Lect 1 2 3
Lect 1 2 3
Research Interests:
• Renewable Energy systems
• Heat and mass transfer analysis
• Piezoelectric materials and their applications
• Thermal energy storage equipment and its applications
Assessment Criteria
Quizzes 3 15%
Assignments 2 10%
Management 1 10%
Project
Final Paper ----- 40%
Concept of Project Management
Overview:
Concept of Project
Project Planning
Project classifications
Project constraint
Project management
Project management components
Project management approaches
Project life cycle
Project environment
Roles and Responsibilities of Project
Manager
Unit 1 Project planning
1.1 Concept of Project
Project
Little and Mirrless have divided projects into broad categories, viz.
quantifiable projects and non-quantifiable projects.
Scope:
What work will be done as part of the project?
What unique product, service, or result does the
customer or sponsor expect from the project?
Time:
How long should it take to complete the project?
What is the project’s schedule?
Cost:
What should it cost to complete the project?
What is the project’s budget?
What resources are needed?
Other people focus on the quadruple
constraint, which adds quality as a
fourth constraint.
Quality:
How good does the quality of the
products or services need to be?
What do we need to do to satisfy the
customer?
The Triple Constraint of Project
Management
Successful project
management
means meeting all
three goals (scope,
time, and cost) –
and satisfying the
project’s sponsor!
Besides the triple constraints, don't
overlook constraints like these that can
cause problems on your project:
Lack of commitment from the executive
management team or project sponsor.
The sponsor may lose interest because
other things have come along that seize the
priority of this project and so on.
Business interruptions or
reorganizations in the midst of the
project.
This could potentially realign your
project resources, leaving you empty-
handed.
Stakeholders who have unrealistic
expectations of project outcomes.
This one is overcome through good project
communications and requiring sign-off of the
project charter and scope statement documents.
Technology.
Advances in technology can cause project delays due
to lack of knowledge of the new technology, training
Project Stakeholders
Stakeholders are the people involved
in or affected by project activities.
Stakeholders include:
◦ Project sponsor
◦ Project manager
◦ Project team
◦ Support staff
◦ Customers
◦ Users
◦ Suppliers
◦ Opponents to the project
Organizational Environment
Organizational Environment
Customer
Contractor
Consultants
Suppliers
Government
Financiers
Competitors
Labour Unions
41
3. External Environment
It is located outside the project.
It cannot be controlled by the project.
It provides opportunities and threats to the
project.
The forces in the external environment
are:
Economic
Technological
Political-Legal
Socio-cultural
43
Project Life-cycle
The generic project life cycle has four phases:
initiating (definition), planning, performing
(execution) , and closing (Termination) the project.
The time span of each phase and the associated
level of effort will vary depending on the specific
project.
Project life cycles vary in length from a few weeks
to several years, depending on the content,
complexity, and magnitude of the project.
Projects Life Cycle and Project Phases
46
Project Life Cycle
Above figure shows the four phases and the relative level of effort and time
devoted to each phase.
Projects Life Cycle and Project Phases
49
Projects Life Cycle and Project Phases
Project life cycle
57
Major tasks for Project Formulation
Technical analysis
– Studies the feasibility of meeting technical
specifications and examines the availability of alternative
technical solutions.
Financial analysis
–Studies the financial sustainability of the project in terms
of capital requirements and capacity for meeting of
financial obligations.
Management analysis –
- Studies the adequacy of management system to direct
and control the project.
64
Contd.
Marketing analysis-
Studies project capacity, market demand and sales
forecast.
Economic analysis –
Studies net contribution of the project to the
economy and to the society.
Benefit/Cost analysis is done for this
purpose.
Environmental analysis-
Studies the impact of the project on the
environment.
Feasibility study should be based on accurate
information. 65
Appraisal
It is the Evaluation of the project’s ability to succeed.
Appraisal is based on the findings of the feasibility
analysis. It addresses -
71
Planning Process
Planning process includes the following steps:
1. Establish project objective. The objective must be agreed upon
by the sponsor or customer and the organization that will perform
the project.
2. Define scope. A project scope document must be prepared. It
should include customer requirements, define the major work tasks or
elements, as well as provide a list of deliverables and associated
acceptance criteria that can be used to verify that the work and
deliverables meet specifications.
3. Create a work breakdown structure. Subdivide the project scope
into pieces or work packages. Although projects may seem
overwhelming when viewed as a whole, one way to conquer even the
most monumental endeavor is to break it down into smaller
components. A work breakdown structure (WBS) is a hierarchical
decomposition of the project scope into work elements or items to be
executed by the project team that will produce the project
deliverables. Figure 1.3 is an example of a work breakdown structure.
Contd
.
4. Assign responsibility. The person or organization
responsible for each work item in the work breakdown
structure must be identified in order to inform the project
team of who is responsible and accountable for the
performance of each work package and any associated
deliverables.
5. Define specific activities. Review each work
package in the work breakdown structure and develop a
list of the detailed activities that need to be performed
for each work package and to produce any required
deliverables.
6. Sequence activities. Create a network diagram that
shows the necessary sequence and dependent
relationships of the detailed activities that need to be
performed to achieve the project objective.
Contd.
7. Estimate activity resources. Determine the
types of resources, such as the skills or expertise
required to perform each activity, as well as the
quantity of each resource that may be needed.
Resources include people, materials, equipment,
etc., that may be required to perform each
activity. Resource estimates must consider the
availability of each type of resource, whether it is
internal or external (such as subcontractors), and
the quantity available over the duration of the
project. Designate a specific individual to be
responsible for each activity.
8. Estimate activity durations. Make a time
estimate for how long it will take to complete
each activity, based on the estimate of the
resources that will be applied.
9. Develop project schedule. Based on the
estimated duration for each activity and the
logical relationships of the sequence of
activities in the network diagram, develop the
overall project schedule, including when
each activity is expected to start and finish,
as well as the latest times that each activity
must start and finish in order to complete the
project by the project required completion
date.
10.Estimate activity costs. Activity costs
should be based on the types and quantities
of resources estimated for each activity as
well as the appropriate labor cost rate or unit
cost for each type of resource.
Contd
Once the
.
project schedule and budget are
developed, it must be determined whether the
project can be completed within the required
time, with the allotted funds, and with the
available resources.
If not, adjustments must be made to the project
scope, activity resource or duration estimates,
or resource assignments until an achievable,
realistic baseline plan, the roadmap for
accomplishing the project scope on time and
within budget, can be
established.
Implementation Phase
Implementation is concerned with mobilization.
The third phase of the project life cycle is performing the
project. Once the base- line plan has been developed,
work can proceed. The project team, led by the project
manager, will execute the plan and perform the activities to
produce all the deliverables and to accomplish the project
objective.
The pace of project activity will increase as more and
various resources become involved in performing
the project tasks.
During the course of performing the project, different types
of resources will be utilized.
This phase results in the accomplishment of the project
objective, leaving the customer satisfied that the full scope
of the work and deliverables were completed according to
specifications, within budget, and on time.
Implementation involves-
74
Control is an inevitable task during
implementation
It involves supervision and control of project
performance to provide feedback.
Monitoring of project performance is done.
Itis a means to improve implementation
identification
through theof problems and the possible corrective
actions.
Various techniques like CPM,PERT and other network
analysis techniques are used for control purpose.
If a project gets too far out of control, it may be difficult to
accomplish the project objective without sacrificing the
scope, budget, schedule, or quality. The key to effective
project control is measuring actual progress and
comparing it to planned progress on a timely and regular
basis throughout the performing phase and taking any
needed corrective action immediately.
75
The Control comprises the following
activities:
Setting of standards
Measuring outputs
Verifying the output with pre set standards
Finding deviations, if any.
Correcting the process/output to the pre
set standards if required
The performing phase of the project life cycle ends when
the sponsor or customer is satisfied that the project
objective has been accomplished and that the
requirements have been met, and
accepts the project deliverables.
80
Termination phase (closing)
The final phase of the project life cycle is closing the project.
The process of closing the project involves various actions,
including collecting and making final payments, evaluating
and recognizing staff, conducting a post-project evaluation,
documenting lessons learned, and archiving project
documents.
The project organization should ensure that copies of
appropriate project doc- umentation are properly organized,
filed and archived so that they can be readily retrieved for use
in the future.
The project team should identify lessons
learned and make recommendations for
improving performance on future projects.
Feedback should also be obtained from the
sponsor or customer to determine whether the
anticipated benefits from the project were
achieved, assess the level of customer
satisfaction, and obtain any feedback that
would be helpful in future business
relationships with this customer or other
customers.
The basic tasks in this phase are:
Project Evaluation:
Evaluation measures the effects and impacts of
the project.
It can be carried out during the project implementation to
improve implementation or can also be carried out after
project completion to improve future project planning and
management.
Project Handover:
Handover begins when the project work is finished.
Resources are then reallocated to other projects.
Project accounts are closed.
Project is terminated.
Most project life cycles tend to progress slowly at the
start, quicken their momentum towards the middle
and drop their momentum towards the end.: