1. The document describes an order received by Electro Fans for 1,000 20-inch fans to be delivered in week 7. Each fan consists of 4 components: a housing assembly, two grills, a fan assembly, and an electrical unit. 2. The document provides a table with lead times, on-hand inventory, and scheduled receipts for each component. It asks to construct a product structure and time-phased product structure, and prepare a net material requirements plan. 3. The second document describes orders received by Karl Knapps over 10 weeks to be fabricated on one machine with 2,250 usable minutes per week. It asks to develop a capacity plan using lot splitting over the 10-
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (1 vote)
778 views11 pages

T06 - Kel - 7 - 14.13, 14.29

1. The document describes an order received by Electro Fans for 1,000 20-inch fans to be delivered in week 7. Each fan consists of 4 components: a housing assembly, two grills, a fan assembly, and an electrical unit. 2. The document provides a table with lead times, on-hand inventory, and scheduled receipts for each component. It asks to construct a product structure and time-phased product structure, and prepare a net material requirements plan. 3. The second document describes orders received by Karl Knapps over 10 weeks to be fabricated on one machine with 2,250 usable minutes per week. It asks to develop a capacity plan using lot splitting over the 10-
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 11

Group 7:

1. Muhammad Arifin Julian


ASSIGNMENT 6 2.
(1606879823)
Fachryal Hiltansyah (1606870521)
3. Rohmat Setiawan (1806244540)
PROBLEM Number 14.13
QUESTIONS
Electro Fans has just received an order for one thousand 20-inch fans due week 7. Each fan
consists of a housing assembly, two grills, a fan assembly, and an electrical unit. The housing
assembly consists of a frame, two supports, and a handle. The fan assembly consists of a hub
and five blades. The electrical unit consists of a motor, a switch, and a knob. The following
table gives lead times, on-hand inventory, and scheduled receipts.
a. Construct a product structure.
b. Construct a time-phased product structure.
c. Prepare a net material requirements plan.
SOLUTION Number 14.13
PROBLEM Number 14.29
QUESTIONS
Karl Knapps, Inc., has received the following orders:

The entire fabrication for these units is scheduled on one machine. There are 2,250 usable
minutes in a week, and each unit will take 65 minutes to complete. Develop a capacity plan,
using lot splitting, for the 10-week time period.
SOLUTION Number 14.29
Capacity Capacity Utilization: New
Week Order Size required avalaible over/(under) Production Planner's Action Production
(Minutes) (Minutes) (Minutes) Schedule
1 0 0 2250 (2250) 2250
split order : menggunakan 350 menit
2 40 2600 2250 350 2250
pada minggu ke 1
3 30 1950 2250 (300) 2250
split order : menggunakan 350 menit
4 40 2600 2250 350 2250
pada minggu ke 1
5 10 650 2250 (1600) 2250
split order : menggunakan 1550 menit
pada minggu ke 1, menggunakan 300
6 70 4550 2250 2300 menit pada minggu ke 3, 2250
menggunakan 450 menit pada minggu
ke 5
split order : menggunakan 350 menit
7 40 2600 2250 350 2250
pada minggu ke 5
8 10 650 2250 (1600) 1500
9 30 1950 2250 (300) 1950
split oder : menggunakan 800 menit
10 60 3900 2250 1650 pada minggu ke 5, menggunakan 850 2250
menit pada minggu ke 8