Sand Bailing Lesson
Sand Bailing Lesson
Lesson
Well CWD-1 (vertical well) has a sand problem,its interval perforation covered by sand that cause oil production decreased. We need to do sand recover until Total Depth so this well can produce oil back normally. Choose which best method if you are an engineer : A. Sand Bailing using Slickline unit B. Sand Bailing using Cavin Pump C. Sand Washing using Bit
*Consider : 1. Time efisiency (calculate) 2. Cost (calculate) 3. Can or cant damage Reservoir condition
Clue
Sand Bailing using Slickline Need : Slickline unit Sand recovered 1 time bailing = 0.01 bbl Estimate Run in Hole (RIH) Slickline string = 2 Hrs Estimate Pull out of Hole (POOH) Slickline string = 2 Hrs 1 x Bailing time = 0.5 Hour Sand Bailing using Cavin Pump Need : Caving Pump & Tubing Sand recovered 1 time bailing = 1 jts tubing 3.5, 9.3 ppf, N-80 Estimate Run in Hole(RIH) Cavin Pump String = 2.5 Hours Pull out of Hole (POOH) Cavin Pump string = 3.5 Hours 1 x Bailing time = 2.5 Hours
Sand Washing Need : KCl Brine, Drill Pipe, Bit Sand recovered 1 time washing = all sand recovered to Total Depth Estimate Run in Hole (RIH) DP string = 4 Hours Pull out of Hole (POOH) DP string =6 Hours 1 x Sand Washing time = 1.5 Hours
Well Data
Total Depth 1072 ft Interval perforation = 980 988 ft Top of Sand (TOS)= 975 ft Capacity vol Casing 7, 26 ppf, K-55 = 0.0383 bbl/ft High Permeability well (lost formation)
Csg 7,26 ppf,K-55
TOS = 975 ft
Others Information
Slickline Price = $1,083/day Rig Cost = $6,500/day KCl Price =$280 1 jts tubing = 30 ft Capacity Vol Tubing 3.5, 9.3 ppf, N-80 = 0.0087 bbl/ft Sand Bailing using slickline unit = Using slickline tools from Service company Sand Bailing using cavin Pump = Using tubing and Cavin pump Sand washing = Using Bit, Drill pipe, KCl (for washing sand/recover to surface)
Sand Washing
Sand recovered 1 time washing = all sand recovered to Total Depth Estimate Run in Hole (RIH) DP string = 4 Hours Pull out of Hole (POOH) DP string =6 Hours 1 x Sand Washing time = 1.5 Hours Answer= Target washing (ft) = TD- TOS = 1072 975 = 97 ft Target washing (bbl) = Capacity csg 7 x Target washing (ft) = 0.0383 bbl/ft x 97 ft = 3.7 bbl 1 ) Total Time Total washing time = (Target washing (bbl)/Sand recover 1 time washing bbl) x sand washing time Hrs = (3.7 bbl/ 3.7 bbl) x 1.5 Hrs = 1.5 Hrs or 0.06 day Total RIH & POOH = 4 hrs + 6 hrs = 10 Hrs or 0.42 day Total Time = Total washing time + total RIH & POOH string = 0.06 day + 0.42 day = 0.48 day or 1 day 2) Total bailing cost = KCl Price + (Rig Cost/day x Total bailing time) = $ 280 + ( $6,500/day x 0.0625 day) = $ 686 3) Effect to Reservoir condition = can cause damaged to reservoir condition