Weekly Report - No#6.... (Sample)

The weekly report provides the following information: 1) Project progress is at 16.1% of total duration and 83.9% of the work remains. Actual progress this week was 3.47% compared to the planned progress of 2.32%. 2) Construction progress is ahead of plan overall with actual progress of 3.88% versus planned progress of 2.28%. 3) Manpower levels averaged 115 people against a plan of 87 people and equipment levels averaged 14 pieces against a plan of 12 pieces.

Uploaded by

Hesham Hassan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
106 views10 pages

Weekly Report - No#6.... (Sample)

The weekly report provides the following information: 1) Project progress is at 16.1% of total duration and 83.9% of the work remains. Actual progress this week was 3.47% compared to the planned progress of 2.32%. 2) Construction progress is ahead of plan overall with actual progress of 3.88% versus planned progress of 2.28%. 3) Manpower levels averaged 115 people against a plan of 87 people and equipment levels averaged 14 pieces against a plan of 12 pieces.

Uploaded by

Hesham Hassan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 10

WEEKLY REPORT

1
Progress Summary up to 4-May-17
Start Date 5-Feb-17 Contract Dates
5-Aug-18
Data Date 4-May-17 5-Feb-17
0 100 200 300 400 500 600
Elapsed Duration Contract Project Duration
Start Date 5-Feb-17
Completion Date 4-Aug-18 16%
Contact Dates

Project Duration 547 Elapsed


Time

Elapsed Duration 88
84%

Elapsed Period % 16.1%


9
Remaining Period % 83.9%
7 Overall
Planned
6 Progress %
Previous
Week This Week Overall Actual
4 Progress %
Overall Actual
Progress % 3.19 3.47 3 Variance %

Overall Planned 15.00


Progress % 1.99 2.32 2.32 3.47 1.15

Variance % 1.2 1.15 Overall Progre...

• Progress Update as at 4.05.2017


2 2
Construction PVA -- up
Construction PVA up to
to 44thth May
May 2017
2017
Planned % Actual % Variance %
Constructio
n 2.28 % 3.88% 1.60%
Zone 1 Zone 2 Zone 3
Planned % Actual % Variance % Planned % Actual % Variance % Planned % Actual % Variance %

4.91% 6.28% 1.37% 4.15% 5.08% 0.93% 0% 5.85% 5.85%

VJ 01 TO
08

3
VH01 TO
08

VA 01 TO VC 01 TO
12
Substation 2 Zone 4 04 05
VE 01 TO
04
ZoneVG501 TO
08
Planned % Actual % Variance % Planned % Actual % Variance % Planned % Actual % Variance %
VB 01 TO
VD 01 TO VF 01 TO
0% 0.49% 0.49% 04
0% 0.52% 0.52%
0.23% 0.72%05 0.49% 04

Substation 1
Planned % Actual % Variance
11
0% 0.00% 0.00%

3
Manpower Histogram
A ve rage M anpow e r/D ay

180

156
160 Planned

Actual
140

11 5
120 1 12

100
87
84

80
65

55

60
51

48
45

40
1 2 27
1 18

18
14

20
3
81 2
57
0
0

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33

Week

Progress Update as at 4.05.2017


4
A ve rage Equipm e nt/D ay

Equipment Histogram

30
27
25 Planned Actual

20
14
1 2 14

15
12
12

8 10

10

10
8
8

8
7
6

6
3 5

5
4
3
3
12

0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 32

Week

Progress Update as at 4.05.2017


5
MAJOR
MAJOR CONCERNS
CONCERNS
SN DESCRIPTION RISK CATEGORY
Work at Zone 4&5 and part of Zone 3 (from grid 29 to grid 56) on hold
due to found
Cavity at zone 4&5 and part of Zone 3 HIGH
1
And subject to M/S ACES instruction given at site until finish their soil
investigation

Still awaiting for authorities approval to close the intermediate road


2 HIGH
3 Receiving Permanent building permit on 20/Apr/2017
IFC Drawings and DC1, DC2 Drawings received on 6/Apr/2017 and ICT to
4 study any change with the tender drawings

CATEGORY HIGH MEDIUM LOW


CATEGORY::
Major
Major Activities
Activities ongoing
ongoing
Activity Zone/Location
Ground beam concrete curing ZONE# 1
Concreting for slab on grade ZONE# 1
Removal of form work for Ground beam ZONE# 1
water proofing bitumine for Ground beam ZONE# 1
Backfilling under slab on grade ZONE# 1
Backfilling ZONE# 2
Blinding concrete under the ground beam ZONE# 2
Shuttering + steel fixing for ground beams ZONE# 2
Water proofing for Blinding concrete footing substation 2 ZONE# 1
Blocks work under the ground beam ZONE# 2

7 7
ZONE#1A Ground beam waterproofing ZONE#1A slab-on-grade

ZONE#1A slab-on-grade
ZONE#1A Ground beam waterproofing

8
ZONE#2 A ground beam Formwork
ZONE#2 A ground beam Reinforcement

ZONE#4 A– waterproofing for Foundation Footings& ZONE#3 A– waterproofing Foundation Footings&


Necks columns Work Necks columns Work

9
Thank You