Job-Mix Formula (Sample)

The document provides a job-mix formula for an asphalt overlay project in Makati City, Philippines. It details the sources and proportions of materials used, including coarse aggregate from Montalban, fine aggregate from Porac, and mineral filler and asphalt cement from Shell Philippines. It also specifies blending proportions, grading requirements, temperature controls, asphalt content testing methods, and test results for properties like stability, unit weight, voids and VFA that meet specifications for heavy traffic conditions. The optimum asphalt content is determined to be 5.9% based on tests.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
25% found this document useful (4 votes)
5K views18 pages

Job-Mix Formula (Sample)

The document provides a job-mix formula for an asphalt overlay project in Makati City, Philippines. It details the sources and proportions of materials used, including coarse aggregate from Montalban, fine aggregate from Porac, and mineral filler and asphalt cement from Shell Philippines. It also specifies blending proportions, grading requirements, temperature controls, asphalt content testing methods, and test results for properties like stability, unit weight, voids and VFA that meet specifications for heavy traffic conditions. The optimum asphalt content is determined to be 5.9% based on tests.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 18

Job-mix Formula

Name of Project: Asphalt


Overlay project along JP Rizal
Makati City,km 292.7 to 592.5

I. Sources of Materials
A. Coarse aggregate- Montalban
Rizal
B. Fine aggregate- Porac,Pampangga
C. Mineral filler-Apo-portland cement
D. Asphalt Cement-60/70-Shell Phils.

II. Blending Proportion of


Aggregates.%
max. size of aggregate (CA)=63
3/8 max. size of aggregate (FA)=31
Mineral Filler (MF)=06

III.Grading of composite
aggregates
Aggregates

Sieve
size(Inch)

Grading C
Specifications
% Passing

Design
Grading %
Passing

Mass
retained
(grams)

CA

100

100

95-100

97

36

68-86

77

240

3/8

56-78

67

120

#4

38-60

49

216

#8
#16

27-47
18-37

37
28

144
108

#30

13-28

21

84

#50

9-20

15

72

#200

4-8

108

FA

MF

P-cement

72

IV.Specific Gravity of
Materials
Specific Gravity of
Aggregates(Combined)=2.72
Specific Gravity of
Asphalt=1.01

V. Temperature Controls
Temperature of aggregates 165 C
Temperature of Asphalt 110 C
Temperature of Mix 130 C
Compaction temperature 120 C

VI. Asphalt Content


% AC by weight of mix or Optimum Asphalt
Content (OAC)
@ Max. stability 6.0
@ Max. unit wt. 6.0
@ Ideal Air voids(4.0)- 5.7
% Optimum Asphalt Content (OAC)=
6.0+6.0+5.7
3
Say 5.9%

VII.Test on Properties of Mix based on AOC


using the graph(Graphical method)

1.
2.
3.
4.
5.
6.

Bulk, specific gravity= 2.499


Marshall stability,kg=1,275
Flow value,0.25mm=9.0
Air voids,%=3.45
Voids Filled with asphalt(VFA),%=75
Voids in mineral aggregates(VMA),
%=13.55

VIII.Analysis of Test Result


Tests

Test result

Specification
s (Heavy
Traffic)

Remarks

Stability,lb
s

2,805

1800 min

complied

Unit wt

2.499

Voids,%

3.45

3-5

complied

Flow,0.25
mm

9.0

8-14

complied

VFA,%

75.00

65-75

complied

VMA,%

13.55

13 min

complied

A. Bulk Specific gravity of


compacted mixture,Gmb
Formula: Gmb=

wt. of sample in air


Wt. of sample in SSD condition- wt. of sample in

water
Gmb@ 5 % AC= 1266 = 2.47
1267-754
Gmb@ 5.5 % AC= 1257 = 2.49
1262-758
Gmb@ 6 % AC= 1295 = 2.50
1297-779
Gmb@ 6.5 % AC= 1264 = 2.49
1265-758
Gmb@ 6.5 % AC= 1264 = 2.49
1265-758
Gmb@ 7 % AC= 1252 = 2.45
1262-750

B. Air voids in compacted


mixture,Va
Formula: Va=Gmm-Gmb x 100
Va@ 5.0%AC
Va@ 5.5%AC
Va@ 6.0%AC
Va@ 6.5%AC
Va@ 7.0%AC

Gmm
= 2.62-2.47
2.62
= 2.61-2.49
2.61
= 2.58-2.50
2.58
= 2.54-2.49
2.54
= 2.47-2.45
2.47

x 100 = 6.0
x 100 = 4.6
x 100 = 3.1
x 100 = 2.0
x 100 = 1.0

C. Voids in Mineral Aggregate,VMA


Formula: VMA=100- Gmb Ps
Gsb
VMA @ 5.0% AC=100 2.47(95) = 13.73
2.72
VMA @ 5.5% AC=100-2.49(94.5) = 13.49
2.72
VMA @ 6.0% AC=100-2.50(94) = 13.60
2.72
VMA @ 6.5% AC=100-2.49(93.5) = 14.41
2.72
VMA @ 7.0% AC=100-2.45(93) = 16.23
2.72

D. Voids Filled with Asphalt,VFA


Formula: VFA=100x VMA-Va
VMA
VFA @ 5.0% AC=100 x(13.73-6) = 56.30
13.73
VFA @ 5.5% AC=100 x(13.49-4.6) = 65.90
13.49
VFA @ 6.0% AC=100 x(13.60-3.1) = 77.20
13.60
VFA @ 6.5% AC=100 x(14.41-2.0) = 86.12
14.41
VFA @ 7.0% AC=100 x(16.23-1.0) = 93.84
16.23

E. For Optimum Asphalt


Content,OAC
1. Asphalt content at maximum stability-=6.0%
2. Asphalt Content at max. bulk sp.gr.---6.0%
3. Asphalt content@ 4% voids in the total mix--5.7%
_______________________________________
Optimum Asphalt Content, OAC = 5.9%

F. Jobmix formula,from the


graph:
1.
2.
3.
4.
5.
6.
7.

Optimum Asphalt Content,%-----=5.90


Max. stability,kg------------------=1275
Max. sp. Gr.(bulk)---------=2.49999
Air voids,%-----------------=3.45
Flow(0.25mm),%----------=9.0
VMA,%----------------------=13.55
VFA,%-----------------------=75

G. Max. Specific gravity of mixtures,Gmm

Formula No.1 (Theoretical Method)


Gmm= Pmm
Ps+ Pb
Gsb Gb

Where:
Pmm - percent by weight of total loose
mixture=100
Ps- aggregate content, percent by total
weight of mixture
Gsb- sp. Gr. Of aggregate
Pb- asphalt content,percent by total wt.
of mixture
Gb- sp.gr. Of asphalt

Formula no.2 (Actual)


Gmm= A - B
(A-B) + C-D
Where:
A- wt. of pot without lid + sample
B- wt. of pot without lid
C- wt. of pot with lid filled with water
D- wt. of pot with lid + water + sample