Vinh Tan 4 Thermal Power Plant Water Treatment System: Instructor: H. T. LEE (ATAI)

The document discusses the water treatment system at Vinh Tan 4 Thermal Power Plant. It provides design parameters for seawater and lake water. It then describes the major equipment in the system including clarifiers, disc filters, activated carbon filters, ultra filters, reverse osmosis units, and mixed bed polishers.

Uploaded by

naturalgrace710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
105 views34 pages

Vinh Tan 4 Thermal Power Plant Water Treatment System: Instructor: H. T. LEE (ATAI)

The document discusses the water treatment system at Vinh Tan 4 Thermal Power Plant. It provides design parameters for seawater and lake water. It then describes the major equipment in the system including clarifiers, disc filters, activated carbon filters, ultra filters, reverse osmosis units, and mixed bed polishers.

Uploaded by

naturalgrace710
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 34

Think Blue

Think Green

VINH TAN 4 THERMAL POWER PLANT

WATER TREATMENT SYSTEM

Instructor : H. T. LEE (ATAI)


Think Blue
Think Green

I. WATER TREATMENT SYSTEM

1 Water Design Data

2 Process Flow Diagram

3 Major Equipment

4 Unit Operation

2
Think Blue
1 Water Design Data Think Green

1) The basic design parameters are as follows (Sea water)

Conductivity pH TDS Silica Hardness Total Soild Sodium

50500 μS/cm 8.34 34,820mg/l 2.96mg/l 61.84 mg/l 35,020mg/l 10,605mg/l

2) The basic design parameters are as follows (Lake water)

Conductivity pH TDS Silica Hardness Total Soild Sodium

159 μS/cm 7.14 163mg/l 36.41mg/l 0.3mg/l 208mg/l 22.4mg/l

3) The quality of demineralized water will be guaranteed as follows


Total Or-
Conductivity pH TDS Silica Hardness ganic Car- Sodium
bon
≤ 0.1 μS/cm 6.8 ~ 7.2 ≤ 0.05mg/l ≤ 0.01mg/l ≤ 0.005mg/l ≤ 0.03 ≤ 0.015mg/l
at 25℃
3
Think Blue
2 Process Flow Diagram Think Green

4
Think Blue
3 Major System Equipment Think Green

1. CLARIFIER
PRETREATMENT

2. DISC FILTER

3. A/C FILTER

4. UF
RALIZATION
DEMINE-

5. RO

6. MBP

5
DISC FILTER

1. CLARIFIER (LAMELLA)

◆ FLOW CONTROL BY THE FIN CHANNEL.


◆ REDUCE SEDIMENTATION BASIN SIZE.
◆ CAPACITY : 250 m3/hr,

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


DISC FILTER

2. DISC FILTER

◆ REMOVAL : SS protecting post Equipment


◆ MAKER : AMIAD
◆ CAPACITY : 220 m3/hr

RUNNING BACKWASH

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


Think Blue
ACTIVATED CARBON FILTER
Think Green

3. A/C FILTER
활성탄 여과기 (ACTIVATED CARBON FILTER)

◆ REMOVAL : COD / Organic Fouling Material


◆ Vessel Size : 4,000 mmID x 3,400 mmH
◆ Activated Carbon : 30.16 m3, 12 x 40 mesh , ◆ Gravel : 1.88 m3, 2~20mm

ACTIVATED CAR- PASSWAY


BON
(2,400 mm)

GRAVEL
(150 mm)
Think Blue
ULTRA FILTER Think Green

4. UF활성탄
(ULTRA
여과기 FILTER)

◆ UF UNIT (3 SET x 50 %)
◆ MEMBRAIN : 44 EA, MAKER : PENTAIR, MODEL : XIGA 64
◆ VESSEL : 11EA, MAKER : PENTAIR, MODEL : 90L12-6
REVERSE OSMOSIS

5. RO (REVERSE OSMOSIS)

Principle of Reverse Osmosis

EXTERNAL PRESSURE –
OSMOTIC PRESSURE

OSMOTIC PRESSURE
HIGH
PRESSURE
HALF TRANSMISSION

HALF TRANSMISSION
LOW SALINITY HIGH SALINITY LOW SALINITY HIGH SALINITY
WATER WATER WATER WATER
MEMBRANE

MEMBRANE
OSMOSIS STEP REVERSE OSMOSIS
STEP

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


REVERSE OSMOSIS

To remove the factor as Metal ion(Mineral), Aqueous salt & etc.

Filtration

Spectrum

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


REVERSE OSMOSIS

Spiral Wound Type RO Membrane Detail Structure

RO Membrane is composed of
a support layer(Thick. 40 ㎛ )
and an Active layer(Thick. 0.2 ㎛ )
 Separation Function

Polyamide
(Active layer)
0.2 ㎛

Support layer Polysulfone 40 ㎛


Polyester 120 ㎛

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


REVERSE OSMOSIS

SWRO UNIT BWRO UNIT

*Manufacture *Manufacture
-Membrane : Toray (TM800K) -Membrane : Toray (TM800M)
-Vessel : Code Line (80S100) -Vessel : Code Line (80S30)

*Spec. *Spec.
-Q’ty : 50% x 2 Train -Q’ty : 50% x 2 Train
-Permeate Flow : 77.5 m3/hr -Permeate Flow : 34.5 m3/hr
- -Concentrate Flow : 122.5 m3/hr - -Concentrate Flow : 6 m3/hr

-Vessel : 20 ea / Unit -Vessel : 6 ea / Unit


-Membrane: 7 ea/ Vessel -Membrane: 36 ea/ Vessel
-Recovery : 39% -Recovery : 85%

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


MIXED BED POLISHER

6. MBP (MIXED BED POLISHER)

To remove the factor as Mineral Ion


 Make for pure water(De-Mineralized Water)

Cation Resin Exchanger Anion Resin Exchanger

WAC HCO3- HCO3-


Ca2+

Mg2+
H+
SAC SO4 2-
SO42-
WBA
Cl -
Na +
Cl -
SBA

SiO2 H2SiO3

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


MIXED BED POLISHER

Selectivity of Normal Condition

Cation Resin Ca2+ > Mg2+ > Na+ > H + Anion Resin SO42- > Cl - > HCO3- > SiO2 > OH -

Mg++ HCO3- HCO3-


Mg2+
Ca++ CI- H
+
CI-
+ (R – H)
+R Ca2+
Na +
SO4 - → SO4 -

Na+
SiO2 SiO2

[ Ion exchange reaction in cation exchange resin ]


Reaction
HCO3-
HCO3-
H+ CI -

+ R – OH) (→ H+ OH- +R Cl -
SO4-
SO42- -

SiO2
SiO2
[ Ion exchange reaction in anion exchange resin ]

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


MIXED BED POLISHER

MBP Design
DESIGN FACTOR

Feed Liner Velocity : 16 ㎥ / ㎡ /hr Flow Type : Down Flow

Capacity : 60 ㎥ /hr SIZE : I.D 2,200×3,200H

INTERNAL STRUCTURE

ANION
RESIN

Mixing of Air
CATION
RESIN

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


MIXED BED POLISHER

Process & Regeneration Step


Valve Open

05 10 Service 01, 02
NaOH
11 B/W 03, 04
Rinse 04 Chmical
01 05, 06, 07
Feed
B/W
Service W/T
Drain Displace
05, 06, 07
Anion -ment
07
Only Pure water Rinse 03, 11, 07
Supply

03 Drain 07, 10
Cation Treated
B/W Water 02 W/T
06 Air Mixing 09, 10
HCL
WT Filling 01, 10
Service Air AIR AIR AIR 08
09 F. Rinse 01, 08

Cond. Chk 01, 02 & Drain

POWER PLANT & ENVIRONMENT HYORIM INDUSTRIES


Think Blue
4 Unit Operation Think Green

 REFER TO NEX PAGE

18
SERVICE - 24hr : 220m3/hr

BACKWASH - 2min : 22m3/hr


SERVICE - 24hr : 220m3/hr

BACKWASH - 15min : 320m3/hr


REST - 5min
RINSE – 5min : 220m3/hr
SERVICE - 50min : 220m3/hr

REST - 20 sec
BACKWASH - 30 sec : 660m3/hr
REST - 20 sec

REST - 20 sec
BACKWASH - 30 sec : 660m3/hr
NaOCl, CAUSTIC - 62 sec : 330m3/hr
SOAKING - 600 sec
RINSE - 50 sec : 660m3/hr
ACID - 62 sec : 330m3/hr
SOAKING - 600 sec
RINSE - 70 sec : 660m3/hr
REST - 20 sec
SERVICE - 24hr : 200m3/hr

CLEANING - 30 min : 100m3/hr


SOAKING - 180 min
RECYCLE - 30 min : 100m3/hr
SOAKING - 180 min
RECYCLE - 20 min : 100m3/hr
DRAIN - 10 min
FLUSHING -10 min : 122m3/hr
SERVICE - 24hr : 40m3/hr

CLEANING - 30 min : 40m3/hr


SOAKING - 180 min
RECYCLE - 30 min : 40m3/hr
SOAKING - 180 min
RECYCLE - 20 min : 40m3/hr
DRAIN - 10 min
FLUSHING -10 min : 40m3/hr
SERVICE – 168hr : 60m3/hr

BACKWASH - 10 min : 75m3/


REST- 5 min : 60m3/hr
DILLUTIONE - 1 min
DOUBLE REGEN. - 130 min
RINSE- 20 min : 60m3/hr
DRAIN - 5 min
AIR MIXING -10 min : 230Nm3/min
AIR DRAIN - 15 sec
REST - 5min
FILLING - 5min : 60m3/hr
RINSE - 12min : 60m3/hr
SERVICE – 24hr : 5m3/hr

BACKWASH - 10 min : 5m3/hr


REST - 5 min : 5m3/hr
RINSE - 10 min : 5m3/hr
Think Blue
Think Green

THANK YOU