Cem Unit-1
Cem Unit-1
Construction engineering
and Management - UNIT-1
Contents
Need of construction management
Objectives
Elements of project management
Construction in India
Unique Features of construction project
Types of construction projects
Stages in construction
agencies involved and their methods of execution
Project Delivery Methods
Construction Team. Organisation – principles and types.
Why Project management
Almost every industry worries about how to manage similar large-scale,
complicated projects effectively Large, often one-time, projects are difficult
challenges to operations managers.
The stakes are high.
Millions in cost overruns have been wasted due to poor planning on
projects.
Unnecessary delays have occurred due to poor scheduling.
companies have gone bankrupt due to poor controls.
As project organisations are set up to handle such jobs and are often, disabled
when the project is complete.
Looks so simple! Yet, research shows that less than 20 per cent of most
construction projects meet the four requirements mentioned above.
Planning
Scheduling
Controlling
Unique Features of a
Construction Project
One-time activity—it must be performed correctly the first time every time
Untrained workforce
Construction in India
Post Independence, a number of notable construction projects have been
undertaken, namely construction of the first nuclear reactor in 1956;
Construction of Hirakud Darn in 1957
Bhakra-Nangal Dam in 1970
Idukki Darn in 1976
construction of Mumbai Pune Expressway in 2000
Tehri Dam in 2005
The construction related to defence is undertaken Military Engineering
Services
BRO (1963) - undertakes the expansion and maintenance of road networks in
border areas;
NHAI(1988) - undertakes the development, maintenance and management of
national highways;
Indian Railways - undertakes the construction and maintenance of rail
network in India.
Central Water Commission - Irrigation projects
Construction in India is the second largest industry next to
agriculture, and it provides employment to about 33 million people.
It constitutes about 5 to 6 per cent of gross domestic product (GDP) and is vital
for the growth of the overall economy.
Classification of construction
projects
Different classification is done based on following factors
(a) Cost of construction
(b) Based on Life requirement and Nature of work –
Based on Life requirement - Permanent, Semi-permanent, Temporary
Based on Nature - Original, Repair, Rehabilitation
(c) Based on the type of structural members and equipment used
Light, Heavy, Industrial
Types of Construction Projects
Projects may be widely varying from one another in their concepts,
targets and sizes. There are hundreds of different projects of diverse
nature and size. Construction projects may be classified depending
upon the type of construction, as under:
Buildings. Residential, office, apartment blocks, educational
institutions, marketing complexes, recreation centres, hospitals,
hotels, factories, utility buildings etc.
Industrial structures., Industrial structures supporting machinery,
equipment, plant and material handling structures.
Tall structures. Cooling towers, chimney, transmission towers, silos,
overhead tanks etc.
Hydraulic structures. Dams, canals, barrages etc.
Power Plants. Structures for hydropower, thermal power, nuclear
power plants.
Special structures. Structures for off-shore platforms, space
research stations etc.
Cont.
Highways, bridges, tunnels.
Airports and runways.
Railway network.
Sewerage and water treatment plants.
Land Development works.
Marine structures, harbours etc.
Oil/gas pipe lines and transmission lines.
Features of Construction Project
Characteristics of Construction Project
Each project is comprised of series of intermediate activities consuming resources and time.
Each project is unique in itself, which means no two projects are absolutely similar with
Each project has a fixed set of objectives. Once the objectives have been achieved, the
A project cycle consists of: project preparation, implementation and operation phases.
A project is dynamic in nature and is subjected to many changes during its life span.
Every project has many constraints in terms of availability of resources and completion of
time.
Every project has large number activities and they need coordination.
Construction projects generally employ high value and huge resources of men, materials
Parameters of Construction Projects
Following are the major parameters for any construction project :
Size. It denotes the number of tasks to be executed in a project, and each task is measured in terms of quantities of work
involved.
Complexity. It is a measure of variety in the nature of tasks to be executed. A project is said to be simple where the tasks
Cost. It is the estimate of expenditure to be incurred for completion of the project, which the client has agreed to commit.
Completion time. It indicates the speed with which the project is to be executed.
Capacity. The capacity of a project indicates the demand which can be met from the project during its operation after its
completion.
Objectives of Construction Projects
The project should be completed in minimum duration, so as to start getting benefits at an earliest.
Project should be completed with minimum capital in-vestment for getting maximum benefits for maximum
duration
Build new projects in order to satisfy demand during their operation after completion.
Construction project should meet the constraints like quality, time, cost and environment.
Resources required for the construction project
Human resources
Material
Equipment
Capital/Funds
Phases of a Construction Project
A construction project also passes through different phases in its life cycle. The term
'phases; 'stages' and 'steps' are used interchangeably in project management literature and,
accordingly.
The phases can be defined as the top-level breakdown; of an •entity, and a construction
project is distinctly characterized by a number of phases or stages during its life cycle,
though there may be some overlaps between the characteristics of two phases.
Considering the definition of construction project as unique, it is really very difficult to
identify some common stages across all the construction projects, since depending on the
type of project, the type of organization and other parameters, the phases as well as the
tasks performed in each of the phases may vary.
For example, some of the stages in a technical project such as a petroleum refinery
project or a chemical project would be different from that of a building construction
project.
Researchers and practitioners do not adopt a common nomenclature to distinguish
different phases of a project. Thus, there is no single standard nomenclature available to
describe the different phases of a construction project.
Different project phases under three broad categories—
Pre-ProjectPhase
Project Phase
Post-Project phase
Pre-Project phase
Initiation phase
Project concept phase
Feasibility phase
Conceptual
project strategy
Estimate
Approval
Initiation or idea phase The pre-project phase aims to identify all
possible projects based on the examination of needs and the possible
options.
This stage is also sometimes referred to as initiation phase or idea
phase.
A possible example would be a municipal authority concerned with the
growing parking problems near a prominent city milestone. The
municipal authority may explore different options to address the parking
problem.
The options shall be evaluated against the mission and vision of the
municipal authority and the limits to which funding is available with the
municipal agency.
Project concepts
The initiation phase aims to sort out all the mentioned information to identify
some project concepts.
As many project concepts as possible are identified, and using some selection
procedure (such as the benefits for the organization that intends to employ
them) in line with the objectives of the organization, several project concepts
are selected.
The project concept phase of a new construction project is most important, since
decisions taken in this phase tend to have a significant impact on the final cost.
It is also the phase at which the greatest degree of uncertainty about the future
is encountered. The selected project concepts, then, are used as the inputs for
the feasibility phase.
Feasibility
This phase aims to analytically appraise project concepts in the context of the
organization, taking into consideration factors such as the needs of the
organization, the strategic charter of the organization, and the capabilities and
know-how of the organization. With this information, the decision maker should
be able to decide whether or not to go ahead with the project concept proposed.
The feasibility phase can be broadly characterized into the following:
Conceptual For the selected project concepts, the preliminary process diagrams and layouts are prepared.
Design basis or design briefs are also formulated. Project strategy The strategy in terms of selection of an in-
house design team or the contractor's design team is deliberated upon. The resources required and their
availability is discussed.
Further, the number and type of contractors required for the execution of project is also formulated. Besides all
these, the project strategy also contains the overall project schedule, the project scope and the overall project
plan. Estimate A preliminary estimate is prepared with reasonable accuracy by first breaking down the project
into work packages/elements.
The estimates may be prepared for each of the work packages using the established historical database and the
resources estimated for each of the work packages.
Approval Approval consists of financial evaluation, identifying details of funding and their timing, capital/
revenue, etc., besides evaluation of different options.
The feasibility phase has sub-phases such as
market feasibility analysis.(to confirm the viability of the project concept from a purely
marketing point of view),
technical feasibility analysis (to demonstrate whether the project is technically feasible and
to estimate the cost of project concept),
environmental analysis (to ensure that the project does not go against ecological issues and
regulations), and
financial feasibility analysis (to establish whether the project once materialized would
generate profits for the organization).
It is only after the first three sub-phases are found to be positive that a financial feasibility
analysis is performed.
If the feasibility analysis is positive, one can go ahead, but if it is negative, the project can
be abandoned and eliminated from the 'project concept' definition.
The feasibility phase is terminated when a decision maker decides to transform the project
concept into a project. At this point, in the case of a plant, the capacity is decided, the
locations are chosen, the financing is agreed upon, the overall budget and schedule
determined, and a preliminary organization is established.
Cont.
Some of the tasks related to pre-project phase are
summarized below:
1. Assigning a task force to conduct preliminary studies for the
proposed project
2. Studying the users requirements
3. Defining the technical specifications and conditions that determine
the quality of the required work
4. Studying how to secure funds to finance the project
5. Estimation of the project cost and duration
6. Approval of the project cost
7. Studying and determining the technical specifications of the
materials
8. Studying the impact of the project on the safety and health of the
community and environment
9. Establishing criteria for the selection of project location
10. Advising members of the task force (consultant, engineering,
etc.) on the approved funds for the project Establishment of
milestones for the project for review and approval
12. Describing the responsibilities and authority of project parties
13. Pre-establishing a system to prepare for 'change order'
procedures
14. Establishment of design criteria for structural specifications
15. Conducting a feasibility study of the proposed project
Project phase
(1) Architect: The role of the architect is to assess the client's functional requirements,
design for pleasing and aesthetic appearance and to assist the engineers for proper
design.
(ii) Structural Engineer: The role of the structural engineer is to prepare structural
design of structures and to prepare the working drawings based on the architect's plans.
(iii) Mechanical Engineer: The role of the Mechanical Engineer is mainly concerned with
design and preparation of working drawings for heating, venti-lating, air conditioning and
other mechanical services associated with the construction project activities during and
after construction.
(iv) Electrical Engineer: The Electrical Engineer is concerned with the design and
preparation of working drawings for electrical power and distri-bution systems during and
after construction.
(v) Quantity Surveyors: The role of the quantity surveyors is to: (a) estimate the cost of
work to be done and actually carried out; (b) prepare the bill of quantities and tender
documents before tendering; (c) assess the extra costs due to special features; (d) prepare
the cash-flow statements during construction; (e) prepare the final account on completion
of the project. (vi) Specialists/Consultants*: They carry out soil investigations and
collect information regarding special requirements for items such as health, safety,
workshop equipment etc. They also suggest solutions to specific problems encountered
Cont.
Contractor The contractor may be an individual undertaking small
contracts or a large construction company undertaking turn-key
projects. Contractors whether small or big need the services of
qualified engineers. Some of the engineers employed by the
contractor deal with office work such as designing, tendering,
scheduling etc. in the head office. Others, known as site engineers,
are concerned with the actual execution of work such as surveying,
levelling, construction, billing etc. In some projects, the contractor
may sublet part of the work to sub-contractors or petty contractors.
This is done because a contractor may not have the required
infrastructure for certain works. The contractor has to execute various
types of works and has to make all necessary arrangements for
labour, machinery, materials, power connection etc. in order to
complete the project within stipulated time and cost.
Organisation-Principles
An organisation is a group of persons working together to achieve an established goal.
It is the relationship which exists between people taking part in a group activity.
It defines the responsibilities and authority of individuals in relation to men, materials,
money and machinery which constitute the resources of an organisation.
An organisation is needed because a manager at any level can effectively manage the
functions of only a limited number of persons working directly under him.
The setting up of a suitable organisation for various civil engineering works is all the
more necessary because the construction industry is a competitive field of endeavour
which is susceptible to many risks, variable labour conditions and diverse construction
problems.
In order to be effective, an organisation has to follow certain basic principles given
below:
(i) Principle of Objectives: The organisational objectives should be clearly defined. The
structure of the organisation should be geared to achieve these objectives at minimum
cost and effort.
(ii) The Scalar Principle: An organisational structure consists of different levels of
authority arranged in a hierarchical manner. The line of authority should be clearly
defined from the chief executive at the top to the first line supervisor at the bottom.
This is known as scalar principle. The importance of scalar principle lies in the fact that
the understanding of authority relationships within an organisation becomes easier. It
Cont.
(iii) Principle of Balance Between Authority and Responsibility: In order
to perform work properly, it is essential that every one knows his duty,
responsibility and authority or powers. Authority means right to act,
decide and command. The delegate will not be able to perform his task
properly unless he is given necessary powers (i.e. authority). So,
whenever a task is assigned to a person, he must be given sufficient
powers to exercise control in order to achieve desired objectives.
Responsibility is the obligation of a subordinate to perform any job
allotted to him by his superiors. A person, who is assigned responsibility
to do a certain job, must be given appropriate authority to achieve the
same. Thus, authority and responsibility go hand in hand and must be
balanced rationally to produce best results. For example, if a civil
engineer in a construction firm is asked to carry out construction of
different structures, and is not given corresponding authority to procure
the various resources, responsibility given to the civil engineer would be
illogical and unbalanced.
Cont.
(iv) Principle of Unity of Command: Each person in an organisation mum know
to whom he has to report and from whom he should receive orders. He should
also know the persons both upwards and downwards whom he is to consult.
The principle that each subordinate should report to only one superior is
called the 'Unity of Command'. This not only avoids confusion but also helps in
maintaining a definite line of command. In order to avoid indiscipline, delay,
disorder and undermining of authority, a subordinate should receive orders
from only one superior and not from a number of superiors.
v) Principle of Span of Control: According to this principle, there is a limit to
the number of subordinates an executive can effectively supervise. There are
many factors on which the span of control depends, such as the type of work,
whether routine or repetitive, level in the organisation, type of problems
encountered and abilities of the persons involved. The optimum span of
control varies from person to person and job to job. Sometimes the number
six is taken as the effective span of control.
(vi) Principle of Departmentation: Departmentation means the division of an
organisation into several distinct departments or sections. This helps in
increasing the efficiency and facilitates the execution of work. In order to
obtain optimum results, the functions and scope of each department must be
dearly defined.
(vii) Principle of Specialisation: According to this principle, activities oi the
organisation should be grouped as per the functions and assigned to
individuals according to their specialisation.
(viii) Principle of Communication: The number of supervisory levels in .a:
organisation must be kept as small as possible. This helps in shortening the of
communication for passing on information, instructions and suggestion, from
the chief executive level to the first line supervisor. The temptation to go too
far in either direction (i.e. horizontal and vertical) means increased lines of
communication which may result in lower overall efficiency and profit.
(ix) Principle of Flexibility and Stability: Flexibility and stability in an
organisation are closely inter-related. On the one hand, an organisation should
be flexible enough to assess the changes which often become necessary
because of internal and external situations. While on the other hand, the
organisation must be stable enough to withstand any organisational change
which becomes necessary for the accomplishment of its objectives.
(x) Principle of Motivation and professional Growth: The
organisational structure should be such that it provides enough
opportunities to its personnel for their professional growth and
upward or lateral mobility. Job roles should be such that each member
of an organisation achieves professional satisfaction and is motivated
towards loyalty for the organisation.
(xi) Principle of Continuity: The organisational structure should be
dynamic so that it not only provides for the activities necessary to
achieve its objectives but also for the continuation of such activities
in the future. This maintains a link between the past and the future.
COMMUNICATION, LEADERSHIP AND HUMAN
RELATIONS (Beyond Syllabus)