Well Foundation
Well Foundation
FOUNDATIONS
CONTENTS ÷
# Introduction
# Types of Well or Caissons
# Components of a Well Foundation
# Shapes of Wells
# Depth of a Well Foundation
# Forces Acting on Well Foundation
# Construction and Sinking of a Well
# INTRODUCTION
1.What is a Well or Caisson?
• Large size prismatic or cylindrical shells which
are built deep into the ground to support hea
vy loads.
2. What is a Well Foundation?
• Large hollow open-ended structure which is g
enerally built in parts and sunk through grou
nd or water to its final position, where it for
ms part of the permanent foundation.
• It is mentioned in the IS-3955:1967
.
What is Caisson?
# Uses of Well or Caisson Foundati
on
• Usually very suitable in deep sandy or soft soils.
• Specially for Boulder Stratum.
• Used to -
• Support and Transfer Heavy Loads (Vertical and Horizontal) and Moments
• Resist Uplift Forces
• Reduce Differential Settlement
• Support Heavy Structures including
• High Rise Buildings,
• Major Bridges on Rivers or Sea from Piers, Abutments of Bridges,
• Foundations of Heavy Machinery,
• Harbour Structures (Docks, Break Waters, etc.),
• High Tension Towers
• Shore Protection Works
• Foundations of Lighthouse, Pumphouse, etc.
# TYPES OF WELLS OR CAISSONS
1.Well Cap
2.Well Steining
3.Well Curb
4.Cutting Edge
5.Bottom plug
6.Top Plug
7.Filling (Sand)
# ALLOWABLE BEARING PRESSURE
# IS -3955:1967 Equation for
Allowable Bearing Pressure
Q=5.4(N^2)B+16(100+N^2)D
Where,
Q=allowable bearing pressure, kg/m^2
N=corrected value of std penetration resistance
B= smaller dimension of well section in metres
D=depth of foundation below scour level in m
# FORCES ACTING ON WELL FOUNDAT
ION
Vertical loads
•Self-weight of well
•Buoyancy
•Dead load of super structure, substructure
•Live load
•Kentledge during sinking operation
•Impact load due to live load only in the design
of pier cap and bridge seat on the abutment
# FORCES ACTING ON WELL FOUN
DATION
Horizontal loads
•Braking and tractive effort of moving vehicles
•Forces due to resistance of bearing
•Forces due to water current or waves
•Centrifugal force, if the bridge is situated on a curve
•Wind forces
•Seismic forces
•Earth pressure
•Other horizontal and uplift forces due to provision of transmis
sion line tower
•Temperature stresses
CONSTRUCTION
AND
SINKING OF A WELL
# CONSTRUCTION OF A WELL
1) Construction of caisson curb or well curb
•Well curb or caisson curb is built in case of a dry river bed, so a
s to place at the correct position after excavating the bed for a
bout 15cm for seating.
•If the depth of water is upto 5m, then sand island is constructe
d.
•For even distribution of load, wooden sleeps can be placed bel
ow cutting edge.
•When the shuttering of caisson curb is done, then reinforceme
nt for the curb is placed in position.
•Concreting of curb is done in one stroke and it should be done
without gap so as to obtain monolithic concreting structure.
# CONSTRUCTION OF A WELL
2) Construction of Caisson steining or well steni
ng:
•For a height of 1.5 m, the caisson steining is co
nstructed at a time when the caisson reaches a
t a depth of 6 m below ground steining can be r
aised with a height of 3 m at a time.
•Sinking of Caisson is commenced after concret
e is set for 24 hrs.
# SINKING PROCESS
• When the curb is cast, then sinking operation is started.
• The first stage of stening is ready after curing. In inner material if
comes as a obstruction can be excavated manually or mechanical
ly. If hard rock comes in the way, then blasting may be done.
• For proper sinking operation, additional loading termed as kentle
dge is used if required. Sand bags can be used as kentledge whic
h can be placed on a suitable platform on the top surface of caiss
on.
• When caisson reaches at a depth of 10 m, dewatering is done by
pumping. Jetting of water is also helpful in sinking operation. Pro
per care has been done by adopting the proper measures and tec
hniques so as to avoid shifts and tilts of caisson during sinking.
• Spade jham is used for excavation under water and rail chisel for
clay stratum(now,dredgers are used).
# Tilting and Shifting of Well or Cai
ssons
• At the time of sinking process well or caisson shoul
d sink exact vertically downward, straight and at th
e corner position without any tilting of well.
• If the well tilt any one side from its position while si
nking operation, then it is called as tilting of well.
• During sinking operation, it may also shift away fro
m the required position.
• Hence it is much essential to take the suitable preca
utions so as to avoid tilting and shifting of well.
# Precautions to be taken to Avoid
Tilts and Shift
• The cutting edge of well or caisson must be thick an
d sharp pointed.
• The external surface of steining and well or caisson
curb should be smooth.
• Dredging should be done uniformly on all sides and
in all pockets of well or caisson.
• Well or Caisson should be symmetrically placed.
• The diameter (D) of the curb must be placed from 4
0 mm to 80 mm or larger or more than external dia
meter of steining.
# Remedial Measures to Rectify Til
t and Shift
• Following are the remedial measures to be carefully implemente
d to avoid tilting and shifting of well or caisson during sinking pr
ocess:
1. Water jetting.
2. Eccentric loading or kentledge.
3. Excavation under Cutting Edge.
4. Regulation of excavation.
5. Providing Temporary Obstacles Below the Cutting Edge.
6. Pushing the Well with Jack.
7. Pulling the Well.
8. Strutting the Well.
1) Water Jetting
• Used to prevent tilting.
• In this method, water j
et is forcedly applied o
n tilt.
• Application of water je
tting on higher side red
uces skin friction. Thus,
the tilting is rectified.
• Not more effective but
gives the better result i
f used with the combin
ation of other methods
.
2) Eccentric Loading or Kentledge
• Well is normally given the ad
ditional loading called kentle
dge in order to have necessar
y sinking effort. In this metho
d, eccentric loading or kentle
dge is applied in higher side s
o as to have greater sinking e
ffort.
• For proper application of ecc
entric loading a platform wit
h projection on higher side ca
n be placed over the top of c
aisson
• The eccentric load is kept on
projected part of platform. T
hus tilt can be rectified.
3) Excavation under Cutting Edge
• During sinking process, fille
d well will not set or straig
hten due to unbroken stiff
strata on its higher side.
• In such situation, dewateri
ng is preferably done to lo
osen stiff strata. If dewater
ing is not possible or unsaf
e, then drivers are sent to l
oosen the stiff strata.
• Sometimes if possible and
safe, an open excavation is
done under the cutting edg
e.
4) Regulation of Excavation