Prefaricated Structures Unit I
Prefaricated Structures Unit I
UNIT I INTRODUCTION 9
Need for prefabrication – Principles – Materials – Modular coordination – Standarization –
Systems – Production – Transportation – Erection.
UNIT II PREFABRICATED COMPONENTS 9
Behaviour of structural components – Large panel constructions – Construction of roof and floor
slabs – Wall panels – Columns – Shear walls
UNIT III DESIGN PRINCIPLES 9
Disuniting of structures- Design of cross section based on efficiency of material used –
Problems in design because of joint flexibility – Allowance for joint deformation.
UNIT IV JOINT IN STRUCTURAL MEMBERS 9
Joints for different structural connections – Dimensions and detailing – Design of expansion
Joints
UNIT V DESIGN FOR ABNORMAL LOADS 9
Progressive collapse – Code provisions – Equivalent design loads for considering abnormal
effects such as earthquakes, cyclones, etc., - Importance of avoidance of progressive collapse.
TOTAL: 45 PERIODS
PREFABRICATED STRUCTURES
UNIT I
INTRODUCTION
DEFINITION
Prefabrication is the practice of assembling
components of a structure in a factory or other
manufacturing site, and transporting complete
assemblies or sub-assemblies to
the construction site where the structure is to be
located.
It is combination of good design with modern high
performance components and quality controlled
manufacturing procedures.
This work is carried out in two stages,
manufacturing of components in a place other than
final location and their erection in position.
• "Prefabricated building is a type of building that
consists of several factory-built components or
units that are assembled on-site to complete the
unit. “Prefabricated” are built in:
Components (panels)
Modules (modular homes)
Transportable sections (manufactured homes)
Mobile homes (houses on wheels)
NEED FOR PREFABRICATION
• For sites which are not suitable for normal construction
(Hilly region)
• Repeated structures (Mass housing)
• Increased Speed
• Areas in which lack of space prevails
• Proper utilization of space
• Quality
• Control over material
• Mass production of materials
• Safety
• Sustainability
• Cost – saving in manpower and material
• Time for change
ADVANTAGES
• Saving in cost, material, time & manpower.
iii)Frame System
- Components are usually linear elements.
- The beams are seated on the corbels of pillars usually
with hinged joints. (rigid connection is also carried out).
- Joints are filled with concrete at site.
iv)Lift Slab System
- Partially prefabricated in plant (pillars) and partially
precasted on site (slabs).
- It consists of one or more high pillars (max 5).
- Up to 30 storey high construction is possible.
- Consists of specially designed joints and temporary
joints.
- Slabs are casted on the ground (one on top of another)
and then lifted with cranes and elevators.
Lift-Slab Procedure:
i)Pillars and first package of slabs (Eg: 5 pieces) are
prepared at the ground level.
ii)Lifting boxes are mounted on the pillars and a single slab
is lifted to first floor level.
iii)Other boxes are sequentially raised to higher position to
enable the slabs to be lifted to their required final
position. Slabs are held in relative position (temporary)
by pinning system.
v)Box Type System
- In this system room size units are prefabricated and
erected at site.
- Toilet and Kitchen blocks could also be similarly
prefabricated and erected at site.
- This system derives its stability and stiffness from the
box units which are formed by four adjacent walls
which are joined to make rigid connection.
PRODUCTION OF PREFABRICATES
• Stand System
• Conveyor belt or production line system
• Aggregate system
Tilting Table
Battery Mould
TRANSPORTATION
• Transportation means taking the prefabricates in a
vehicle of wagon or truck from the prefabrication
industry to the place of site work for erection.
• In addition to railway wagons, special transporters are
used to carry the prefabricated units from the factory to
the building site.
• These are designed to suit the prefabricate dimensions
and weight and convenient method of loading.
• In some places, the lorries are used to transport large
prefabricates which are equipped or having power
operated unloading derricks.(cranes or lifting
mechanism)
• The following points should be considered for
transporting the prefabricates
i) It must be carried out with extreme care to avoid any
jerk and distress in elements and handled
/transported in the same orientation as it is to be
placed in final position.
ii) It should be properly planned and conformity with
traffic rules and regulation.
iii) The size of element decide the mode and size of
transport vehicle.
iv) Check the load carrying capacity of the bridges.
vi) Avoid excessive cantilever projection while transport.
vii) Special care should be taken while moving in curves
and uneven roads which may lead to undesirable
stresses.
viii) Before loading, proper base packing materials, proper
location and packing must be done one over the other.
Delivery:
i) Delivery of prefabricate elements should be planned
according to the general erection sequence to
minimize unnecessary site storage and handling.
ii) Prefabricate elements should be loaded and delivered with
proper supports and frames. Cushioning and tie-downs to
prevent damage during transports.
iii) Adequate packing or protection to the edges of
prefabricate elements should also be provided to minimize
the risk of damage during transport.
Handling:
i) Lifting and handling position shall be clearly defined
particularly if sections are critical.
ii) It mainly involves the removal of prefabricate elements
from mould, transportation to the storage yard and
unloading operation and erection of these element at the
job site.
iii) Prefabricate elements are demoulded and transported
to the site only when concrete reach required strength.
iv) But these elements haven’t got full design strength and
prone to damage during handling.
v) So it has to be carefully handled to avoid excessive
stress during handling.
ERECTION
• Erection of building means keeping of prefabricated
products in proper and correct position at the site.
• Before doing the erection the setting out should be
done and carefully checked with survey instruments.
• While erection the working of the crane and the correct
layout of the crane must be checked.
• Uneveness of the ground, makes it difficult to lay a
horizontal crane truck.
• When there is steep slope, high embankment is
required and this is costly and technically difficult.
• Prefabricated buildings are erected in convenient
sections.
• Sections should be correctly fixed and should be rigid in
all directions.
• The normal sequences of erections are
i)Structural wall units.
ii)Non-structural wall units (partition).
iii)Floor panels, balconies, staircase units.
iv)Specialized pre-fabricates( chimneys, ventilation
ducts, sanitary installations).
• The materials required for construction are also lifted by
crane and stacked on the floor at the place of work.
• In large panel buildings, where two external and one
internal wall panels meet at common joint, the external
panels are erected first and the joint between them is
sealed or covered and then the internal wall panel is
placed.
ERECTION PREPARATION:
i)Check the crane access to site and erection platform to
prevent cranes or trucks damaging the concrete floors
during access.
ii)Obtain verification that the erection platform can
support the erection loads.
iii) Ensure the locating dowels and levelling shims are
correctly located.
iv)Clear the site for truck.
v)Ensure sufficient space is available for precast propping
or panel bracing.
vi)Builder must ensure that adequate temporary base
restraint is provided for any prefabricate element to
prevent sliding failure at the base.
vii)Check lifting inserts are in their correct location and
recesses are cleaned in preparation for lifting.
Types of Cranes
1)Stationary Cranes
a)Guyed derrick crane
b)Climbing crane
c)Tower crane with fixed base
2)Cranes on rails
a)Portal crane
b)Tower cranes
3)Mobile crane moving on ground
a)Truck mounted
b)Crawler mounted
a)Guyed derrick crane
• Used on framed buildings for erection of floor panel,
columns and slab strips.
Guyed Derrick Crane
Climbing Crane
Tower Crane
Portal Cranes
Tower Cranes on rail
Truck Mounted Crane
Crawler Mounted Crane