Objectives of Cost Analysis Control
Objectives of Cost Analysis Control
& CONTROL
QUESTIONS:
Q1. If you were a Client, what would you expect your project Q.S. to
provide in respect of cost planning, analysis and control ?
Q 2. How do you define a successful cost analysis and control ?
LET US INVESTIGATE
Objectives of Cost Analysis and
Control
Best use of resources to gain the good value for money during the design and
construction processes.
Controlling measures exercised in the design and construction processes, to ensure
the total construction cost / final sum does not exceed the client’s approved budget.
Cost as an element of design during the design and construction processes to
achieve a suitably balanced costs throughout all parts of the Project.
Concept of Cost Analysis &Control
Sub-contractors;
Plant
Other expenses.
Material
Direct: traceable to one particular process, job or product identified with
each unit of product
Example: manufacturing an apparel
Cloth, collar, buttons, cufflinks, thread
Primary packing material (e.g., carton, wrapping, cardboard, boxes, etc.).
Fuel, lubricating oil etc for operating & maintenance of machine
Small tools
Materials used for repairs & maintenance
Labour
Inspectors
Supervisors
Internal transport staff
Storekeeper, maintenance staff
Skilled
Unskilled
Expenses
Expenses leading to a job or contract
Traveling expenses for negotiation
Special pattern, design
Special tools for executing the contract
Rent
Insurance
Canteen, hospital, power , lighting, maintenance
Main Elements of a Control Process
The preparation of a plan that will achieve the objectives of the work.
The recording of the plan in terms of the inputs to or the outputs from the system.
The definition of the quantities and organization of the resources that will be
necessary for the conversion of inputs to outputs.
The use of feedback in order to compare what is happening in practice with that
which was planned.
The evaluation of variances arising from the comparison, leading to decisions as to
whether corrective action is required and whether a change in resources allocation is
necessary.
Implementation of Cost Control
In order to achieve the cost control function, there are three elements needed
to be executed:
1. Cost Planning – to formulate the realistic cost plan for the project.
2. Cost Monitoring – continuous process to compare the actual cost with the
planned cost.
What is the main cost control function of an employer’s quantity surveyor during post-contract
stage ?
To ensure that :
Tender Sum (Contract Sum) = Final Account (Final Contract Sum).
What is the main cost control function of a contractor’s quantity surveyor during post-contract
stage ?
To ensure that :
Actual Expenditure <= Budget (maintain the same or better profitability).
Cost Control during Post-Contract Stage
Activities include the following:
Interim valuation and certificates for payments.
Cash flow control and forecasts through budgetary control.
Financial statements showing the current and expected final costs for the project.
Final account, the agreement of the final certificate and the settlement of claims.
Attendance at site meetings.
Preparation of documentation for subcontractors and suppliers, examination of
quotations and invoices and making recommendations.
Advising on contractual implications.
Negotiation.
Preparation of special reports on cost implications.
Cost Control during Post-Contract Stage
Activities Contd.
Confirmation of payments to domestic /nominated subcontractors (NSC).
Advising on the implications of extensions of the contract period.
Completion of documentation which may be required for some clients,
particularly government departments.
Working with accounting department.
“How can an employer’s quantity surveyor control the cost during the post-
contract stage, with the understanding that he has no authority under the
Contract to issue instructions ?”
Cost Control during Post-Contract Stage
At an early stage, agree with the Contractor for a suitable arrangement for
dealing with day work vouchers and claims for increased costs.
Maintain effective cost control arrangements by keeping a constant check on
costs and by supplying cost advice to the Architect for any proposed variations.
Control the use of contingency sum, make sure that the majority of it is to cover
the cost of extra work that could not be reasonably foreseen at the design stage,
rather than to cater for design alterations.
Cost Control during Post-Contract Stage
Ensure that the probable cost of all variations should be computed before
the Architect formally issues variation orders.
Early consideration should be given to expenditure against provisional and
prime cost sums and the contingency fund, and the examination of sub-
contractors and suppliers 'quotations.
Produce monthly forecasts of final expenditure, and predict and monitor
cash flow.
Cost Analysis and Control
Successful Cost Control
1. The contract sum is within the client’s approved budget or cost limit.
2. Tender Sum (Contract Sum) = Final Account (Final Contract Sum).
3. Value for money.
Q&A