lec4 (2)
lec4 (2)
three-step process:
Step 1: Estimate System Size
project manager estimates the size of the
project in terms of the number of lines of
code the new system will require.
Or complete
2-7
(cont’d)
• The staffing plan describes the kinds of people working on the project
For example, if the first phase was completed 10% over schedule, increase the
rest of your estimates by 10%.
© Copyright 2011 John Wiley & Sons, Inc. 2-18
Managing Scope
• Scope creep – Scope creep happens when new requirements are
added to the project after the original project scope was defined
and “frozen.”
• Reasons for scope creep:
Users may suddenly understand the potential of the new system
and realize new functionality that would be useful;