 32.56 17.81 9,513.06 9,513.05 5,203.55 0.10%
804(1)a1 Embankment from Structure Excavation cu.m. 33.33 190.66 6,354.69 0.07% 20.12 20.12 13.21 3,836.08 3,836.07 2,518.62 0.04%
804(4) Gravel Fill cu.m. 11.38 2,578.33 29,341.39 0.31% 6.54 6.54 4.84 16,862.28 16,862.27 12,479.12 0.18%
900(1)c1 Structural Concrete (Class A, 28 days) cu.m. 38.04 8,045.54 306,052.34 3.19% 15.20 15.20 22.84 122,292.21 122,292.20 183,760.14 1.27%
Structural Concrete for Footing and Slab on Fill,
900(1)c2 cu.m. 40.71 8,024.80 326,689.60 3.40% 20.55 20.55 20.16 164,909.64 164,909.64 161,779.96 1.72%
(Class A, 28 Days)
900(1)c4 Structural Concrete for Column (Class A, 28 Days) cu.m. 5.46 9,016.39 49,229.48 0.51% 0.20 0.20 5.26 1,803.28 1,803.27 47,426.21 0.02%
902(1)a Reinforcing Steel Grade 40 kg 10,765.89 85.40 919,407.00 9.57% 6,402.00 6,402.00 4,363.89 546,730.80 546,730.80 372,676.20 5.69%
902(1)b Reinforcing Steel Grade 60 kg 10,246.54 89.21 914,093.83 9.52% 4,505.00 4,505.00 5,741.54 401,891.05 401,891.05 512,202.78 4.18%
903(2) Formworks and Falseworks sq.m. 245.27 1,037.11 254,371.96 2.65% 145.00 145.00 100.27 150,380.95 150,380.95 103,991.01 1.57%
1000(1) Soil Poisoning L. 5.33 572.38 3,050.78 0.03% 5.33 5.33 - 3,050.79 3,050.78 - 0.03%
1001(10) Pipes with Fittings Connection l.s. 1.00 ### 3,427,674.23 35.69% - 1.00 - - 3,427,674.23 0.00%
1032(1)c Painting Works (Steel) sq.m. 47.90 286.21 13,709.45 0.14% - 47.90 - - 13,709.45 0.00%
1047(1) Structural Steel l.s. 1.00 144,259.42 144,259.42 1.50% - 1.00 - - 144,259.42 0.00%
1102(18) Solar Panel with Inverter, Battery and Other Devices l.s. 1.00 368,711.62 368,711.62 3.84% - 1.00 - - 368,711.62 0.00%
1600(2) Pipeline Trench Excavation cu.m. 4,198.32 315.86 1,326,081.35 13.81% 1,220.10 1,220.10 2,978.22 385,380.79 385,380.78 940,700.57 4.01%
1601(1) Fill and Backfill cu.m. 4,164.66 158.04 658,182.86 6.85% - 4,164.66 - - 658,182.86 0.00%
1603(1) Valve l.s. 1.00 308,558.30 308,558.30 3.21% - 1.00 - - 308,558.30 0.00%
Percentage 20.01%
Prepared by: Verified by: Checked and R Recommending Approval: APPROVED FOR PAYMENT
RODNEY ROSS L. ROLEDA GREATCHEN T. FIRMALO ELMER M. TO BOY ALEXIS E. MINANO ELENA M. CASTILAN
Pres./Authorized Managing Officer DPWH, Project Engineer I Chief, Construc OIC, Assistant District Engineer District Engineer
Date: ____________________________ Date: ____________________________ Date: ______ Date: ____________________________ Date: ____________________________
CONTRACTOR'S STATEMENT OF WORK ACCOMPLISHED
As for : March 20, 2023 to March 24, 2023
Contract ID : 22EH0141
Contract Name : Construction/Rehabilitation of Water Supply/Septage and Sewerage/Rain Water Collector System- Construction of Level III Public Water Supply System
Location : Canduyong, Odiongan, Romblon
Contractor : B. VICENCIO BUILDERS (BVB), INC.
Page ____ of ____
ORIGINAL CONTRACT REVISED CONTRACT DUE TO AS-STAKED QUANTITY ACCOMPLISHMENT AMOUNT ACCOMPLISHMENT
RELATIVE
ITEM ACTIVITIES UNIT PERCENTAGE
WEIGHT
QUANTITY UNIT COST AMOUNT QUANTITY UNIT COST AMOUNT Previous This Period To Date Balance Previous This Period To Date Balance
B.5 Project Billboard/Sign Board each 1.00 8,602.73 8,602.73 1.00 8,602.73 8,602.73 0.09% 1.00 1.00 - 8,602.73 8,602.73 - 0.09%
B.7(2) Occupational Safety and Health Program l.s. 1.00 185,949.79 185,949.79 1.00 185,949.79 185,949.79 1.94% 0.50 0.50 0.50 92,974.90 92,974.89 92,974.90 0.95%
B.9 Mobilization and Demobilization l.s. 1.00 86,136.32 86,136.32 1.00 86,136.32 86,136.32 0.90% 0.50 0.50 0.50 43,068.16 43,068.16 43,068.16 0.44%
803(1) Structure Excavation (Common Soil) cu.m. 50.37 292.17 14,716.60 131.47 292.17 38,411.59 0.15% 131.47 131.47 - 38,411.59 38,411.59 - 0.39%
804(1)a1 Embankment from Structure Excavation cu.m. 33.33 190.66 6,354.69 3.96 190.66 755.01 0.07% 3.96 3.96 - 755.02 755.01 - 0.01%
804(4) Gravel Fill cu.m. 11.38 2,578.33 29,341.39 6.50 2,578.33 16,759.15 0.31% 6.50 6.50 - 16,759.15 16,759.15 - 0.17%
900(1)c1 Structural Concrete (Class A, 28 days) cu.m. 38.04 8,045.54 306,052.34 12.93 8,045.54 104,028.83 3.19% 12.93 12.93 - 104,028.84 104,028.83 - 1.06%
900(1)c2 Structural Concrete for Footing and Slab on Fill, (Class A, 28 Days) cu.m. 40.71 8,024.80 326,689.60 17.58 8,024.80 141,075.98 3.40% 17.58 17.58 - 141,075.99 141,075.98 - 1.44%
900(1)c4 Structural Concrete for Column (Class A, 28 Days) cu.m. 5.46 9,016.39 49,229.48 24.14 9,016.39 217,655.65 0.51% 24.14 24.14 - 217,655.66 217,655.65 - 2.22%
900(1)c5 Structural Concrete for Suspended Slab (Class A, 28 Days) cu.m. 6.81 8,156.90 55,548.49 0.00% 6.81 6.81 - 55,548.49 55,548.49 - 0.57%
902(1)a Reinforcing Steel Grade 40 kg 10,765.89 85.40 919,407.00 3,797.83 85.40 324,334.68 9.57% 3,797.83 3,797.83 - 324,334.69 324,334.68 - 3.31%
902(1)b Reinforcing Steel Grade 60 kg 10,246.54 89.21 914,093.83 828.80 89.21 73,937.25 9.52% 828.80 828.80 - 73,937.25 73,937.25 - 0.75%
903(2) Formworks and Falseworks sq.m. 245.27 1,037.11 254,371.96 272.16 1,037.11 282,259.86 2.65% 272.16 272.16 - 282,259.86 282,259.86 - 2.88%
1000(1) Soil Poisoning L. 5.33 572.38 3,050.78 5.33 572.38 3,050.78 0.03% 5.33 5.33 - 3,050.79 3,050.78 - 0.03%
1001(10) Pipes with Fittings Connection l.s. 1.00 ### 3,427,674.23 1.00 3,427,674.23 4,139,263.01 35.69% 0.80 0.80 0.20 2,742,139.39 2,742,139.38 1,397,123.63 27.98%
1013(1) Corrugated Metal Roofing 50.00 783.17 39,158.50 25.00 25.00 25.00 19,579.25 19,579.25 19,579.25 0.20%
1032(1)a Painting Works (Masonry/Concrete) 191.44 349.82 66,969.54 - 191.44 - - 66,969.54 0.00%
1032(1)c Painting Works (Steel) sq.m. 47.90 286.21 13,709.45 22.80 286.21 6,525.59 0.14% 11.40 11.40 11.40 3,262.80 3,262.79 3,262.80 0.03%
1046(2)a1 CHB Non-Load Bearing (Including Reinforcing Steel), 100mm 93.60 1,003.59 93,936.02 93.60 93.60 - 93,936.03 93,936.02 - 0.96%
1047(1) Structural Steel l.s. 1.00 144,259.42 144,259.42 1.00 198,919.93 198,919.93 1.50% 0.50 0.50 0.50 99,459.97 99,459.96 99,459.97 1.01%
1102(18) Solar Panel with Inverter, Battery and Other Devices l.s. 1.00 368,711.62 368,711.62 1.00 368,711.62 368,711.62 3.84% - 1.00 - - 368,711.62 0.00%
1600(2) Pipeline Trench Excavation cu.m. 4,198.32 315.86 1,326,081.35 5,078.20 315.86 1,604,000.25 13.81% 4,053.10 4,053.10 1,025.10 1,280,212.17 1,280,212.16 323,788.09 13.06%
1601(1) Fill and Backfill cu.m. 4,164.66 158.04 658,182.86 4,991.61 158.04 788,874.04 6.85% 3,074.50 3,074.50 1,917.11 485,893.98 485,893.98 302,980.06 4.96%
1603(1) Valve l.s. 1.00 308,558.30 308,558.30 1.00 702,257.40 702,257.40 3.21% 0.30 0.30 0.70 210,677.22 210,677.22 491,580.18 2.15%
1724(2) Submersible Vertical Axial Flow Pump set 2.00 73,071.53 146,143.06 2.00 73,071.53 146,143.06 1.52% - 2.00 - - 146,143.06 0.00%
Percentage 65.57%