I-10 Calcasieu Bridge
RISING FOR A NEW I-10 BRIDGE
HISTORY
 Built in 1952 under governorship of Earl K. Long
 135 foot high span
 In 2009, the National Bridge Inventory (NBI)
denotes the bridge is “basically intolerable
requiring high priority of corrective action”; LDOTD
disputes saying it is safe
 Environmental Impact Study underway since March
2012 – currently delayed to mid 2017 due to
Navigational Use Study
 No design to date
 Approximately 53,000 vehicles per day
 Crossed pistols represent Jean Lafitte / cherished
by preservation organizations & community
THE PROBLEMS
 THE BRIDGE IS NOT SAFE!
• Reduction of lanes
• No place to pull over
• Steep roadway grades slowing traffic
• Low vertical clearance
 Declining capacity and increased congestion
in all directions
 Lack of connectivity and continuity on I-10
 Inadequate road limit
 Lack of shoulders and vertical geometry
 Traffic increasing in all directions!
 SWLA has an infrastructure problem that
needs solving!
I-210 BRIDGE CONSTRUCTION
(2-year project)
INCREASED CONGESTION
DELAYED I-10 BRIDGE
PROJECT
WHAT NEW BRIDGE???
FACTS
 I-10 is a problem
 Environmental Impact Statement (EIS) has been
delayed – Now due in Mid 2017
 Traffic volume is already increasing – expected 72,000
vpd from current 53,000 vpd by 2025
 Southwest Louisiana is growing and congestion will
continue
 Southwest Louisiana is the ENERGY CAPITAL OF THE
SOUTH
 Not a statewide “top of mind” -- other Louisiana
State highway projects are receiving priority
 Infrastructure improvements are IMMINENT
LDOTD’s Plan
What the LDOTD is saying. . .
MISSION
 Build a unified coalition that proactively:
• Generates urgency to fast track and rebuild I-10 Bridge
• Creates value for a new I-10 Bridge
• Clears environmental problems
• Addresses safety concerns
• Identifies funding
• Manages preservation and environmental groups
• Reinforces agency coordination to move forward
GOVERNMENT
BUSINESS
CITIZENS
GRASSROOTS COALITION
 ARE YOU IN FOR 10???
 Build a unified coalition of stakeholders from SW Louisiana, SE
Texas and other areas in Louisiana
 Elected officials from SW Louisiana, SE Texas and other parts of
Louisiana working together in support of I-10 Bridge Project
• Parish Governments
• Cities/Municipalities
• U.S. Congressional Representatives
• LA State Police
• Governor & State Officials
• Parish Officials
• Agencies
 Proactively drive support
GRASSROOTS CAMPAIGN
MOVING FORWARD. . .
CREATE URGENCY and SUPPORT
 Clear Environmental Issues
 Research and Secure Funding Options
 Design Approval and Completion
 Stakeholder Support
CLEAR
ENVIRONMENTAL
ISSUES
BRIDGE DESIGN
STATEWIDE
STAKEHOLDER
SUPPORT
SECURE
FUNDING

More Related Content

PPTX
Future of London 2018 Conference (morning keynote & panels)
PPT
Mayor's - slides - Sustainable suburbia forum April 2011
PPT
Powerpoint400
PPT
Bases solides - Strong Foundations
PPT
Jeremy liu 社會住宅國際研討會2
PPT
Westminster's Digital inclusion framework
PPTX
Jo Oxlade Ambition
PPT
Jane Parfitt - Managing Assistance: Experiences from Christchurch: A Snapshot
Future of London 2018 Conference (morning keynote & panels)
Mayor's - slides - Sustainable suburbia forum April 2011
Powerpoint400
Bases solides - Strong Foundations
Jeremy liu 社會住宅國際研討會2
Westminster's Digital inclusion framework
Jo Oxlade Ambition
Jane Parfitt - Managing Assistance: Experiences from Christchurch: A Snapshot

Similar to I-10 Calcasieu River Bridge Project (20)

PDF
Move2059 Vestavia Rotary
PPTX
Big Impact Small Communities
PPSX
Flint Water Crisis Presentation
PDF
SB 743 Legislative Intent, versus CEQA Practice
PDF
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
PPTX
Houbolt Road Bridge A Landmark of Modern Infrastructure in Illinois.pptx
PPT
Gov. Culver: I-JOBS presentation
PDF
2020 Annual Report - Menomonee Valley Partners
PDF
Menomonee Valley Partners 2020 Annual Report
PPT
Splost Presentation 2008
PPT
Splost Projects
PPT
State and Local Road Project Updates: Part 3
PPT
Nj future redevelopment forum 2014 plenary baudouin
PDF
Governor's Transportation Summit - Municipal Highway Infrastructure Overview
PDF
Charlotte Capital Improvement Program Proposal
PDF
Why Community Matters - GSMSummit 2014, Noelle MacKay
PDF
"News and Views" newsletter
PPTX
Vancouver's Low Level Road - First Envision Platinum Project
PPT
Brad_Jones.ppt
PDF
2014-IrishtownGreenway-Final-WEB-LOWRES
Move2059 Vestavia Rotary
Big Impact Small Communities
Flint Water Crisis Presentation
SB 743 Legislative Intent, versus CEQA Practice
Presentation_to_PMI-Calumet_Northwestern_Indiana_Region
Houbolt Road Bridge A Landmark of Modern Infrastructure in Illinois.pptx
Gov. Culver: I-JOBS presentation
2020 Annual Report - Menomonee Valley Partners
Menomonee Valley Partners 2020 Annual Report
Splost Presentation 2008
Splost Projects
State and Local Road Project Updates: Part 3
Nj future redevelopment forum 2014 plenary baudouin
Governor's Transportation Summit - Municipal Highway Infrastructure Overview
Charlotte Capital Improvement Program Proposal
Why Community Matters - GSMSummit 2014, Noelle MacKay
"News and Views" newsletter
Vancouver's Low Level Road - First Envision Platinum Project
Brad_Jones.ppt
2014-IrishtownGreenway-Final-WEB-LOWRES
Ad

Recently uploaded (20)

PDF
BRAZIL NEEDS TO OVERCOME ITS EXTERNAL DEPENDENCE TO EXERCISE ITS SOVEREIGNTY.pdf
PPTX
British Colonialism in the Subcontinent.pptx
PDF
The Blogs_ Israel's Doctrine of Deterrence and Survival _ Andy Blumenthal _ T...
PPTX
Thailand Fashion Week 2025 Set to Ignite Bangkok with Daring Spring-Summer 20...
PDF
Public Attention on IRB System Problems: Key Trigger Explained
PPTX
Haitian Revolution presentation 1804 YO Z
PDF
30082025_First India Newspaper Jaipur.pdf
PPTX
Political ideologies ann their values and characteristics
PPTX
political economy meaning and importance.pptx
PDF
GAZA STRIP: Famine confirmed in Gaza Governorate, projected to expand
PDF
ORIGIN-HISTORY-METAPHORS-OF-GLOBALIZATION.pdf
PPTX
Thai Women Hosts Redefine Hospitality as Empowerment.
PPTX
Thailand and India Shine at PATA Travel Mart 2025 in Bangkok.
DOC
办理UofM毕业证学历认证,克莱顿州立大学毕业证国外硕士毕业证
DOC
买USF毕业证学历认证,卡罗大学毕业证本科/硕士学位
DOC
哪里买MCAD毕业证学历认证,加利福尼亚州立理工大学洪堡分校毕业证成绩单图片
PPTX
Challenges, strengths and prospects of Pakistan in.pptx
DOCX
Coinography: Breaking Down the Latest Cryptocurrency and Bitcoin News
PPTX
British Colonialism in the Subcontinent.pptx
PDF
Beyond the Buzz: Consumer Tech and Lifestyle Innovations
BRAZIL NEEDS TO OVERCOME ITS EXTERNAL DEPENDENCE TO EXERCISE ITS SOVEREIGNTY.pdf
British Colonialism in the Subcontinent.pptx
The Blogs_ Israel's Doctrine of Deterrence and Survival _ Andy Blumenthal _ T...
Thailand Fashion Week 2025 Set to Ignite Bangkok with Daring Spring-Summer 20...
Public Attention on IRB System Problems: Key Trigger Explained
Haitian Revolution presentation 1804 YO Z
30082025_First India Newspaper Jaipur.pdf
Political ideologies ann their values and characteristics
political economy meaning and importance.pptx
GAZA STRIP: Famine confirmed in Gaza Governorate, projected to expand
ORIGIN-HISTORY-METAPHORS-OF-GLOBALIZATION.pdf
Thai Women Hosts Redefine Hospitality as Empowerment.
Thailand and India Shine at PATA Travel Mart 2025 in Bangkok.
办理UofM毕业证学历认证,克莱顿州立大学毕业证国外硕士毕业证
买USF毕业证学历认证,卡罗大学毕业证本科/硕士学位
哪里买MCAD毕业证学历认证,加利福尼亚州立理工大学洪堡分校毕业证成绩单图片
Challenges, strengths and prospects of Pakistan in.pptx
Coinography: Breaking Down the Latest Cryptocurrency and Bitcoin News
British Colonialism in the Subcontinent.pptx
Beyond the Buzz: Consumer Tech and Lifestyle Innovations
Ad

I-10 Calcasieu River Bridge Project

  • 1. I-10 Calcasieu Bridge RISING FOR A NEW I-10 BRIDGE
  • 2. HISTORY  Built in 1952 under governorship of Earl K. Long  135 foot high span  In 2009, the National Bridge Inventory (NBI) denotes the bridge is “basically intolerable requiring high priority of corrective action”; LDOTD disputes saying it is safe  Environmental Impact Study underway since March 2012 – currently delayed to mid 2017 due to Navigational Use Study  No design to date  Approximately 53,000 vehicles per day  Crossed pistols represent Jean Lafitte / cherished by preservation organizations & community
  • 3. THE PROBLEMS  THE BRIDGE IS NOT SAFE! • Reduction of lanes • No place to pull over • Steep roadway grades slowing traffic • Low vertical clearance  Declining capacity and increased congestion in all directions  Lack of connectivity and continuity on I-10  Inadequate road limit  Lack of shoulders and vertical geometry  Traffic increasing in all directions!  SWLA has an infrastructure problem that needs solving!
  • 4. I-210 BRIDGE CONSTRUCTION (2-year project) INCREASED CONGESTION DELAYED I-10 BRIDGE PROJECT
  • 6. FACTS  I-10 is a problem  Environmental Impact Statement (EIS) has been delayed – Now due in Mid 2017  Traffic volume is already increasing – expected 72,000 vpd from current 53,000 vpd by 2025  Southwest Louisiana is growing and congestion will continue  Southwest Louisiana is the ENERGY CAPITAL OF THE SOUTH  Not a statewide “top of mind” -- other Louisiana State highway projects are receiving priority  Infrastructure improvements are IMMINENT
  • 8. What the LDOTD is saying. . .
  • 9. MISSION  Build a unified coalition that proactively: • Generates urgency to fast track and rebuild I-10 Bridge • Creates value for a new I-10 Bridge • Clears environmental problems • Addresses safety concerns • Identifies funding • Manages preservation and environmental groups • Reinforces agency coordination to move forward GOVERNMENT BUSINESS CITIZENS
  • 10. GRASSROOTS COALITION  ARE YOU IN FOR 10???  Build a unified coalition of stakeholders from SW Louisiana, SE Texas and other areas in Louisiana
  • 11.  Elected officials from SW Louisiana, SE Texas and other parts of Louisiana working together in support of I-10 Bridge Project • Parish Governments • Cities/Municipalities • U.S. Congressional Representatives • LA State Police • Governor & State Officials • Parish Officials • Agencies  Proactively drive support GRASSROOTS CAMPAIGN
  • 12. MOVING FORWARD. . . CREATE URGENCY and SUPPORT  Clear Environmental Issues  Research and Secure Funding Options  Design Approval and Completion  Stakeholder Support CLEAR ENVIRONMENTAL ISSUES BRIDGE DESIGN STATEWIDE STAKEHOLDER SUPPORT SECURE FUNDING

Editor's Notes

  • #2: “In for 10” is a campaign sponsored by the Southwest Louisiana Alliance to influence public opinion by building a grassroots coalition generating urgency and need for a new I-10 bridge for Southwest Louisiana. The “In for 10” coalition will proactively: Generate urgency to fast track and rebuild the I-10 bridge Communicate need for a new I-10 bridge Clear environmental and litigation hurdles Address safety concerns Identify funding Manage preservation and environmental groups Reinforce agency coordination to move forward
  • #6: Bridge Timeline
  • #7: Environmental Impact Statement has been underway since March 14, 2012. Study includes an Interchange Justification Report. Report was slowed due to Navigational Use Study. Study was to be complete and finalized with Record of Decision (ROD) by March 2016 I—49 Geaux South coalition is moving faster and getting more attention – more expensive than I-10 Bridge Project $97 billion in announced petrochemical industry expansion
  • #9: I-10 Calcasieu River Bridge Maintenance Project Project Details State Proj. No.: H.006783 Cost: $5.7 million Contractor: Topcor Services Map ItThis maintenance and repair project on the Interstate 10 Calcasieu River will repair many aspects of the bridge including repairing and resealing joints on the road surface, removing rust, repainting, replacing damaged rivets with bolts, and repairing portions of hand rails. Crews will work on the bridge seven days a week and in some phases, crews will work around the clock. The contractor is required to maintain one lane of through and local traffic at all times, and shall conduct operations to cause the least possible interference with traffic. Lane closures will be only between 9 a.m. to 3 p.m. and 9 p.m. to 5 a.m. During one phase (approximately 45 days), there will be 24-hour-a-day closure of one lane in each direction. Motorists approaching Lake Charles on I-10 will be advised to take the I-210 Loop to avoid bridge construction.
  • #11: Public Relations & Community Outreach Strategic informational and education tools to key stakeholders community & business leaders will be developed: Communications Powerpoint Presentations Website & Social Media Giveaway Items External links (See PR & Community Outreach Plan)
  • #12: Personal Meetings Public Hearings & Open Houses Letter Writing Campaign Political Support Resolutions