0% found this document useful (0 votes)
82 views50 pages

Developing A Project Plan

The document discusses developing a project network plan. It covers: 1) The key components of a project network plan including a flow chart that depicts activities, dependencies, and critical path. This provides the basis for scheduling, budgeting, and identifying critical activities. 2) How to construct a project network including defining activities, events, paths, critical path, and two approaches - activity-on-node and activity-on-arrow. 3) How to perform the forward and backward passes to calculate early/late start/finish times and determine slack on the critical path.

Uploaded by

say2shekhar3062
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
82 views50 pages

Developing A Project Plan

The document discusses developing a project network plan. It covers: 1) The key components of a project network plan including a flow chart that depicts activities, dependencies, and critical path. This provides the basis for scheduling, budgeting, and identifying critical activities. 2) How to construct a project network including defining activities, events, paths, critical path, and two approaches - activity-on-node and activity-on-arrow. 3) How to perform the forward and backward passes to calculate early/late start/finish times and determine slack on the critical path.

Uploaded by

say2shekhar3062
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 50

• Developing a Project Plan

Chapter 6
Developing
Developing the
the Project
Project Plan
Plan
• The Project Network
– A flow chart that graphically depicts the sequence,
interdependencies, and start and finish times of the
project job plan of activities that is the critical path
through the network.
• Provides the basis for scheduling labor and equipment.
• Enhances communication among project participants.
• Provides an estimate of the project’s duration.
• Provides a basis for budgeting cash flow.
• Identifies activities that are critical.
• Highlights activities that are “critical” and can not be delayed.
• Help managers get and stay on plan.
From
From Work
Work Package
Package to
to Network
Network
WBS/Work Packages to Network

FIGURE 6.1
From
From Work
Work Package
Package to
to Network
Network (cont’d)
(cont’d)
WBS/Work Packages to Network (cont’d)

FIGURE 6.1 (cont’d)


Constructing
Constructing aa Project
Project Network
Network
• Terminology
– Activity: an element of the A
project that requires time.
– Merge Activity: an activity that
has two or more preceding B D
activities on which it depends.
– Parallel (Concurrent) Activities:
C
Activities that can occur
independently and, if desired, not
at the same time.

McGraw-Hill/Irwin 6–
6–6
Constructing
Constructing aa Project
Project Network
Network (cont’d)
(cont’d)
• Terminology
– Path: a sequence of connected, dependent activities.
– Critical path: the longest path through the activity
network that allows for the completion of all project-
related activities; the shortest expected time in which
the entire project can be completed. Delays on the
critical path will delay completion of the entire project.

A B D

(Assumes that minimum of A + B > minimum of C in length of times to complete activities.)


Constructing
Constructing aa Project
Project Network
Network (cont’d)
(cont’d)
• Terminology
– Event: a point in time when an activity is started or
completed. It does not consume time.
– Burst Activity: an activity that has more than one
activity immediately following it (more than one
dependency arrow flowing from it).
B
• Two Approaches
– Activity-on-Node (AON)
• Uses a node to depict an activity. A C
– Activity-on-Arrow (AOA)
• Uses an arrow to depict an activity.
D
Basic
Basic Rules
Rules to
to Follow
Follow in
in Developing
Developing
Project
Project Networks
Networks
• Networks typically flow from left to right.
• An activity cannot begin until all of its activities are
complete.
• Arrows indicate precedence and flow and can cross over
each other.
• Identify each activity with a unique number; this number
must be greater than its predecessors.
• Looping is not allowed.
• Conditional statements are not allowed.
• Use common start and stop nodes.
Activity-on-Node
Activity-on-Node Fundamentals
Fundamentals

FIGURE 6.2
Activity-on-Node
Activity-on-Node Fundamentals
Fundamentals (cont’d)
(cont’d)

FIGURE 6.2 (cont’d)


Network
Network Information
Information

TABLE 6.1
Koll
Koll Business
Business Center
Center—Partial
—Partial Network
Network

FIGURE 6.3
Koll
Koll Business
Business Center
Center—Complete
—Complete Network
Network

FIGURE 6.4
Network
Network Computation
Computation Process
Process
• Forward Pass—Earliest Times
– How soon can the activity start? (early start—ES)
– How soon can the activity finish? (early finish—EF)
– How soon can the project finish? (expected time—ET)
• Backward Pass—Latest Times
– How late can the activity start? (late start—LS)
– How late can the activity finish? (late finish—LF)
– Which activities represent the critical path?
– How long can it be delayed? (slack or float—SL)
Network
Network Information
Information

TABLE 6.2
Activity-on-Node
Activity-on-Node Network
Network

FIGURE 6.5
Activity-on-Node
Activity-on-Node Network
Network Forward
Forward Pass
Pass

FIGURE 6.6
Forward
Forward Pass
Pass Computation
Computation
• Add activity times along each path in the
network (ES + Duration = EF).
• Carry the early finish (EF) to the next activity
where it becomes its early start (ES) unless…
• The next succeeding activity is a merge activity,
in which case the largest EF of all preceding
activities is selected.
Activity-on-Node
Activity-on-Node Network
Network Backward
Backward Pass
Pass

FIGURE 6.7
Backward
Backward Pass
Pass Computation
Computation
• Subtract activity times along each path in the
network (LF - Duration = LS).
• Carry the late start (LS) to the next activity
where it becomes its late finish (LF) unless
• The next succeeding activity is a burst activity, in
which case the smallest LF of all preceding
activities is selected.
Determining
Determining Slack
Slack (or
(or Float)
Float)
• Slack (or Float)
– The amount of time an activity can be delayed after
the start of a longer parallel activity or activities.
• Total slack
– The amount of time an activity can be delayed without
delaying the entire project.
• The critical path is the network path(s) that has
(have) the least slack in common.
Activity-on-Node
Activity-on-Node Network
Network with
with Slack
Slack

FIGURE 6.8
Practical
Practical Considerations
Considerations
• Network Logic Errors
• Activity Numbering
• Use of Computers to Develop Networks
• Calendar Dates
• Multiple Starts and Multiple Projects
Illogical
Illogical Loop
Loop

FIGURE 6.9
Air
Air Control
Control Project
Project

FIGURE 6.10
Air
Air Control
Control Project
Project (cont’d)
(cont’d)

FIGURE 6.11
Extended
Extended Network
Network Techniques
Techniques
to
to Come
Come Close
Close to
to Reality
Reality

• Laddering
– Activities are broken into segments so the following
activity can begin sooner and not delay the work.
• Lags
– The minimum amount of time a dependent activity
must be delayed to begin or end.
• Lengthy activities are broken down to reduce the delay in the
start of successor activities.
• Lags can be used to constrain finish-to-start, start-to-start,
finish-to-finish, start-to-finish, or combination relationships.
Example
Example ofof Laddering
Laddering Using
Using
Finish-to-Start
Finish-to-Start Relationship
Relationship

FIGURE 6.12
Use
Use of
of Lags
Lags

Finish-to-Start Relationship

FIGURE 6.13

Start-to-Start Relationship

FIGURE 6.14
Use
Use of
of Lags
Lags Cont’d
Cont’d

Use of Lags to Reduce Detail

FIGURE 6.15
New
NewProduct
ProductDevelopment
Development
Process
Process

FIGURE 6.16
Use
Use of
of Lags
Lags (cont’d)
(cont’d)

Finish-to-Finish
Relationship
FIGURE 6.17

Start-to-Finish
Relationship FIGURE 6.18

Combination
Relationship
FIGURE 6.19
Network
Network Using
Using Lags
Lags

FIGURE 6.20
Hammock
Hammock Activities
Activities
• Hammock Activity
– An activity that spans over a segment of a project.
– Duration of hammock activities is determined after the
network plan is drawn.
– Hammock activities are used to aggregate sections of
the project to facilitate getting the right amount of
detail for specific sections of a project.
Hammock
HammockActivity
Activity Example
Example

FIGURE 6.21
Key
Key Terms
Terms

Activity Gantt chart


Activity-on-arrow (AOA) Hammock activity
Activity-on-node (AON) Lag relationship
Burst activity Merge activity
Concurrent engineering Network sensitivity
Critical path Parallel activity
Early and late times Slack/float—total and free
Activity-on-Arrow
Activity-on-Arrow Network
Network Building
Building Blocks
Blocks

FIGURE A6.1
Activity-on-Arrow
Activity-on-Arrow Network
Network Fundamentals
Fundamentals

FIGURE A6.2
Activity-on-Arrow
Activity-on-Arrow Network
Network Fundamentals
Fundamentals

FIGURE A6.2 (cont’d)


Koll
Koll Center
Center Project:
Project: Network
Network Information
Information

TABLE A6.3
Partial
Partial Koll
Koll Business
Business Center
CenterAOA
AOANetwork
Network

FIGURE A6.3
Partial
PartialAOA
AOAKoll
Koll Network
Network

FIGURE A6.4
Partial
PartialAOA
AOAKoll
Koll Network
Network (cont’d)
(cont’d)

FIGURE A6.4 (cont’d)


Activity-on-Arrow
Activity-on-Arrow Network
Network

FIGURE A6.5
Activity-on-Arrow
Activity-on-Arrow Network
Network Forward
Forward Pass
Pass

FIGURE A6.6
Activity-on-Arrow
Activity-on-Arrow Network
Network Backward
Backward Pass
Pass

FIGURE A6.7
Activity-on-Arrow
Activity-on-Arrow Network
Network Backward
Backward Pass,
Pass,
Forward
Forward Pass,
Pass, and
and Slack
Slack

FIGURE A6.8
Air
Air Control
Control Inc.
Inc. Custom
Custom Order
Order Project
Project——
AOA
AOA Network
Network Diagram
Diagram

FIGURE A6.9
Comparison
Comparisonof
ofAON
AONand
andAOA
AOA
Methods
Methods

TABLE A6.2

You might also like