Premise
• Over much of the 20th century, utilities, regulators and customers each
relied upon lab and field meter testing efforts which were primarily focused
upon the accuracy of the watt-hour meter and demand register.
• This focus is now changing with overwhelming deployment of electronic
meters and significant deployment of AMR and AMI meters throughout the
installed base in North America.
• The focus has now shifted to the metering installation as a whole and not
the accuracy of the meter.
Slide 2
Field Testing
Common Features and Common Sources of Concern
Electro Mechanical meters were
subject to registration errors caused
by mechanical issues with moving
parts resulting in either the loss of
revenue to the utility or over billing
for the customer. Some of the more
common problems were:
• Friction wear
• Gear mesh misalignment
• Retarding magnet failure
• Timing motors
Slide 3
Electronic Meters – new failure modes require new testing
and inspection methods
Electronic meters fail as do electro mechanical meters but differently
• Their overall life expectancy is not nearly the same
• Failure modes include drift (unexpected)
• Failure modes include catastrophic (expected)
• Failure modes include non-catastrophic but significant measurement error
modes
• Failure modes can include non-measurement issues which render the meter
ineffective or inaccurate for billing purposes.
Slide 4
Best Practices
• Residential vs Commercial
• Self-Contained vs Transformer Rated
• Follow the money and be as proactive as possible
Slide 5
• Double check the meter number, the location the test result and the meter record
• Perform a visual safety inspection of the site. This includes utility and customer equipment.
Things to look for include intact down ground on pole, properly attached enclosure,
unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded
seals, etc.)
• Visually inspect for energy diversions (intentional and not). This includes broken or missing
wires, jumpers, open test switch, unconnected wires and foreign objects on meters or
other metering equipment. Broken or missing wires can seriously cause the under
measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to
1/2 of the registration on either 3 element or 2 element metering, respectively.
• Visually check lightning arrestors and transformers for damage or leaks.
• Check for proper grounding and bonding of metering equipment. Poor grounding and
bonding practices may result in inaccurate measurements that go undetected for long
periods of time. Implementing a single point ground policy and practice can reduce or
eliminate this type of issue.
• Burden test CTs and voltage check PTs.
Potential Site Check List
Slide 6
• Verify service voltage.
• Check that the transformers are wired correctly.
• Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires,
loose connections, etc.
• Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs are not cross
wired. Be sure CTs are grounded in one location (test switch) only.
• Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify
amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet
(voltage).
• Check rotation by closing in one phase at a time at the test switch and observing the phase meter
for forward rotation. If forward rotation is not observed measurements may be significantly impacted
as the phases are most likely cancelling each other out.
• Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing
compensation (line and/or transformer losses) the compensation should be verified either through
direct testing at the site or by examining recorded pulse data.
Potential Site Check List (cont)
Slide 7
• Verify metering vectors. Traditionally this has been done using instruments such as a circuit
analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and
values using meter manufacturer software or meter displays. Many of these desired values are
programmed into the meters Alternate/Utility display. Examining these values can provide much
information about the metering integrity. It may also assist in determining if unbalanced loads are
present and if CTs are sized properly. The vendor software generally has the ability to capture
both diagnostic and vector information electronically. These electronic records should be kept in
the meter shop for future comparisons.
• If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for
totalization they also should be verified vs. the known load on the meter.
• Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary
Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on
measured/reported values.
• Verify CT shunts are all opened.
Potential Site Check List (cont)
Slide 8
• Accuracy Testing
• Meter Communications
Performance
• Software & Firmware
Verification
• Setting Verification
• Functional Testing
• Disconnect/Reconnect
Functionality
and as left setting
Shop Testing
Slide 9
• Incorrect firmware
• Bad settings
• Alarms and errors that do
not clear
• Communication test
failures
• Bad tables
• Failed disconnect switches
What are we looking for?
Slide 10
Field Testing
• Accuracy Testing
• Meter Communications Performance
• Software & Firmware Verification
• Setting Verification
• Functional Testing
• Disconnect/Reconnect Functionality
and as left setting
• Tamper Verification
• Site Audits appropriate to the type
of meter
RMA’s, Root Cause Analysis and
In Service Testing
Opportunities to Learn:
• Meters returned from the field as bad or flagged on incoming inspection. These
RMA’s need to be tracked not only for warranty purposes but more importantly to
understand the root cause of the issues.
• In Service Test programs need to be utilized to understand
the overall performance of AMI meters and as failures are
identified these meters need to be dissected and the
failure mode understood. If necessary, once the failure
mode is understood the meter population may need to also
be dissected to identify sub-groups of meter that may be
similarly affected. This could be a group of meters…
• from the same shipment.
• that were deployed in the same geographic area.
• that saw the same type of usage or environment.
No one knows the actual life of their AMI meter. To do this we must learn as
much as we can from the failures and the performance of the meters we have
deployed.
Post-Deployment Needs
• AMI Population Management
• Once deployment is complete the certification and acceptance testing does not stop.
• Everyone understands the importance of acceptance testing, but future generations
of a smart meter also require certification testing.
• New software and firmware needs to be tested and compared against the
performance of older generations.
• New hardware must be tested and compared to older generations.
• Firmware upgrades need to be checked
• New head end systems or IT protocols need to be tested against a large
group of meters before going live.
Testing Frequency & Cost
• Tools (hardware and software)
• Personnel
• Frequency
• Test
• Report
• Analyze
• Learn, Share, Adapt
Slide 14
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
215-688-0298 (cell)
1-800-762-8211
This presentation can also be found under Meter
Conferences and Schools on the TESCO web site:
www.tesco-advent.com
Slide 15

More Related Content

PPT
Site Verification - Protocols & Tools for Complex Metering Installations
PPT
Site Verification - Protocols & Tools for Complex Metering Installations
PPT
Site Verification - Protocols & Tools for Complex Metering Installations
PPT
AMI Site Verification - Protocols & Tools for Complex Metering Installations
PPT
Site Verification - Protocols & Tools for Complex Metering Installations
PPTX
AMI Technology Overview
PPTX
Field Test Kits and Hot Socket Repair Kits
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
AMI Technology Overview
Field Test Kits and Hot Socket Repair Kits

What's hot (20)

PPTX
PPTX
Introduction to Meter Testing
PPTX
Introduction to Transformer Rated Metering
PPTX
Self-Contained Fundamentals
PPTX
Field Verification: Test Equipment and Best Practices
PPTX
Self Contained Metering Fundamentals and Introduction to Meter Testing
PPT
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
PPT
Customer Request Field Meter Testing Programs
PDF
Leading Indicator Program OverView Rev A
PPT
Standards - Accuracy, Precision & Traceability
PPT
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
PDF
Chap 2 standards and organization
PDF
Using the AC Drive Motor as a Transducer for detecting electrical and electro...
PDF
Sinetec automation pvt ltd
PPTX
Electronic Measurement and Instrumentation
PPTX
Identifying Energy Waste in your Plant/Facility Webinar with Fluke
PDF
SMC ETP System Power Transformer Maintenance
PDF
Smc EDA System Rotary Machine Insulation Analysis
Introduction to Meter Testing
Introduction to Transformer Rated Metering
Self-Contained Fundamentals
Field Verification: Test Equipment and Best Practices
Self Contained Metering Fundamentals and Introduction to Meter Testing
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Customer Request Field Meter Testing Programs
Leading Indicator Program OverView Rev A
Standards - Accuracy, Precision & Traceability
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Chap 2 standards and organization
Using the AC Drive Motor as a Transducer for detecting electrical and electro...
Sinetec automation pvt ltd
Electronic Measurement and Instrumentation
Identifying Energy Waste in your Plant/Facility Webinar with Fluke
SMC ETP System Power Transformer Maintenance
Smc EDA System Rotary Machine Insulation Analysis
Ad

Viewers also liked (7)

PPTX
Electric Vehicle Service Equipment (EVSE)
PPT
Meter Operations in a Post AMI World
PPTX
ECNC 2016 - Managing Meter Shops of the Future
PPT
Meter Asset Management at Coop's, IOU's, & Muni's
PPTX
History of Electric Metering
PPT
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
PPTX
TechAdvantage 2017 Hot Socket Issues - Causes and Best Practices
Electric Vehicle Service Equipment (EVSE)
Meter Operations in a Post AMI World
ECNC 2016 - Managing Meter Shops of the Future
Meter Asset Management at Coop's, IOU's, & Muni's
History of Electric Metering
Nebraska Meter Conference 2017 - CT Testing - Ratio, Burden, and Admittance
TechAdvantage 2017 Hot Socket Issues - Causes and Best Practices
Ad

Similar to Field Testing (20)

PPT
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
PPT
Instrument Transformer Testing
PPT
TESCO Site Verification in a Pre and Post AMI World
PPT
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
PPT
Instrument Transformer Testing in the Shop and Field
PPT
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
PPTX
Single Phase Meter Testing Overview
PPTX
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
PPT
Meter Operations During and After AMI Deployment
PPTX
Site Verification for Newer Employees
PPT
New Tools for a Next Generation of Metering - TESCO Solutions
PPT
Meter Operations in a Post AMI World
PPT
Meter Shops of the Future
PPT
Meter Operations In a Post AMI World
PPT
Meter Operations in a Post AMI World
PPT
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
PPTX
power quality monitoring and its devices.pptx
PPT
SEMA 2016 - Managing Meter Shops of the Future
PPTX
PPTX
Introduction to Self-Contained Metering
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformer Testing
TESCO Site Verification in a Pre and Post AMI World
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Single Phase Meter Testing Overview
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Meter Operations During and After AMI Deployment
Site Verification for Newer Employees
New Tools for a Next Generation of Metering - TESCO Solutions
Meter Operations in a Post AMI World
Meter Shops of the Future
Meter Operations In a Post AMI World
Meter Operations in a Post AMI World
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
power quality monitoring and its devices.pptx
SEMA 2016 - Managing Meter Shops of the Future
Introduction to Self-Contained Metering

Recently uploaded (20)

PDF
sbt 2.0: go big (Scala Days 2025 edition)
PDF
Flame analysis and combustion estimation using large language and vision assi...
DOCX
search engine optimization ppt fir known well about this
PPTX
Build Your First AI Agent with UiPath.pptx
PDF
CXOs-Are-you-still-doing-manual-DevOps-in-the-age-of-AI.pdf
PDF
Lung cancer patients survival prediction using outlier detection and optimize...
PDF
Convolutional neural network based encoder-decoder for efficient real-time ob...
PDF
Produktkatalog für HOBO Datenlogger, Wetterstationen, Sensoren, Software und ...
PPTX
Custom Battery Pack Design Considerations for Performance and Safety
PPTX
Training Program for knowledge in solar cell and solar industry
PDF
The-Future-of-Automotive-Quality-is-Here-AI-Driven-Engineering.pdf
PDF
Early detection and classification of bone marrow changes in lumbar vertebrae...
PDF
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
PPTX
Internet of Everything -Basic concepts details
PPTX
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
PDF
AI.gov: A Trojan Horse in the Age of Artificial Intelligence
PDF
sustainability-14-14877-v2.pddhzftheheeeee
PDF
Consumable AI The What, Why & How for Small Teams.pdf
PDF
5-Ways-AI-is-Revolutionizing-Telecom-Quality-Engineering.pdf
PDF
Transform-Quality-Engineering-with-AI-A-60-Day-Blueprint-for-Digital-Success.pdf
sbt 2.0: go big (Scala Days 2025 edition)
Flame analysis and combustion estimation using large language and vision assi...
search engine optimization ppt fir known well about this
Build Your First AI Agent with UiPath.pptx
CXOs-Are-you-still-doing-manual-DevOps-in-the-age-of-AI.pdf
Lung cancer patients survival prediction using outlier detection and optimize...
Convolutional neural network based encoder-decoder for efficient real-time ob...
Produktkatalog für HOBO Datenlogger, Wetterstationen, Sensoren, Software und ...
Custom Battery Pack Design Considerations for Performance and Safety
Training Program for knowledge in solar cell and solar industry
The-Future-of-Automotive-Quality-is-Here-AI-Driven-Engineering.pdf
Early detection and classification of bone marrow changes in lumbar vertebrae...
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
Internet of Everything -Basic concepts details
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
AI.gov: A Trojan Horse in the Age of Artificial Intelligence
sustainability-14-14877-v2.pddhzftheheeeee
Consumable AI The What, Why & How for Small Teams.pdf
5-Ways-AI-is-Revolutionizing-Telecom-Quality-Engineering.pdf
Transform-Quality-Engineering-with-AI-A-60-Day-Blueprint-for-Digital-Success.pdf

Field Testing

  • 1. Prepared by Tom Lawton,TESCO For the North Carolina Electric Meter School June 29, 2016 Polyphase Track Field Testing
  • 2. Premise • Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. • This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America. • The focus has now shifted to the metering installation as a whole and not the accuracy of the meter. Slide 2
  • 3. Field Testing Common Features and Common Sources of Concern Electro Mechanical meters were subject to registration errors caused by mechanical issues with moving parts resulting in either the loss of revenue to the utility or over billing for the customer. Some of the more common problems were: • Friction wear • Gear mesh misalignment • Retarding magnet failure • Timing motors Slide 3
  • 4. Electronic Meters – new failure modes require new testing and inspection methods Electronic meters fail as do electro mechanical meters but differently • Their overall life expectancy is not nearly the same • Failure modes include drift (unexpected) • Failure modes include catastrophic (expected) • Failure modes include non-catastrophic but significant measurement error modes • Failure modes can include non-measurement issues which render the meter ineffective or inaccurate for billing purposes. Slide 4
  • 5. Best Practices • Residential vs Commercial • Self-Contained vs Transformer Rated • Follow the money and be as proactive as possible Slide 5
  • 6. • Double check the meter number, the location the test result and the meter record • Perform a visual safety inspection of the site. This includes utility and customer equipment. Things to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded seals, etc.) • Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3 element or 2 element metering, respectively. • Visually check lightning arrestors and transformers for damage or leaks. • Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue. • Burden test CTs and voltage check PTs. Potential Site Check List Slide 6
  • 7. • Verify service voltage. • Check that the transformers are wired correctly. • Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. • Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs are not cross wired. Be sure CTs are grounded in one location (test switch) only. • Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage). • Check rotation by closing in one phase at a time at the test switch and observing the phase meter for forward rotation. If forward rotation is not observed measurements may be significantly impacted as the phases are most likely cancelling each other out. • Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the site or by examining recorded pulse data. Potential Site Check List (cont) Slide 7
  • 8. • Verify metering vectors. Traditionally this has been done using instruments such as a circuit analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and values using meter manufacturer software or meter displays. Many of these desired values are programmed into the meters Alternate/Utility display. Examining these values can provide much information about the metering integrity. It may also assist in determining if unbalanced loads are present and if CTs are sized properly. The vendor software generally has the ability to capture both diagnostic and vector information electronically. These electronic records should be kept in the meter shop for future comparisons. • If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for totalization they also should be verified vs. the known load on the meter. • Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on measured/reported values. • Verify CT shunts are all opened. Potential Site Check List (cont) Slide 8
  • 9. • Accuracy Testing • Meter Communications Performance • Software & Firmware Verification • Setting Verification • Functional Testing • Disconnect/Reconnect Functionality and as left setting Shop Testing Slide 9
  • 10. • Incorrect firmware • Bad settings • Alarms and errors that do not clear • Communication test failures • Bad tables • Failed disconnect switches What are we looking for? Slide 10
  • 11. Field Testing • Accuracy Testing • Meter Communications Performance • Software & Firmware Verification • Setting Verification • Functional Testing • Disconnect/Reconnect Functionality and as left setting • Tamper Verification • Site Audits appropriate to the type of meter
  • 12. RMA’s, Root Cause Analysis and In Service Testing Opportunities to Learn: • Meters returned from the field as bad or flagged on incoming inspection. These RMA’s need to be tracked not only for warranty purposes but more importantly to understand the root cause of the issues. • In Service Test programs need to be utilized to understand the overall performance of AMI meters and as failures are identified these meters need to be dissected and the failure mode understood. If necessary, once the failure mode is understood the meter population may need to also be dissected to identify sub-groups of meter that may be similarly affected. This could be a group of meters… • from the same shipment. • that were deployed in the same geographic area. • that saw the same type of usage or environment. No one knows the actual life of their AMI meter. To do this we must learn as much as we can from the failures and the performance of the meters we have deployed.
  • 13. Post-Deployment Needs • AMI Population Management • Once deployment is complete the certification and acceptance testing does not stop. • Everyone understands the importance of acceptance testing, but future generations of a smart meter also require certification testing. • New software and firmware needs to be tested and compared against the performance of older generations. • New hardware must be tested and compared to older generations. • Firmware upgrades need to be checked • New head end systems or IT protocols need to be tested against a large group of meters before going live.
  • 14. Testing Frequency & Cost • Tools (hardware and software) • Personnel • Frequency • Test • Report • Analyze • Learn, Share, Adapt Slide 14