PERFORMANCE–BASED
PROJECT MANAGEMENT®
The Principles and Practices needed to increase the
Probability of Program Success (PoPS).
V1.0
9/14/2013
Niwot Ridge, LLC
5 Principles of Project Success
What does done look like?
How do we get there?
Are there enough resources?
What are progress impediments?
How do we measure progress?
Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
Deliver capabilities for stakeholders defined through Scenarios and Use
Cases, assessed with Measures of Effectiveness (MoE) for each
deliverable, that fulfills the mission or business case. Capabilities state
what Done looks like in units meaningful to the end user.
Define a Master Plan and Master Schedule that periodically assesses the
increasing maturity of the project through Measures of Effectiveness (MoE).
Schedules describe the sequence of work assessed using Measures of
Performance (MoP).
Define and allocate staff, facilities, materials, and external dependencies
for each deliverable. All conflicts are identified and mitigation plans put in
place. Periodic assessments of these dependencies, the probability of
future conflicts, and their mitigations are shown in the master schedule.
Embed risk management in all activities to identify the probability of
occurrence; probabilistic consequences; impacts on cost, schedule, and
technical performance; handling plans and residual risk handling; and
overall probability of project success is part of the business rhythm.
Measure physical percent complete with tangible evidence of progress to
plan. Measures of Effectiveness (MoE), Measures of Performance (MoP),
Technical Performance Measures (TPM), and compliance with cost and
schedule plans define the probability of success. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
Identify
Needed
Capabilities
Identify
Baseline
Requirements
Establish
Performance
Measurement
Baseline
Execute
Performance
Measurement
Baseline
Perform Continuous Risk Management (CRM)
4
5 Practices That Increase the Probability of
Project Success (PoPS)
Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
Identify the Capabilities needed to achieve a project objective or end
state. Define these capabilities through scenarios or Use Cases from the
customers Point of View. The success of these capabilities are defined
through Measures of Effectiveness (MoE) for the business.
Identify both technical and operational requirements that fulfill the
needed capabilities at the planned time, for the planned cost, with the
planned performance. Assure each requirement is traceable to the needed
capability and each capability has a defined requirement.
Develop the Performance Measurement Baseline (PMB) showing the
sequence of work, the planned budget for that work, the outcomes from
the work effort, the risk reduction activities for each outcome. Measure
these activities in Measures of Performance (MoP).
Execute the PMB in the planned order, assuring all work is completed
before moving the next step in the plan. During execution measure project
performance with adherence to cost, schedule, and Technical Performance
Measures (TPM) and their Key Performance Parameters (KPP)
Perform Continuous Risk Management during all steps by Identifying Risks
that impede success, analyze them for their impact, make plans to handle
the risks, track the effectiveness of these plans, control the work of the
handling efforts, and Communicate with everyone on the project.Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
5 Processes Needed to Implement the
Principles and Practices
Organizing
Budgeting &Scheduling
Project Accounting
Performance Analysis
Change Control
Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
Describe the work performed during the project, the functional
organizations executing this work and how they are related. Define the
authorized work, identify resources needed to deliver this work, and how
integration of the work delivers value to the customer.
Use tools and processes to create the schedule and the budget for the
work, so it can be performed in the planned sequence. Identify significant
interdependencies required to meet the physical delivery requirements to
the customer and the risk handling processes needed for success.
Define, track, report, and adjust funding, budgeting, and staff to assure
the project maintains its planned production of value to the customer.
Capture all costs to match the budget and identify the variances between
plan and actual cost and project performance.
Measure progress to plan in terms of cost, schedule, and technical
performance by comparing planned expenditures to actual expenditures,
planned schedule to actual schedule, and planned technical performance
to actual technical performance. All three are needed for success.
Identify variances, take corrective actions to close gaps. Record these
corrective actions in the Performance Measurement Baseline and use these
to forecast future cost, schedule, and technical performance.
Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
Connecting Performance-Based Project Management®
with the 9 Knowledge Areas of PMI PMBOK®
The 9 Knowledge Areas
of PMBOK®
Capabilities Based
Planning
Requirements
Baseline
Performance
Measurement
Baseline
PMB
Execution
Continuous Risk
Management
1 Integration Management
Concept of
Operations
IPT dependencies
SE interface
management
Interface
Management
2 Scope Management Capability flow down
Requirements
Flowdown Tree
WBS/TPM
Integration
REQ
Management
Growth Control
3 Time Management Capability need date
SA/AC Delivery
Dates
Integrated
Master Schedule
Schedule
Variance
EAC Control
4 Cost Management
Traceability
Matrix
Integrated
Master Schedule
Cost Variance EAC Control
5 Quality Management
Quality Mgmt
Impact Matrix
Integrated
Master Schedule
TPM Variance
Variance
Management
6
Human Resource
Management
Responsibility
Assignment
Matrix
Resource Loaded
Schedule
Resource
Management
Plan
FTE Management
7
Communications
Management
Requirements
Traceability
Performance Risk Messaging
9 Risk Management
Risk Management
Plan
Risk Register IMS / Risk Risk Buy Down RM Processes
9
Procurement
Management
Supply Chain
Management
SCM Channels SCM Activities
SCM
Performance
SK Management
ChapterX
8
Connecting Performance-Based Project Management®
with the 5 Process Groups of PMI PMBOK®
Performance-Based Project Management® Process Areas
The 5 Process
Groups of PMBOK®
Capabilities
Baseline
Requirements
Baseline
Performance
Measurement
Baseline
PMB
Execution
Continuous
Risk
Management
1 Initiating
Concept of
Operations
2 Planning
Integrated
Master Plan
Integrated
Master
Schedule
Plan Risks
3 Executing
Work
Package
Sequencing
Work
Authorization
Measure Risks
4
Monitoring and
Control
Integrated
Master
Schedule
Performance
Based Earned
Value
Monitor Risks
5 Closing
Integrated
Master
Schedule
Integrated
Master
Schedule
Retire Risks
ChapterX
9
Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013

More Related Content

PDF
Stephen bowerman professional curriculum vitae 2016
DOCX
Managing risk as Opportunity
PDF
Estimating cost and schedule for monte carlo simulation
PPTX
Project Performance Measurement Earned Value A Starter
PDF
Establishing the performance measurement baseline (pmi northern utah)(v1)
PPTX
Getting To Done - A Master Class Workshop
PDF
Deliverables based planning handbook
PDF
Capabilities Based Planning
Stephen bowerman professional curriculum vitae 2016
Managing risk as Opportunity
Estimating cost and schedule for monte carlo simulation
Project Performance Measurement Earned Value A Starter
Establishing the performance measurement baseline (pmi northern utah)(v1)
Getting To Done - A Master Class Workshop
Deliverables based planning handbook
Capabilities Based Planning

What's hot (20)

PDF
IMP & WBS - Getting Both Right is Paramount
PDF
Practices of risk management
PDF
Program Management Office Services
PDF
The simple problem of schedule performance indices
PDF
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
PPTX
Integrating risk with earned value
PDF
IMP / IMS Step by Step
PDF
IMP IMS overview
PDF
Pmp t09 project_execution_plan_rev_a
PPTX
Project Monitoring and Control
PDF
Integrating Risk With Earned Value
DOCX
Risk Management Guidance
PPTX
5 Immutable Principles of Capital Project SUccess
PDF
Project Management Theory
PPTX
From WBS to Integrated Master Schedule
PDF
Policy and Procedure Rollout
PDF
Cure for cost and schedule growth
PPT
Project performance tracking analysis and reporting
PDF
Risk Management Processes (v2)
IMP & WBS - Getting Both Right is Paramount
Practices of risk management
Program Management Office Services
The simple problem of schedule performance indices
Measures of Effectiveness, Measures of Performance, Technical Performance Mea...
Integrating risk with earned value
IMP / IMS Step by Step
IMP IMS overview
Pmp t09 project_execution_plan_rev_a
Project Monitoring and Control
Integrating Risk With Earned Value
Risk Management Guidance
5 Immutable Principles of Capital Project SUccess
Project Management Theory
From WBS to Integrated Master Schedule
Policy and Procedure Rollout
Cure for cost and schedule growth
Project performance tracking analysis and reporting
Risk Management Processes (v2)
Ad

Similar to Connecting PMB® with PMBOK® (20)

PDF
5 immutable principles and 5 processes in 60 seconds
PDF
Performance based management in a nut shell (v5)
PPTX
Breaking the Project Failure Cycle
PDF
Chapter 0 of Performance Based Project Management (sm)
PDF
Increasing the Probability of Project Success with Five Principles and Practices
PDF
Performance based planning in a nut shell (V5)
PDF
Increasing the probability of project success using Earned Value Management
PDF
Niwot Ridge LLC Capabilities
PDF
PetroSync - Successful Project Cost Estimation & Control
PPTX
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
PDF
Earning Value from Earned Value Management
PDF
Five Immutable Principles of Program Success and Their Supporting Processes a...
PDF
Agile in an ANSI-748-C environment
PPTX
Deliverables based planning
PDF
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
PDF
Building a Credible Performance Measurement Baseline in Two Days
PDF
Ev+agile=success
PDF
My Single Point project portfolio and demand
PDF
Building risk tolerance
PDF
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
5 immutable principles and 5 processes in 60 seconds
Performance based management in a nut shell (v5)
Breaking the Project Failure Cycle
Chapter 0 of Performance Based Project Management (sm)
Increasing the Probability of Project Success with Five Principles and Practices
Performance based planning in a nut shell (V5)
Increasing the probability of project success using Earned Value Management
Niwot Ridge LLC Capabilities
PetroSync - Successful Project Cost Estimation & Control
From Needed Capabilities to Project Deliverables - On Time, On Budget, On Spe...
Earning Value from Earned Value Management
Five Immutable Principles of Program Success and Their Supporting Processes a...
Agile in an ANSI-748-C environment
Deliverables based planning
Pm blackjack the21thingsyour-projectsponsorreallywantstoknow.-whitepaper_15
Building a Credible Performance Measurement Baseline in Two Days
Ev+agile=success
My Single Point project portfolio and demand
Building risk tolerance
Deliverables Based Planning, PMBOK® and 5 Immutable Principles of Project Suc...
Ad

More from Glen Alleman (20)

PDF
Managing risk with deliverables planning
PDF
A Gentle Introduction to the IMP/IMS
PDF
Increasing the Probability of Project Success
PDF
Process Flow and Narrative for Agile+PPM
PDF
Principles of Risk Management
PDF
From Principles to Strategies for Systems Engineering
PDF
NAVAIR Integrated Master Schedule Guide guide
PDF
Building a Credible Performance Measurement Baseline
PDF
Integrated master plan methodology (v2)
PDF
DHS - Using functions points to estimate agile development programs (v2)
PDF
Making the impossible possible
PDF
Heliotropic Abundance
PDF
Capabilities based planning
PDF
Process Flow and Narrative for Agile
PDF
Building the Performance Measurement Baseline
PPTX
Program Management Office Lean Software Development and Six Sigma
PDF
Integrated Master Plan Development
PDF
Seven Habits of a Highly Effective agile project manager
PDF
Paradigm of agile project management (update)
PDF
The 5 Immutable principles of project management
Managing risk with deliverables planning
A Gentle Introduction to the IMP/IMS
Increasing the Probability of Project Success
Process Flow and Narrative for Agile+PPM
Principles of Risk Management
From Principles to Strategies for Systems Engineering
NAVAIR Integrated Master Schedule Guide guide
Building a Credible Performance Measurement Baseline
Integrated master plan methodology (v2)
DHS - Using functions points to estimate agile development programs (v2)
Making the impossible possible
Heliotropic Abundance
Capabilities based planning
Process Flow and Narrative for Agile
Building the Performance Measurement Baseline
Program Management Office Lean Software Development and Six Sigma
Integrated Master Plan Development
Seven Habits of a Highly Effective agile project manager
Paradigm of agile project management (update)
The 5 Immutable principles of project management

Recently uploaded (20)

PDF
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
PDF
Planning-an-Audit-A-How-To-Guide-Checklist-WP.pdf
PDF
Dell Pro Micro: Speed customer interactions, patient processing, and learning...
PDF
NewMind AI Weekly Chronicles – August ’25 Week IV
PDF
CXOs-Are-you-still-doing-manual-DevOps-in-the-age-of-AI.pdf
PPTX
Microsoft User Copilot Training Slide Deck
PDF
IT-ITes Industry bjjbnkmkhkhknbmhkhmjhjkhj
PPTX
Custom Battery Pack Design Considerations for Performance and Safety
PDF
Auditboard EB SOX Playbook 2023 edition.
PDF
The-2025-Engineering-Revolution-AI-Quality-and-DevOps-Convergence.pdf
PPTX
Internet of Everything -Basic concepts details
PDF
Aug23rd - Mulesoft Community Workshop - Hyd, India.pdf
PDF
Lung cancer patients survival prediction using outlier detection and optimize...
PPTX
SGT Report The Beast Plan and Cyberphysical Systems of Control
PPTX
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
PDF
LMS bot: enhanced learning management systems for improved student learning e...
PDF
sbt 2.0: go big (Scala Days 2025 edition)
PDF
Transform-Your-Factory-with-AI-Driven-Quality-Engineering.pdf
PDF
AI.gov: A Trojan Horse in the Age of Artificial Intelligence
PDF
MENA-ECEONOMIC-CONTEXT-VC MENA-ECEONOMIC
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
Planning-an-Audit-A-How-To-Guide-Checklist-WP.pdf
Dell Pro Micro: Speed customer interactions, patient processing, and learning...
NewMind AI Weekly Chronicles – August ’25 Week IV
CXOs-Are-you-still-doing-manual-DevOps-in-the-age-of-AI.pdf
Microsoft User Copilot Training Slide Deck
IT-ITes Industry bjjbnkmkhkhknbmhkhmjhjkhj
Custom Battery Pack Design Considerations for Performance and Safety
Auditboard EB SOX Playbook 2023 edition.
The-2025-Engineering-Revolution-AI-Quality-and-DevOps-Convergence.pdf
Internet of Everything -Basic concepts details
Aug23rd - Mulesoft Community Workshop - Hyd, India.pdf
Lung cancer patients survival prediction using outlier detection and optimize...
SGT Report The Beast Plan and Cyberphysical Systems of Control
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
LMS bot: enhanced learning management systems for improved student learning e...
sbt 2.0: go big (Scala Days 2025 edition)
Transform-Your-Factory-with-AI-Driven-Quality-Engineering.pdf
AI.gov: A Trojan Horse in the Age of Artificial Intelligence
MENA-ECEONOMIC-CONTEXT-VC MENA-ECEONOMIC

Connecting PMB® with PMBOK®

  • 1. PERFORMANCE–BASED PROJECT MANAGEMENT® The Principles and Practices needed to increase the Probability of Program Success (PoPS). V1.0 9/14/2013 Niwot Ridge, LLC
  • 2. 5 Principles of Project Success What does done look like? How do we get there? Are there enough resources? What are progress impediments? How do we measure progress? Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
  • 3. Deliver capabilities for stakeholders defined through Scenarios and Use Cases, assessed with Measures of Effectiveness (MoE) for each deliverable, that fulfills the mission or business case. Capabilities state what Done looks like in units meaningful to the end user. Define a Master Plan and Master Schedule that periodically assesses the increasing maturity of the project through Measures of Effectiveness (MoE). Schedules describe the sequence of work assessed using Measures of Performance (MoP). Define and allocate staff, facilities, materials, and external dependencies for each deliverable. All conflicts are identified and mitigation plans put in place. Periodic assessments of these dependencies, the probability of future conflicts, and their mitigations are shown in the master schedule. Embed risk management in all activities to identify the probability of occurrence; probabilistic consequences; impacts on cost, schedule, and technical performance; handling plans and residual risk handling; and overall probability of project success is part of the business rhythm. Measure physical percent complete with tangible evidence of progress to plan. Measures of Effectiveness (MoE), Measures of Performance (MoP), Technical Performance Measures (TPM), and compliance with cost and schedule plans define the probability of success. Performance Based Management(sm), Copyright ® Glen B. Alleman, 2012
  • 4. Identify Needed Capabilities Identify Baseline Requirements Establish Performance Measurement Baseline Execute Performance Measurement Baseline Perform Continuous Risk Management (CRM) 4 5 Practices That Increase the Probability of Project Success (PoPS) Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
  • 5. Identify the Capabilities needed to achieve a project objective or end state. Define these capabilities through scenarios or Use Cases from the customers Point of View. The success of these capabilities are defined through Measures of Effectiveness (MoE) for the business. Identify both technical and operational requirements that fulfill the needed capabilities at the planned time, for the planned cost, with the planned performance. Assure each requirement is traceable to the needed capability and each capability has a defined requirement. Develop the Performance Measurement Baseline (PMB) showing the sequence of work, the planned budget for that work, the outcomes from the work effort, the risk reduction activities for each outcome. Measure these activities in Measures of Performance (MoP). Execute the PMB in the planned order, assuring all work is completed before moving the next step in the plan. During execution measure project performance with adherence to cost, schedule, and Technical Performance Measures (TPM) and their Key Performance Parameters (KPP) Perform Continuous Risk Management during all steps by Identifying Risks that impede success, analyze them for their impact, make plans to handle the risks, track the effectiveness of these plans, control the work of the handling efforts, and Communicate with everyone on the project.Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
  • 6. 5 Processes Needed to Implement the Principles and Practices Organizing Budgeting &Scheduling Project Accounting Performance Analysis Change Control Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
  • 7. Describe the work performed during the project, the functional organizations executing this work and how they are related. Define the authorized work, identify resources needed to deliver this work, and how integration of the work delivers value to the customer. Use tools and processes to create the schedule and the budget for the work, so it can be performed in the planned sequence. Identify significant interdependencies required to meet the physical delivery requirements to the customer and the risk handling processes needed for success. Define, track, report, and adjust funding, budgeting, and staff to assure the project maintains its planned production of value to the customer. Capture all costs to match the budget and identify the variances between plan and actual cost and project performance. Measure progress to plan in terms of cost, schedule, and technical performance by comparing planned expenditures to actual expenditures, planned schedule to actual schedule, and planned technical performance to actual technical performance. All three are needed for success. Identify variances, take corrective actions to close gaps. Record these corrective actions in the Performance Measurement Baseline and use these to forecast future cost, schedule, and technical performance. Performance-Based Project Management℠, Copyright ® Niwot Ridge Consulting, LLC, 2012
  • 8. Connecting Performance-Based Project Management® with the 9 Knowledge Areas of PMI PMBOK® The 9 Knowledge Areas of PMBOK® Capabilities Based Planning Requirements Baseline Performance Measurement Baseline PMB Execution Continuous Risk Management 1 Integration Management Concept of Operations IPT dependencies SE interface management Interface Management 2 Scope Management Capability flow down Requirements Flowdown Tree WBS/TPM Integration REQ Management Growth Control 3 Time Management Capability need date SA/AC Delivery Dates Integrated Master Schedule Schedule Variance EAC Control 4 Cost Management Traceability Matrix Integrated Master Schedule Cost Variance EAC Control 5 Quality Management Quality Mgmt Impact Matrix Integrated Master Schedule TPM Variance Variance Management 6 Human Resource Management Responsibility Assignment Matrix Resource Loaded Schedule Resource Management Plan FTE Management 7 Communications Management Requirements Traceability Performance Risk Messaging 9 Risk Management Risk Management Plan Risk Register IMS / Risk Risk Buy Down RM Processes 9 Procurement Management Supply Chain Management SCM Channels SCM Activities SCM Performance SK Management ChapterX 8
  • 9. Connecting Performance-Based Project Management® with the 5 Process Groups of PMI PMBOK® Performance-Based Project Management® Process Areas The 5 Process Groups of PMBOK® Capabilities Baseline Requirements Baseline Performance Measurement Baseline PMB Execution Continuous Risk Management 1 Initiating Concept of Operations 2 Planning Integrated Master Plan Integrated Master Schedule Plan Risks 3 Executing Work Package Sequencing Work Authorization Measure Risks 4 Monitoring and Control Integrated Master Schedule Performance Based Earned Value Monitor Risks 5 Closing Integrated Master Schedule Integrated Master Schedule Retire Risks ChapterX 9 Performance-Based Project Management®, Copyright © Glen B. Alleman, 2012, 2013