unit 4 SPM
unit 4 SPM
FORMAL INFORMAL
1. Purpose:
1. To provide a snapshot(short description) of progress.
2. To inform stakeholders (clients, managers, team members) about how much work is completed
and what remains.
2. Includes:
Percentage of task completed.
Milestones achieved so far.
Resources used versus planned.
Challenges or delays faced.
Estimated completion time.
3. Uses:
1. Helps in performance tracking and project monitoring.
2. Facilitates timely decision-making.
3. Enables corrective actions if a project is off track.
Reporting Risk
Risk reporting uses a traffic light method concept and consists of
the following steps:
1. Identify the first level elements for assessment
2. Break the first level elements into second level elements.
3. Assess the second level elements and mark the color as
Green – on target
Amber – not on target but recoverable
Red – not on target and difficult to recover
4. Review all the second level assessments to arrive at first level
assessments
5. Review first and second level assessments to produce an overall
assessment
This method only focuses on non-achievement factors and do not
mention about any delay in the development process.
Assessment forms can be used to evaluate the overall status of the
project.
Critical activities denoted by red color must be reconsidered during
the revision of project schedule.
VISUALIZING PROGRESS
• A manager needs some way of presenting that data to the greatest
effect.
• It has to be shown visually so that everybody involved in the project
work is pleased about its progress.
• Presenting project effectively plays a vital role.
Categories of Visualizing
Progress
The techniques that are used in visualizing project progress are:
• Gantt chart
• Slip Chart
• Ball Chart
• Timeline Chart
1.The Gantt Chart
• Gantt chart is a type of a bar chart that is used for illustrating project
schedules.
• Gantt charts can be used in any projects that involve effort, resources,
milestones and deliveries.
• Through Gantt charts, the project manager can keep a track of the
individual tasks as well as of the overall project progression.
• The simplest kind of Gantt chart can be created using a software tool
such as Microsoft Excel.
Advantages
• The ability to grasp the overall status of a project and its tasks at
once is the key advantage
• Informed decisions can be made just by looking at it.
• The software-based Gantt charts are able to show the task
dependencies in a project schedule. This helps to identify and
maintain the critical path of a project schedule.
Disadvantage
• For large projects, the Gantt chart tool should be supported by other
means of documentation.
• The information displayed in Gantt charts may not be sufficient for
decision making.
Timeline Chart
• Timeline usually records and displays the target changes during the
project life cycle.
• The chart represents the planned time along the horizontal axis and
the actual time along the vertical axis.
• A line down the horizontal axis represents the scheduled activity
completion dates and the slip in the line indicates a delay in the
respective activities.
• This timeline chart is used to calculate the duration of execution of
the project as a part of post-implementation review.
Cost Monitoring
1. 0/100 technique: Task value is assigned zero till completion and the
budgeted value is 100%.
2. 50/50 technique : Task value is assigned 50% and then increased to
100% once it completes.
3. Milestone technique : Task is assigned a value based on the
achievement of milestones as part of original plan.
Out of all these method, the 0/100 technique is used because the
other techniques are not suitable for longer duration cost
estimation.
Baseline Budgets
• For earned value analysis, the first step is to create a baseline budget.
• It shows the forecast growth of the project plan in earned value with
respect to time.
• Common ways of measuring earned value in software development
process is persons- hours or work-days.
• The figure depicts the scheduled completion of all activities involved
in the development of the project.
Monitoring earned value
• EVM consists of the following three basic elements:
1. Planned Value
2. Actual Cost
3. Earned Value
All the three elements are captured on a regular basis as of a reporting
date.
Indicators for earned value analysis
1. Planned value (PV): denotes the assigned value is the original budgeted cost
for the item. It is known as budgeted cost of work scheduled (BCWS).
2. Earned value (EV): denotes the total value credited to a project at any
point. It is known as budgeted cost of work performed (BCWP).
3. Actual cost (AC): The total cost taken to complete the work as of a reporting
date.
4. Schedule variance (SV): indicates the degree to which the value of
completed work differs from that planned.
Schedule variance (SV) = EV - PV
• A negative schedule variance (SV) calculated at a given point in time means
the project is behind schedule
5. Cost variance (CV):- important factor to measure project
performance. CV indicates how much over or under-budget the project
is .
Cost variance (CV) = EV - AC
• A negative cost variance (CV) means the project is over budget
6. Performance ratios:- Two ratios are commonly tracked:
a) Cost performance index (CPl =EV/AC)
b) Schedule performance index (SPl = EV/PV).
7. For Forecasting EAC (Estimated Time at completion)=BAC/CPI.
Prioritizing Monitoring
The list of priorities defined in the level of monitoring are:
1. Critical path activities: denote those activities in the critical path that are delayed in
project completion date.
2. Activities with no free float: These delayed activities will have a delay in subsequent
ones but still stick on target. These activities can have a serious effect on the
resource schedule because the subsequent activities have to wait for its completion.
3. Activities with less than a specified float: If there is a very little float in the activity
say less than one week, these activities must be monitored very closely.
4. High risk activities: These high risks are identified in the risk management plan itself
and results in over spending.
5. Activities using critical resources: Critical activities are very expensive and are
available only for a limited period and hence require high level of monitoring.