FEA for
Early Stage Design
SimScale Demo and Discussion
CASE 1 – ROBOTIC GRIPPER – FEA
Plant Management
Fixed to the load block or boom here
200N gripping force
Objective: before starting official approval process, the designer
wants to assess the uniformity of the deflection during grappling.
● New design for gripper assembly
● 50+ part assembly, Roark hand calcs overly simplified
● 6 times safe working load for lifting equipment
● Proof load testing a complete entire assembly is expensive to get
wrong
How can I assess the assembly
stresses quickly and accurately?
Are my calculations correct?
Design Engineer
CASE 1 – ROBOTIC GRIPPER – FEA
Plant Management
Objective: before starting official approval process, the designer
wants to assess the uniformity of the deflection during grappling.
● New design for gripper assembly
● 50+ part assembly, Roark hand calcs overly simplified
● 6 times safe working load for lifting equipment
● Proof load testing a complete entire assembly is expensive to get
wrong
Design Engineer
200N gripping force
Fixed to the load block or boom here
How can I assess the assembly
stresses quickly and accurately?
Are my calculations correct?
- Whole assembly simulated in
15 mins with 5 mins setup time
- Design changes evaluated
- Easy to use set up, with ready
to use templates and live
support.
- SAAS without expensive
hardware and software to
install or maintain
Summary
200N gripping force
Fixed to the load block or boom here

More Related Content

PPS
Af Bagger
PPT
Gold river wwmps
PDF
Single Minute Exchange of Dies
PDF
Leadec conveyor integration 2019
PDF
Configurable Stack DFMA Report
PDF
Boiler Supporting structure-Steel detailing
PPTX
AMPC - Innovation Theme on a Page - Remote Operations
PDF
Hybrid Ventilation using CFD Simulation in the Cloud
Af Bagger
Gold river wwmps
Single Minute Exchange of Dies
Leadec conveyor integration 2019
Configurable Stack DFMA Report
Boiler Supporting structure-Steel detailing
AMPC - Innovation Theme on a Page - Remote Operations
Hybrid Ventilation using CFD Simulation in the Cloud

More from SimScale (20)

PPTX
Simulation for Passively Cooled LED Design
PPTX
Design Buildings Faster by Harnessing the Power of the Cloud
PPTX
Fast & Easy Electronics Thermal Management
PPTX
Smart Data Center Design
PPTX
SimScale Demo and Discussion on External AEC
PPTX
SimScale Demo and Discussion on Internal AEC
PPTX
SimScale to IES for Building Simulation
PPTX
Conjugate Heat Transfer Best Practices in SimScale
PPTX
Evaluating the Thermal Performance of Lighting Solutions With Cloud-Based CFD
PPTX
Pressure Coefficients on Building Facades for Building Simulation
PPTX
How to Model Trees with Porous Media — Pedestrian Wind Comfort
PDF
Early-Stage Design Simulation for Architects
PDF
An Introduction to Electronics Cooling
PDF
Accélérer le développement produit via la simulation dans le Cloud avec SimScale
PDF
Using SimScale for Demonstrating Compliance With LEED, BREEAM & the WELL Buil...
PDF
SimScale: Unparalleled CFD Speeds with Parallel Computing
PDF
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...
PDF
Basics of building aerodynamics & their effects on pedestrian comfort
PDF
Plasticity and Nonlinear Materials in FEA
PDF
Thermal Resistance Modelling with SimScale
Simulation for Passively Cooled LED Design
Design Buildings Faster by Harnessing the Power of the Cloud
Fast & Easy Electronics Thermal Management
Smart Data Center Design
SimScale Demo and Discussion on External AEC
SimScale Demo and Discussion on Internal AEC
SimScale to IES for Building Simulation
Conjugate Heat Transfer Best Practices in SimScale
Evaluating the Thermal Performance of Lighting Solutions With Cloud-Based CFD
Pressure Coefficients on Building Facades for Building Simulation
How to Model Trees with Porous Media — Pedestrian Wind Comfort
Early-Stage Design Simulation for Architects
An Introduction to Electronics Cooling
Accélérer le développement produit via la simulation dans le Cloud avec SimScale
Using SimScale for Demonstrating Compliance With LEED, BREEAM & the WELL Buil...
SimScale: Unparalleled CFD Speeds with Parallel Computing
Simulating the Performance of the Unique MicroLouvre™ for Low Energy Building...
Basics of building aerodynamics & their effects on pedestrian comfort
Plasticity and Nonlinear Materials in FEA
Thermal Resistance Modelling with SimScale
Ad

Recently uploaded (20)

PPT
Chapter 1 - Introduction to Manufacturing Technology_2.ppt
PPTX
wireless networks, mobile computing.pptx
PPTX
tack Data Structure with Array and Linked List Implementation, Push and Pop O...
PDF
Beginners-Guide-to-Artificial-Intelligence.pdf
PPTX
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
PPTX
Module 8- Technological and Communication Skills.pptx
PDF
Exploratory_Data_Analysis_Fundamentals.pdf
PDF
MLpara ingenieira CIVIL, meca Y AMBIENTAL
PDF
Computer organization and architecuture Digital Notes....pdf
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PDF
20250617 - IR - Global Guide for HR - 51 pages.pdf
PPTX
Management Information system : MIS-e-Business Systems.pptx
PDF
Applications of Equal_Area_Criterion.pdf
PPTX
Petroleum Refining & Petrochemicals.pptx
PPTX
Micro1New.ppt.pptx the mai themes of micfrobiology
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PDF
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PPTX
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
PDF
Java Basics-Introduction and program control
Chapter 1 - Introduction to Manufacturing Technology_2.ppt
wireless networks, mobile computing.pptx
tack Data Structure with Array and Linked List Implementation, Push and Pop O...
Beginners-Guide-to-Artificial-Intelligence.pdf
Chemical Technological Processes, Feasibility Study and Chemical Process Indu...
Module 8- Technological and Communication Skills.pptx
Exploratory_Data_Analysis_Fundamentals.pdf
MLpara ingenieira CIVIL, meca Y AMBIENTAL
Computer organization and architecuture Digital Notes....pdf
distributed database system" (DDBS) is often used to refer to both the distri...
20250617 - IR - Global Guide for HR - 51 pages.pdf
Management Information system : MIS-e-Business Systems.pptx
Applications of Equal_Area_Criterion.pdf
Petroleum Refining & Petrochemicals.pptx
Micro1New.ppt.pptx the mai themes of micfrobiology
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
UEFA_Embodied_Carbon_Emissions_Football_Infrastructure.pdf
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
CN_Unite_1 AI&DS ENGGERING SPPU PUNE UNIVERSITY
Java Basics-Introduction and program control
Ad

FEA for Early Stage Design

  • 1. FEA for Early Stage Design SimScale Demo and Discussion
  • 2. CASE 1 – ROBOTIC GRIPPER – FEA Plant Management Fixed to the load block or boom here 200N gripping force Objective: before starting official approval process, the designer wants to assess the uniformity of the deflection during grappling. ● New design for gripper assembly ● 50+ part assembly, Roark hand calcs overly simplified ● 6 times safe working load for lifting equipment ● Proof load testing a complete entire assembly is expensive to get wrong How can I assess the assembly stresses quickly and accurately? Are my calculations correct? Design Engineer
  • 3. CASE 1 – ROBOTIC GRIPPER – FEA Plant Management Objective: before starting official approval process, the designer wants to assess the uniformity of the deflection during grappling. ● New design for gripper assembly ● 50+ part assembly, Roark hand calcs overly simplified ● 6 times safe working load for lifting equipment ● Proof load testing a complete entire assembly is expensive to get wrong Design Engineer 200N gripping force Fixed to the load block or boom here How can I assess the assembly stresses quickly and accurately? Are my calculations correct?
  • 4. - Whole assembly simulated in 15 mins with 5 mins setup time - Design changes evaluated - Easy to use set up, with ready to use templates and live support. - SAAS without expensive hardware and software to install or maintain Summary 200N gripping force Fixed to the load block or boom here