NORTHERN RAILWAY
Office of the
Chief Administrative Officer,
USBRL Project,
Satyam Complex, Marble Market,
Jammu Tawi
No. 287-Sig/USBRUJAT/KRCU2021 (E-office file No. E-240425) Dated: 02.04.2025
TO WHOM IT MAY CONCERN
This is certify that M/s Konkan Railway Corporation Ltd. has been assigned the work of "Design and
construction of New B.G. Rail Link from Katra (excluding)- Laole (including) between Km 30 to Km
73.785 and Km 91 to Km 100.868 inclusive of planning, design and construction of the all service and
residential buildings, circulating area, parking platforms, Subways, Shelters and other allies structures
of all stations, including Electrical, Signal & Telecommunication works & any other works (required for
successful completion of project) vide Contract Agreement No. 74-W/16/60/WA/KQ dated 09.08.2005
on total cost plus 10% basis.
The present status of S&T works as under: -
Sr. Description of Present Progress up to 28.02.2025
Present Scope with KRCL
No. works
1 Signalling Works Design, supply, installation,
testing & commissioning of New
Stations comprising of
(i) MACLS
(ii) Electronic Interlocking
(iii) HA-SSDAC with UFSBI
(iv) Integrated Power Supply
system (IPS)
(v) Axle Counter Based TC
(a) Indoor Signalling 06 Stations %of Work
Station Remarks
Comoleted
Katra 100%
Reasi 100%
Bakkal 100%
Work Completed
Dugga 100%
Sawalkote 100%
Sangaldan 100%
(b) Outdoor OS: Stations %of Work
Station Remarks
Signalling Comoleted
Katra 100%
Reasi 100%
Bakkal 100%
Work Completed
Dugga 100%
Sawalkote 100%
Sangaldan 100%
4\J
...
~~-
2:-\~ti)A)1.~-
Chlef Signal & Telecomrr 1. E ngmeer
.
U.S B.RL Project,
Northern Railway, Jammu
Sr. Description of Present Progress up to 28.02.2025
No. Present Scope with KRCL
works
2 . Telecommunication Design, supply, installation,
Works testing & commissioning of IP
MPLS technology based
Telecommunication back bone
comprising of:
(i) STM-4 system on 24 fiber
OFC (LSZH) Network
(ii) 6 Quad Cable (LSZH)
communication
(iii) PA system at Stations, with
facility for centralized
Announcement
(iv) Integrated Passenger
Information System (IPIS)
(a) STM-4, Integrated 05 Stations %of Work
Pa-ssenger Station Remarks
Completed
Information Reasi 100%
System (I PIS) &
CClV system at Bakkal 100%
stations Dugga 100% Work Completed
Sawalkote 100%
Sangaldan 100%
(b) 6 Quad 65Kms Total Completed
Communication Length Length Remarks
(Km) (Km)
65 65 Work Completed
(c) OFC 65Kms Total Completed
Communication Length Length Remarks
(Km) (Km)
65 65 Work Completed
3 Integrated Tunnel Communication Works (ITCW) .
(a) VHF Total 5 Radio Sections Radio %of Work
Remarks
Communications consisting of 20 Tunnels with Section Completed
inside Tunnels total length of 91 Kms Katra- 95% Work in
Reasi progress
Reasi- 100%
Bakkal
Work Completed
Bakkal- 100%
Dugga
Dugga- 95% Work in
Sawalkote progress
Sawalkote- 95% Work in
Sangaldan progress
(b) Video Total 5 Block Sections Block % ofWork
Remarks
Surveillance consisting of 19 Tunnels with Section Completed
System (CClV) total length of 65 Kms Katra- 100%
inside Tunnels & Reasi
SCADA Reasi- 100%
Bakkal
Bakkal- 100% Work Completed
Dugga
Dugga- 100%
Sawalkote
Sangaldan 100%
- Sumber
tt~Q '~~
...t\~\~
Chref Signal & Telecomrr._ Engineer
U S.B.R.L Project,
Northern Railway, Jammu
Sr. Description of I .
No. works Present Scope w1th KRCL
··Status of S.& T works as on 28.02.2025:
I Present Progress up to 28.02.2025
All S&T works at Katra, Reasi, Bakkal, Dugga, Sawalkote & Sangaldan Stations and section are
completed. The lTC works are completed in all respect in Reasi-Bakkal, Bakkai-Dugga and Sangaldan-
Sumber (Upto Dharam) Block sections.
The progress of lTC works in balance three Block sections is (a) Katra- Reasi: 98% completed, (b)
Dugga- Sawalkote: 97% completed (c) Sawalkote- Sangaldan: 98% completed.
After C~S Authorization
(i) Sangaldan - Sumber section Commissioned on 20.02.2024
(ii) Sangaldan- Reasi section Commissioned on 27.06.2024
(iii) Katra- Reasi section Commissioned on 20.12.2024
Station wise commissioning dates:
Katra- 20.12.2024
Reasi - 27.06.2024
Bakkal- 27.06.2024
Dugga- 27.06.2024
Sawalkote- 27.06.2024
Sangaldan- 16.02.2024
FINANCIAL PROGRESS (S&T):
Sr. Year-wise payment made to KRCUS&T Amount (Rs. Cr.)
No.
1. 2021-22 20.77 (S&T Works*: 20.77, CCTV, PA, Emergency &
Service Telephone Works: NIL) incl. GST
2. 2022-23 225.76 (S&TWorks*: 149.34, CCTV, PA, Emergency &
Service Telephone Works: 76.42) incl. GST
3. 2023-24 184.26 (S&TWorks*: 126.49, CCTV, PA, Emergency &
Service Telephone Works: 57.77) incl. GST
4. 2024-25 (till Feb'25) 168.36 (S&T Works*: 65.93, CCTV, PA, Emergency &
Service Telephone Works: 102.43) incl. GST
*S&T Works mclude S•gnalhng, Telecom & VHF Works
Sr Against Contracts of Revised Payment % Payment Total
Contract Received Progress Received Payment
Value excl PVC Towards Received
(Rs. in crore) (Rs. in PVC (Rs. in incl. PVC
crore) crore) (Rs. in crore)
1 Signal & Telecommunication 226.78 212.23 93.58% 53.99 266.22
Work
2 VHF Communication Work 97.81 96.31 98.47% - 96.31
3 Integrated Tunnel 248.22 236.62 95.33% - 236.62
Communication Works
Total 572.81 545.16 95.17% 53.99 599.15
Performance of the PSU while executing the work has been satisfactory.
This certificate has been issued as per specific request of Konkan Railway Corporation Limited for tender
purpose only.
~., Q_~~
(Anil Kumar) oZ \
y \ ')...v }..- -
Chief Signalling & Telecommunication Engineer, . ~
USBRL Project, Jammu
Chief Signal & Telecomm. Engineer
No. 287-Sig/USBRUJAT/KRCU2021 (E-office file No. E-240425) U.S.B.R.L Project,
Date: 02-04-2025 Northern Railway. Jammu