ADD-2N1830 (On Hold) (MTA) Review/comment DU14 Advanced design for 7 7 0% 06-Jul-24 12-Jul-24 -163 (On Hold) (MTA) Review/comment DU14 Advanced design for temporary stair
temporary stair
ADD-2N1840 (On Hold) Prepare/submit DU14 Final design for temporary stair 25 25 0% 15-Jul-24 16-Aug-24 -115 (On Hold) Prepare/submit DU14 Final design for temporary stair
ADD-2N1850 (On Hold) (MTA) Review/comment DU14A Final design for temporary 7 7 0% 17-Aug-24 23-Aug-24 -163 (On Hold) (MTA) Review/comment DU14A Final design for temporary stair
stair
ADD-2N1860 (On Hold) Prepare/submit DU14 RFC 10 10 0% 26-Aug-24 09-Sep-24 -115 (On Hold) Prepare/submit DU14 RFC
ADD-2N1870 (On Hold) (MTA) Review and issue permit DU14 RFC 15 15 0% 10-Sep-24 30-Sep-24 -115 (On Hold) (MTA) Review and issue permit DU14 RFC
DU10 Permanent Replac
Replace-in-kind Stair Design
ADD-2N1900 (DOT) Review and approve Master Lease Drawings 20 1 20% 08-Nov-23 A 03-Jun-24 -29 (DOT) Review and approve Master Lease Drawings
ADD-2N1940 (MTA) Review/comment DU10 Advanced RIK Stair Design 7 7 0% 10-May-24 A 10-Jun-24 -42 (MTA) Review/comment DU10 Advanced RIK Stair Design
ADD-2N1950 Prepare/submit DU10 Final RIK Stair Design 20 1 0% 10-May-24 A 11-Jun-24 -29 Prepare/submit DU10 Final RIK Stair Design
ADD-2N1960 (MTA) Review/approve DU10 Final RIK Stair Design 14 14 0% 12-Jun-24 25-Jun-24 -42 (MTA) Review/approve DU10 Final RIK Stair Design
ADD-2N1970 Prepare/submit DU10 RFC RIK Stair Design 10 10 0% 26-Jun-24 10-Jul-24 -29 Prepare/submit DU10 RFC RIK Stair Design
ADD-2N1980 (MTA) Review/Approve DU10 RFC RIK Stair Design 15 15 0% 11-Jul-24 25-Jul-24 -42 (MTA) Review/Approve DU10 RFC RIK Stair Design
(DU11) State of Good Repair at
a 61st Woodside Station
AEC11900-R107 MTA provide direction on DU11B SOGR (Platform Girder SOGR 15 1 0% 30-Jun-23 A 03-Jun-24 -184 MTA provide direction on DU11B SOGR (Platform Girder SOGR Impact)
Impact)
ADD-2N1200 RFC (DU11B) - Prepare and submit (Platform Girder SOGR Impact) 10 10 0% 04-Jun-24 17-Jun-24 -184 RFC (DU11B) - Prepare and submit (Platform Girder SOGR Impact)
ADD-2N1210 (MTA) Review/approve RFC DU11B-C1/C2 Track (Platform Girder 15 15 0% 18-Jun-24 02-Jul-24 -265 (MTA) Review/approve RFC DU11B-C1/C2 Track (Platform Girder SOGR Impact)
SOGR Impact)
Temporary Works Design/Engineering
Design/Engine
Temporary Works' Design/Eng
Design/Engineering Prepared by Construction Team
Temp. Platforms at 33 Rawson
Raw St, 40 Lowery St, & 46 Bliss St. Stations
PRE10530 Prepare/submit temp. platform design/engineering 40 10 85% 28-Jul-23 A 14-Jun-24 -179 Prepare/submit temp. platform design/engineering
PRE10540 Review/approve temp. platform design/engineering 20 20 0% 17-Jun-24 15-Jul-24 -179 Review/approve temp. platform design/engineering
PRE10550 Prepare/submit shop dwgs for temp. platform design/engineering 20 20 0% 16-Jul-24 12-Aug-24 -179 Prepare/submit shop dwgs for temp. platform design/engineering
PRE10560 Review/approve shop dwgs for temp. platform design/engineering 20 20 0% 13-Aug-24 10-Sep-24 -179 Review/approve shop dwgs for temp. platform design/engineering
ADD1540 Material procurement - framing materials, behind cladding - 74th 60 30 50% 28-May-24 A 15-Jul-24 -139 Material procurement - framing materials, behind cladding - 74th Street SOGR issue
Street SOGR issue
Escalators Finishes-Rains
Finishes-Rainscreen
PRE25060 Prepare/submit shop dwgs/data-74th Station Roof/Rainscreen 30 30 0% 03-Jun-24 15-Jul-24 14 Prepare/submit shop dwgs/data-74th Station Roof/Rainscreen (Impacted by CO#006)
(Impacted by CO#006)
PRE16310 Review/approve shop dwgs/data - Trackworks (Impacted by CO#01) 20 1 85% 28-Feb-23 A 07-Jun-24 -162 Review/approve shop dwgs/data - Trackworks (Impacted by CO#01)
ADD1801 Install Track Drains - C1 Track 27 27 0% 18-Mar-25 23-Apr-25 -226 Install Track Drains - C1 Track
ADD1802 Install Track Drains - C2 Track 27 27 0% 02-Sep-25 08-Oct-25 -240 Install Track Drains - C2 Track
61 St Station - Bird Deterrent Systems
S
PRE26120 Vendor on board - 61 St Station - Bird Deterrent Systems 20 20 0% 03-Jun-24 28-Jun-24 -152 Vendor on board - 61 St Station - Bird Deterrent Systems
PRE26130 Prepare/submit shop dwgs/data - 61 St Station - Bird Deterrent 30 30 0% 01-Jul-24 12-Aug-24 -152 Prepare/submit shop dwgs/data - 61 St Station - Bird Deterrent Systems
Systems
PRE26110 Review/approve shop dwgs/data - 61 St Station - Bird Deterrent 15 15 0% 13-Aug-24 27-Aug-24 -219 Review/approve shop dwgs/data - 61 St Station - Bird Deterrent Systems
Systems
PRE26140 Material procurement - bird netting and spikes 60 60 0% 28-Aug-24 21-Nov-24 -154 Material procurement - bird netting and spikes
CBTC/Signal
PRE20872 Fabrication/purchase-CBTC (C1 Outage) 40 32 20% 14-Aug-23 A 17-Jul-24 -12 Fabrication/purchase-CBTC (C1 Outage)
PRE20874 Fabrication/purchase-CBTC (C2 Outage) 40 40 0% 18-Jul-24 12-Sep-24 65 Fabrication/purchase-CBTC (C2 Outage)
Architectural Finishes-Mezz Level
L Area
Procurement-Doors/Frame
Procurement-Doors/Frames/Hardware
ADD1330 Review/approve shop dwgs/data - doors, frames and hardware, incl 15 1 50% 26-Sep-23 A 01-Jun-24 211 Review/approve shop dwgs/data - doors, frames and hardware, incl hangers access panels
hangers access panels
ADD1350 Material procurement - doors, frames and hardware, incl hangers 40 40 0% 03-Jun-24 29-Jul-24 144 Material procurement - doors, frames and hardware, incl hangers access panels
access panels
Procurement-Expansion Joints
Jo & Storefront Angles
ADD1590 Prepare/submit shop dwgs/data 30 8 75% 01-Feb-24 A 12-Jun-24 134 Prepare/submit shop dwgs/data
ADD1580 Review/approve shop dwgs/data 15 15 0% 13-Jun-24 27-Jun-24 195 Review/approve shop dwgs/data
ADD1600 Procurement-Expansion Joints & Storefront Angles 40 40 0% 28-Jun-24 23-Aug-24 132 Procurement-Expansion Joints & Storefront Angles
Procurement-Cane Rail/Re
Rail/Rebar/Exp. Joint/Map Frames
ADD1370 Prepare/submit shop dwgs/data -Cane Rail/Rebar/Exp. Joint/Map 30 30 0% 03-Jun-24 15-Jul-24 90 Prepare/submit shop dwgs/data -Cane Rail/Rebar/Exp. Joint/Map Frames
Frames
ADD1360 Review/approve shop dwgs/data -Cane Rail/Rebar/Exp. Joint/Map 15 15 0% 16-Jul-24 30-Jul-24 128 Review/approve shop dwgs/data -Cane Rail/Rebar/Exp. Joint/Map Frames
Frames
ADD1380 Procurement-Cane Rail/Rebar/Exp. Joint/Map Frames 40 40 0% 31-Jul-24 25-Sep-24 88 Procurement-Cane Rail/Rebar/Exp. Joint/Map Frames
Procurement-Roll-up secur
security grille, top of street stairs
ADD1400 Prepare/submit shop dwgs/data - roll-up security grille, top of street 30 30 0% 03-Jun-24 15-Jul-24 133 Prepare/submit shop dwgs/data - roll-up security grille, top of street stairs
stairs
ADD1390 Review/approve shop dwgs/data - roll-up security grille, top of street 15 15 0% 16-Jul-24 30-Jul-24 195 Review/approve shop dwgs/data - roll-up security grille, top of street stairs
stairs
ADD1410 Material procurement - roll-up security grille, top of street stairs 40 40 0% 31-Jul-24 25-Sep-24 133 Material procurement - roll-up security grille, top of street stairs
Procurement-Door Glazing/
Glazing/Ceramic Tile/Gypsum Board
ADD1440 Procurement-Door Glazing/Ceramic Tile/Gypsum Board 40 40 0% 29-Mar-24 A 25-Sep-24 123 Procurement-Door Glazing/Ceramic Tile/Gypsum Board
ADD1430 Prepare/submit shop dwgs/data - Door Glazing/Ceramic Tile/Gypsum 30 30 0% 03-Jun-24 15-Jul-24 123 Prepare/submit shop dwgs/data - Door Glazing/Ceramic Tile/Gypsum Board
Board
ADD1420 Review/approve shop dwgs/data - Door Glazing/Ceramic Tile/Gypsum 15 15 0% 16-Jul-24 30-Jul-24 181 Review/approve shop dwgs/data - Door Glazing/Ceramic Tile/Gypsum Board
Board
Procurement-Plumbing System
Syste
ADD-N1140 Material procurement-Plumbing System 40 20 50% 25-Apr-24 A 28-Jun-24 -141 Material procurement-Plumbing System
ADD-N1580 Material procurement-61st Telephone & Intercome System 80 80 0% 01-Jul-24 23-Oct-24 -108 Material procurement-61st Telephone & Intercome System
Electrical-74st Street Station
Statio - Telephone and Intercom System
ADD-N1630 Material procurement-74th Telephone & Intercome System (Impacted 80 47 50% 16-Apr-24 A 07-Aug-24 -146 Material procurement-74th Telephone & Intercome System (Impacted by seperate MTA Contract)
by seperate MTA Contract)
Electrical-61st Station-Emergency
Station-Eme Alarm (EA) and Emergency Telephone (ET) Systems
ADD-N1650 Prepare/submit shop dwgs/data-61st station-EA & ET System 20 20 0% 03-Jun-24 28-Jun-24 -15 Prepare/submit shop dwgs/data-61st station-EA & ET System
ADD-N1660 Review/approve shop dwgs/data-61st station-EA & ET System 15 15 0% 29-Jun-24 13-Jul-24 -20 Review/approve shop dwgs/data-61st station-EA & ET System
ADD-N1670 Material procurement-61st station-EA & ET System 60 60 0% 15-Jul-24 07-Oct-24 -14 Material procurement-61st station-EA & ET System
Electrical-61st Street Station
Statio - CCTV System
ADD-N1690 Prepare/submit shop dwgs/data-61st station-CCTV System 20 4 80% 08-Nov-23 A 06-Jun-24 -90 Prepare/submit shop dwgs/data-61st station-CCTV System
ADD-N1700 Review/approve shop dwgs/data-61st station-CCTV System 15 15 50% 13-Nov-23 A 21-Jun-24 -128 Review/approve shop dwgs/data-61st station-CCTV System
ADD-N1710 Material procurement-61st station-CCTV System 80 80 0% 24-Jun-24 16-Oct-24 -90 Material procurement-61st station-CCTV System
Electrical-61st-PA & CIS Sy
System (Mezz. Level)
ADD-N1760 Material procurement-61st-PA & CIS System (Mezz. Level) 80 60 0% 20-Nov-23 A 26-Aug-24 -141 Material procurement-61st-PA & CIS System (Mezz. Level)
Electrical-61st-PA & CIS System
Sy (MB-Platform)
ADD-N1790 Review/approve shop dwgs/data-61st-PA & CIS System (MB Platform) 15 15 50% 16-Nov-23 A 29-Jun-24 -124 Review/approve shop dwgs/data-61st-PA & CIS System (MB Platform)
ADD-N1800 Prepare/submit shop dwgs/data-61st-PA & CIS System (MB Platform 20 10 50% 17-Nov-23 A 14-Jun-24 -88 Prepare/submit shop dwgs/data-61st-PA & CIS System (MB Platform)
ADD-N1810 Material procurement-61st-PA & CIS System (MB Platform) 80 80 0% 01-Jul-24 23-Oct-24 -88 Material procurement-61st-PA & CIS System (MB Platform)
Electrical-61st-PA & CIS Sy
System (FB-Platform)
ADD-N1840 Review/approve shop dwgs/data-61st-PA & CIS System (FB Platform) 15 15 50% 16-Nov-23 A 29-Jun-24 19 Review/approve shop dwgs/data-61st-PA & CIS System (FB Platform)
ADD-N1850 Prepare/submit shop dwgs/data-61st-PA & CIS System (FB Platform) 20 10 50% 17-Nov-23 A 14-Jun-24 13 Prepare/submit shop dwgs/data-61st-PA & CIS System (FB Platform)
ADD-N1860 Material procurement-61st-PA & CIS System (FB Platform) 80 80 0% 01-Jul-24 23-Oct-24 13 Material procurement-61st-PA & CIS System (FB Platform)
Electrical-61st-Fire Detecti
Detection & ALarm System
ADD-N1900 Prepare/submit shop dwgs/data-61st-Fire Detection & Alarm System 20 11 50% 12-Apr-23 A 17-Jun-24 -37 Prepare/submit shop dwgs/data-61st-Fire Detection & Alarm System
ADD-N1890 Review/approve shop dwgs/data-61st-Fire Detection & Alarm System 15 15 25% 13-Apr-23 A 02-Jul-24 -54 Review/approve shop dwgs/data-61st-Fire Detection & Alarm System
ADD-N1910 Material procurement-61st-Fire Detection & Alarm System 80 80 0% 03-Jul-24 25-Oct-24 -37 Material procurement-61st-Fire Detection & Alarm System
Electrical-61st- Advertising Concession (Outfront Media)
ADD-N1990 Prepare/submit shop dwgs/data-61st-Advertising Concession (Outfront 20 10 50% 07-Sep-23 A 14-Jun-24 -39 Prepare/submit shop dwgs/data-61st-Advertising Concession (Outfront Media) - Impacted - See SRJV Letter #86
Media) - Impacted - See SRJV Letter #86
ADD-N2000 Review/approve shop dwgs/data-61st-Advertising Concession 15 15 50% 21-Sep-23 A 29-Jun-24 -54 Review/approve shop dwgs/data-61st-Advertising Concession (Outfront Media) - Impacted - See SRJV Letter #86
(Outfront Media) - Impacted - See SRJV Letter #86
ADD-N2010 Material procurement-61st-Advertising Concession (Outfront Media) 30 30 0% 01-Jul-24 12-Aug-24 -38 Material procurement-61st-Advertising Concession (Outfront Media)
Electrical-61st-Escalator Monitoring
M System (Lift-Net) Power
ADD-N2040 Prepare/submit shop dwgs/data-61st-Escalator Monitoring Sys 20 20 0% 03-Jun-24 28-Jun-24 -129 Prepare/submit shop dwgs/data-61st-Escalator Monitoring Sys (Lift-Net) Power on hold by MTA -Impacted by SRJV letter #89
(Lift-Net) Power on hold by MTA -Impacted by SRJV letter #89
ADD-N2030 Review/approve shop dwgs/data-61st-Escalator Monitoring System 15 15 0% 29-Jun-24 13-Jul-24 -185 Review/approve shop dwgs/data-61st-Escalator Monitoring System (Lift-Net) Power - Impacted by SRJV letter #89
(Lift-Net) Power - Impacted by SRJV letter #89
ADD-N2050 Material procurement-61st-Escalator Monitoring System (Lift-Net) 100 100 0% 15-Jul-24 05-Dec-24 -128 Material procurement-61st-Escalator Monitoring System (Lift-Net) Power
Power
Electrical-74th-Escalator Monitoring
M System (Lift-Net) Power
ADD-N2270 Material procurement-61st-Operational Network System 80 80 0% 08-Jul-24 29-Oct-24 -101 Material procurement-61st-Operational Network System
Electrical-Instrumentation & Control
ADD-N2300 Material procurement-Instrumentation & Control 80 80 0% 03-Jun-24 24-Sep-24 -69 Material procurement-Instrumentation & Control
Architectural Finishes-Platform & Track Area
Procurement-Platform CIS Hangers
ADD1110 Prepare/submit shop dwgs/data-CIS Hangers 30 30 0% 03-Jun-24 15-Jul-24 -99 Prepare/submit shop dwgs/data-CIS Hangers
ADD1120 Review/approve shop dwgs/data-CIS Hangers 15 15 0% 16-Jul-24 30-Jul-24 -141 Review/approve shop dwgs/data-CIS Hangers
ADD1130 Fabrication/purchase-CIS Hangers 40 40 0% 31-Jul-24 25-Sep-24 -99 Fabrication/purchase-CIS Hangers
Procurement-Platform Win
Windscreen Panels
ADD1150 Review/approve shop dwgs/data - Platform Windscreen Panels 15 8 50% 22-Apr-24 A 08-Jun-24 -38 Review/approve shop dwgs/data - Platform Windscreen Panels
ADD1160 Fabrication/purchase-Platform Windscreen Panels 40 40 0% 10-Jun-24 05-Aug-24 -26 Fabrication/purchase-Platform Windscreen Panels
Procurement-Platform Map Signs
ADD1170 Prepare/submit shop dwgs/data - Platform Map Signs 30 30 0% 03-Jun-24 15-Jul-24 -62 Prepare/submit shop dwgs/data - Platform Map Signs
ADD1180 Review/approve shop dwgs/data - Platform Map Signs 15 15 0% 16-Jul-24 30-Jul-24 -90 Review/approve shop dwgs/data - Platform Map Signs
ADD1190 Fabrication/purchase-Platform Map Signs 40 40 0% 31-Jul-24 25-Sep-24 -62 Fabrication/purchase-Platform Map Signs
Procurement-Platform Topping
Topp Slab Rebar
ADD1220 Fabrication/purchase-Platform Topping Slab Rebar 40 40 0% 03-Jun-24 29-Jul-24 -30 Fabrication/purchase-Platform Topping Slab Rebar
Procurement-Platform dete
detectable warning panels & exp. joint covers
ADD1250 Fabrication/purchase-Platform detectable warning panels & exp. joint 40 40 0% 03-Jun-24 29-Jul-24 -150 Fabrication/purchase-Platform detectable warning panels & exp. joint covers
covers
Procurement-Platform furnishings
furn items
ADD1270 Review/approve shop dwgs/data - Platform furnishings items 15 1 80% 24-Oct-23 A 01-Jun-24 -221 Review/approve shop dwgs/data - Platform furnishings items
ADD1280 Fabrication/purchase-Platform furnishings items 40 38 5% 08-May-24 A 25-Jul-24 -151 Fabrication/purchase-Platform furnishings items
Procurement-Platform pick
picket railing/gates/rubbing board
ADD1570 Fabrication/purchase-Platform picket railing/gates/rubbing board 40 35 0% 11-Mar-24 A 22-Jul-24 -144 Fabrication/purchase-Platform picket railing/gates/rubbing board
O&M Manuals