Power Point3
Power Point3
The activities and the activity duration are the basic building
blocks needed to construct a graphic picture of the project.
. The earliest time at which work can begin on every activity that
makes up the project.
. The earliest expected completion date of the project.
Envisioning a Complex Project Network Diagram:
A project network diagram is a pictorial representation of the
sequence in which the project work can be done.
The relationships between the activities in the project are
represented in a flow diagram called a network diagram or logic
diagram.
1
Benefits to Network-Based Scheduling:
The Gantt chart is the oldest of the two and is used effectively in
simple, short duration types of projects.
.Second, the Gantt chart does not tell the project manager
whether the schedule that results from the Gantt chart completes
the project in the shortest possible time or even uses the
resources most effectively.
2
Network diagrams can be used for detailed project
planning, during implementation as a tool for analyzing
scheduling alternatives, and as a control tool:
Implementation.
Start-to-finish.
The start-to-finish (SF) dependency is a little more complex
than the FS and SS dependencies. Here activity B cannot be
finished sooner
than activity A has started. For example, suppose you have built 5
a new
Finish-to-finish. The finish-to-finish (FF) dependency states that
activity B cannot finish sooner than activity A.
Constraints:
There are four types of constraints that will affect the sequencing
of project activities and, hence, the dependency relations
between activities:
■Technical constraints
■ Management constraints
■ Interproject constraints
■Date constraints
Technical Constraints:
Technical dependencies between activities are those that arise
because one activity (the successor) requires output from
another (the predecessor) before work can begin on it.
Discretionary constraints.
Discretionary constraints are judgment calls by the project
manager that result in the introduction of dependencies. These
judgment calls may be merely a hunch or a risk-aversion strategy
taken by the project manager.
6
Best-practices constraints.
Best practices are past experiences that have worked well for the
project manager or are known to the project manager based on
the experiences of others in similar situations.
Logical constraints.
Logical constraints are like discretionary constraints that arise
from the project manager’s way of thinking about the logical way
to sequence a pair of activities. We feel that it is important for
the project manager to be comfortable with the sequencing of
work.
Unique requirements.
These constraints occur in situations where a critical resource,
say, an irreplaceable expert or a one-of-a kind piece of
equipment, is involved on several project activities.
Management Constraints
A second type of dependency arises as the result of a
management-imposed constraint.
Interproject Constraints
Interproject constraints result when deliverables from one project
are needed by another project. 7
Date Constraints
Date constraints impose start or finish dates on an activity that
force it to occur according to a particular schedule.
Date constraints come in three types:
Critical Path
the critical path is the longest path or sequence of activities (in
terms of activity duration) through the network diagram. The
critical path
drives the completion date of the project. Any delay in the
completion of any one of the activities in the sequence will delay
the completion of the project.
8
Computing Slack
The second method of finding the critical path requires us to
compute a quantity known as the activity slack time. Slack time
(also called float) is the amountof delay expressed in units of
time that could be tolerated in the starting time or completion
time of an activity without causing a delay in the completion of
the project. Slack time is a calculated number. It is the difference
between the late finish and the early finish (LF – EF). If the result
is greater than zero, the
activity has a range of time in which it can start and finish
without delaying the project completion date.
There are two types of slack:
9
10
11
12
13
14
15
16
17
18
19
20
21