Pipelines Installation
Pipelines Installation
SIZING
MATERIAL
PIPELINE DESIGN
WALL THICKNESS
DESIGN PRESSURE
PIPE SIZE
Calculate the head loss - When the fluid flow through the pipeline there is a resistance to the flow due to the friction force and the pressure is form cause the energy loss. Design flow rate Diameter of pipe is from 4 to 48 inches
Type of material common used are steel, ductile iron, reinforced concrete and fiberglass Mechanical resistance consideration
MATERIAL
Hoop stress Hoop stress must be less than the maximum allowable stress
WALL THICKNESS
Buried pressure pipe installation quite similar the design method for gravity pipe installations For internal pressure: Hydrostatic pressure and surge pressure For low pressure: - nominal diameter= 114-630mm - internal pressure= 545kpa or less High pressure: - nominal pressure= 21-710mm - internal pressure= 550-2170kpa
DESIGN PRESSURE
Cause by natural disaster, less maintenance or human error. To avoid this failure: - modern welded steel pipe with butt electric arc welded joints - Construct parallel pipelines in independent alignments
PIPELINE FAILURE
Balboa Neighborhood Burned by Exploding Gas Line in Northridge Earthquake (left); Fire ball that Burned the Neighborhood.
PIPELINES INSTALLATION
ON-shore Pipeline installation Offshore pipeline
On-Shore installation
Pre construction of pipelines
1) Acquisition/Requisition of Land
Acquisition- permanent use of land for pipeline activities Requisition- temporary use of land for pipeline activities
2) Submission of proposal
Acquire permission from government to access the land
On-Shore installation
Construction of pipelines 1) Cleaning the ROW(Rights Of Way)
ROW rights to make a way over a piece of land for pipeline construction. Heavy equipments are used to clean up the ROW
Bulldozer- to clean Excavator- used for the ROW trenching and pipe lifting
On-Shore installation
2) Stringing the Pipeline
the process of sorting the pipeline in a ROW so that the
pipeline can be welded together
Lift Boom are used to lift the pipe for welding process.
On-Shore installation
3) Bending and Welding
Welding machine is used to join the pipe together 3 or more layer of welding maybe necessary depends on the pipe thickness Bending machine is used to slightly bend the pipelines especially when the pipes encounter changes in route and topography.
On-Shore installation
On-Shore installation
On-Shore installation
6) Set On Weight
Once the pipeline lies on the land, weight is installed over
the pipeline to provide a secure fit of the pipe.
make it stable
On-Shore installation
Construction of pipelines
J-Lay Installation
This installation used tall tower instead of stringer to reduce tension or stress on the pipeline. Thus overcome problems with S-lay installation associated with the stress on the pipeline.