Project crashing
• It is common in project management that
additional resources are used to either speed up
some activities to get the project back on
schedule or to reduce the project completion
time.
• Crashing an activity refers to the speeding up or
shortening of the duration of an activity by using
additional resources. These include overtime,
hiring temporary staff, renting more efficient
equipment, and other measures.
Project crashing
• Project crashing refers to the process of
shortening the duration of the project by
crashing the duration of a number of activities.
• Since it generally results in an increase of the
overall project costs, the challenge faced by the
project manager is to identify the activities to
crash and the duration reduction for each
activity such that as the project crashing is done
in the least expensive manner possible.
Project crashing
• The normal time refers to the estimated activity
duration used with CPM or PERT in the
computation of earliest (latest) start or finish
times.
• The normal cost refers to the activity cost under
the normal activity time.
•
Project crashing
• The crash time refers to the shortest possible time to
complete an activity with additional resources.
• The crashing cost refers to the activity cost under the
crashing activity time. This relationship is assumed to
be linear. Hence, for each activity a crash cost per
period (e.g.,per week) can be derived as follows:
• crash cost per period = (Crash cost - Normal Cost)/
(Normal time - Crash time)
Project crashing
• the cost to crash per period assumes that the
relationship between adding more money to
the activity and reducing the time is linear.
Spend half of the money, and get half the time
reduction, spend _ of the money and get _
time reduction. This is not always true in
practice, but works alright for a rough
planning technique
THE GENERAL RELATIONSHIP OF TIME
AND COST
• Crashing costs increase as project duration
decreases.
3
1
3
1
5(0)
3
1
5(0)
1 3
8(0)
that is 8 weeks
If the cost for path 1-2 and path 2-3 is the same
then
We can random pick them to crash so that its
completion
Time is 8 weeks
4(0) 4(1)
5 (1) 2 6(3)
3
1
8(0)
OR
5 (1) 3(0)
2 6(3)
1
3
8(0)