PP Audit Rep 2018 BPSCL
PP Audit Rep 2018 BPSCL
1
Good safety practices prevailing:
• Positive & supportive attitude by all employees towards
safety.
• All Safety documents are maintained in Safety Deptt.
• Safety issues are discussed in the Daily Planning
Meeting.
• Daily safety inspections are carried out by the Safety
Officer.
• Use of Safety Helmets with Chin Straps on.
• Submission of Online Annual return on safety to Factory
Inspectorate.
2
Statutory Provisions required to be fulfilled
Sl. No Statutory points / issues Observations Recommendations
1 Safety Manual & Policy as per Factories Safety Manual is To be approved and
Act & CEA Regulation-2011 prepared and Policy to be displayed
submitted to CEO at site
2 On Site Emergency Plan and Mock Emergency Plan is To be approved by
Drill, prepared and CIF, Jharkhand
(MSIHC Rule) submitted to CEO.
3 Constitution of Plant Safety Committee Committee Equal representation
and meetings(Factories Act- Sec 41G) constituted and of management as
regular meetings well as workers
are organized. should be there.
4 Inspection and testing of Lifting tools Done by Display of SWL, Next
and tackles/Lifts & Hoists(Factories Act- Competent Person due date to be done.
Sec 28 & 29) in July-2018. Copy of all such test
reports should be
available in Safety
Department
5
General observations
• Growth of heavy grasses & bushes inside entire plant &
peripheral area.
• Accumulation of Scraps and unwanted material
scattered in entire plant,
• Conveyor belt scrap accumulated near Hammer crusher
behind SMS II bursting yard which is prone to Fire
hazard
• All the structure and metallic parts are either rusted /
corroded or discolored need urgent repainting.
• Growth of grasses and vegetation on roof tops of boiler
and turbine main building, conveyor gallery ,window
sheds & all temporary sheds.
• Temporary stores and sheds below gas pipeline behind
GMI/c PP’s office and ID & FD fan area
6
• Almost All the doors ,windows , structures and Equipments are
found having thick coat of dust
• Lack of Safety display boards, signage and area identification
boards in entire plants
• Exclusive agency for Fire protection and prevention needs to be
engaged to take care of fire eventualities. Static water tank,
jockey pumps, fire tenders are not available in the plant.
• Trench covers found missing in many areas in entire Power Plant
• Two level crossings are found without manning.
7
Site Observations
8
A. Switch yard:
• Wild vegetation inside the switch yard.
• Entry gate should be in closed position.
• Proper Display of “un authorized entry restricted “to be made
B. TG Building: (I – VIII)
• Unguarded trench and openings at various locations at “0” mtr.
• Electrical panel boards without back covers
• Loose wires with temp. Joints lying on ground
• Connection taken from boards without plug top
• H2 cylinder Manifold rooms found in open condition.
• Motor Earthing found missing in some cases
• T.G Hall out side wall towards Boiler found totally damaged
because of seepage of Water. 9
C. PTW system: (UCR)
• LOTO system is not implemented.
• One single format for all types of permits.
• Format is not matching with the present situation, needs review
• Checklist for different types of jobs can be made to ensure better safety.
• Safety department should be involved in permit checking
• Fire protection system in UCR to be installed (Inert Gas system)
D. Boiler: (I – V)
• Extended / projected rods / channels at number of locations in Zero meter
• Temporary welding sheds (Unit # I – V) needs to be removed
• All platforms and walk ways should have toe guards
• Very bad house keeping in front of defunct lifts
• All opening should be adequately covered or guarded
• Obstruction in front of stair case going down to be removed
• Damaged and hanging insulation on coal pipe lines at various location
• Shabby cabling at different locations
• Damaged stair case and hand rails at various elevations/locations
• Coupling guards and motor terminal boards missing in AC plant room motor at
13 meter.
• Electrical panel boards without back covers
• All ID Fan coupling Guards are not there 10
E. FOS :
• No display Board near Unloading area for Furnace Oil Tank ,
• Foam Pouring System is not available for Fire Fighting.
• Sprinkler network for external cooling of tank is also not installed.
• Lot of wild vegetation found inside dyke area.
• Oil Tank earthing and lightning arrester found missing.
F. WCTP Plant :
• Repainting of display board near entry gate to be done
• No Eye shower installed in entire WCTP plant
• No insulating Rubber mats found in front of control panel
• Loose & Temp. wires found everywhere in very shabby condition.
• Proper Dos & Donts to be displayed in local language
11
G. CHP Area :
• Housekeeping to be improved in crusher house & all conveyor
galleries.
• Lot of coal dust accumulated on various floors of crusher house
• DE system to be made functional
• Photo cell barrier on both side of wagon tippler may be installed for
restriction of trespassers
• Water sprinkling system is not available in conveyor galleries
• Water logging seepage, slippery floors of walkways in almost all
conveyor galleries
• Roof ceiling found damage at many places of gallery & below gallery
• Barricading near entrance of Track Hopper to be provided
• No Warning boards & public alarm system found in this area .
• Speed of the Coal Rake found higher and unsafe
• Workers are engaged for clearing of boulders from the grating area
which was found very unsafe.
• Wagon is in tilted position for almost half an hour instead of 3
minutes cycle which is another dangerous situation.
• Caution boards to be displayed on either sides of railway track 12
Thanks