EQUIPMENT CAPACITIES
CALCULATIONS IN PLANNING
-A.V.REDDY
• Estimates capacity (KW/HP) of machines,
Electric power, Power cost/ton of coal or
OB , For OCs Capacities of shovels
dumper combination, capital required for
Plant and machinery etc, of New
Projects to in corporate in Feasibility
Reports. (FRs)
• Estimates P&M for Revised Feasibility
Reports of projects.
• Estimates P&M requirement of completed
projects and on going projects.
Technology adopted
a) Hand section
b) Mechanised mining
a) Hand Section :
Equipment required :
Haulers (DH,EH), Pumps, Drill M/Cs, Main
mechanical ventilator, Auxiliary fans
connected Electricals
• Gradient (1:3.5 or 1:4) Approx= 57/gradient
• Weight to be pulled
Calculation :
Pull = Pull due to rope(w) + Pull due tubs(W)
(kgs)
Pull due to rope= Resistance against gradient (w)
+ Rope rolling resistance(f)
= w x Gradient (Sin O) + w/10
( w is weight/mtr of rope)
=w/3.5+ w/10 (10% weight of rope)
Pull due to tubs/(man riding cars)
= Resistance against gradient (W) + Rolling
resistance of tubs (F)
= W x Gradient + W/40 (W/20)
where W is the total weight of tubs
= W / 3.5 + W/40 (W/20)
Total Pull = w/3.5+w/10 +W / 3.5 + W/40
(W/20) Kgs
Based on pull, rope is selected.
Breaking load of rope as per IS 1570 =352 KN for
26 mm rope dia
Factor of safety =9
Breaking Load = 350 x1000/9.81 Kgs
=35678 Kgs
Safe load =35678/9
=3964 kgs
HP =Total Pull x speed(mps)/75
KW =Total pull x speed(mps)/102
Peripheral speed of rope= 3.14xN
xD/60x1000 m/sec D is Drum Dia, in mm
N is RPM
Total Length of Installation,L in mtrs. 2200
Max. Lift,H in mtrs 134
Distance between two chairs m 16
Max. Travelling Speed,V m/s 3
Man Riding Capacity,C Nos. 675
Weight of person,Mper
in kgs 80
Weight of Chair,Mchair
in kgs 13
Weight of Rope,Mrope
in kg/m 1.6
Drive&Return wheel Dia,D in mtrs 1.5
Power required to raise mass of persons,Ppers
in W
= C x H x 9.81 x 80/3600 = 675x133.52x9.81x80/3600 =19647 W
Power to overcome Frictions,PFriction
Line Friction,PFriction1
Chair Spacing ,X chair
in mtrs 16
Total Continuous Rope length,LRope
in mtrs
=2 x L + 3.14 x D = 2x 2200 + 3,14x1.5 = 4404.71
Total no. of chairs, X
=L rope / Chair spacing = 4404.71/16 = 275.29
Total no.of persons on one side only,Y =275/2 = 134
PFricion1
= 0.09((Lrope x Mrope) +( Y*Mper) +X * Mchairs)) V = 5304 W
Friction included by vertical&horizontal curve stations,
PFriction2
P Friction C=
K*(Ppers
+PFriction1
)
where K is a constant that increases with angle
of deflection
Angle of Deflection % Value of K
5°To10° 1 0.01
10°To20° 2 0.02
20°To30° 3.5 0.035
30°To40° 5 0.05
Three curve stations are there
Sl.No Horizontal Angle Vertical Angle
1 33° 2.34°
2 37° 2.04°
3 33° 1.00°
At 1st Station,PFrictionCH1
= 0.05 x (19647 +5304) = 1247.57 W
PFrictionCV1
= 0.01 x (19647 +5304) = 249.51
At2nd Station,PFrictionCH2
= 1247.57w
PFrictionCV2
= 249.51W
At3rd Station,PFrictionCH3
= 1247.57W
PFrictionCV3
= 249.51W
Total PFriction2
= 3 * (1247.57+249.51) =4491W
Friction induced by Return sheeve
Wheel,PFriction3
0.02x(Ppers
+PFriction1
+PFriction2
)
0.02x(19647.468+5304.0042+4491.
27)
=588.854844
Therefore ,PFriction
=(5304+4491+588)
= 10384.12904
Total Power at the Driving Wheel,P Ppers
+PFriction
Efficiency of the System 0.76
Therefore,Input Power 39515.25927
Taking5%extra,Required Power will be 41491.02223
Standard Available Power,KW 45
Rope Pull Calculation
Power at Driving Wheel
= 30 KW =30/0.746=40HP
HP=2NT / 4500
So, T=HPX4500 / 2N
= (40*4500*7)/ (2*22*19.1)
= 1499.286054
= 15kN
Power = QxHx Sp.gravity/75x Efficiency HP
= Qx Hx Sp.gravity/102 x Efficiency KW
Q = Ltr/sec
H = Head in mtrs
Sp.gravity = 1.03 gms/cc
one gallon =4.54 Ltrs
Generally GPM of pump is taken
Say 2250 LPM = 2250/4.54 = 495 GPM or
500 GPM
Generally in SCCL mines single, Double,
multistage centrifugal pumps are being
used for pumping water from under
ground to surface.
7.5 HP to 500 HP.
• Depending upon depth and sump capacity
pumps are deployed.
Air Power in KW =
Air Discharge (Cu.m/sec)x water gauge in
mm/ 102
Fan efficiency = Air power in KW / brake
shaft Power in KW
Brake shaft power = Transmission efficiency
x motor efficiency x Measured input power
in KW
Overall efficiency = Air power KW x100/
Measured power in KW
Auxiliary fans of 20 KW is deployed in
galleries where the flow is less than
requirement
High water gauge fans of 90 KW (200 to
500mm water gauge) are deployed in
Road header drivages.
In SCCL mines1 to 3 lakh CFT/min i.e
(3000 to 9000 Cu.m/min) are working with
blade angle 14 to 22 deg
For Adriyala shaft 15000Cu.m/min fan is
required.
Mechanised mining :
To increase the production and safety
mechanised mining is adopted with
following technologies.
a) Long wall :
Shearer is the deciding factor
1 Determine the mining rate, TPH
Assume
Cutting height,H mtrs 3.0
Web depth,D mtrs 1.0
Max. cutting speed,Vs mt/min 12.0
Coal density(solid), T/Cu.m 1.5
TPM= H*D*Vs
* T/min 54
TPH 3240
Drum Dia. mtrs 1.8
Web mtrs 1
Cutting speed, Vs mt/min 12.0
Density of coal (solid) T/m3
1.5
Q(Mining rate in tonnes per hour by one drum) TPH 1944
K is Specific energy consumption factor in HP-hr/Ton
Normally K is 0.5 for hard coal and 0.25-0.35 for soft coal
P(HP) = QK HP 972
There fore, for 3mtr extraction, the other drum requires only
a power of
(3-1.8)*1*12*1.5*0.5 HP 648
But, in practice, both drums will require equal power for bi-
directional
operation
KW 725.112
• (Assumed 1TPH=1KG)
• For 1000 TPH,
• S1 = 1000 Kg.
• S1 - Tension
• gc1 – Gravitational resistance on slack side (weight
component acting along the bottom for chain)
• gc2 - Gravitational resistance on tension side
• RC1 - Frictional resistance on slack side
• RC2 - Frictional resistance on tension side
• gc1 = qc x L x Sinø
• Where qc = Wt. of chain/mt.
• L = Length of chain in mt.
• Ø = Inclination
• RC1 = qc x L x fc x Cosø
• Where qc - Wt. of chain/mt.
• L - Length of chain in mt.
• fc - Frictional co-efficient of
chain with pan
• ~ 0.35 to 0.4 for
soft chain
• ~ 0.45 for shaking
& watering
• S2 = S1 + gc1 + RC1 or S1 + qcL (Sinø + fc
Cosø)
• (S1, S2 are in the opp. Direction)
• S3 > S2 and there will be some loss
• Thus S3 = 1.05 S2
• S4 = S3 – Gc2 + RC2
• Where
• gc2 = (qc x L x Sinø) + (qy x L x Sinø)
• RC2 = (qc x L x fc Cosø) + qy x L x fy x Cosø
• qy = Q/3.6V (Q = TPH, V = Velocity m/s)
• Fy = Frictional co-efficient of material conveyed
• 0.45 to 0.8 for dry soft coal,
• 0.8 for silica, rock etc, normally 0.7
• Now S4 = S3 – gc2 + RC2
• Or S4 = S3 – (qc L Sinø + qy L Sinø) + (qc L fc Cosø +
qy L fy Cosø)
• = S3 + qc L (fc Cosø – Sinø) + qy L (fy Cosø
– Sinø)
• Power (P) = (S4 – S1) KW
• 102
• Motor Power - P/h h = 0.8 to 0.9
Based on shearer capacity AFC,BSL, Gate
Belts, Trunk belts are designed.
The supports are designed by taking load
coming to supports / Sq.m area as per
finite element method.
The connected electricals are designed
basing on the above capacities
Power pack is designed on the design of
support load.
In SCCL Long wall technologies produced 4
to 7 lakhs per annum
BG technology the following equipment is
deployed
a) Jumbo Drills
b) LHDs
c) Hydraulic props
d) Power pack
SDL Low height are deployed in hand
section mines to increase productivity,
safety and decrease in man power
Based on production No. of LHD,SDL are
deployed
For CTX,811 Eimco LHDs annual
production = 50,000 T
For 912 Eimco LHDs = 60,000 T/ annum
For Low height SDLs = 45,000 T/ annum
Connected Electricals like GEBs, HT/LT
switches, transformers are calculated on
the No. of SDLs / LHDs deployed
a) Power to move load horizontally
=2.72 x L x F x (C+46)/1000 kW
b) Power to move empty belt
= 9.81 x F x G x (C+46) x S/1000 kW
c) Power to elevate load
=2.72 x L x H/1000 kW
Total Power P = (a) +( b) +(c)
Taking safety factor as 1.1 to 1.2 Total
power requirement is calculated
C = Centre distance in mtrs
F = Friction factor (0.03)
G = Inertia factor
H = Change in elevation in mtrs
L = Peak load in Tonnes/Hour
S = Belt speed in mtrs/sec
L= B x D x S/1000 Tonnes/Hr
L = Peak load
B =Belt capacity Factor
D = Material density Kg/Cu.m
S = Belt speed in mtrs/sec
• Selection of belt
T = K x P/S kN
P is power required, K = Belt Drive factor
S = speed mtrs/sec
= kN/1 m = kN/m Taking Factor of Safety as
10:1 for PVC F.S 7:1 for steel cordvalue from
table can be used for selection PVC/ Steel cord
Based on coal production, OB removal and
depth of the mine No. of shovels( Coal,
OB), Dumpers, RBH Drills (Coal, OB),
Dozers, Graders,Pumps and water
sprinklers and other common equipment
are calculated
Sl.No Particulars 3cu.mShovel
along with
35T Dumper
1 No. of Annual working days 330
2 No. of duty shifts 3
3 Duration of shift in Hr 8
4 Total No. of Annual shift hrs 7920
5 Annual utilisation of shift hrs 61%
6 Annual working hr 4831.2
7 Shovel bucket capacity (m3) 3
8 Material density - Tes/BCM 2.2
9 Swell Factor 0.732
10 Bucket fill factor 0.905
11 Swell cum fill factor 0.662
12 Material quantity per shovel bucket (T) 4.3722
13 Pay load capacity of dumper (T) 31.5
14 No. of passes per dumper load 7.204
15 No. of passes adopted 7
16 Adopted Pay load capacity of dumper (T) 30.605
17 Bucket cycle time (Minutes) 0.6
18 Loading time per dumper (Minutes) 4.2
19 Spotting time of dumper 0.5
20 Shovel time for loading dumper (Minutes) 4.7
21 Hourly shovel capacity Cum/hr 177.595
22 Factor for travelling positioning etc. 0.85
23 Annual shovel capacity (Cum) 729300
M.Cum 0.73
Sl.No DESCRIPTION 0.5
1 Shovel loading time for dumper ,min 4.70
2 Spotting for unloading ,min 0.5
3 Unloading time ,min 0.6
4 Travelling time ,up ,min 1.20
5 Travelling time, down, min 1.00
6 Dumper cycle time. min 8.00
7 Dumper waiting time 1.40
8 Cycle time adopted 9.40
9 No. of trips per hour 6.382979
10 Dumper utilisation hours 2376
12 No. of trips per annum 15165.96
13 Dumper capacity,Cu.m 14.43182
14 Corrected dumper capacity 14.03093
15 Annual Dumper capacity,M.cum 0.212793
16 Calculated capacity of shovel, M.cum 0.73
17 No.of Dumpers required per shovel 3.524559
18 Rounded no. 4
Assessment of volume of water to be
pumped
Q = A x H x Run off coefficient
A = Catchment area in Sq.m
H = Maximum daily precipitation in m
Run off coefficients
For mined out area = 0.60
Area beyond excavation =0.10
For internal dump area =0.15
Maximum capacity of pump is determined
on operating time 20 Hrs for 10 days i.e
200 Hrs as per CMPDI
In SCCL 20 Hrs for 6 days i.e 120 hrs
Add 10% seepage for attaining total make
up
Peak pumping capacity = /120
No of pumps is determined from above
depend on pump capacity Cu.m/Hr
For coal based on coal & OB No. of Drills is
calculated
Drilling pattern for coal = 5 x 5 x 6/5
Height of bench =5 m
Spacing =5 m
Burden =5 m
Volume of coal exposed/ mtr drilling =30 Cu.m
Annul working hrs =2112
Annual meterage = 42000
Volume of coal exposed by one drill =1.26 M.Cu.m
Drill employed =150mm
For OB 250mm RBH drills are used
Depending on OB removal/ year No. of drills
calculated
Drilling pattern =8 x 8 x 9/8
Volume of OB exposed /mtr of drilling =72 Cu.m
Annual working Hrs =2112
Annual meterage = 40000
Volume of OB exposed M.Cu.m = 2.88
Road Length to be graded, Km 17
Road Width to be graded, Mtr 20
Area to be Graded, Sq.mtrs 340000
Speed of the Grader ,Mtrs / Hr 6100
Blade Length ,Mtrs 4.32
Blade overlap ,Mtrs 0.3
Width of Graded area/each pass ,Mtrs 4.32 SIN 600
3.74
Graded Area/hr,Sq,Mtrs((3.74-0.3)*6100) 20984
No of Hours required /day 16.20
No. of Graders available at GKOC 2
Working hours required / each Grader/Day 8.1
% of utilization on SSH 34
Dozers are 50% of shovel population
Water Sprinklers 28 kL -2 Nos
Common equipment
Cranes 10T to 70/100T
Diesel bouser
Maintenance van
Compact vibrator, Tyre handlers, Front end
loaders, Fire tenders etc, are provided
Power calculations
Connected load = kW
Active load = Connected load x demand factor kW
Demand factor = 0.6 to 0.9
kVA = Active load / Power factor
Power factor = 0.8
No. of annual working hrs = say 3000
Energy consumption/annum = Active load x No.of
hrs/annum
Unit cost =2.80 x kWH
Surcharge @ 0.06Rs/kWH
Maximum demand/ kVA= Rs.250
SURVEY OFF NORMS FOR HEMM
Sl.
Equipment
Existing(CMPDI) Proposed(SCCL)
No. Hours Years Hours Years
1 10 Cu.m Rope Shovel 80000 22 100000 25
2 4.6-5 Cu.m Rope Shovel 36000 12 40000 15
3 5-10 Cu.m Hydraulic Excavators 20000 9 40000 15
4 2.2-3.5 Cu.m Hydraulic Excavators 20000 9 35000 15
5 85 T Rear Dumpers 22000 10 35000 15
6 35 T Rear Dumpers 12000 9 20000 15
7 Water Sprinklers 12000 9 25000 15
8 420&310HP Dozers 14000 9 20000 12
9 250mm RBH Drills 20000 9 35000 15
10 150mm RBH Drills 10000 9 25000 15
11 Motor Graders 10000 9 20000 15
12 Front End Loader 16000 9 25000 15
Basic E&Mcalculations for a coal mining project

More Related Content

PPT
Types of slope failures
PPTX
Material handling equipments : conveyors and elevators
PPTX
Laws and theorems
PPT
Transport & digging capacity calculation
PDF
Design of material handling system belt conveyor system for crushed coal for ...
PPTX
Types of cranes
PDF
ANFO, Emulsion and Heavy ANFO blends - Useful explosive and blasting agent fo...
PPTX
Shovel dumper productivity calculation.pptx
Types of slope failures
Material handling equipments : conveyors and elevators
Laws and theorems
Transport & digging capacity calculation
Design of material handling system belt conveyor system for crushed coal for ...
Types of cranes
ANFO, Emulsion and Heavy ANFO blends - Useful explosive and blasting agent fo...
Shovel dumper productivity calculation.pptx

What's hot (20)

PPTX
Analysing shovel dumper productivity for coal mine
PDF
Semimechanization sdls&lh ds
PPT
Working with Dragline
PPTX
Bord and pillar working with LHD/SDL
PPTX
Transportation in underground mines
PPTX
Shaft sinking.
PPTX
LHD Load haul dump ppt
PPTX
Road Header and Bolter Miner
PPTX
Shaft sinking
PPTX
Kope winder or friction winder ppt
PDF
Side Discharge Loader (SDL) / Layout of SDL
PDF
Haulage system in Mines
PPTX
Mechanical braking system of mine winders
PDF
Belt conveyor and Haulage system in the mine
PPTX
U, w and z ventilation system
PDF
Basics of drilling 1
PPT
High angle conveying
PPTX
Shaft sinking 1
PPTX
Shovel and Dumper Combinatio by Auqib Javed.pptx
Analysing shovel dumper productivity for coal mine
Semimechanization sdls&lh ds
Working with Dragline
Bord and pillar working with LHD/SDL
Transportation in underground mines
Shaft sinking.
LHD Load haul dump ppt
Road Header and Bolter Miner
Shaft sinking
Kope winder or friction winder ppt
Side Discharge Loader (SDL) / Layout of SDL
Haulage system in Mines
Mechanical braking system of mine winders
Belt conveyor and Haulage system in the mine
U, w and z ventilation system
Basics of drilling 1
High angle conveying
Shaft sinking 1
Shovel and Dumper Combinatio by Auqib Javed.pptx
Ad

Viewers also liked (20)

PDF
Differnt technologies in oc mines
PPTX
Dumper Cycle Study
PDF
Oc mechanical excavation
PPS
Bucket wheel excavator
PDF
Basics of openpit mining
PDF
Design of openpit mining
PDF
Openpit fundamentals
PDF
Surface mining planning and design of open pit mining
PPT
21 febrero sandino vive 2014
PDF
Cloud desktop for byod
PDF
Toxic Blue-Green Algae Reminders
PDF
Calendario tenis competiciones castilla la mancha 2013
PDF
Jones aleph acqorders
DOCX
Sainilk Awasiya Mahavidyalaya announces admissions open for BBA.
PPT
Concept02
PPS
Asteroides
PPTX
Clausura 1ª promoción curso experto community manager cámara de comercio málaga
PDF
Briviesca a través del tiempo. La judería de Briviesca
PDF
ေႀကးမံု 1-nov-13-km
PPSX
H3 o product presentation
Differnt technologies in oc mines
Dumper Cycle Study
Oc mechanical excavation
Bucket wheel excavator
Basics of openpit mining
Design of openpit mining
Openpit fundamentals
Surface mining planning and design of open pit mining
21 febrero sandino vive 2014
Cloud desktop for byod
Toxic Blue-Green Algae Reminders
Calendario tenis competiciones castilla la mancha 2013
Jones aleph acqorders
Sainilk Awasiya Mahavidyalaya announces admissions open for BBA.
Concept02
Asteroides
Clausura 1ª promoción curso experto community manager cámara de comercio málaga
Briviesca a través del tiempo. La judería de Briviesca
ေႀကးမံု 1-nov-13-km
H3 o product presentation
Ad

Similar to Basic E&Mcalculations for a coal mining project (20)

PPTX
project ppt
DOCX
gantry crane report
PPTX
Design and development of ridge profile power weeder
PDF
Design of Machine Elements - Unit 4 Procedures
PDF
trainingonchp-170107190647.pdf
PPTX
Cylindrical liner
PPTX
Ship design project Final presentation
PDF
Design of Machine Elements - Unit 5 Procedure
PPTX
Ship design project & presentation 3
PPTX
Design and analysis of solar support structure and daily tilting mechanism
PPTX
Casement Type Wind Turbine
PDF
project ppt 2 pdf.pdf
PPT
transmission line
PDF
IRJET- Study on Different Estimation Methods of Propulsion Power for 60 Mts O...
PDF
Design of Synchronous machine.pdf
PPTX
Presentation-for-teachers.pptx
PPTX
Basic Theory & Formulae Training Module
PPTX
Feasibility analysis of offshore wind power plants with DC collection grid
PPTX
Bidirectional floating hydro turbine
project ppt
gantry crane report
Design and development of ridge profile power weeder
Design of Machine Elements - Unit 4 Procedures
trainingonchp-170107190647.pdf
Cylindrical liner
Ship design project Final presentation
Design of Machine Elements - Unit 5 Procedure
Ship design project & presentation 3
Design and analysis of solar support structure and daily tilting mechanism
Casement Type Wind Turbine
project ppt 2 pdf.pdf
transmission line
IRJET- Study on Different Estimation Methods of Propulsion Power for 60 Mts O...
Design of Synchronous machine.pdf
Presentation-for-teachers.pptx
Basic Theory & Formulae Training Module
Feasibility analysis of offshore wind power plants with DC collection grid
Bidirectional floating hydro turbine

Recently uploaded (20)

PPT
Adolescent Emergencies for undergraduate
PPTX
SOBALAJE WORK.pptxe4544556y8878998yy6555y5
PPTX
supertech supernova queen tower at noida
PDF
1 Introduction to Networking (06).pdfbsbsbsb
PPTX
Arunesh_Kevin Lynch.pptxynynynyunynynynnynyn
PDF
Pfthuujhgdddtyygghjjiuyggghuiiiijggbbhhh
PPTX
UNITy8 human computer interac5ion-1.pptx
PPT
Unit I Preparatory process of dyeing in textiles
PPTX
immunotherapy.pptx in pregnancy outcome f
PDF
Interior_Design_and_Interior_Architectur.pdf
PPTX
Drafting equipment and its care for interior design
PDF
IARG - ICTC ANALOG RESEARCH GROUP - GROUP 1 - CHAPTER 2.pdf
PDF
This presentation is made for a design foundation class at Avantika Universit...
PDF
Engineering drawing lecture no 2 building blocks
PDF
analisis snsistem etnga ahrfahfffffffffffffffffffff
PDF
Social Media USAGE .............................................................
PPTX
Project_Presentation Bitcoin Price Prediction
PDF
Jamil Islam, Diplpma in Electrical Engineer,CV.pdf
PPTX
Applied Anthropology Report.pptx paulapuhin
PDF
Instagram Marketing in 2025 Reels, Stories, and Strategy (14) (2).pdf
Adolescent Emergencies for undergraduate
SOBALAJE WORK.pptxe4544556y8878998yy6555y5
supertech supernova queen tower at noida
1 Introduction to Networking (06).pdfbsbsbsb
Arunesh_Kevin Lynch.pptxynynynyunynynynnynyn
Pfthuujhgdddtyygghjjiuyggghuiiiijggbbhhh
UNITy8 human computer interac5ion-1.pptx
Unit I Preparatory process of dyeing in textiles
immunotherapy.pptx in pregnancy outcome f
Interior_Design_and_Interior_Architectur.pdf
Drafting equipment and its care for interior design
IARG - ICTC ANALOG RESEARCH GROUP - GROUP 1 - CHAPTER 2.pdf
This presentation is made for a design foundation class at Avantika Universit...
Engineering drawing lecture no 2 building blocks
analisis snsistem etnga ahrfahfffffffffffffffffffff
Social Media USAGE .............................................................
Project_Presentation Bitcoin Price Prediction
Jamil Islam, Diplpma in Electrical Engineer,CV.pdf
Applied Anthropology Report.pptx paulapuhin
Instagram Marketing in 2025 Reels, Stories, and Strategy (14) (2).pdf

Basic E&Mcalculations for a coal mining project

  • 2. • Estimates capacity (KW/HP) of machines, Electric power, Power cost/ton of coal or OB , For OCs Capacities of shovels dumper combination, capital required for Plant and machinery etc, of New Projects to in corporate in Feasibility Reports. (FRs) • Estimates P&M for Revised Feasibility Reports of projects. • Estimates P&M requirement of completed projects and on going projects.
  • 3. Technology adopted a) Hand section b) Mechanised mining a) Hand Section : Equipment required : Haulers (DH,EH), Pumps, Drill M/Cs, Main mechanical ventilator, Auxiliary fans connected Electricals
  • 4. • Gradient (1:3.5 or 1:4) Approx= 57/gradient • Weight to be pulled Calculation : Pull = Pull due to rope(w) + Pull due tubs(W) (kgs) Pull due to rope= Resistance against gradient (w) + Rope rolling resistance(f) = w x Gradient (Sin O) + w/10 ( w is weight/mtr of rope) =w/3.5+ w/10 (10% weight of rope)
  • 5. Pull due to tubs/(man riding cars) = Resistance against gradient (W) + Rolling resistance of tubs (F) = W x Gradient + W/40 (W/20) where W is the total weight of tubs = W / 3.5 + W/40 (W/20) Total Pull = w/3.5+w/10 +W / 3.5 + W/40 (W/20) Kgs Based on pull, rope is selected. Breaking load of rope as per IS 1570 =352 KN for 26 mm rope dia Factor of safety =9
  • 6. Breaking Load = 350 x1000/9.81 Kgs =35678 Kgs Safe load =35678/9 =3964 kgs HP =Total Pull x speed(mps)/75 KW =Total pull x speed(mps)/102 Peripheral speed of rope= 3.14xN xD/60x1000 m/sec D is Drum Dia, in mm N is RPM
  • 7. Total Length of Installation,L in mtrs. 2200 Max. Lift,H in mtrs 134 Distance between two chairs m 16 Max. Travelling Speed,V m/s 3 Man Riding Capacity,C Nos. 675 Weight of person,Mper in kgs 80 Weight of Chair,Mchair in kgs 13 Weight of Rope,Mrope in kg/m 1.6 Drive&Return wheel Dia,D in mtrs 1.5
  • 8. Power required to raise mass of persons,Ppers in W = C x H x 9.81 x 80/3600 = 675x133.52x9.81x80/3600 =19647 W Power to overcome Frictions,PFriction Line Friction,PFriction1 Chair Spacing ,X chair in mtrs 16 Total Continuous Rope length,LRope in mtrs =2 x L + 3.14 x D = 2x 2200 + 3,14x1.5 = 4404.71 Total no. of chairs, X =L rope / Chair spacing = 4404.71/16 = 275.29 Total no.of persons on one side only,Y =275/2 = 134 PFricion1 = 0.09((Lrope x Mrope) +( Y*Mper) +X * Mchairs)) V = 5304 W
  • 9. Friction included by vertical&horizontal curve stations, PFriction2 P Friction C= K*(Ppers +PFriction1 ) where K is a constant that increases with angle of deflection Angle of Deflection % Value of K 5°To10° 1 0.01 10°To20° 2 0.02 20°To30° 3.5 0.035 30°To40° 5 0.05
  • 10. Three curve stations are there Sl.No Horizontal Angle Vertical Angle 1 33° 2.34° 2 37° 2.04° 3 33° 1.00° At 1st Station,PFrictionCH1 = 0.05 x (19647 +5304) = 1247.57 W PFrictionCV1 = 0.01 x (19647 +5304) = 249.51 At2nd Station,PFrictionCH2 = 1247.57w PFrictionCV2 = 249.51W At3rd Station,PFrictionCH3 = 1247.57W PFrictionCV3 = 249.51W Total PFriction2 = 3 * (1247.57+249.51) =4491W
  • 11. Friction induced by Return sheeve Wheel,PFriction3 0.02x(Ppers +PFriction1 +PFriction2 ) 0.02x(19647.468+5304.0042+4491. 27) =588.854844 Therefore ,PFriction =(5304+4491+588) = 10384.12904 Total Power at the Driving Wheel,P Ppers +PFriction
  • 12. Efficiency of the System 0.76 Therefore,Input Power 39515.25927 Taking5%extra,Required Power will be 41491.02223 Standard Available Power,KW 45 Rope Pull Calculation Power at Driving Wheel = 30 KW =30/0.746=40HP HP=2NT / 4500 So, T=HPX4500 / 2N = (40*4500*7)/ (2*22*19.1) = 1499.286054 = 15kN
  • 13. Power = QxHx Sp.gravity/75x Efficiency HP = Qx Hx Sp.gravity/102 x Efficiency KW Q = Ltr/sec H = Head in mtrs Sp.gravity = 1.03 gms/cc one gallon =4.54 Ltrs Generally GPM of pump is taken Say 2250 LPM = 2250/4.54 = 495 GPM or 500 GPM
  • 14. Generally in SCCL mines single, Double, multistage centrifugal pumps are being used for pumping water from under ground to surface. 7.5 HP to 500 HP. • Depending upon depth and sump capacity pumps are deployed.
  • 15. Air Power in KW = Air Discharge (Cu.m/sec)x water gauge in mm/ 102 Fan efficiency = Air power in KW / brake shaft Power in KW Brake shaft power = Transmission efficiency x motor efficiency x Measured input power in KW Overall efficiency = Air power KW x100/ Measured power in KW
  • 16. Auxiliary fans of 20 KW is deployed in galleries where the flow is less than requirement High water gauge fans of 90 KW (200 to 500mm water gauge) are deployed in Road header drivages. In SCCL mines1 to 3 lakh CFT/min i.e (3000 to 9000 Cu.m/min) are working with blade angle 14 to 22 deg For Adriyala shaft 15000Cu.m/min fan is required.
  • 17. Mechanised mining : To increase the production and safety mechanised mining is adopted with following technologies. a) Long wall : Shearer is the deciding factor
  • 18. 1 Determine the mining rate, TPH Assume Cutting height,H mtrs 3.0 Web depth,D mtrs 1.0 Max. cutting speed,Vs mt/min 12.0 Coal density(solid), T/Cu.m 1.5 TPM= H*D*Vs * T/min 54 TPH 3240
  • 19. Drum Dia. mtrs 1.8 Web mtrs 1 Cutting speed, Vs mt/min 12.0 Density of coal (solid) T/m3 1.5 Q(Mining rate in tonnes per hour by one drum) TPH 1944 K is Specific energy consumption factor in HP-hr/Ton Normally K is 0.5 for hard coal and 0.25-0.35 for soft coal P(HP) = QK HP 972 There fore, for 3mtr extraction, the other drum requires only a power of (3-1.8)*1*12*1.5*0.5 HP 648 But, in practice, both drums will require equal power for bi- directional operation KW 725.112
  • 20. • (Assumed 1TPH=1KG) • For 1000 TPH, • S1 = 1000 Kg. • S1 - Tension • gc1 – Gravitational resistance on slack side (weight component acting along the bottom for chain) • gc2 - Gravitational resistance on tension side • RC1 - Frictional resistance on slack side • RC2 - Frictional resistance on tension side • gc1 = qc x L x Sinø • Where qc = Wt. of chain/mt. • L = Length of chain in mt. • Ø = Inclination
  • 21. • RC1 = qc x L x fc x Cosø • Where qc - Wt. of chain/mt. • L - Length of chain in mt. • fc - Frictional co-efficient of chain with pan • ~ 0.35 to 0.4 for soft chain • ~ 0.45 for shaking & watering • S2 = S1 + gc1 + RC1 or S1 + qcL (Sinø + fc Cosø) • (S1, S2 are in the opp. Direction) • S3 > S2 and there will be some loss • Thus S3 = 1.05 S2 • S4 = S3 – Gc2 + RC2
  • 22. • Where • gc2 = (qc x L x Sinø) + (qy x L x Sinø) • RC2 = (qc x L x fc Cosø) + qy x L x fy x Cosø • qy = Q/3.6V (Q = TPH, V = Velocity m/s) • Fy = Frictional co-efficient of material conveyed • 0.45 to 0.8 for dry soft coal, • 0.8 for silica, rock etc, normally 0.7 • Now S4 = S3 – gc2 + RC2 • Or S4 = S3 – (qc L Sinø + qy L Sinø) + (qc L fc Cosø + qy L fy Cosø) • = S3 + qc L (fc Cosø – Sinø) + qy L (fy Cosø – Sinø) • Power (P) = (S4 – S1) KW • 102 • Motor Power - P/h h = 0.8 to 0.9
  • 23. Based on shearer capacity AFC,BSL, Gate Belts, Trunk belts are designed. The supports are designed by taking load coming to supports / Sq.m area as per finite element method. The connected electricals are designed basing on the above capacities Power pack is designed on the design of support load.
  • 24. In SCCL Long wall technologies produced 4 to 7 lakhs per annum BG technology the following equipment is deployed a) Jumbo Drills b) LHDs c) Hydraulic props d) Power pack SDL Low height are deployed in hand section mines to increase productivity, safety and decrease in man power
  • 25. Based on production No. of LHD,SDL are deployed For CTX,811 Eimco LHDs annual production = 50,000 T For 912 Eimco LHDs = 60,000 T/ annum For Low height SDLs = 45,000 T/ annum Connected Electricals like GEBs, HT/LT switches, transformers are calculated on the No. of SDLs / LHDs deployed
  • 26. a) Power to move load horizontally =2.72 x L x F x (C+46)/1000 kW b) Power to move empty belt = 9.81 x F x G x (C+46) x S/1000 kW c) Power to elevate load =2.72 x L x H/1000 kW Total Power P = (a) +( b) +(c)
  • 27. Taking safety factor as 1.1 to 1.2 Total power requirement is calculated C = Centre distance in mtrs F = Friction factor (0.03) G = Inertia factor H = Change in elevation in mtrs L = Peak load in Tonnes/Hour S = Belt speed in mtrs/sec
  • 28. L= B x D x S/1000 Tonnes/Hr L = Peak load B =Belt capacity Factor D = Material density Kg/Cu.m S = Belt speed in mtrs/sec • Selection of belt T = K x P/S kN P is power required, K = Belt Drive factor S = speed mtrs/sec = kN/1 m = kN/m Taking Factor of Safety as 10:1 for PVC F.S 7:1 for steel cordvalue from table can be used for selection PVC/ Steel cord
  • 29. Based on coal production, OB removal and depth of the mine No. of shovels( Coal, OB), Dumpers, RBH Drills (Coal, OB), Dozers, Graders,Pumps and water sprinklers and other common equipment are calculated
  • 30. Sl.No Particulars 3cu.mShovel along with 35T Dumper 1 No. of Annual working days 330 2 No. of duty shifts 3 3 Duration of shift in Hr 8 4 Total No. of Annual shift hrs 7920 5 Annual utilisation of shift hrs 61%
  • 31. 6 Annual working hr 4831.2 7 Shovel bucket capacity (m3) 3 8 Material density - Tes/BCM 2.2 9 Swell Factor 0.732 10 Bucket fill factor 0.905 11 Swell cum fill factor 0.662
  • 32. 12 Material quantity per shovel bucket (T) 4.3722 13 Pay load capacity of dumper (T) 31.5 14 No. of passes per dumper load 7.204 15 No. of passes adopted 7 16 Adopted Pay load capacity of dumper (T) 30.605 17 Bucket cycle time (Minutes) 0.6
  • 33. 18 Loading time per dumper (Minutes) 4.2 19 Spotting time of dumper 0.5 20 Shovel time for loading dumper (Minutes) 4.7 21 Hourly shovel capacity Cum/hr 177.595 22 Factor for travelling positioning etc. 0.85 23 Annual shovel capacity (Cum) 729300 M.Cum 0.73
  • 34. Sl.No DESCRIPTION 0.5 1 Shovel loading time for dumper ,min 4.70 2 Spotting for unloading ,min 0.5 3 Unloading time ,min 0.6 4 Travelling time ,up ,min 1.20 5 Travelling time, down, min 1.00
  • 35. 6 Dumper cycle time. min 8.00 7 Dumper waiting time 1.40 8 Cycle time adopted 9.40 9 No. of trips per hour 6.382979 10 Dumper utilisation hours 2376 12 No. of trips per annum 15165.96
  • 36. 13 Dumper capacity,Cu.m 14.43182 14 Corrected dumper capacity 14.03093 15 Annual Dumper capacity,M.cum 0.212793 16 Calculated capacity of shovel, M.cum 0.73 17 No.of Dumpers required per shovel 3.524559 18 Rounded no. 4
  • 37. Assessment of volume of water to be pumped Q = A x H x Run off coefficient A = Catchment area in Sq.m H = Maximum daily precipitation in m Run off coefficients For mined out area = 0.60 Area beyond excavation =0.10 For internal dump area =0.15
  • 38. Maximum capacity of pump is determined on operating time 20 Hrs for 10 days i.e 200 Hrs as per CMPDI In SCCL 20 Hrs for 6 days i.e 120 hrs Add 10% seepage for attaining total make up Peak pumping capacity = /120 No of pumps is determined from above depend on pump capacity Cu.m/Hr
  • 39. For coal based on coal & OB No. of Drills is calculated Drilling pattern for coal = 5 x 5 x 6/5 Height of bench =5 m Spacing =5 m Burden =5 m Volume of coal exposed/ mtr drilling =30 Cu.m Annul working hrs =2112 Annual meterage = 42000 Volume of coal exposed by one drill =1.26 M.Cu.m Drill employed =150mm
  • 40. For OB 250mm RBH drills are used Depending on OB removal/ year No. of drills calculated Drilling pattern =8 x 8 x 9/8 Volume of OB exposed /mtr of drilling =72 Cu.m Annual working Hrs =2112 Annual meterage = 40000 Volume of OB exposed M.Cu.m = 2.88
  • 41. Road Length to be graded, Km 17 Road Width to be graded, Mtr 20 Area to be Graded, Sq.mtrs 340000 Speed of the Grader ,Mtrs / Hr 6100 Blade Length ,Mtrs 4.32 Blade overlap ,Mtrs 0.3
  • 42. Width of Graded area/each pass ,Mtrs 4.32 SIN 600 3.74 Graded Area/hr,Sq,Mtrs((3.74-0.3)*6100) 20984 No of Hours required /day 16.20 No. of Graders available at GKOC 2 Working hours required / each Grader/Day 8.1 % of utilization on SSH 34
  • 43. Dozers are 50% of shovel population Water Sprinklers 28 kL -2 Nos Common equipment Cranes 10T to 70/100T Diesel bouser Maintenance van Compact vibrator, Tyre handlers, Front end loaders, Fire tenders etc, are provided
  • 44. Power calculations Connected load = kW Active load = Connected load x demand factor kW Demand factor = 0.6 to 0.9 kVA = Active load / Power factor Power factor = 0.8 No. of annual working hrs = say 3000 Energy consumption/annum = Active load x No.of hrs/annum Unit cost =2.80 x kWH Surcharge @ 0.06Rs/kWH Maximum demand/ kVA= Rs.250
  • 45. SURVEY OFF NORMS FOR HEMM Sl. Equipment Existing(CMPDI) Proposed(SCCL) No. Hours Years Hours Years 1 10 Cu.m Rope Shovel 80000 22 100000 25 2 4.6-5 Cu.m Rope Shovel 36000 12 40000 15 3 5-10 Cu.m Hydraulic Excavators 20000 9 40000 15 4 2.2-3.5 Cu.m Hydraulic Excavators 20000 9 35000 15 5 85 T Rear Dumpers 22000 10 35000 15 6 35 T Rear Dumpers 12000 9 20000 15 7 Water Sprinklers 12000 9 25000 15 8 420&310HP Dozers 14000 9 20000 12 9 250mm RBH Drills 20000 9 35000 15 10 150mm RBH Drills 10000 9 25000 15 11 Motor Graders 10000 9 20000 15 12 Front End Loader 16000 9 25000 15