Production Organization Lecture 5: Project Risk and Change
Production Organization Lecture 5: Project Risk and Change
Dr. Manjula Nanayakkara (BSc.Eng, PhD) Department of Production Engineering University of Peradeniya Sri Lanka
Risk Management
Chances for risk event occurring are greatest in concept, planning and start up phases Cost and the impact is lesser if it starts earlier than the later Identifying the project risk events and deciding a response before the project begins is more prudent
Risk Identification
Generate a possible list of risks Team effort: Risk management team Risk breakdown structure (RBS) in conjunction with WBS Later these risks are analyzed and filtered out Event that produce consequence is important, not just focusing the objectives
Risk Assessment
Some risks identified may not deserve attention, can be ignored- redundant Stratifying only once needed to be addressed Scenario analysis- technique to analyze risks Significance of the risk is assessed in terms of
Probability of the event Impact of the event
Mitigating Risk
Reduce the likelihood that the event will occur
Mostly used- successful Less costly
Reduce the impact that the adverse event would have on the project
Avoiding Risk
Changing the project plan to eliminate the risk or condition Not all, bust some elements of risks can be avoided Eg: Adopting to proven technology rather than experimenting
Transferring Risk
Passing the risk to another party Associated with a premium Insurance Performance bonds Warranties Guarantees
Retaining Risk
Acceptance the risk, effects of some risks are large, not feasible to transfer or mitigate Generally changes for such occurrence is slim Risk is retained by adopting to a contingency plan if risk arises
Contingency Plan
An alternative plan that will be used in risk appears This plan presents actions if risks foreseen Plan answers all possible questions related to a possible risks Conditions to activate the contingency plan has to be clearly documented Risk response matrix is a good tool to for managing risks
Opportunity Management
What can be positive in a risk? Same process applies in managing Identified, assessed for the likelihood of the impact Responses are determined, contingency plans and funding is organized
Budget Reserves
Identified for specific work packages or segments These are found in WBS or Baseline curve Reserve amount is determined by costing out the accepted contingency recovery plan Communicated to the project team
Management Reserves
Funds are needed to cover major unforeseen risks and applied to the total project Established after budget reserves are identified and funds established Management reserved are independent of budget reserves Management reserves are often based on historical data and judgements
Time Buffers
Is a cushion against potential delays Amount and the time depends on the inherent uncertainty of the project More uncertain the project, more the time should be reserved To assign extra time to critical moments
Changes
Scope changes Changes in implementation and contingency plans Improvement changes