TBR & TBH UTILITY HUBS
DEMOBLIZATION WORKS
PROJECT
19- Dec - 2024
Project Kick-Off
TABLE OF CONTENT
Project Brief
Project Location
Project Scope of Work
Project Organization
Vendor List (Proposed)
Project KPI`s
Project Schedule
Project Activity Schedule With Manpower
Project Activity Schedule With Equipment
Manpower Histogram (Estimated)
Health, Safety, Security & Environment
Quality Assurance/Quality Control
PROJECT BRIEF
TBR & TBH UTILITY HUBS DEMOBLIZATION
Project Name
WORKS PROJECT
Owner/Consultant RED SEA REAL ESTATE COMPANY
CONTRACTOR ANA STAR CONTRACTING CO
TBR & TBH UTILITY HUBS DEMOBLIZATION WORKS,
Scope Generators , tanks ,cables , loose soil, waste, poles,
electric room, security room, fence etc
Build Up Area - Floor 7,869 Sq. m
Build Up Area - Terrace & Infinity Pool 2,044 Sq. m
Project Commencement Date 15-December-2024 (Assumed Date of Contract)
As a Baseline 14-Feb-25 & (As an Acceleration 31st-
Project Finish
January-2025)
As a Baseline 60 Calendar Days (As an Acceleration 45
Contract Duration
Calendar Days)
Location Near Turtle Bay Hotel
Current Status Contract Awarded R12-T07C06
Project Site
PROJECT LOCATION Location
– Site TBH
– Site TBR
Figure 1 - The Kingdom of Saudi Arabia Figure 2 – AMAALA Location
Figure 2 – Site TBR & TBH
Marina
Precinct
PROJECT SCOPE OF WORK
Outline Scope of Works
PROJECT ORGANIZATION
VENDORS LIST (PROPOSED)
Activity Name Proposed Vendors
Loose soil Removal AVERDA / GEMS
Transport / Heavy Equipment AL Thoraya/ Al Saad
Purging Tank third Party
Al Thoraya International
Environment Third Party Environmental/ Green/ Canada Leeds Consultant or Other
PROJECT KPI`S
PROJECT SCHEDULE Classic Shedule.pdf
PROJECT ACTIVITY SCHEDULE WITH MANPOWER Activity Shedule with Manpower (1).pdf
PROJECT ACTIVITY SCHEDULE WITH EQUIPMENT Activity Shedule with Equipment.pdf
ACTION PLAN
Establishing of DCS
• Request for Aconex Access & project templets
• Submitting Projects QA/QC documentation
• Submitting Projects HSE documentation
• Establishing project control system
SITE MOBILIZATION
• Site Hording
• Site offices & workshops
• Man-force mobilization
PROCURMENT
• Finalizing of site office safety material
• Submitting Of Material For Approvals (MS) (If
applicable)
• Placing Purchase orders (Third party contracts If
applicable)
• Material/Equipment deliveries on site (IF REQUIRED)
Initiating of Construction works
• Site handover
• Survey Application (IF REQUIRED)
• Machinery and equipment's set up (IF REQUIRED)
• Early works (dismantling)
Manpower Histogram.pdf
MANPOWER HISTOGRAM (ESTIMATED ACCORDING TO NORMAL SCHEDULE)
HEALTH, SAFETY, SECURITY &
ENVIRONMENT
HSE Program
Management Leadership and Organizational Commitment
Hazard Identification and Assessment
Hazard Controls
Environmental Aspects and Impacts Determination
Inspections
Competency, Training and Awareness
Emergency Response
Accident and Incident Investigation
Communication, Participation and Exchange of Information
Occupational Health and Safety Management Systems Documentation
HEALTH, SAFETY, SECURITY & ENVIRONMENT
Training and Education
• Safety Orientation
• Toolbox Talk (TBT)
• Training Matrix
• Third Party Trainers ( First Aider , Operator’s Quality
Veritas/Green)
Reports, Investigations and Records
• Daily HSE and Weekly HSE Statistics reports
• All near misses and incidents will be reported and investigated on
time. AANA Incident Investigation report template will be used (it
can be updated as per client requirement)
• All records will be kept as hard copy in the HSE Smart cabinet
and as softy copy in the site HSE computer.
HEALTH, SAFETY, SECURITY &
ENVIRONMENT
Field HSE Systems
• HSE Plan
• Demobilization Environmental Plan (CEMP)
• Emergency Response Plan
• Fire Safety Plan
• Traffic Management Plan
• Lifting Plan
• COVID-19 Response Plan (Not Applicable)
• HSE Inspections and Audits
• Hazard and Risk Register
• Accident Incident Reporting
• Client HSE Requirements
Quality Assurance/Quality Control
1. Project Quality Plan.
2. Inspection & Test Plans (if applicable).
3. Document records & controls.
4. Demobilization quality controls.
5. Dismantling procedures.
6. Preventive & corrective actions (if required).
7. Third Party Inspections & Testing (if required).
8. Tool Box Talks & Trainings (if applicable).
QUALITY ASSURANCE/QUALITY CONTROL
IMPLEMENTATION OF PQP
1. Identification of required inputs and development of PQP as per project
requirements
2. Distribution of quality plan
3. Internal / External monitoring for the conformity with the quality plan
Reviews
Audits
4. Trainings
5. Revision of project quality plan
6. Feedback and Improvement
THANK YOU
Ana Star Contracting Company