IRRIGATION ENGINEERING
TOPIC NAME: CROSS SECTION OF THE CANAL,
BALANCING DEPTH, AND CANAL F.S.L.
SUBJECT CODE: 2I70609
BRANCH: CIVIL ENGG,. 7TH SEM
PREPARED BY:
GUIDED BY: PROF. MAMTA PATEL
SR NO. NAME ENROLL. NO.
1. PATEL PRASHANT S. 141100106078
2. PATEL TWINKAL D. 141100106092
3. MISTRY ADITYA P. 151103106009
4. PATEL KAJAL M. 151103106011
5. RATNANI MANISHA N. 151103106016
CONTENT
 Cross section of an irrigation channel
- In cutting
- In filling
- In partial cutting and filling
 Balancing depth
 Canal F.S.L.
CROSS SECTION OF AN IRRIGATION CHANNEL
An irrigation channel section may be either,
1) In cutting
2) In filling
3) In partial cutting and filling
Cross section of canal in cutting
Cross section of canal in filling
Cross section of canal in partial cutting and filling
The main components of the canal cross- section are:
1. Side slope
2. Berm
3. Free board
4. Banks
5. Dowla
6. Inspection road
7. Borrow pits
8. Spoil bank
9. Lang width
10. Counter berm
1. SIDE SLOPES
 The side slope of channel depend on the nature of the soil.
 In average loam soil the side slopes are usually kept 1 : 1 in
cutting and 1.5 : 1in filling.
 In sandy soil say 1.5 : 1 in cutting and 2 : 1 in filling to be used.
2. BERM
 Berm is the horizontal distance left at ground level
between the toe of the bank and top edge of cutting.
 Berm is provided additional strength to bank and help in
safe guarding them against breaches.
 It is also provided for future widening of channel.
3.FREE BOARD
Free board is defined as the vertical distance between the designed full
supply level ( F.S.L.) in the canal and top level of canal banks.
It is provided to allow for wave action and floating debris.
 free board is consideration of
- canal capacity
- soil characteristics
- hydraulic gradient
4. BANKS
The purpose of the bank is to retain water so long as the berm is
not formed. They thus have to with stand full pressure of water above
the ground level.
5. INSPECTION ROAD
 An inspection road is usually provided on one or both bank of the
canal for the purpose of inspection, repair and maintenance of the
roads.
6.DOWEL
As the measure of safety for the vehicles, a raised projection of
soil, called dowel, is provided on the channel side of the inspection
road.
The top width of dowel is 0.5m, height above road level is 0.5m
and side slope is 1.5 : 1.
7. BORROW PITS
Borrow pits are small
pits which are dug to
obtain the extra earth for
making banks if the soil
obtained from cutting is
not sufficient.
The borrow pits are
usually located at distance
of 4D to 6D away from
outer toe of the bank.
The borrow pits may be
located either inside or
outside the channel.
8. SPOIL BANK
When the quantity of earth obtained from excavation or cutting of
the channel section is in excess of the quantity required for forming
the bank and service road then extra earth is usually deposited in the
form of spoil bank.
9. LAND WIDTH
The total land required for the construction of channel is divided in to two
parts. Permanent land and temporary land.
The permanent land is the land which will be required permanently during
and after construction of channel.
During construction period of the canal, some extra land is required for
storage of materials and machineries nearer the site of construction.
10.COUNTER BERM
Even after providing the usual embankment section of a bank,
saturation gradient may cut the downstream side of the bank .
In such case the saturation line should always be covered by 0.3
to 0.6 m of earth.
BALANCING DEPTH
The channel section is entirely in cutting, the extra soil has to be
deposited in spoil bank.
For the channel section entirely in filling the soil has to be obtained
from borrow pits. In both case required double handling and increased
cost of earth work.
If for a channel section the depth of cutting is such that the quantity
of excavation or cutting is equal to the earth filling required for making
the banks, then depth of cutting is known as balancing depth or most
economical depth of cutting.
The normal maximum operating water level of a water storage
when not affected by floods.
 This water level corresponds to 100% capacity.
CANAL F.S.L.
THANK YOU

More Related Content

PPTX
Cross Drainage Works
PPTX
Cavity walls
PPTX
Canal outlets and modules
PPTX
Canal Fall
PPTX
Canal irrigation
PDF
types of canals
PPT
Geographic information system
PPTX
Canal irrigation
Cross Drainage Works
Cavity walls
Canal outlets and modules
Canal Fall
Canal irrigation
types of canals
Geographic information system
Canal irrigation

What's hot (20)

PDF
Diversion headwork
PPT
Rigid pavement
PPTX
Plain sedimentation
PPT
Design Of Hydraulic Structure - Kennedy's Theory
PPTX
Gravity dam
PPTX
Laying and Testing of sewer
PPTX
Reservoir Planning
PPTX
02 Types of Intake Structures
PPTX
Types of joints in rigid pavement
PPT
Types of earth dams
PPTX
Diversion Headworks
PDF
Canal regulation works. m4pptx
PPTX
Intake structures
PPT
Flexible and-rigid-pavements
PPTX
Silt excluders
PPTX
ELECTRO OSMOSIS METHOD OF DEWATERING
PPTX
Design of flexible pavement
PPTX
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
Diversion headwork
Rigid pavement
Plain sedimentation
Design Of Hydraulic Structure - Kennedy's Theory
Gravity dam
Laying and Testing of sewer
Reservoir Planning
02 Types of Intake Structures
Types of joints in rigid pavement
Types of earth dams
Diversion Headworks
Canal regulation works. m4pptx
Intake structures
Flexible and-rigid-pavements
Silt excluders
ELECTRO OSMOSIS METHOD OF DEWATERING
Design of flexible pavement
DIFFERENT TYPES OF Well foundation & THEIR RELATIVE MERITS &DEMRITS
Ad

Similar to Cross section of the canal, balancing depth and canal fsl (20)

PDF
WREII Canals Head Works and Distribution system
PPTX
Canal Irrigation
PDF
Irrigation and Drainage Engineering (Chapter-3& 4).pdf
PDF
08. Classification of Canals.pdf
PPTX
Unit 4-canal
PPT
Design of a channel Reach
PPTX
Geological factor for canal alignment
PPTX
Lectures on Pavement Shoulder design and construction.pptx
PPT
Canal & canal types with design of channels by dj sir covered kennedy lacey t...
PPTX
Module 03 Distribution Works.pptx
PPTX
Canal of design
PPTX
Information about the perception tank ppt
PPTX
7. TUNNEL ENGINEERING
PDF
Topic 3 - Earth Dams. Preliminary inf.pdf
PDF
3. Highway Drainage.pdf
PDF
3. Highway Drainage.pdf
PPTX
Water Resources Engineering types of wells with figures Denish Jangid Open we...
PDF
Travis_Smith_Work_Term_Report_F2016
PPTX
Lined or non erodible design channel study
PPTX
Module-5.pptx
WREII Canals Head Works and Distribution system
Canal Irrigation
Irrigation and Drainage Engineering (Chapter-3& 4).pdf
08. Classification of Canals.pdf
Unit 4-canal
Design of a channel Reach
Geological factor for canal alignment
Lectures on Pavement Shoulder design and construction.pptx
Canal & canal types with design of channels by dj sir covered kennedy lacey t...
Module 03 Distribution Works.pptx
Canal of design
Information about the perception tank ppt
7. TUNNEL ENGINEERING
Topic 3 - Earth Dams. Preliminary inf.pdf
3. Highway Drainage.pdf
3. Highway Drainage.pdf
Water Resources Engineering types of wells with figures Denish Jangid Open we...
Travis_Smith_Work_Term_Report_F2016
Lined or non erodible design channel study
Module-5.pptx
Ad

More from Aditya Mistry (20)

PPTX
Valuation
PPTX
Traffic studies
PPTX
Earthquake design example
PPT
Urban transportation system
PPT
Water and Waste Water Engineering
PPT
Railway Bridge and Tunnel Engineering
PPT
Applied Fluid Mechanics
PPT
Advance Construction & Equipment
PPTX
Traffic control devices
PPTX
Shear strength of soil
PPTX
Stiffness Matrix
PPTX
Flood Management
PPTX
Air Pollution
PPTX
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATION
PPTX
Special concrete and concreting method
PPTX
Modern surveying instruments
PPTX
Earthquake resistant building
PPTX
Direct and bending stress
PPT
Temporary works
PPT
Notches and weir
Valuation
Traffic studies
Earthquake design example
Urban transportation system
Water and Waste Water Engineering
Railway Bridge and Tunnel Engineering
Applied Fluid Mechanics
Advance Construction & Equipment
Traffic control devices
Shear strength of soil
Stiffness Matrix
Flood Management
Air Pollution
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATION
Special concrete and concreting method
Modern surveying instruments
Earthquake resistant building
Direct and bending stress
Temporary works
Notches and weir

Recently uploaded (20)

PPTX
CyberSecurity Mobile and Wireless Devices
PPTX
Petroleum Refining & Petrochemicals.pptx
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PDF
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PDF
Abrasive, erosive and cavitation wear.pdf
PPTX
Building constraction Conveyance of water.pptx
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PDF
Java Basics-Introduction and program control
PPTX
Software Engineering and software moduleing
PDF
Soil Improvement Techniques Note - Rabbi
PDF
Applications of Equal_Area_Criterion.pdf
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
PDF
First part_B-Image Processing - 1 of 2).pdf
PDF
20250617 - IR - Global Guide for HR - 51 pages.pdf
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PDF
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
PPTX
Feature types and data preprocessing steps
PDF
Design Guidelines and solutions for Plastics parts
CyberSecurity Mobile and Wireless Devices
Petroleum Refining & Petrochemicals.pptx
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
UEFA_Carbon_Footprint_Calculator_Methology_2.0.pdf
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
Abrasive, erosive and cavitation wear.pdf
Building constraction Conveyance of water.pptx
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
Java Basics-Introduction and program control
Software Engineering and software moduleing
Soil Improvement Techniques Note - Rabbi
Applications of Equal_Area_Criterion.pdf
August 2025 - Top 10 Read Articles in Network Security & Its Applications
First part_B-Image Processing - 1 of 2).pdf
20250617 - IR - Global Guide for HR - 51 pages.pdf
August -2025_Top10 Read_Articles_ijait.pdf
Prof. Dr. KAYIHURA A. SILAS MUNYANEZA, PhD..pdf
Feature types and data preprocessing steps
Design Guidelines and solutions for Plastics parts

Cross section of the canal, balancing depth and canal fsl

  • 2. TOPIC NAME: CROSS SECTION OF THE CANAL, BALANCING DEPTH, AND CANAL F.S.L. SUBJECT CODE: 2I70609 BRANCH: CIVIL ENGG,. 7TH SEM PREPARED BY: GUIDED BY: PROF. MAMTA PATEL SR NO. NAME ENROLL. NO. 1. PATEL PRASHANT S. 141100106078 2. PATEL TWINKAL D. 141100106092 3. MISTRY ADITYA P. 151103106009 4. PATEL KAJAL M. 151103106011 5. RATNANI MANISHA N. 151103106016
  • 3. CONTENT  Cross section of an irrigation channel - In cutting - In filling - In partial cutting and filling  Balancing depth  Canal F.S.L.
  • 4. CROSS SECTION OF AN IRRIGATION CHANNEL An irrigation channel section may be either, 1) In cutting 2) In filling 3) In partial cutting and filling Cross section of canal in cutting
  • 5. Cross section of canal in filling Cross section of canal in partial cutting and filling
  • 6. The main components of the canal cross- section are: 1. Side slope 2. Berm 3. Free board 4. Banks 5. Dowla 6. Inspection road 7. Borrow pits 8. Spoil bank 9. Lang width 10. Counter berm
  • 7. 1. SIDE SLOPES  The side slope of channel depend on the nature of the soil.  In average loam soil the side slopes are usually kept 1 : 1 in cutting and 1.5 : 1in filling.  In sandy soil say 1.5 : 1 in cutting and 2 : 1 in filling to be used.
  • 8. 2. BERM  Berm is the horizontal distance left at ground level between the toe of the bank and top edge of cutting.  Berm is provided additional strength to bank and help in safe guarding them against breaches.  It is also provided for future widening of channel.
  • 9. 3.FREE BOARD Free board is defined as the vertical distance between the designed full supply level ( F.S.L.) in the canal and top level of canal banks. It is provided to allow for wave action and floating debris.  free board is consideration of - canal capacity - soil characteristics - hydraulic gradient
  • 10. 4. BANKS The purpose of the bank is to retain water so long as the berm is not formed. They thus have to with stand full pressure of water above the ground level. 5. INSPECTION ROAD  An inspection road is usually provided on one or both bank of the canal for the purpose of inspection, repair and maintenance of the roads.
  • 11. 6.DOWEL As the measure of safety for the vehicles, a raised projection of soil, called dowel, is provided on the channel side of the inspection road. The top width of dowel is 0.5m, height above road level is 0.5m and side slope is 1.5 : 1.
  • 12. 7. BORROW PITS Borrow pits are small pits which are dug to obtain the extra earth for making banks if the soil obtained from cutting is not sufficient. The borrow pits are usually located at distance of 4D to 6D away from outer toe of the bank. The borrow pits may be located either inside or outside the channel.
  • 13. 8. SPOIL BANK When the quantity of earth obtained from excavation or cutting of the channel section is in excess of the quantity required for forming the bank and service road then extra earth is usually deposited in the form of spoil bank.
  • 14. 9. LAND WIDTH The total land required for the construction of channel is divided in to two parts. Permanent land and temporary land. The permanent land is the land which will be required permanently during and after construction of channel. During construction period of the canal, some extra land is required for storage of materials and machineries nearer the site of construction.
  • 15. 10.COUNTER BERM Even after providing the usual embankment section of a bank, saturation gradient may cut the downstream side of the bank . In such case the saturation line should always be covered by 0.3 to 0.6 m of earth.
  • 16. BALANCING DEPTH The channel section is entirely in cutting, the extra soil has to be deposited in spoil bank. For the channel section entirely in filling the soil has to be obtained from borrow pits. In both case required double handling and increased cost of earth work. If for a channel section the depth of cutting is such that the quantity of excavation or cutting is equal to the earth filling required for making the banks, then depth of cutting is known as balancing depth or most economical depth of cutting.
  • 17. The normal maximum operating water level of a water storage when not affected by floods.  This water level corresponds to 100% capacity. CANAL F.S.L.