TBR & TBH Project Kick Off Final - 01

Uploaded by

Aaban khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views19 pages

TBR & TBH Project Kick Off Final - 01

Uploaded by

Aaban khan
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 19

TBR & TBH UTILITY HUBS

DEMOBLIZATION WORKS
PROJECT

19- Dec - 2024

Project Kick-Off
TABLE OF CONTENT
 Project Brief
 Project Location
 Project Scope of Work
 Project Organization
 Vendor List (Proposed)
 Project KPI`s
 Project Schedule
 Project Activity Schedule With Manpower
 Project Activity Schedule With Equipment
 Manpower Histogram (Estimated)
 Health, Safety, Security & Environment
 Quality Assurance/Quality Control
PROJECT BRIEF
TBR & TBH UTILITY HUBS DEMOBLIZATION
Project Name
WORKS PROJECT
Owner/Consultant RED SEA REAL ESTATE COMPANY

CONTRACTOR ANA STAR CONTRACTING CO

TBR & TBH UTILITY HUBS DEMOBLIZATION WORKS,


Scope Generators , tanks ,cables , loose soil, waste, poles,
electric room, security room, fence etc

Build Up Area - Floor 7,869 Sq. m

Build Up Area - Terrace & Infinity Pool 2,044 Sq. m

Project Commencement Date 15-December-2024 (Assumed Date of Contract)


As a Baseline 14-Feb-25 & (As an Acceleration 31st-
Project Finish
January-2025)
As a Baseline 60 Calendar Days (As an Acceleration 45
Contract Duration
Calendar Days)
Location Near Turtle Bay Hotel

Current Status Contract Awarded R12-T07C06


Project Site
PROJECT LOCATION Location

– Site TBH

– Site TBR
Figure 1 - The Kingdom of Saudi Arabia Figure 2 – AMAALA Location

Figure 2 – Site TBR & TBH


Marina
Precinct
PROJECT SCOPE OF WORK
 Outline Scope of Works
PROJECT ORGANIZATION
VENDORS LIST (PROPOSED)

Activity Name Proposed Vendors

Loose soil Removal AVERDA / GEMS

Transport / Heavy Equipment AL Thoraya/ Al Saad

Purging Tank third Party


Al Thoraya International

Environment Third Party Environmental/ Green/ Canada Leeds Consultant or Other


PROJECT KPI`S
PROJECT SCHEDULE Classic Shedule.pdf
PROJECT ACTIVITY SCHEDULE WITH MANPOWER Activity Shedule with Manpower (1).pdf
PROJECT ACTIVITY SCHEDULE WITH EQUIPMENT Activity Shedule with Equipment.pdf
ACTION PLAN
 Establishing of DCS
• Request for Aconex Access & project templets
• Submitting Projects QA/QC documentation
• Submitting Projects HSE documentation
• Establishing project control system

 SITE MOBILIZATION
• Site Hording
• Site offices & workshops
• Man-force mobilization
 PROCURMENT
• Finalizing of site office safety material
• Submitting Of Material For Approvals (MS) (If
applicable)
• Placing Purchase orders (Third party contracts If
applicable)
 • Material/Equipment deliveries on site (IF REQUIRED)
Initiating of Construction works
• Site handover
• Survey Application (IF REQUIRED)
• Machinery and equipment's set up (IF REQUIRED)
• Early works (dismantling)
Manpower Histogram.pdf
MANPOWER HISTOGRAM (ESTIMATED ACCORDING TO NORMAL SCHEDULE)
HEALTH, SAFETY, SECURITY &
ENVIRONMENT
 HSE Program

 Management Leadership and Organizational Commitment


 Hazard Identification and Assessment
 Hazard Controls
 Environmental Aspects and Impacts Determination
 Inspections
 Competency, Training and Awareness
 Emergency Response
 Accident and Incident Investigation
 Communication, Participation and Exchange of Information
 Occupational Health and Safety Management Systems Documentation
HEALTH, SAFETY, SECURITY & ENVIRONMENT
 Training and Education
• Safety Orientation
• Toolbox Talk (TBT)
• Training Matrix
• Third Party Trainers ( First Aider , Operator’s Quality
Veritas/Green)
 Reports, Investigations and Records

• Daily HSE and Weekly HSE Statistics reports

• All near misses and incidents will be reported and investigated on


time. AANA Incident Investigation report template will be used (it
can be updated as per client requirement)

• All records will be kept as hard copy in the HSE Smart cabinet
and as softy copy in the site HSE computer.
HEALTH, SAFETY, SECURITY &
ENVIRONMENT
 Field HSE Systems

• HSE Plan
• Demobilization Environmental Plan (CEMP)
• Emergency Response Plan
• Fire Safety Plan
• Traffic Management Plan
• Lifting Plan
• COVID-19 Response Plan (Not Applicable)
• HSE Inspections and Audits
• Hazard and Risk Register
• Accident Incident Reporting
• Client HSE Requirements
Quality Assurance/Quality Control

1. Project Quality Plan.

2. Inspection & Test Plans (if applicable).

3. Document records & controls.

4. Demobilization quality controls.

5. Dismantling procedures.

6. Preventive & corrective actions (if required).

7. Third Party Inspections & Testing (if required).

8. Tool Box Talks & Trainings (if applicable).


QUALITY ASSURANCE/QUALITY CONTROL
IMPLEMENTATION OF PQP

1. Identification of required inputs and development of PQP as per project


requirements

2. Distribution of quality plan

3. Internal / External monitoring for the conformity with the quality plan

 Reviews
 Audits

4. Trainings

5. Revision of project quality plan

6. Feedback and Improvement


THANK YOU