Boiler For Presentation
Boiler For Presentation
Boilers
SWARAJ ZODEY
Manager,
1
PBS Boilers
PRESENTATION MODULE
• Boiler Introduction
• Major Boiler Components
• Boiler startup procedure
• Important process description
• MFT details
• Targeted operation detail
• Routine operation
• Emergency identification & its handling
• Special instructions
2
INTRODUCTION
• M/S. Bhilai Steel Plant (BSP) expand its capacity from 4.0 MTPA to 7.0
MTPA, by adding one more Blast Furnace – 8.
• For critical power, air blast and process steam requirement of the 7.0 MT
stage, Power and Blowing Station expanded
• 1 X 4 MW BPTG
PURPOSE OF BOILER IN PBS
To provide the high pressure steam to
4
DESIGN DATA FOR BOILER
5
COMBUSTION CONDITION
The boilers are designed for the following combinations (the ratios given are based on calorific values)
Note - Any point of time only one oil (LDO/PCM) will be fired
Evaporator
Outlet Header
HT Superheater
Lower Economizer
Outlet Header
Inlet Header
100% FWL
100% FWL Down comer
30% FWL Spray Water
Steam Collector
25% FWL
AIR/FLUE GAS TEMPERATURE
REGIME Air Filter
1359 C (100 MCR)
o
30oC /
30oC /
30oC
Air Filter
HT LT Evaporator
Superheater Superheater
FD fan
STEAM DRUM
V1 = 7.34 m3
10
BOILER START UP CURVES
40
30
Pressure
(kg/cm2}
20
10
0
0 18 36 54 72 90
11 Time (mins)
MAJOR ACTIVITIES TO START
BOILER
Open drum side vents
Open superheater
drains
Open recirculation
valve
Drum fill to lower level
Start second ID fan Start both FD fan Start one ID fan Start Scanner Air fan
Start furnace purge Start CO Gas purging CO gas U seal break Fire with CO gas
Seal Pot
U-seal Make or
up water line Drip Pot
U-seal Drain
SOP FOR BREAKING U-SEAL OF CO/BF GAS LINE
1. Ensure the manual bleeder after the COG/BFG U-seal is open.
2. Start steam purging between U seal and MOV and ensue steam is coming out
of the manual vent.
3. Start Purging in the COG/BFG line and ensure steam from vent lines of
COG/BFG.
4. Ensure drain valves of gas line to seal pot is open.
5. Ensure flow of make up water in the seal pots.
6. Ensure water is coming from overflow line of seal pots.
7. Remove the Blank plate fitted after the drain valve of U-seal.
8. Close the makeup water line manual valve.
9. Open the drain valve of the U-seal.
10. Close the Overflow manual valve.
11. Observe the discharge of the vent line, as soon as gas start coming along with
steam from the vent, close the manual vent valve.
12. Stop the steam purging between U-seal and MOV.
13. Line will be charge up to MOV.
U-SEAL BREAK PROCEDURE
Detail:
Remove
Close
Open Purging
the
theblank
Drain
make
Purge
after
steam
up
valve
Steam
water
drain
ofvalve
valve
U-Seal
valve
valve.
and
and
manual
and
then overflow
Ventvent
valve.
valve
after U-Seal
valve of U-Seal.
SOP FOR FILLING U SEAL
Detail:
Optionthe
Close
Open Overflow
the
to put
purging
manual
U-seal
steam
Drainvalve
valve
steam.
purging
vent
blank and
valve.
after
valve
Makeup
after
drain
water
the
valve,
filling
valve.
depend
of U-seal
on
by water.
lead time of next
fire
PURGING & FIRING METHOD
19
FIRING BY COG
Guillotine Damper
MOV FCV
Trip
Valve
Gas U-seal
Boiler
Furnace
Detail:
TV CRV
Close
Open
Insert
Charge
Remove
Break the
thePilot
Guillotine
igniter
Start Purging COrod of
U-seal
valve
damper
and
gas and
fire
line
Blanking
Gas line byRetract
the
and Boiler Pilot Valve
the
stop igniter
purging
draining rod
the water
system
filled in U-seal
COG Burner Detail
On DCS On Field or Inside Boiler
Spark Command
CTV
CORNER B CORNER
C
MOV FCV
Trip
Valve
Gas U-seal
EL. 6
Detail: EL. 4
Wait for
Break
Open
Start
Charge Purging
Guillotine
the
theUBF– seal
gas EL. 3
of Gas
damper
line
temperature
andline
stopbyof TV CRV
draining system
purging
furnace to
the650
water
o
C EL. 2
Action occurred by it
• Close of LDO/PCM Trip valve and all Oil Nozzle Valves, thus cutting off total oil supply.
• It also ensures the closure of COG/BFG gas trip valves and Corner valves
36 – 37 kg/cm 2
37
DCS operator monitor and maintain
Monitor and maintain some important parameters
38
Operator action perform
Major actions perform by operator during normal operation
39
Operator routine job & special tasks
Important routine jobs performed
HP dosing in Boiler
IBD to the boiler
LDO system control and monitor
40
ROUTINE OPERATION
42
NEGATIVE
Critical Parameter
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
43 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Main Steam Pressure Vs Header Pressure
36 – 37 kg/cm2
Boiler Under load
Action perform:
• Increase the Gas Flow
Alert for:
Collector 1 Pressure
DRUM FURNACE
OXYGEN Collector 2 Pressure
LEVEL DRAFT
45
36 – 37 kg/cm2
Reason
• Gas Pressure may dropped
• Turbine load may increased
• Process steam demand may increased
• Any Boiler may reduce load tripped
Boiler Over load
Action perform:
• Reduce the Gas Flow
Alert for:
Collector 1 Pressure
DRUM FURNACE
OXYGEN Collector 2 Pressure
LEVEL
46
DRAFT
36 – 37 kg/cm2
Reason
• Gas Pressure may increased
• Process steam demand may reduced
•Turbine may tripped or demand dropped
• Any Boiler may taken in range
Boiler performer
In the month of December 2020 to January 2021
A performance report prepared through out the shift.
Mr. Kamal Sirmor perform 88% best operation to maintain the Header pressure
between 36-37.5 kg/cm2.
Worst
47 performance observed 13%
EMERGENCY IDENTIFICATION
48
& ITS HANDLING
ID Fan Trip
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
49 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – One ID fan trip
Step 1: Reduce the BF gas
Step 2: Reduce ID fan load & both FD fans load
Step 3: Reduce CO gas to maintain the Oxygen %
Step 4: Inform to Shift In-charge or Station Engineer
Step 5: Restrict the Boiler load approx. 85 tph
Step 6: Identify the cause
Action Plans – Both ID fan trip
MFT initiated automatically and both FD fan stop
Step 1: Check BF & CO gas MOV start closing
Step 2: Close the CO gas and BF gas trip valve
Step 3: Close MSSV of Boiler. Open Start up vent
Step 4: Manually operate feed water line to control drum level
Instruction: Do not open Man hole of boiler
Step 5: Inform to Shift In-charge or Station Engineer
Step 6: Identify the cause
FD fan Trip
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
52 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – One FD fan trip
Step 1: Reduce one FD fan load & both ID fan load to maintain furnace
pressure
Step 2: Reduce CO gas immediately
Step 3: Reduce BF gas with maintaining furnace pressure
Step 3: Inform to Shift In-charge or Station Engineer
Step 4: Restrict the Boiler load 85 tph
Step 6: Identify the cause
Action Plans – Both FD fan trip
MFT initiated automatically
Step 1: Check MOV start closing
Step 2: Close the CO gas and BF gas trip valve
Step 3: Stop one ID fan
Step 4: Close MSSV of Boiler. Open Start up vent
Step 5: Manually operate feed water line to control drum level
Step 6: Inform to Shift In-charge or Station Engineer
Step 7: Identify the cause
Scanner Air fan Trip
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
55 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – Scanner Air fan trip
If DC scanner air fan also not start.
Step 1: Try to start DC scanner air fan manually from DCS
Even it not start
Step 2: Move furnace draft to negative side
Step 3: Immediately open the service air line manual valve continuously
coordinating with DCS operator to maintain pressure of 450 mmWC – 550
mmWC.
Step 4: Once it achieve, again maintain the furnace pressure
Step 5: Inform to shift In-charge; Coordinate with Eletrical Shift incharge
Step 6: Inspection team check the burner scanners
Step 7: Identify the cause
BFP Trip
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
57 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – One BFP trip
If BFP in auto mode not start than One BFP in operation
Step 1: Reduce total load of Boiler – 7, 8 & 9 to 250 tph.
Step 2: Monitor Feed line pressure should not reduce to 62 kg/cm2
Step 3: Inform to Shift In-charge or Station Engineer
Step 4: Identify the cause
Action Plans – Both BFP trip
No signal of Feed water line pressure increase and drum level continuously
falling.
Water level not seen in gauge glass
Step 1: Close Trip valve of both CO gas & BF gas.
Step 2: Close MSSV of Boiler
Step 3: Inform to Shift In-charge or Station Engineer
Step 4: Start Boiler inspection
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
60 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – LDO pump trip
Do not start another LDO pump
Step 1: Click Stop button of all running burners.
Wait till purge completed
Step 2: Clearance from shift in-charge, start another pump
Step 3: Fire the LDO burner as per SOP
Step 4: Identify the cause
BF Gas MOV trip or Trip Valve Close
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
62 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – BFG MOV or TV close
Step 1: Immediately maintain the furnace pressure.
Step 2: Reduce the load to approx. 45 tph
Step 3: Try to maintain the Steam temperature
Steam temperature should not go below 400oC
Case 1: Identify the issue, if resolved than purge the BF gas line after MOV
and take BF gas in Boiler
Case 2: If issue not resolved and temperature maintained than continuously
run the boiler.
Case 3: If issue not resolved and temperature still in falling trend below
400oC, immediately close MSSV and open start up vent and wait for further
instruction from Shift In-charge.
CO Gas MOV trip or Trip Valve
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
64 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – COG MOV or TV close
Step 1: Furnace temperature should more than 650oC
Case 1: If issue resolved, Purge the CO gas line after MOV and take CO gas
in furnace.
Case 2: If issue not resolved than shut down the boiler as per SOP.
MSV or Header Valve Trip
Drum Drum Condensa BF gas CO gas
LDO Flow
Level Pressure te Flow Flow Flow
Feed Feed
Instrument
Water Water FD fan A
CBD Flow Collector Pressure rate change Oxygen Air
Header 1 Header 1 Air Flow
Kg/cm2/min Pressure
Flow Pressure
Feed Feed
Purge Collector 1 Pressure Scanner
Water Water Furnace FD fan B
66 Steam Air
Header 2 Header 2 Collector 2 Pressure Pressure Air Flow
Pressure Pressure
Flow Pressure
Action Plans – MSV closed
Step 1: Close the Trip valve of BF gas
Step 2: Manage the furnace draft
Step 3: Open the warm up vent
Step 4: Reduce the CO gas to 3000 Nm3/hr immediately
Step 5: Manage Air flow
Step 6: Manually operate the feed water system
Step 7: Inform to shift In-charge or station engineer.
Step 8: Identify the cause
Action Plans – Low BF pressure
Pressure of BF gas at 335 mmWC
Step 1: Avoid increase the BF gas flow
Step 2: Try to increase the CO gas flow
Step 3: If steam pressure not maintain than inform to shift in charge or
station engineer.