IRICEN 24jan, Bharat Mala
IRICEN 24jan, Bharat Mala
2 2
NATIONAL
`` HIGHWAYS DEVELOPMENT
PROJECT (NHDP): Existing Programmes
Phase-I: 4 laning of Golden Quadrilateral (GQ) and parts of NS-EW Corridor and
other projects- Approved in December 2000.
Phase-V: 6 laning of 6500 kms of GQ and high density corridors – approved in Oct
2006.
3 3
Approval
`` sought in the NHDP CCEA Note of
November 2000
4
``
CCEA Decision of 2000
5
Triggers for Bharatmala
Border and International Connectivity to border areas & trade points with neighboring
Connectivity Roads countries(Nepal, Bhutan, Bangladesh, Myanmar)
2
Mapping of Shortest Route for 12,000
routes carrying 90% of the freight
3
Automated Technology-based automated traffic surveys
Traffic Surveys over 1,500+ points across the country
4
Satellite mapping of corridors to identify
upgradation requirements
10
1
Origin – Destination study conducted: e.g. Chennai
Top import Top export
districts: 44% 48% districts:
• Hyderabad Kolkata • Hyderabad
(NH 16)
• Pondicherry • Pondicherry
• Erode • Bangalore
• Bangalore • Vijayawada
• Bellary • Mumbai
Commodities moving from each district to all other 600 districts studied
1. Road Freight Projections for FY 25; Including freight originating in Bhopal and freight destined to Bhopal; 2. POL – Petroleum Oil & Lubricants 11
Source: RITES – Planning Commission OD Study
Shortest route identified for
2
Shortest route was identified for all Origin- Destination movement. 20% of them different
from fastest route
12
Objectives:
Overview of Logistics Efficiency Enhancement Program (LEEP)
Documentation
Logistics Procedural standardization
Freight time
Efficiency complexity
reduction
Enhancement reduction Electronic Toll
Collection deployment
3
Origin 1 Dest. 1 Evaluate the
route (NH1/SH1/
Origin 2 Dest. 2 Freight flow projections for other roads) for
FY 25 using GSDP growth top ODs
… …
projections and commodity contributing to
growth projections 80% of the
freight
X%NHDP1 Non
NHDP1
Other NH
roads
4
6 5 Freight flow model to identify
Identification of 43 new Economic Overlay IHMCL traffic
corridors and feeder routes survey data key stretches with high
contributing to 70% of the total freight
freight movement
Commodity and route study pan-India: @ Nagpur
Mumbai
20%
(NH 53) Raipur
Top import Top export
commodities: (NH 53) commodities:
27%
• Building materials Hyderabad • Cotton
• Cement & structures (NH 44) • Iron & Steel
• Provision & • Provision &
household goods household goods
• Iron & steel • Fruits & vegetables
• Fruits & vegetables • Coal
Key Commodities originating in Nagpur by Road
Key Commodities entering Nagpur by Road
Source: Planning Commission – RITES Total Transport System Study(2008) updated for FY15 and projected for
FY 25, A.T. Kearney Analysis
Advantage of commodity freight flow model over
traffic survey approach (Eg: Mumbai - Cochin)
Mumbai – Cochin: Preferred Route Mumbai – Cochin: Shortest Route
Source: Planning Commission – RITES Total Transport System Study(2008) updated for FY15 and projected for FY 25, A.T. Kearney Analysis
~51,000 km of road development needed to
cater to 70% of inter-district freight flows
Proposed corridors and feeder routes
(km) ~ 51,000
~15,060
~ 22,850
~13,060
Key Imperatives
• Corridor approach (vs ‘road’
approach) through a dedicated
agency to ensure
– Consistent 4 lane + infrastructure
– Allied infrastructure (Logistics
parks, way side amenities, city
bypasses, removal of blackspots,
etc.)
1. Based on IHMCL Traffic Surveys conducted this year
2. Indicates the current status of the road;
Source: Planning Commission – RITES Total Transport System Study(2008) updated for FY15 and projected for FY 25; MoRTH; NHAI, A.T. Kearney
B Economic corridors
Down laning1
Up laning1
Kharagpur
46
7 Kolkata
6
Baharagora
Amravati Durg Raipur 5 24
Bhilai Tileibani
Jalna 4 Karanja Nagpur 42
Khambale
42 4 2 24
• 20% length (~370
1 2 3
Sultanpur 2
Sonewadi
24
Mumbai km) under SH3
Down laning1
Up laning1
Kharagpur
46
7 Kolkata
6
Baharagora
Amravati Durg Raipur 5 24
Bhilai Tileibani
Jalna 4 Karanja Nagpur 42
Khambale
42 4 2 24
• 20% length (~370
1 2 3
Sultanpur 2
Sonewadi
24
Mumbai km) under SH3
1. Does not include feeder routes in North East Region – to be detailed out as part of separate North East Corridor
2. Based on IHMCL Traffic Surveys conducted this year
3. Indicates the current status of the road;
Source: Planning Commission – RITES Total Transport System Study(2008) updated for FY15 and projected for FY 25; MoRTH; NHAI, A.T. Kearney
Road development Initiatives - Summary
Economic corridors & Feeder routes – Overlap with existing programs
(km)
4 + Lane - Completed DPR Being Prepared
4 Lane - UI DPR Needs to be Prepared
4 Lane - BFA
2,416 37,913
10,222 382
1,659 251
363 1,395 5,610
893 112
25,276 7,570 12
11,329
3,965
3,450
10,853 2,505
3,437 15,020
1,230
5,791
NH SH Others Total
Upgradation needed for 15,000 km; DPRs initiated for 9,000 km by NHAI in
Phase I
Source: Inputs from MoRTH and NHAI RO, State PWD; A.T. Kearney Analysis
Actions initiated by NHAI on corridor
development
# Activity Details
Intervention • Need for road upgradation finalized based on the existing status of road
3
finalization infrastructure and the proposed programs on the corridor network
70 70
9
34 5 3
4
24
45 63
10
20
24 25
52
11
13
Ring Road3 Bypass Lane Expansion Stand Alone Others Intervention to Total
Structure be Planned3
• 24,800 km will be taken up in the first phase. The exact projects to be taken up
for upgradation in Phase I will be based on DPRs
• DPRs already initiated for 16,000+ km and 5,000 km will be completed by
November, 2017
Proposal for Bharatmala Phase I
(award by 2020 and construction by 2022)
Funding
Length -
Components requirement -
km
Rs crores
Economic corridors 9,000 1,20,000
Inter-corridor & feeder roads 6,000 80,000
National Corridors Efficiency Improvements 5,000 100,000
Shri R.C. Sinha (former MD, MSRDC & DG, NICMAR) and Shri
Deepak Dasgupta (former Chairman, NHAI) Committee Report
mentions the following:
Mode of
SFC/EFC/PIB/
delivery,
2-3 MoRTH
PPPAC
months
Cost Committee,
IFD, MoRTH
MoRTH
Timeline for start of civil work for NH projects
Time saving in
Time Cumulative
case powers
Sl.No. Activity period time
delegated to
(Months) (Months)
NHAI
1 Decision to take up a project 0 0 -
2 Proposal invitation for DPR consultancy 1 1 -
3 Proposal submission for DPR Consultancy 1.5 2.5 -
4 Evaluation/Award/start
4 months savings of DPRinpreparation 1.5 4 -
5 Preparation
case ofand submission/finalization
successful bid of DPR 8 12 -
6 Pre-construction activities (land acquisition, utility shifting,
in first attempt 4 16
environmental clearance etc.) -
7 a.) Proposal examination in MoRTH 0.5
b.) SFC meeting, (including SFC minutes) 0.5
20 4 months
c.) SFC/PPPAC approval 1.5
d.) Approval by competent Autority/CCEA 1.5
8 Bid invitation for civil works and submission of bids - in
0 20
parallel to appraisal/approval process -
9 Bid evaluation and award of civil work 1 21 -
10 a.) Appointed date for BOT/Hybrid Annuity projects 6 27
b.) In case of EPC projects 1 22 -
11 In case bids are not received on BOT mode/ bids are not
1 22 1 month
reasonable - change of mode to9Hybridmonths savings in
Annuity/EPC
12 Modification of proposal in linecase
with Hybrid
mode Annuity/EPC
changemode and 1 23 -
13 The steps from Sl.No.7 to Sl.No.10 are followed again.
second round bid is 4 months
a.) For Hybrid Annuity 11 34
required
b) For EPC 8 29
Appraisal and Approval of Projects
All PPP Projects [ BOT(Annuity), Hybrid Annuity] project upto 2000 Cr.(
TPC excluding Land Cost) , will be appraised by the SFC chaired by
Secretary (RT&H) and approved by the Minister (RT&H).
PPP Projects costing more than Rs. 2,000 crore (excluding land price)
will be appraised by the SFC chaired by Secretary DEA and approved by
CCEA.
All PPP which need VGF will continue to be appraised as before by DEA
Appraisal and Approval of Projects
Project Appraisal and Technical Scrutiny Committee within NHAI
Member ( Technical), Tech Advisor(Retd. Expert), CGM(Fin),NITI
Maximum of 2 stretches not exceeding 100 kms will be allowed per State/ FY.
State will have to select roads out of the final list of the roads included in the
Bharatmala proposal – to indicate preference in April each year.
MoRTH will send a preliminary confirmation to the State and proceed to finalize
the alignment and prepare the DPR.
If the State helps to acquire 50% of land by the time DPR is ready, projects will
be put on fast track. MoRTH will send secondary confirmation to State.
From such projects, cases where the State helps to acquire additional 30% of
land by the time of bidding of the projects shall be bid out.
Expeditious project implementation –
adoption of ‘Grand Challenge’ - 3
From such successful bids, projects will be awarded where 90% land has already
been acquired at the time of award of the project.
If within a State, there are competing project proposals satisfying the above
requirements, then those that are connecting Ports/Industrial or commercial
hubs/other economically/strategically important locations will be taken up first.
05. FINANCING PLAN
SOURCES OF FUNDS
Amount in Rs. Crores
Additional Budgetary
Support (b) 2029 850 600 470 1140 1993
Capital Gain
Tax
Exemption
Bonds 2902 2942 3343 4281 4279 4000
Tax
Free/Taxable/
Others Infra
Debt Bonds -- 5000 -- 19000 55000 60500
64500
Total Debt (c) 2902 7942 3343 23281 59279
Total Funds
received/required by
NHAI (a+b+c) 23713 28149 25146 48343 86072 95027
APPLICATION OF FUNDS
Amount in Rs. Crores
* Projected Figures
Public and Private Investment in National
Highways
Financial
2012-13 2013-14 2014-15 2015-16* 2016-17* 2017-18*
year
Public expenditure:
29900
Private 19887 21155 17293 27350
(29%)
35500 ~70%
Expenditure (53%) (51%) (42%) (40%) (18%)
Private: expenditure
~60%
37264.79 41756.31 41083 68438 102039 126674
Total
(100%) (100%) (100%) (100%) (100%) (100%)
• With the increase in the total number of projects awarded, expenditure on Land Acquisition is
expected to increase
• Bharat Mala and BRT are not included in the projections
Bharat Mala (3543 km) and BRT (4705 km)
Projects: Projections ( 8248 Km)
Amount in Rs. Crores In km
Grant on Hybrid
Annuity Projects
(40% of TPC)
576 1880 2607
(20:40:40) Bharat Mala
1200 1400
Projects/Hybrid
Annuity on Hybrid
Projects (4% of
TPC + Interest NA NA NA
@10.5% p.a on
Balance amount)
Total 3600 4400
Total 14706 37173 30409
Increasing Repayment Liabilities of NHAI
With Cess @ Rs 2000 Cr.
RITES
Freight Flow
1 Origin –
Model
Destination Study1
Origin 1 Dest. 1
3 Evaluate the
Origin 2 Dest. 2 Freight flow projections for route (NH1/SH1/
FY 25 using GSDP growth other roads) for
… …
projections and commodity the top 3,600 O-D
growth projections routes
X%NHDP1 Non
NHDP1
Other NH
roads
4
6 5 Freight flow model to identify
Identification of 44 new Economic Overlay IHMCL traffic key stretches with high
corridors and feeder routes survey data (where freight
available)
1. O-D: Origin Destination; NH – National Highways; SH – State
Highways; NHDP – National Highways Development Project
Illustrative : Route Mapping Process
End Point
Origin Dest. Road # Start Point (SP) Latitude Longitude Latitude Longitude Distance
(EP)
Ballari Chennai NH 67 Ballari 15.12394 76.905336 Gooty 15.116758 77.633271
85.7
Ballari Chennai AP SH 57 Gooty 15.116758 77.633271 Rayalacheru 15.051205 77.82271
vu 23.7
…
Ballari Chennai NH 16 Janappanchatra 13.262802 80.155314 Chennai 13.145154 80.219919
m 15.8
Ballari Chennai Chennai - - Chennai 13.145154 80.219919 Chennai 13.117808 80.262281
Renigunta 6.0
Hwy
Illustrative : Identification of Lane status
through satellite imagery by BISAG
Kolkata
Baharagora
Amravati Durg Raipur 24
Bhilai Tileibani
Jalna Karanja Nagpur 42
Khambale
42 42 24
Sultanpur2
Sonewadi
24
Mumbai
109 Jorhat-Neamati 10
115 Naltoli-Silghat 4
Total 9,481
National Corridors
S No Stretch Length (km)
Total 13,053
Border Roads (1/2)
S No State Project Length (km)
Munnabao - Sundra - Lunar - Dhanna - Bhuvana - Nawatala - Shahgarh -
1 Rajasthan 323
Asutar - Ghotan – Tanot
2 Rajasthan Jaisalmer - Bhadasor - Ramgarh – Tanot 125
3 Rajasthan Kishangarh - Bhutewala - Sarjam Tala - Dadoorewala – Bharewala 128
4 Rajasthan Gagaria - Baonkalam - Serwa - Satta – Gandhav 190
5 Rajasthan Jaisalmer – Myalijar 99
6 Rajasthan Jhaighat - Nedai Phata 49
Poogal - Dantor - Jaggasar - Tawarwala - Gokul - Godu - Rajatpura -
7 Rajasthan 185
Charanwala - Naukh – Bap
Khema Kara (Indo - Pak Border) - Bhikhiwind - Chabal Kalan - Amritsar -
8 Punjab 162
Ajnala - Ramdas - Dera Baba Nanak – Gurudaspur
9 Punjab Fazilka - Jalalabad - Mamdot – Firozpur 85
Askot - Dharchula - Tawaghat - Sirkha - Malpa - Garbyang - Lipu Lekh
10 Uttarakhand 80
Pass
Simli - Narayanbagar - Kulsari Talwari - Gwaldan - Dangoli - Baijnath -
11 Uttarakhand Bageshwar - Balighat - Kapjot - Sama - Quiti - Birthi - Girgaon - Ratapani - 306
Munsiyari - Darkot - Madkot - Sheraghat - Mawani – Jolljivi
12 Uttarakhand Bhaironghati - Nelang - Naga - Angar - PDA – Medikay 70
13 Uttarakhand Mana - Mussapani - Gastoli - Rattakana – Manapass 63
Border Roads (2/2)
S No State Project Length (km)
16 Uttar Pradesh Naugarh - Geinsari - Tulsipur – Jarwa 72
17 Bihar Chakia – Bairgania 50
3 Delhi-Meerut Expressway 96
4 Kanpur – Lucknow 75
Total 1,837