CH 6 Road Constrxn 3

The document outlines the construction procedures, material selection, and quality control for various types of bituminous pavements, including Grouted or Penetration Macadam, Bitumen Bound Macadam, Premix Bituminous Carpet, and Bituminous Concrete. It details the equipment needed, recommended thicknesses, and specific tests for aggregates and bitumen to ensure quality. Additionally, it describes the construction process for Cement Concrete Pavement, including curing and joint construction requirements.

Uploaded by

Ishwor Neupane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views7 pages

CH 6 Road Constrxn 3

The document outlines the construction procedures, material selection, and quality control for various types of bituminous pavements, including Grouted or Penetration Macadam, Bitumen Bound Macadam, Premix Bituminous Carpet, and Bituminous Concrete. It details the equipment needed, recommended thicknesses, and specific tests for aggregates and bitumen to ensure quality. Additionally, it describes the construction process for Cement Concrete Pavement, including curing and joint construction requirements.

Uploaded by

Ishwor Neupane
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

5/12/2025

Grouted or Penetration Macadam

 Penetration macadam consists of 3 layers of successively


finer broken or crushed rock interspersed with applications
of heated bitumen to grout voids and eventually seal the
surface.

 May be full grout (bitumen penetrates up to full depth of


aggregate) or semi-grout (bitumen penetrates up to half the
depth)

 Recommended for thickness of 50 to 75 mm

Grouted or Penetration Macadam Grouted or Penetration Macadam


 Construction Procedure
 Equipment: Hot bitumen spray equipment; Roller,
 Preparation of existing surface and recondition itas
Aggregate spreader, mechanical brooms, Hand tools
necessary
such as shovels, wheelbarrows, and hard broomsetc.
 Spreading of Coarse aggregates
 Rolling – 10 tonnes
 Material Selection:
 Apply the first layer of bituminous material – 5-6.7kg/m2
 Aggregate - FI ≤ 25%, LAA ≤ 40%, Impact value ≤ 30%,
 Spreading of key aggregates
stripping at 40oC ≤ 25%, loss withNA2SO4≤ 25%, Coarse
aggregate (<63 mm for 7.5 cm thick, <50 mm for 5 cm  Rolling by 10 tonnes but excessive rollingavoided
thick), key aggregates (<25 mm for 7.5 cm thick , <19mm  Apply the second layer of bituminousmaterial.
for 5 cm thick, stone chipping or fine (<10 mm )  Apply stonechippings.
 Bitumen grade 80/100, 60/70, 30/40 (5-6.7 kg/m2 for  Drag-broom, roll, and hand-broom the surface
first application, second application 2-3 perm2)  Opening of traffic – After 24 hours
5/12/2025

Grouted or Penetration Macadam


 Quality Control
 Temperature of binder,
 Tests on aggregates (LAA, FI, Impact value, Stripping
test etc,
 gradation test,
 rate of application of binder andaggregate,
 test on bitumen (penetration, viscosity, ductilityetc.)

6.9 Construction of Different Types of


6.9.1 Bitumen Bound Macadam
Bituminous Premixes
 It is an open graded mixture of mineral aggregate
and appropriate binder, mixed in a hot mix plant
 Bitumen Bound Macadam
 Bituminous premixed carpet  It is laid in a single course or in a multiple layers
 Bituminous concrete
 Thickness of single layer is 50 mm to 75mm.

 However, may trap water or moisture vapor


within the pavement system
5/12/2025

6.9.1 Bitumen Bound Macadam 6.9.1 Bitumen Bound Macadam


 Equipment: Hot bitumen sprayer; mechanical or  Construction Procedure
hand mixer, mechanical paver, bitumen heating device,  Preparation of existing layer
hot mix plant, Pneumatic Roller, mechanical brooms  Tack Coat or prime coat application – 4 to 7.5 kg/10m2 for
etc. black top; 7.5 to 10 kg/10m2 for WBMlayer
 Premix Production – temperature tolerance of +- 10oC
 Material Selection:  Placement of the mix at site with paver or grader or manual
 Aggregate - FI ≤ 25%, LAA ≤ 40%, Impact value ≤ 30%,
 Rolling compaction by 8 to 10 tone pneumaticroller
stripping at 40oC ≤ 25%, loss withNA2SO4≤ 12% for  Application of seal coat
binder course, FI ≤ 15%, LAA ≤ 50%, Impact value ≤ 35%,  Opening to traffic
stripping at 40oC ≤ 25%, loss withNA2SO4≤ 12% for base
course
 Bitumen grade 80/100, 60/70, 30/40 penetration, RT-4
tar, bitumen content 3 to 4.5% byweight

6.9.1 Bitumen Bound Macadam 6.9.2 Premix Bituminous Carpet


 It is an open graded premix of stone chipping of
 Quality Control size 10~12 mm with bitumen or tar binder
 Temperature of binder,
 Tests on aggregates (LAA, FI, Impact value, Stripping
test etc,  Being open graded, it should be covered with
 gradation test, sand seal or chipseal
 rate of application of binder
 Spread of mix material  Thickness of single layer is 20 mm to 25mm.
 test on bitumen (penetration, viscosity, ductilityetc.)
 Density of compacted layer
5/12/2025

6.9.2 Premix Bituminous Carpet 6.9.2 Premix Bituminous Carpet


 Equipment: Hot bitumen sprayer; mechanical paver,  Construction Procedure
bitumen heating device, Pneumatic Roller, mechanical  Preparation of the existing surface
brooms etc.  Application of tack coat or prime coat
 Premix is prepared by heating both bitumen and aggregate
up to the required temp and mixed in mechanicalmixer
 Material Selection:
 Mix is taken out and spread with thickness 15 cm using
 Coarse aggregate - angular, clean, hard, tough, durable
paver
≤ 16 mm for 40 mm thick and ≤ 10 mm for 20 mm thick
with LAA value 40% (max), Aggregate Impact value –  Rolling is done with Tandem or Pneumatic roller of 6 to 9
35%(max), Flakiness index – 30%(max) tonnes
 Sand - clean, hard, durable  Premix sand seal coat or chip seal is applied and light
tandem roller is rolled
 Bitumen grade 80/100 penetration
 Open to traffic after 24 hours

6.9.2 Premix Bituminous Carpet 6.9.3 Bituminous Concrete


 Highest quality of construction among
 Quality Control bituminous pavement
 Temperature of binder,
 Tests on aggregates (LAA, FI, Impact value, Stripping
test etc,  It is carefully proportioned mix of coarse, fine
 gradation test,
and mineral fillers with bitumen binders
 rate of application of binder
 Spread of mix material  Thickness of single layer is 50 mm to 100mm
 test on bitumen (penetration, viscosity, ductilityetc.)
 Density of compacted layer
 Durable, impervious, better riding quality and
load carrying capacity
5/12/2025

6.9.3 Bituminous Concrete 6.9.3 Bituminous Concrete


 Equipment: Hot bitumen sprayer; mechanical paver,  Construction Procedure
hot mix plant, Tandem/Pneumatic Roller, mechanical  Preparation of the existing surface - sweeping, correcting
irregularities such as potholes
brooms etc.
 Application of tack coat at the rate of 6.0~7.5 kg/102m
 Production of mix from hot mixplant
 Material Selection:  Hot mix bituminous concrete is transported to site and spread by
 Coarse aggregate - LAA value ≤ 40%, Aggregate Impact mechanical paver to the required grade and shape
value ≤ 30%, Flakiness index ≤ 30%, stripping ≤ 25%,  The mix is thoroughly rolled. Rolling first two passes by either 8
water absorption ≤ 1%, Loss with Na2SO4 ≤ 12%, dense tonnes smooth wheel roller, 4 tones vibro roller and then with 8
grading to 12 tonnes pneumaticroller
 Bitumen grade 30/40, 60/70, 80/100 penetration  Open to traffic

6.9.3 Bituminous Concrete


 Quality Control
 Temperature of bituminous mix, aggregate
 Tests on aggregates (LAA, FI, Impact value, Stripping
test etc,
 gradation test,
 rate of application of tack coat
 Spread of mix material
 test on bitumen (penetration grade, viscosity, ductility
etc.)
 Marshal test for compacted layer
5/12/2025

6.10 Cement Concrete Pavement 6.10 Cement Concrete Pavement


 Two Types of construction:  Plant and equipment: concrete mix plant,
concrete truck mixer, Concrete mixture, batching
 Cement Grouted layer – an open graded compacted
device, wheel barrow, needle vibrators, brush,
aggregate (18 to 25 mm) laid mixture of cement and finishing tools etc.
sand (1:1.5:2.5) is spread over it.
 Material Selection: Portland cement, coarse
 Rolled Concrete layer – Aggregate, sand, cement and aggregates with Crushing Value≤30%, Aggregate
water with less plasticity is used and compacted.
Impact Value≤30%, LAA≤16%, Soundness
Value≤12% in Na2SO4 and ≤16% MgSO4 and fine
aggregate (natural sand), M30 concrete orhigher

6.10 Cement Concrete Pavement 6.10 Cement Concrete Pavement


 Construction Procedure  Construction Procedure
 Preparation of Sub Grade and subbase  Curing of cement Concrete: surface is with jute mat for 24
 All formwork are placed and well secured to resistthe hours, Upon the removal of wet covers, the slabs cured by
tamping forces ponding for 14 days.
 Coarse aggregate, fine aggregate, cement and required  Concrete road is opened to traffic after 28 days
amount of water are either mixed on site in batch mixer or Joint construction
transported from mixing plant.
 Expansion joints are provide at 140 m interval, width 20
 Concrete is transported to the site and deposited on the
to 25 mm
sub base to the requireddepth
 Contraction joints are provided at 4.5 m interval for plain
 Compaction is carried out using a mechanicalpoker
and 14 m for reinforced
(needle) vibrator.
 Longitudinal joints are provided if slab width more than
 The surface is textured with an approved longhandled
4.5 m
steel or fiber brush.
5/12/2025

6.10 Cement Concrete Pavement


 Quality Control
 Ordinary Portland cement or rapid hardeningtype
 Max size of aggregate = ¼ of slabthickness
 Tests on aggregates (LAA, FI, Impact value, soundness)
 gradation test,
 Proportioning of concrete