The document provides details on the scope of work for a project to provide engineering, procurement, construction and commissioning of overhead transmission lines and substations for Petronas Carigali Iraq Holding B.V. The scope includes civil works, an offsite facilities substation, overhead transmission lines, well-pad substations, and a communication system. It outlines the engineering, procurement, construction, and commissioning process and timelines.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
303 views33 pages

03 Technical

The document provides details on the scope of work for a project to provide engineering, procurement, construction and commissioning of overhead transmission lines and substations for Petronas Carigali Iraq Holding B.V. The scope includes civil works, an offsite facilities substation, overhead transmission lines, well-pad substations, and a communication system. It outlines the engineering, procurement, construction, and commissioning process and timelines.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 33

PCIHBV/2018/PD&T/2202 -REBIDDING

PROVISION OF ENGINEERING, PROCUREMENT,


CONSTRUCTION AND COMMISSIONING OF 33KV
DOUBLE CIRCUIT OVERHEAD TRANSMISSION
LINES AND TAPPING WORK (OHTL PHASE 2) FOR
PETRONAS CARIGALI IRAQ HOLDING B.V.

KICK-OFF MEETING
6 JUNE 2021
SCOPE OF WORK:

 CIVIL WORKS
 OFFSITE FACILITIES SUBSTATION (OFS)
 OVERHEAD TRANSMISSION LINES (OHTL)
 WELL-PAD SUBSTATIONS
 COMMUNICATION SYSTEM
SCOPE OF WORK:

 CIVIL WORKS
 OFFSITE FACILITIES SUBSTATION (OFS)
 OVERHEAD TRANSMISSION LINES (OHTL)
 WELL-PAD SUBSTATIONS
 COMMUNICATION SYSTEM
SCOPE OF WORK:
 CIVIL AND STEEL STRUCTURE WORKS:
 Topographical Works
 Construction of new OFS building inside GIFT area
 Construction of power transformer foundation inside well-pads
 Construction of 33 KV OHTL tower foundations
 33 KV Towers assembling and installation
SCOPE OF WORK:
 TOPOGRAPHICAL WORKS

1. Establishing of Control Point by using Differential GPS device


2. Conducting survey works for the OHTL route line
3. Site clearance and preparation for the related work area
4. Design the topographic route line (coordinates and elevations)
5. The route line will b marked as per the IPs and Span, and
determine the elevations for each towers according to the
topographic region.
SCOPE OF WORK:
 OFFSITE FACILITIES SUBSTATION (OFS): (CIVIL)
SCOPE OF WORK:
 POWER TRANSFORMER FOUNDATION INSIDE WELL-PADS
SCOPE OF WORK:
 33 KV OHTL TOWER FOUNDATIONS
 Sample of our similar works

Reinforcement Installation

Pouring concrete
SCOPE OF WORK:
 33 KV TOWERS ASSEMBLING AND INSTALLATION
SCOPE OF WORK:
 OFFSITE FACILITIES SUBSTATION (OFS): (ELECTRICAL)
Is located at GIFT area and will be fed from the power source.
OFS includes:

33 KV power cable, fiber optics & control Low Voltage system
cables.
UPS
2 units of 33/34.5 KV 50 MVA Main
Transformers Fire Alarm System

2 units of 33/0.4 KV 300 KVA Auxiliary HVAC System


Transformers
33 KV incomer switchgears
33 KV outgoing switchgears
33 KV BUS coupler unit
SCOPE OF WORK:
 OFFSITE FACILITIES SUBSTATION (OFS):
Single line Diagram (SLD)
SCOPE OF WORK:

 OVERHEAD TRANSMISSION LINES (OHTL):


 ENGINEERING:
 Line Profile and topographic surveying.
 Tower location and coordinates.
SCOPE OF WORK:
 OVERHEAD TRANSMISSION LINES (OHTL):
 ROUTE LINE:
SCOPE OF WORK:

 OVERHEAD TRANSMISSION LINES (OHTL):


 The approximated total length for 33 double circuit OHTL is 18 km, divided by two
feeders.
 Feeder No. 1: 33 KV double circuit OHTL with OPGW will feed WP-G and WP-E, and will
be connected to existing 33 KV OHTL phase 1 (branch tower No. 38).
 Feeder No. 2: 33 KV double circuit OHTL with OPGW will feed WP-D, WP-H and WP-K,
and will be connected to OFS by 33KV underground cables.
 Tapping work by 33 KV underground cable for all substations of Well Pads.

OHTL includes:
 Towers
 Conductors
 Insulators & Hard wares
 OPGW & Accessories
 Disconnector switch
SCOPE OF WORK:
 OVERHEAD TRANSMISSION LINES (OHTL):
SCOPE OF WORK:
 WELL-PAD SUBSTATIONS:
Are located at outside GIFT area and will be fed from 33 KV OHTL

W-P Substation includes:


 33 KV incomer switchgear
 33 KV transformer switchgear
 33 KV BUS coupler
 33/6.6 KV power transformers
 6.6 KV outgoing switchgear
 6.6/ 0.42 KV auxiliary transformer
 Communication system
SCOPE OF WORK:
 WELL-PAD SUBSTATIONS:
SCOPE OF WORK:

 TELECOMMUNICATION SYSTEMS:
1. Telephone Connection
2. CCTV System
3. PAGA System
PROJECT CONTROL: (PROJECT SCHEDULE)
PROJECT CONTROL: (MILESTONES)

Milestones PCIHBV/2018/PD&T/2022

No. Activity Name Start Finish


1 Kick-off Meeting 06-Jun-21 06-Jun-21
2 Effective Date 15-Jun-21  
3 Commencement of Engineering 15-Jun-21  
4 Completion of Engineering   06-Oct-21
5 Commencement of Procurement 26-Jul-21  
6 Completion of Procurement   15-Oct-22
7 Commencement of Construction 29-Mar-22  
8 Completion of OFS Sub-station   14-Jan-23
9 Completion of 33 KV OHTL   12-Jan-23
10 Completion of Wellpads   12-Jan-23
11 Completion of Construction   14-Jan-23
12 Commencement of Testing & Commessioning 15-Jan-23  
13 Completion of Testing & Commessioning   13-May-23
14 Provisional Acceptance   13-May-23
PROJECT CONTROL: (REPORTING)
Weekly and Monthly Reports:
Weekly and Monthly Reports:
DOCUMENTATION: (LETTER TEMPLATE)
DOCUMENTATION
Document Template (Procedures, Plans, Specifications etc.)
DOCUMENTATION
Document Template (Data Transmittal)
DOCUMENTATION
Daily Report Template
DOCUMENTATION
Drawing Template (AFC, SLDs, etc)
LIST OF SUBCONTRACTORS AND VENDORS

Sub-contractor:
1- BAN Company is the main subcontract for civil works.
Venders and Suppliers:
1- Local supplier for (Cement, gravels, sand, rebars etc.)
2- Schneider
3- SIEMENS
4- ABB
5- SARA
6- MiTAS
ENGINEERING OFFICE LOCATIONS

 ALMARWA Company Office: Nasiriyah, Thi Qar, Iraq (Main Office).


 Dubai Office: Dubai, JLT Towers, Cluster X (sub-office for Technical
meeting with vendors and suppliers).
OVERALL PROJECT ORGANISATION CHART
TEMPORARY FACILITIES

Main
Camp

Inside
GIFT
Camp
HSE

Health Safety and Environment


QA/QC
THANK YOU

ALMARWA TEAM