METHOD STATEMENT FOR MSE WALL
PANEL
REPLACEMENT
BASE GENERAL CONTRACTING L.L.C. WORKS
INDEX
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
4.0 ABBREVIATIONS & DEFINITIONS
5.0 ROLES & RESPONSIBILITIES
6.0 ASSOCIATED REQUIREMENTS
7.0 PROCEDURE
8.0 RECORD
Method Statement for Road Base Work
BASE GENERAL CONTRACTING LLC
1.0 PURPOSE
The purpose of this method statement is to outline the procedures for safely and efficiently replacing
damaged in-situ MSE wall panels in compliance with project specifications and quality standards.
2.0 SCOPE
This method is applicable to all MSE wall panel replacement works under the project, including
demolition, reinforcement, formwork, concreting, and finishing.
3.0 REFERENCES
• Project Quality Plan
• Tender Specification – Volume 3
• Approved IFC Drawings
• Manufacturer's Technical Data Sheets
4.0 ABBREVIATIONS & DEFINITIONS
a) ABBREVIATIONS
• IFC: Issued for Construction
• PPE: Personal Protective Equipment
• SCC: Self-Compacting Concrete
• GRP: Glass Reinforced Plastic
b) DEFINITIONS
• Client: Project Owner or Authorized Representative
• Contractor: Base General Contracting LLC
• Project: The designated works covered under the scope of this method
• Shall/Should/May: As per contract terminology
5.0 ROLES & RESPONSIBILITIES
Responsibilities are as per standard roles outlined in the attached method statement template. Refer to:
Project Manager, Site Engineer, Office Civil Engineer, QA/QC Inspector, HSE Officer, etc.
Method Statement for Road Base Work
BASE GENERAL CONTRACTING LLC
6.0 ASSOCIATED REQUIREMENTS
a) HSE Requirements
• Area to be barricaded.
• PPE to be worn at all times.
• Use of calibrated tools and certified machinery.
• Weather conditions monitored (work prohibited during rain, fog, high wind, or extreme
temperatures).
• Permit to Work and Toolbox Talks to be conducted.
b) Materials, Tools, Equipment and Machineries
• Concrete (SCC or micro-concrete)
• Reinforcement steel
• HDPE bearing pads
• Chipping gun, grinder, chisel, vacuum/blower
• Concrete pump and mixer
• Wood, steel or GRP formwork
• Hand tools and curing compound
c) Manpower Resources
• Site Engineer
• Steel Fixers
• Shuttering Carpenters
• Concrete Workers
• Helpers
• Safety Helper
7.0 PROCEDURE
a. General
• Ensure the availability of the following documents at the work site:
• IFC Drawings
• Approved Material Submittals
Method Statement for Road Base Work
BASE GENERAL CONTRACTING LLC
• Approved Method Statement
b. Panel Demolition
• Carefully mark and remove the damaged panel without disturbing backfill.
▪ Provide propping if necessary.
▪ Clean and stabilize the exposed area with patching mortar.
c. Reinforcement Installation
• Cut and install steel as per design.
• Connect new rebars to existing tie-strips.
• Install HDPE bearing pads in place.
d. Formwork Installation
• Assemble formwork matching existing panel dimensions and textures.
• Properly seal and brace the formwork.
• Provide inlet chute for concrete pouring.
e. Concrete Placement
• Pump self-compacting concrete gradually.
• Monitor flow to avoid overfilling.
• Ensure complete void-free filling.
f. Curing and Formwork Removal
• Apply curing compound after concrete placement.
• Remove formwork after concrete achieves the specified strength.
• Clean up and prepare the surface for finishing.
g. Finishing and Inspection
• Match surface finish with existing panels.
• Remove any burrs or marks.
• Perform visual inspection and record quality observations.
Method Statement for Road Base Work
BASE GENERAL CONTRACTING LLC
8.0 RECORDS & DOCUMENTS
Request for Approval (RFA)
Site Inspection Reports
Concrete Delivery Tickets
Cube Test Reports
Reinforcement Inspection Checklists
Approved Drawings
END OF PROCEDURE