Method Statement For Excavation and Backfilling

The document outlines the Method Statement for Excavation and Backfilling Works for the EIA Aviation Fuel Farm Rehabilitation project at Erbil Airport, detailing procedures, equipment, manpower, and safety measures. It specifies the responsibilities of various personnel involved, the scope of work including excavation, backfilling, and site preparation, and emphasizes adherence to safety and environmental standards. The document also includes references to relevant standards and procedures to ensure compliance and quality control throughout the project.

Uploaded by

Yusuff Yuzuakk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views9 pages

Method Statement For Excavation and Backfilling

The document outlines the Method Statement for Excavation and Backfilling Works for the EIA Aviation Fuel Farm Rehabilitation project at Erbil Airport, detailing procedures, equipment, manpower, and safety measures. It specifies the responsibilities of various personnel involved, the scope of work including excavation, backfilling, and site preparation, and emphasizes adherence to safety and environmental standards. The document also includes references to relevant standards and procedures to ensure compliance and quality control throughout the project.

Uploaded by

Yusuff Yuzuakk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 9

Project EIA AVIATION FUEL FARM REHABILITATION

Client MACH MONUMENT AVIATION FUELLING CO


LTD (MMAFCO)

PMC
BILFINGER TEBODIN MIDDLE EAST LTD

EPC Main HAVATEK MAKINA SAN. VE TIC. A.Ş


Contractor

EPC Job No. BP-224-002

EPC Document Title Method Statement for Excavation and Backfilling Works

EPC Doc No. BP224002-CV-MST-00040 Rev.

1 13.07.2025 Issued for Const AF IK YY


0 15.03.2025 Issued for Const AN HM HD
C 11.03.2025 Issued for Approval AN HM HD
B 10.03.2025 Issued for Review AN HM HD
A 31.12.2024 Issued for Review AN HM HD
Page 1 / 9
Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 2/ 9

Rev. Date Description Prepared Checked Approved

TABLE OF CONTENTS
1. INTRODUCTION..............................................................................................................................................3
2. SCOPE................................................................................................................................................................3
3. DEFINITIONS AND ABBREVIATIONS.......................................................................................................4
4. REFERENCES...................................................................................................................................................4
5. EQUIPMENT.....................................................................................................................................................5
6. MANPOWER.....................................................................................................................................................5
7. RESPONSIBILITIES........................................................................................................................................5
9. CONSTRUCTION WORKS.............................................................................................................................7
9.1 SITE SURVEY WORKS...................................................................................................................................7
9.2 EXCAVATION WORKS..................................................................................................................................8
9.3 BACKFILLING WORKS.................................................................................................................................8
10. SAFETY, HEALTH AND ENVIRONMENTAL ISSUES.............................................................................9
11. ATTACHMENTS..............................................................................................................................................9
Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 3/ 9

1. INTRODUCTION

This Method of Statement outlines the procedures, resources, and quality control measures for the execution of
Excavation and Backfilling Works at the BP Fuel Farm and Unloading Station, Erbil Airport.

2. SCOPE

This scope covers all necessary activities related to earthworks, including excavation, backfilling, filling,
grading with granular material, and compaction for building foundations. All works shall be carried out in
accordance with the drawings and project specifications. All Safety measures and environmental
considerations – such as proper barricading, construction signs, lighting, and protective measures shall be
implemented within the working area. Only trained personnel with relevant experience shall be permitted to
operate the equipment.

The scope of work includes the following items:

 Stripping and preparation of areas beneath the fill and pavement layers to make them ready for
construction,
 Execution of project excavations,
 Filling for slope adjustment where necessary,
 General filling works
 Clay sub-base filling
 Construction of perimeter(belt) drainage channels
 Installation of external settlement benchmarks (reference points)
 All works to be executed as per standard specifications, technical datasheets, and Inspection and Test Plans
(ITPs).

3. DEFINITIONS AND ABBREVIATIONS

Project EIA Fuel Farm Rehabilitation Project


PMC Bilfinger Tebodin Middle East Ltd
Contractor Havatek Makina Sanayi ve Ticaret A.S.
Client Mach Monument Aviation Fueling Co. Ltd. on Behalf of Air BP
PPE Personal Protective Equipment
HSE Health, Safety and Environment
ASTM American Society for Testing and Materials
EIA Erbil International Airport
API American Petroleum Institute
ITP Inspection & Test Plan
PTW Permit To Work
Means all locations, where EPC CONTRACTOR performs any construction,
SITE
fabrication, materials handling, or similar WORK.
PL Packing List
Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 4/ 9

RA Risk Assesment
MS Method Statement
QA/QC Quality Assurance/Quality Control

4. REFERENCES

Number Subject

ASTM D2487 Classification of Soil for Engineering purpose

ASTM D 1557 Test methods for Laboratory Compaction of Soil Modified


Effort
ASTM D 1241 Specification for material for soil aggregate sub-base, base
& surface
ASTM D422 Standard test method for particle -size analyses of soils
ASTM C128 Relative density and absorption fine aggregate

ASTM C131 Standard Test Method for Resistance to Degradation of


Small-Size Coarse Aggregate by Abrasion and Impact in the
LA
ASTM C136 Standard Test Method for Sieve Analysis of Fine and Coarse
Aggregates
BP224002-QC-ITP-00350 Inspection and Test Plan (ITP) - Civil Works
BP224002-HS-PRO-00010 Permit to Work Procedure
BP224002-HS-PRO-00011 Personal Protective Equipment Procedure

5. EQUIPMENT

 Excavator
 Loader
Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 5/ 9

 Truck
 Grader
 Drilling Machine
 Roller
 Water Tanker

6. MANPOWER

 Civil Works Engineer


 Civil Works Foreman
 Surveyor
 Civil Works Helper
 Machinery Operators
 Drivers

7. RESPONSIBILITIES

Construction Manager, Site Engineer & Site Supervisor, QA/QC Engineer and HSE Supervisor are responsible
for the implementation of the Method Statement.

Construction Manager

 Oversee all activities to monitor compliance with Scope of work.


 Responsible for distribution updated work instructions, method of statement and drawings.
 Supports on implementation & promotion the Quality Management System.
 Review the project in-depth to schedule deliverables and estimate costs.
 Coordinate with workers and sub-contractors.
 Select tools, materials and equipment.
 Developing maintaining and improving the project schedule system.
 Review the work progress on daily basis.

Site Civil Engineer/Supervisor

 Implementing work at site as per the project drawings and specifications.


 Maintaining and improving the works at site in a safe manner.
 Ensuring the safe environment for the personnel at site.

QA/QC Engineer

 Supports on implementation Quality Management System at work site.


Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 6/ 9

 Oversee all activities to monitor compliance with scope of work and Inspection and Testing plan.
 Ensuring all audit findings on non-conformance are properly addressed.
 Supervising the Conformity and effectiveness of the quality system implemented.
 Coordinating with the client representative and third-party inspection agency.
 Prepare QA/QC reports and witness during testing / sample collection.
 Reporting to Construction Manager for QA/QC related matters.
 Monitoring and reporting the status of project progress.
 Participating in planning and throughout management of the project.
 Assistant construction managers to finish overall control on Project progress and costs.

Civil Surveyor

 Supports on implementation Quality Management System at work site.


 Responsible for survey as per drawing specifications.
 Responsible for making Bench Mark.
 Responsible during survey equipment handling and storing.
 Follow the instruction from Construction Manager and Site Engineer.
 Report to Site Engineer and Construction Manager.

Site HSE Supervisor

 The HSE Supervisor shall be responsible for overall HSE requirements, executes random verification of
the works at site, monitoring all applicable HSE requirements and implementing the HSE project
procedure requirements at site.

Foreman

 Foreman is responsible for all site activities ensuring that the work is carried out in a safe and efficient
manner in respect of this Method Statement and Risk Assessment. Foreman shall coordinate with
construction work to priorities and plans adhering to project safety and quality plan. Foreman shall but not
limited to produce work plan with responsible engineer, monitor the work, allocate general and daily
responsibilities, supervise and train the crew as required, guarantee all safety precautions and quality
standards are comply with project requirement, resolve the problems when arise, report on progress to
managers, engineers etc.

8. HSE REQUIREMENT
 Conduct awareness to all workers about the excavation operations which should be committed to avoid
accidents.
Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 7/ 9

 Inspect the excavation daily by a person with experience to ensure the safety of the excavation before
allow any body to enter the excavation area
 Report any signs of cracks in soil or any leakage of sand or water as well as any bulged at the sides of the
excavation
 Any excavation edges shall be sloped with an inclination depending by the nature of the ground in order to
prevent edges collapse
 If excavation is considered confined space, all the safe work instruction of confined space must be
followed.
 All excavations shall be provided with safe access/egress points
 Barriers and warning signs must be placed around the excavation area to prevent falling
 Ensure the availability of alternative roads for persons and vehicles before start the excavation operations.
 Ensure that all personnel employed on the job wear their PPE

9. CONSTRUCTION WORKS

9.1 Site Survey Works

Setting out the excavation setting out of the foundation and civil works, levels, formworks, installation of
embeds and fresh concrete levels in accordance with the approved drawings including, but not limited to any
other works may be required to execute the activities related to the scope of work as required under the
contract.
The execution of the surveying works will be performed by qualified surveyors.
The surveying devices i.e. total station, auto levels will be subjected to a regular basis calibration program
associated with the related calibration follow up sheet for each device working in site to ensure calibration
before the next calibration due date and this will be a direct responsibility to the quality control surveyor.
Verify the detail of excavation according to the latest construction drawing before the start of the work.
Drawing must be indicated inside PTW, in particular for Brownfield. In these areas before excavation
activities, UG utilities must be verified by scanning. Conduct a survey and mark the location and the limits of
the area to be excavated. Allowance should be provided to have enough working space between the foundation
to be constructed and the edge of the bottom of the excavation for the personnel and forms, bracing and
supports to be installed. In marking the excavation limits, consideration should also be given for additional
area to accommodate side slopes of the excavation.
Determine the depth of the excavation from the existing ground taking reference from a latest construction
drawing.
Coordinate with other disciplines involved to verify any existing service/utility lines such as water line, power
line and telephone line running through boundaries of excavation.
Scanning- to identify the presence of underground facilities prior mechanical or by hand excavation in the
project site.
Trial Digs and/or slit trenches to be performed as per project drawings, to verify the site existing underground
facilities.
Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 8/ 9

9.2 Excavation Works

 Set up barricade and signboards around the area to prevent unwanted personnel from the excavation site.

 Report immediately any unknown underground installation encountered during excavation. Stop work and
wait for further instructions

 After trial digs, Manual excavation shall be performed in the existing facility where existing utility lines or
facilities are encountered, to establish the exact location. The excavation shall be done manually and
carefully in order not to damage the utility lines or facilities.

 Where the excavation site is close to the existing structures, proper shoring and bracing system shall be
planned and approved by client and then built against the excavation wall to prevent any possible collapse
of the excavation slope and also damage to the structures. In case the excavation extends below the
foundation of existing adjacent structures the work will not proceed until well planned and proper
measures to protect that structure will be approved by client.

 Excavate up to the design level, width and length as required to conform to the latest construction drawing.
The vertical tolerance shall be as per specification.

 Once design bottom elevation is reached, levelling and compaction shall be done on ground by using an
appropriate machine such as 1 ton roller or plate compactors up to the required density to conform with the
Project Specification.

 Provide a monitoring crew during excavation equipped with a dumpy level to avoid unnecessary over
excavation.

9.3 Backfilling Works

 Before filling, the compacted area shall be inspected and approved. QC Inspector shall witness the
sampling of fill material to be conducted by an approved independent testing laboratory to determine the
maximum density value and optimum moisture content and test reports shall be submitted accordingly.
 Backfill areas to contours and elevations with approved materials.

Backfilling layer thickness will be max 200 mm and compaction test frequency will be as below:
Method Statement for Excavation and
Backfilling Works

Document No: Issue Date: 02.07.2025 Rev. No: Rev. Date: Sht No: 9/ 9

Note: Sub base material report will be issued later.

 Backfilling shall commence after the compaction of the natural ground, with the backfill material placed
layer by layer.
 Backfill material is to be compacted layer by layer in loose depth for full with of the cross section.
 Full survey control of each layer depth is required.
 Compaction of backfill material shall be facilitated by maintaining its moisture within +-3% of optimum
moisture content. Layers shall be compacted to at least 95 % of maximum modified proctor density as
determined by ASTM 1557 for cohesive soils
 Compaction areas shall be kept separate and no layer shall be covered by another until the proper density
 Compaction and testing activities shall continue until the final level is achieved.
 Structural fill shall be compacted to 70 % relative density for cohesive less soil or 95 % of the maximum
density as per ASTM D1557.
 The excavated areas and each layer of backfill shall be levelled by a grader and immediately checked by
the Subcontractor’s surveyor
 Ground shall be restored to its original contour as shown in the project drawing after the completion of
backfilling works. Final area to be cleaned of debris and other construction materials

10. SAFETY, HEALTH AND ENVIRONMENTAL ISSUES

 Permit to Works should be prepared and signed before commence of any work activities on site as agreed
with the company.
 Conditions and precautions listed in the project specifications shall be followed as a minimum.
 All staff involved in the project shall be inducted on the safety, health and environmental issues associated
with the work.
 Only trained personnel with relevant experience shall be allowed to handle machinery.
 All the activities will be envisaged a week in advance and job safety requirements will be worked out by
analyzing the likely hazards and resorting to preventive.
 Proper housekeeping at the end of the day is a part of the mandatory tasks assigned to workers to avoid
accidents due to littered tools and materials.

11. ATTACHMENTS

 Risk Assesment
 Scanning Report