PCIHBV/2018/PD&T/2202 -REBIDDING
PROVISION OF ENGINEERING, PROCUREMENT,
CONSTRUCTION AND COMMISSIONING OF 33KV
DOUBLE CIRCUIT OVERHEAD TRANSMISSION
LINES AND TAPPING WORK (OHTL PHASE 2) FOR
PETRONAS CARIGALI IRAQ HOLDING B.V.
KICK-OFF MEETING
6 JUNE 2021
SCOPE OF WORK:
CIVIL WORKS
OFFSITE FACILITIES SUBSTATION (OFS)
OVERHEAD TRANSMISSION LINES (OHTL)
WELL-PAD SUBSTATIONS
COMMUNICATION SYSTEM
SCOPE OF WORK:
CIVIL WORKS
OFFSITE FACILITIES SUBSTATION (OFS)
OVERHEAD TRANSMISSION LINES (OHTL)
WELL-PAD SUBSTATIONS
COMMUNICATION SYSTEM
SCOPE OF WORK:
CIVIL AND STEEL STRUCTURE WORKS:
Topographical Works
Construction of new OFS building inside GIFT area
Construction of power transformer foundation inside well-pads
Construction of 33 KV OHTL tower foundations
33 KV Towers assembling and installation
SCOPE OF WORK:
TOPOGRAPHICAL WORKS
1. Establishing of Control Point by using Differential GPS device
2. Conducting survey works for the OHTL route line
3. Site clearance and preparation for the related work area
4. Design the topographic route line (coordinates and elevations)
5. The route line will b marked as per the IPs and Span, and
determine the elevations for each towers according to the
topographic region.
SCOPE OF WORK:
OFFSITE FACILITIES SUBSTATION (OFS): (CIVIL)
SCOPE OF WORK:
POWER TRANSFORMER FOUNDATION INSIDE WELL-PADS
SCOPE OF WORK:
33 KV OHTL TOWER FOUNDATIONS
Sample of our similar works
Reinforcement Installation
Pouring concrete
SCOPE OF WORK:
33 KV TOWERS ASSEMBLING AND INSTALLATION
SCOPE OF WORK:
OFFSITE FACILITIES SUBSTATION (OFS): (ELECTRICAL)
Is located at GIFT area and will be fed from the power source.
OFS includes:
33 KV power cable, fiber optics & control Low Voltage system
cables.
UPS
2 units of 33/34.5 KV 50 MVA Main
Transformers Fire Alarm System
2 units of 33/0.4 KV 300 KVA Auxiliary HVAC System
Transformers
33 KV incomer switchgears
33 KV outgoing switchgears
33 KV BUS coupler unit
SCOPE OF WORK:
OFFSITE FACILITIES SUBSTATION (OFS):
Single line Diagram (SLD)
SCOPE OF WORK:
OVERHEAD TRANSMISSION LINES (OHTL):
ENGINEERING:
Line Profile and topographic surveying.
Tower location and coordinates.
SCOPE OF WORK:
OVERHEAD TRANSMISSION LINES (OHTL):
ROUTE LINE:
SCOPE OF WORK:
OVERHEAD TRANSMISSION LINES (OHTL):
The approximated total length for 33 double circuit OHTL is 18 km, divided by two
feeders.
Feeder No. 1: 33 KV double circuit OHTL with OPGW will feed WP-G and WP-E, and will
be connected to existing 33 KV OHTL phase 1 (branch tower No. 38).
Feeder No. 2: 33 KV double circuit OHTL with OPGW will feed WP-D, WP-H and WP-K,
and will be connected to OFS by 33KV underground cables.
Tapping work by 33 KV underground cable for all substations of Well Pads.
OHTL includes:
Towers
Conductors
Insulators & Hard wares
OPGW & Accessories
Disconnector switch
SCOPE OF WORK:
OVERHEAD TRANSMISSION LINES (OHTL):
SCOPE OF WORK:
WELL-PAD SUBSTATIONS:
Are located at outside GIFT area and will be fed from 33 KV OHTL
W-P Substation includes:
33 KV incomer switchgear
33 KV transformer switchgear
33 KV BUS coupler
33/6.6 KV power transformers
6.6 KV outgoing switchgear
6.6/ 0.42 KV auxiliary transformer
Communication system
SCOPE OF WORK:
WELL-PAD SUBSTATIONS:
SCOPE OF WORK:
TELECOMMUNICATION SYSTEMS:
1. Telephone Connection
2. CCTV System
3. PAGA System
PROJECT CONTROL: (PROJECT SCHEDULE)
PROJECT CONTROL: (MILESTONES)
Milestones PCIHBV/2018/PD&T/2022
No. Activity Name Start Finish
1 Kick-off Meeting 06-Jun-21 06-Jun-21
2 Effective Date 15-Jun-21
3 Commencement of Engineering 15-Jun-21
4 Completion of Engineering 06-Oct-21
5 Commencement of Procurement 26-Jul-21
6 Completion of Procurement 15-Oct-22
7 Commencement of Construction 29-Mar-22
8 Completion of OFS Sub-station 14-Jan-23
9 Completion of 33 KV OHTL 12-Jan-23
10 Completion of Wellpads 12-Jan-23
11 Completion of Construction 14-Jan-23
12 Commencement of Testing & Commessioning 15-Jan-23
13 Completion of Testing & Commessioning 13-May-23
14 Provisional Acceptance 13-May-23
PROJECT CONTROL: (REPORTING)
Weekly and Monthly Reports:
Weekly and Monthly Reports:
DOCUMENTATION: (LETTER TEMPLATE)
DOCUMENTATION
Document Template (Procedures, Plans, Specifications etc.)
DOCUMENTATION
Document Template (Data Transmittal)
DOCUMENTATION
Daily Report Template
DOCUMENTATION
Drawing Template (AFC, SLDs, etc)
LIST OF SUBCONTRACTORS AND VENDORS
Sub-contractor:
1- BAN Company is the main subcontract for civil works.
Venders and Suppliers:
1- Local supplier for (Cement, gravels, sand, rebars etc.)
2- Schneider
3- SIEMENS
4- ABB
5- SARA
6- MiTAS
ENGINEERING OFFICE LOCATIONS
ALMARWA Company Office: Nasiriyah, Thi Qar, Iraq (Main Office).
Dubai Office: Dubai, JLT Towers, Cluster X (sub-office for Technical
meeting with vendors and suppliers).
OVERALL PROJECT ORGANISATION CHART
TEMPORARY FACILITIES
Main
Camp
Inside
GIFT
Camp
HSE
Health Safety and Environment
QA/QC
THANK YOU
ALMARWA TEAM