CPM Report Tridev

The project has a total duration of 17 days with a critical path consisting of activities A, D, F, and H. The detailed CPM calculations provide early start (ES), early finish (EF), late start (LS), late finish (LF), and total float for each activity. The Gantt chart illustrates the scheduling of activities over time.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
14 views3 pages

CPM Report Tridev

The project has a total duration of 17 days with a critical path consisting of activities A, D, F, and H. The detailed CPM calculations provide early start (ES), early finish (EF), late start (LS), late finish (LF), and total float for each activity. The Gantt chart illustrates the scheduling of activities over time.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Critical Path Method (CPM) Worked Example

Assumed Project Network with Forward/Backward Pass, Floats, and Gantt Schedule

Problem Statement:
A project consists of the following activities with durations (days) and precedence: A(4), B(3) start concurrently; C(2) after A;
D(5) after A; E(4) after B; F(6) after C and D; G(3) after D and E; H(2) after F and G. Determine ES, EF, LS, LF, total float for
each activity, identify the critical path, and the total project duration. Assume project start at time 0.

Summary:
Project Duration: 17 days
Critical Path: A D F H

Note: All computations follow standard CPM forward/backward pass.


Detailed CPM Calculations

Activity Duration Predecessors ES EF LS LF Total Float


A 4 - 0 4 0 4 0
B 3 - 0 3 5 8 5
E 4 B 3 7 8 12 5
C 2 A 4 6 7 9 3
D 5 A 4 9 4 9 0
F 6 C, D 9 15 9 15 0
G 3 D, E 9 12 12 15 3
H 2 F, G 15 17 15 17 0
Gantt Chart (Earliest Schedule)

D
Activities

0 2 4 6 8 10 12 14 16
Time (days)