Introductiontorelaying_module1
Introductiontorelaying_module1
Jagadish Subbaramaiah
Agenda
• Electrical Power System
• Protection – Introduction
• Fault statistics
• Bus configurations
• Desirable attributes
• Zones of Protection
• Fault clearance chain
• Evolution and types
• Examples
Electrical power System
The purpose
To generate and supply electrical energy to consumers
The system
Design should be reliable and economical
Frequent or prolonged power outages
Result in severe disruption to the normal routine of modern society.
Electrical power System
Three Layered structure of electrical Power system
This equipment helps maintain the power system at its
normal voltage and frequency, generates sufficient power to
meet the load and maintains optimum economy and security
Control equipment
in the interconnected network. The control equipment is
organized in a hierarchy of its own, consisting of local and
central control functions
The control aspect of relaying systems also helps return the power system to an acceptable
configuration as soon as possible so that service to customers can be restored.
Some Definitions
• Protection equipment – a collection of Protection devices (Relays,
fuses etc.). Excluded are devices such as CT’s, CB’s contactors etc.
• Protection System – a complete arrangement of protection
equipment and other devices required to achieve a specific function
based on a Protection principal (IEC60255-20)
• Protection Scheme – a collection of Protection equipment providing
a defined function and including all equipment required to make the
scheme work (i.e., Relays, CT’s CB’s batteries etc.)
Fault Statistics
Fault %
Single Phase to Ground 80%
Two phase 5%
Three phase 5%
What is the fault current at Bus 2 when all lines are in service?
If the Line 2-3 goes out what is the change in fault current for a fault at bus 2?
What is the fault current at bus 9 when all generators are in service ?
What is the change in fault current at bus 9 when one of the two generators is tripped?
Bus configurations
Now consider the fault at F3. This fault lies in two open zones. The fault should cause circuit
breaker B6 to trip. B5 is the backup breaker for this fault, and will trip if for some reason B6 fails
to clear the fault.
Protection performance
Statistical assessment
Duplication of Protection
Local
Backup Protection
Remote
EHV systems
System stability is at risk
Multiple primary protections operating in Parallel
Figure 2
Figure 1
International practices
Although the fundamental protective and relay operating concepts are similar throughout the world,
there are very significant differences in their implementation. These differences arise through
different
traditions, operating philosophies, experiences and national standards.
For example, their preference may be for relays manufactured inside their respective countries. In
some developing countries, the choice of relays may be influenced by the availability of low-cost
hard-currency loans, or a transfer-of technology agreement with the prospective vendor of the
protective equipment. The evolutionary stage of the power system itself may have an influence on
the protection philosophy.. Long transmission lines are quite common in countries with large areas,
e.g. the USA or Russia. Many European and Asian countries have relatively short transmission lines,
and, since the protection practice for long lines is significantly different from that for short lines, this
may be reflected in the established relaying philosophy.
As mentioned in section earlier reclosing practices also vary considerably among different countries.
An important factor in the application of specific relay schemes is associated with the configuration
of the lines and substations. Multiple circuit towers as found throughout Europe have different
fault histories than single circuit lines, and therefore have different protection system needs.
Relay evolution
Introduced in 1960’s
Size – reduced
Burden – reduced
Passive Components
Analogue to digital
conversion
Speed of operation
Display Unit
Numerical relays
Platform concept
Multiprocessor techniques
Communication
New Technology Benefits
Numerical technique - Advantages
Comparison
Repair
Numerical protection
with
self supervision
MTTR: hours
Numerical technique - Advantages
Communication
C
E
FREJA/XS92b
RTS PC Local HMI SCS SMS
Parameter setting Parameter setting Information Supervision Calculation
Resetting of Control
Automatic Energizing Status Parameter setting
testing of contacts indications
Change of monitoring
Reporting Status check parameters Sequential Evaluation
Back-up control Control
Simulation Directional Statistics Expert
check analysis
Bay Protection and Control Units
• Integrated approach
• Platform concept
• Flexible functionality
selection
Any device incorporating one or more processors with the capability to receive or send data/control
from or to an external source. (Example- Multifunction meters, Numerical relays and controllers)
Examples / problems
For the radial power system shown in Figure 1, below calculate the line-to-ground fault current flowing in each of the
circuit breakers for faults at each of the buses. The system data are given in the accompanying table. Also determine
the corresponding faulted phase voltage, assuming that the generator is ideal, with a terminal voltage of 1.0 pu.
From To Positive sequence Zero sequence impedance
1 2 0.01 + j0.05 0.02 + j0.13
2 3 0.003 + j0.04 0.01 + j0.16
3 4 0.008 + j0.04 0.04 + j0.15
4 5 0.01 + j0.05 0.03 + j0.15
5 6 0.003 + j0.02 0.01 + j0.06
Figure 1
In a single loop distribution system shown in Figure 2, determine the fault currents flowing in circuit breakers B1, B2
and B3 for a b–c fault at F. What are the corresponding phaseto-phase voltages at those locations? Consider the
generator to be of infinite short-circuit capacity, and with a voltage of 1.0 pu. Consider two alternatives: (a) both
transformers T1 and T2 in service and (b) one of the two transformers out of service. The system data are given in
the accompanying table.
Examples / problems
From To Positive sequence impedance
1 2 0.0 + j0.01(T1)
0.0 + j0.01(T2)
2 3 0.0 + j0.08
3 4 0.02 + j0.05
4 5 0.01 + j0.03
5 6 0.0 + j0.06
6 7 0.01 + j0.09
2 7 0.01 + j0.09
Figure 2
Broadly list out benefits of Numerical protection systems
Figure 1 Figure 2
Examples / problems
For the system shown in Figure below, the following circuit
breakers are known to operate: (a) B1 and B2; (b) B3, B4, B1, B5
and B7; (c) B7 and B8; (d) B1, B3, B5 and B7. Assuming that all
primary protection has worked correctly, where is the fault located
in each of these cases?