.Role of estimation in cost planning
What is estimation

       The definition of estimation according to dictionaries is known as "an approximate
       calculation of quantity" ;or "A judgment based on one's impressions' opinion".
       Estimation is the process that provides the benefit , funding and resorting figures that
       required for a variety of decision – making purposes.

What is project estimation

       According to John Smyrk:
       "Estimation has meanings at two levels of discussion:

           •   A general definition: Estimating is the process of establishing values for the
               critical parameters in analytical model of a project.
           •   A specific definition : Estimation is the process of establishing values for
               critical parameter in an analytical model of a project.

       According to Rory Burke:
       "Estimate is a quick method for pricing a project based on incomplete parts list of
       materials".

       Estimation is used to

           •   underpin benefit –cost analysis
           •   set expectation of timeframes.

       Unexpected changes in the project's variables will impact , usually adversely , on the
       project . It is important for good estimation to be provided , otherwise there may not
       be enough allocated time and money to execute the project successfully.


       Will discuses the role of estimation in cost planning within the structural steel
       fabrication industry ,estimation play an important role on cost planning for any steel
       fabricator because cost is important to all clients , there are different methods used
       on estimation will discuss some of these .

Detailed Estimate

       Detailed estimate is commonly used for medium size and small steel projects,
       method is based on the following
          1. Steel member length take off from tender drawings
          2. Classify members by type (beam, column, rafter, purlin, bracing, tie, post,
               lintel, canopy).
          3. Multiply each member by unit rate, which is varying according to member
               type.
          4. Add a risk factor depends to cover any contingencies.




                                                                                                1
Single rate estimate method

        It is only based on the tonnage rate or price per ton for cost of steel fabricating and
        erecting , it is preferred by the engineers and clients based on the fabricator rate
        per ton figure they can plan the project budget.
        Simply the estimation method role is to know the structure type if portal frame,
        multistory building, house, bridge, stadium, truss, stairs, handrails, light structures.




What is cost

        Cost is defined as detailed price based on a complete parts list of material, costing
        requires
                 • The design .
                 • The scope of work
                 • The parts list.
                 • The detailed planning.
                 • Firm prices from sub-contracts and suppliers.
                 •
Benefit of cost planning

    •   Greater satisfaction with end results
    •   Better value for money
    •   Improved building quality and performance
    •   Budget and value accountability
    •   Improved relationships between all project participants
    •   Design problems identified and solved earlier
    •   Early identification of high-cost element

Factors in Successful Cost Planning

    •    Confirm that all project team members are speaking, and understand, a
         common language
    •    Manage expectations. Acknowledge change is inevitable and establish contingencies
         and escalation in cost planning
    •    Establish and document a solid base of prioritized needs
    •    Study as many feasible site and building alternatives as possible
    •    Establish well defined, manageable project schedules
    •    Insure the budget has the confidence and acceptance of all project team members




                                                                                                   2
Cost Management Cycle

                                                          Planning &
                                                          Preliminary
                                                          Budgeting


                                                                                 Pre-Design
                                 Post                                                    &
                              Construction                                      Programmin
                                                                                          g



                                                              &Design
                                                           Construction




Cost planning based on detailed estimate.

   Project is broken down into tasks each task has a specific duration and resources, these
   tasks extracted from project estimate according to the tender drawings these tasks are

       •   Shop drawing preparation


                                                                                              3
•   Ordering materials
       • Component fabrication
       • Fabricating and welding
       • Painting
       • Transporting
       • Erection
   Using Microsoft project feed all date calculated during estimation process into the
   program, which will automatically calculate the CPM and provide accurate cash flow
   during the project , compare actual cost to estimated budget for each task and identify
   any change.


       At what stage of design is used

       •   At tender stage only .

       Advantages

           1. The most accurate method Accuracy about 1 to 5%
           2. Quantity servier prefers this way it works the same way he work.
           3. Provide accurate competitive cost.
           4. The lower risk margin.
           5. Can be sued to any type of project.

       Disadvantages

           1.   Time consuming.
           2.   Require height skilled estimator.
           3.   Only used at tender stage and depends on drawings information.
           4.   Estimator has to revise his tender with each revised set of documents.
           5.   Require meeting with client and engineers to discuss any documents
                quires.


Cost planning based on single rate estimate.

   Based on the client requirement will work out how many tons of steel involved in the
   project ,then project is broken down into tasks each task has a specific duration and
   resources, these tasks extracted from historical recorded information from similar projects
   Using Microsoft project feed all data calculated during estimation process into the
   program, which will automatically calculate the CPM and provide accurate cash flow
   during the project

       At what stage of design is used

       •   At brief design stage.

       Advantages

           1.   Clients prefer this method they can easy understand it.
           2.   The quickest method.
           3.   Very simple.
           4.   Do not require skilled estimator.



                                                                                             4
Disadvantages

             1. Difficult to make allowances for building location, shape, drawing
                revisions, lack of information, poor documentation and so on.
             2. Do not know the cost of each item.
             3. Accuracy about 15 to 20%
             4. Cannot used for minor variation or special projects.



Conclusion

   There is no easy way to produce accurate estimations, except with experience and using
   better practice from other projects, comparing both methods on regard to the cost
   planning effect it is obvious that the detailed estimate is more accurate and provide a
   small

   It is not always possible to have the required information for the detailed estimation at
   planning time especially for small projects so fabricator should deal with a both methods
   According to the available information in fact they use the single rate method if not
   possible to make a detail estimate due to time or document limitation.

   Estimation is a major effecting factor in successful cost planning the closer the estimate
   the better and efficient will be the cost planning. Which if fails might cause cost overrun
   effecting on the company financial stability.

   There are different ways of improving estimation such as recoding actual costs for all
   projects and compare it with the current applied rates, implement lesson learned from
   past to new projects , up skill estimators by providing training , keep new technology to
   a minimum .




       References:
   •   Ten step project management process (www.tenstep.com)
   •   Project management fact sheet: project estimation version 1.0
   •   Burke, R. Project management planning and control.




                                                                                               5
6

More Related Content

PPT
ادارة تكلفة المشروع
PDF
ESTIMATING.pdf
PPTX
Establishing schedule margin using monte carlo simulation
PDF
Estimate costs in fragile and transitional contexts - July - 2014
PDF
Project Management and Development Economics Project (Slides)
PDF
Construction Project Schedule Example- Residential Building
PDF
5 Popular Types of Construction Contracts
PPSX
Project Control System
ادارة تكلفة المشروع
ESTIMATING.pdf
Establishing schedule margin using monte carlo simulation
Estimate costs in fragile and transitional contexts - July - 2014
Project Management and Development Economics Project (Slides)
Construction Project Schedule Example- Residential Building
5 Popular Types of Construction Contracts
Project Control System

What's hot (20)

PPTX
Power Point For Cmgt 410
PPTX
construction project managment_civileng
PDF
Managing the Construction Claims Effectively
PDF
Project Performance Analysis And Delivery Methods - Quantitative Analysis
PDF
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
PPTX
Construction project management
PDF
Matt.gonzales
PDF
J.S. Daniel paper for practical checklist of schedule
PDF
Value Management Assignment (Slides)
PDF
Capabilities based planning
PPTX
Process of pre construction phase drawbacks
PDF
Cpm500 d _alleman__tpm lesson 3 (v1)
PDF
Project Cost & Schedule Integration Lessons Learnt
PPTX
Construction phases
PDF
Osterkamp jeff
PDF
Project Management Notes 3
PDF
Planning and Scheduling Construction Projects, Part 1: The Planning Process
PPTX
Construction Project Management
PDF
Earned Value Management Meets Big Data
PDF
Construction KPIs & Dashboards
Power Point For Cmgt 410
construction project managment_civileng
Managing the Construction Claims Effectively
Project Performance Analysis And Delivery Methods - Quantitative Analysis
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Construction project management
Matt.gonzales
J.S. Daniel paper for practical checklist of schedule
Value Management Assignment (Slides)
Capabilities based planning
Process of pre construction phase drawbacks
Cpm500 d _alleman__tpm lesson 3 (v1)
Project Cost & Schedule Integration Lessons Learnt
Construction phases
Osterkamp jeff
Project Management Notes 3
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Construction Project Management
Earned Value Management Meets Big Data
Construction KPIs & Dashboards
Ad

Viewers also liked (20)

PDF
Neat solutions bim hub_projects 2013_low
PDF
Civil Quantity Survey and Estimation
PDF
Design and estimation of rural road in vaddeswaram
PPTX
Vernacular Architecture
PDF
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
PPT
Presentation1
PPTX
Urban design criteria the holistic approach for design assessment
PDF
Baseplate
PDF
Pile design guide (Collected)
PPT
Housing1
PPTX
Civil Engineering Project Presentation
PPTX
Design of staircases
PDF
Quantity surveying drawing FNBE 2014
PPTX
Final BUILDING CONSTRUCTION 1
PPTX
Ppt of mini project.
PDF
Construction work of a multi storied residential building
PPTX
Pile foundation ppt
PDF
estimation and quantity surveying
DOCX
Cafe construction project report
PPT
Pile foundation
Neat solutions bim hub_projects 2013_low
Civil Quantity Survey and Estimation
Design and estimation of rural road in vaddeswaram
Vernacular Architecture
Sachpazis: 4 rc piles cap design with eccentricity example (bs8110 part1-1997)
Presentation1
Urban design criteria the holistic approach for design assessment
Baseplate
Pile design guide (Collected)
Housing1
Civil Engineering Project Presentation
Design of staircases
Quantity surveying drawing FNBE 2014
Final BUILDING CONSTRUCTION 1
Ppt of mini project.
Construction work of a multi storied residential building
Pile foundation ppt
estimation and quantity surveying
Cafe construction project report
Pile foundation
Ad

Similar to Estimation (20)

PDF
GROUP PRESENTATION Construction Management .pdf
PDF
Lec.1 Introduction to Estimation
PDF
Construction estimator
PDF
Construction Estimator
PPTX
Reduction of cost in construction
PDF
Estimation
PDF
Construction-project-management-2-pdf-free.pdf
PDF
H1303055462
PPT
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
PDF
Rethink cost estimation with core processes that drive 5D BIM
PDF
introduction to estimating in construction.pdf
PDF
Exploration of risks and risk management in construction project delivery
PDF
SPECIFICATION AND ESTIMATION
PDF
Project Cost Management for IEM talk on 13 January 2018.
PPTX
Software Project Cost Management and estimation
PPTX
SPM 13 PROJECT PLANNING FOR YOUR FUTUR E
PDF
Varun Garg_CV
PPTX
7 Project planning for software engineering.pptx
DOCX
What is Project Expense Tracking? .docx
PPT
Suvarna consultancy services
GROUP PRESENTATION Construction Management .pdf
Lec.1 Introduction to Estimation
Construction estimator
Construction Estimator
Reduction of cost in construction
Estimation
Construction-project-management-2-pdf-free.pdf
H1303055462
CONSTRUCTION-PROJECT-MANAGEMENT-ppt.ppt
Rethink cost estimation with core processes that drive 5D BIM
introduction to estimating in construction.pdf
Exploration of risks and risk management in construction project delivery
SPECIFICATION AND ESTIMATION
Project Cost Management for IEM talk on 13 January 2018.
Software Project Cost Management and estimation
SPM 13 PROJECT PLANNING FOR YOUR FUTUR E
Varun Garg_CV
7 Project planning for software engineering.pptx
What is Project Expense Tracking? .docx
Suvarna consultancy services

More from Khaled Eid (15)

PDF
pre cast tilt up panel
PDF
What every engineer should know
PDF
Steel stacks guide
PPTX
Loading
PDF
Calculation note 29 11-2014
PPTX
Design of column base plates anchor bolt
PDF
Steel silo failure case study
DOC
Quality managment impacts in construction
PDF
Opera sydney case study analysis
PDF
Cheq plate span
PDF
Mathcad anchors (2)
DOCX
Impact of new codes in silos design
PPT
Writing engineering report
DOC
Steel detailing guide scope document
PDF
Khaled(beca)
pre cast tilt up panel
What every engineer should know
Steel stacks guide
Loading
Calculation note 29 11-2014
Design of column base plates anchor bolt
Steel silo failure case study
Quality managment impacts in construction
Opera sydney case study analysis
Cheq plate span
Mathcad anchors (2)
Impact of new codes in silos design
Writing engineering report
Steel detailing guide scope document
Khaled(beca)

Recently uploaded (20)

PPTX
The various Industrial Revolutions .pptx
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PPTX
cloud_computing_Infrastucture_as_cloud_p
PDF
August Patch Tuesday
PPTX
Tartificialntelligence_presentation.pptx
PDF
A comparative study of natural language inference in Swahili using monolingua...
PPTX
Final SEM Unit 1 for mit wpu at pune .pptx
PDF
Getting started with AI Agents and Multi-Agent Systems
PDF
Developing a website for English-speaking practice to English as a foreign la...
PDF
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
PDF
TrustArc Webinar - Click, Consent, Trust: Winning the Privacy Game
PPTX
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx
PDF
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
PDF
Assigned Numbers - 2025 - Bluetooth® Document
PPTX
TLE Review Electricity (Electricity).pptx
PPTX
Chapter 5: Probability Theory and Statistics
PDF
project resource management chapter-09.pdf
PDF
NewMind AI Weekly Chronicles – August ’25 Week III
PDF
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf
The various Industrial Revolutions .pptx
Zenith AI: Advanced Artificial Intelligence
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
cloud_computing_Infrastucture_as_cloud_p
August Patch Tuesday
Tartificialntelligence_presentation.pptx
A comparative study of natural language inference in Swahili using monolingua...
Final SEM Unit 1 for mit wpu at pune .pptx
Getting started with AI Agents and Multi-Agent Systems
Developing a website for English-speaking practice to English as a foreign la...
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
TrustArc Webinar - Click, Consent, Trust: Winning the Privacy Game
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx
From MVP to Full-Scale Product A Startup’s Software Journey.pdf
Assigned Numbers - 2025 - Bluetooth® Document
TLE Review Electricity (Electricity).pptx
Chapter 5: Probability Theory and Statistics
project resource management chapter-09.pdf
NewMind AI Weekly Chronicles – August ’25 Week III
ENT215_Completing-a-large-scale-migration-and-modernization-with-AWS.pdf

Estimation

  • 1. .Role of estimation in cost planning What is estimation The definition of estimation according to dictionaries is known as "an approximate calculation of quantity" ;or "A judgment based on one's impressions' opinion". Estimation is the process that provides the benefit , funding and resorting figures that required for a variety of decision – making purposes. What is project estimation According to John Smyrk: "Estimation has meanings at two levels of discussion: • A general definition: Estimating is the process of establishing values for the critical parameters in analytical model of a project. • A specific definition : Estimation is the process of establishing values for critical parameter in an analytical model of a project. According to Rory Burke: "Estimate is a quick method for pricing a project based on incomplete parts list of materials". Estimation is used to • underpin benefit –cost analysis • set expectation of timeframes. Unexpected changes in the project's variables will impact , usually adversely , on the project . It is important for good estimation to be provided , otherwise there may not be enough allocated time and money to execute the project successfully. Will discuses the role of estimation in cost planning within the structural steel fabrication industry ,estimation play an important role on cost planning for any steel fabricator because cost is important to all clients , there are different methods used on estimation will discuss some of these . Detailed Estimate Detailed estimate is commonly used for medium size and small steel projects, method is based on the following 1. Steel member length take off from tender drawings 2. Classify members by type (beam, column, rafter, purlin, bracing, tie, post, lintel, canopy). 3. Multiply each member by unit rate, which is varying according to member type. 4. Add a risk factor depends to cover any contingencies. 1
  • 2. Single rate estimate method It is only based on the tonnage rate or price per ton for cost of steel fabricating and erecting , it is preferred by the engineers and clients based on the fabricator rate per ton figure they can plan the project budget. Simply the estimation method role is to know the structure type if portal frame, multistory building, house, bridge, stadium, truss, stairs, handrails, light structures. What is cost Cost is defined as detailed price based on a complete parts list of material, costing requires • The design . • The scope of work • The parts list. • The detailed planning. • Firm prices from sub-contracts and suppliers. • Benefit of cost planning • Greater satisfaction with end results • Better value for money • Improved building quality and performance • Budget and value accountability • Improved relationships between all project participants • Design problems identified and solved earlier • Early identification of high-cost element Factors in Successful Cost Planning • Confirm that all project team members are speaking, and understand, a common language • Manage expectations. Acknowledge change is inevitable and establish contingencies and escalation in cost planning • Establish and document a solid base of prioritized needs • Study as many feasible site and building alternatives as possible • Establish well defined, manageable project schedules • Insure the budget has the confidence and acceptance of all project team members 2
  • 3. Cost Management Cycle Planning & Preliminary Budgeting Pre-Design Post & Construction Programmin g &Design Construction Cost planning based on detailed estimate. Project is broken down into tasks each task has a specific duration and resources, these tasks extracted from project estimate according to the tender drawings these tasks are • Shop drawing preparation 3
  • 4. Ordering materials • Component fabrication • Fabricating and welding • Painting • Transporting • Erection Using Microsoft project feed all date calculated during estimation process into the program, which will automatically calculate the CPM and provide accurate cash flow during the project , compare actual cost to estimated budget for each task and identify any change. At what stage of design is used • At tender stage only . Advantages 1. The most accurate method Accuracy about 1 to 5% 2. Quantity servier prefers this way it works the same way he work. 3. Provide accurate competitive cost. 4. The lower risk margin. 5. Can be sued to any type of project. Disadvantages 1. Time consuming. 2. Require height skilled estimator. 3. Only used at tender stage and depends on drawings information. 4. Estimator has to revise his tender with each revised set of documents. 5. Require meeting with client and engineers to discuss any documents quires. Cost planning based on single rate estimate. Based on the client requirement will work out how many tons of steel involved in the project ,then project is broken down into tasks each task has a specific duration and resources, these tasks extracted from historical recorded information from similar projects Using Microsoft project feed all data calculated during estimation process into the program, which will automatically calculate the CPM and provide accurate cash flow during the project At what stage of design is used • At brief design stage. Advantages 1. Clients prefer this method they can easy understand it. 2. The quickest method. 3. Very simple. 4. Do not require skilled estimator. 4
  • 5. Disadvantages 1. Difficult to make allowances for building location, shape, drawing revisions, lack of information, poor documentation and so on. 2. Do not know the cost of each item. 3. Accuracy about 15 to 20% 4. Cannot used for minor variation or special projects. Conclusion There is no easy way to produce accurate estimations, except with experience and using better practice from other projects, comparing both methods on regard to the cost planning effect it is obvious that the detailed estimate is more accurate and provide a small It is not always possible to have the required information for the detailed estimation at planning time especially for small projects so fabricator should deal with a both methods According to the available information in fact they use the single rate method if not possible to make a detail estimate due to time or document limitation. Estimation is a major effecting factor in successful cost planning the closer the estimate the better and efficient will be the cost planning. Which if fails might cause cost overrun effecting on the company financial stability. There are different ways of improving estimation such as recoding actual costs for all projects and compare it with the current applied rates, implement lesson learned from past to new projects , up skill estimators by providing training , keep new technology to a minimum . References: • Ten step project management process (www.tenstep.com) • Project management fact sheet: project estimation version 1.0 • Burke, R. Project management planning and control. 5
  • 6. 6