Module 4 Planning
Module 4 Planning
• Network Analysis
1. Activity on the arrow
2. Activity on the node networks (Precedence
diagrams)
Linked bar-chart
Limitations of Bar-charts
• Do not show the inter-relationship
between various activities.
• Do not indicate the effect of a succeeding
activity when a preceding activity is
delayed or stopped.
• Do not show the activities where the time
schedule should be maintained and
where it may be delayed without
affecting the completion of the project.
Network Analysis
• planning,
• scheduling and
• time monitoring.
Planning-
• how it is to be performed,
Inputs needed
Line diagrams/BOQ
Taking-off sheets
Drawings etc.
Producing a network showing the
logical relationship between activities
• regulations,
1
5
5 7 9
Activity 6-8 cannot start until activities 4-6 and 5-7 are completed
But activity 7-9 can start when activity 5-7 is completed and is not dependent on
activity 4-6
Dummy activities are sometimes necessary in arrow diagram. These do not take time
to perform and are used either to make the sequence clear or to give a unique
numbering system.
Electrical works
2 3
Plumbing works
Electrical
2 Electrical works
works 4 2 4
Plumbing works
Plumbing works
3 3
Assessing the duration of each activity
Determine Determine
quantities number of crews
Determine
Initial duration
production rate
Technology, site
Estimate
characteristic, Modify time
downtime
learning, etc.
Activity
duration
Producing a schedule, and determining
the start and finish times of each
activity and the available float.
Demonstration
F
B
A G J
C
E H
D
I
6 10
F
4
6 12
B
J
3 G 6
0 3 6
A
C 8
3 12
5 E 20
H
0 3 8
9 3
D
12 20
7
10 I
9
11
Total float
• Total float is the total amount of spare time available in an activity. It is calculated
by subtracting its earliest finish time from the latest finish time.
• It should be noted that total float can be the amount of float in a chain of activities.
Free float
• Free float is a part of total float and represents the amount of spare time which can
be used without affecting subsequent activities, providing the activity starts at its
earliest time.
• It is calculated by subtracting its earliest finish time from the earliest start time of
the activities directly following.
Interfering float
• Interfering float is the amount of spare time available which, if used, will affect
subsequent activities, and may be calculated by: total float – free float.
Independent float
• Independent float is amount of spare time available which can be used without
affecting any succeeding activity and which cannot be affected by any preceding
activity.
• The calculation is: earliest succeeding event time – latest preceding event time –
activity duration.
Types of relationships- ADM
Finish-to-Start Finish-to-Finish
FS
FF
Start-to-Start
Start-to-Finish
SS
SF
Line of Balance
Number of days