MAINTENANCE
Mario Milošević
05.10.2016.
5.10.2016.
PROJECT GOAL
Reduce the down time of presses-sucess indicator
Better press cleaning
Better organising preventive maintenance
Maintenance scheme
Implementation of schedule for
calibration,monitoring and maintenance
Training programm
Manpower
New shift model
5.10.2016.
REDUCE THE PRESS DOWN TIME
This is a maintenance value indicator
According IFRA standards we can measure our
maintennace effiencience
Down times/operating times
Example : 24sata Geoman production
Operating time 16 hours for 26 days(September)
16 x 26 = 416 operative monthly hours
68 hours was down time
68/416 Geoman efficiency ratio is 16 %
0 % efficiency – no press down time
5.10.2016.
GEOMAN MONTHLY EFFICIENCY RATIO
5.10.2016.
0
50
100
150
200
250
300
350
400
450
operative
hours
down time
hours
efficience
main. ratio
UNISET 75 MONTHLY EFFICIENCY RATIO
5.10.2016.
0
100
200
300
400
500
600
700
operative
hours
down time
hours
efficience
main. ratio
BETTER PRESSES CLEANING
Do not underestimate cleaning like maintennace
begining
5.10.2016.
BETTER PREVENTIVE MAINTENANCE
ORGANISING
Special maintennace list for printers
Special maintenance list for electrical&mechanical
staff
Special maintenance list for mailroom
Daily,weekly,monthly and annualy checking
maintenance
TZMaintenance_List_Printers_Tiskara all
presses.xls
maintenance
TZMaintenance_List_MECHANICAL&ELECTRICA
L_Tiskara all equipment.xls
5.10.2016.
MAINTENANCE SCHEME
MAINTENANCE TZMASTER MAINTENANCE PLAN
KBA COLORA.MPP
5.10.2016.
MAINTENANCE PROCESS MONITORING
New software programmmaintenance TZGraph
maintenance.jpg
Easy tool handling
Easy checking and controling
Efficience reporting(server visible,multi language)
1 month implementation
5.10.2016.
TRAINING PROGRAMM
Manpower motivation
Printing house visits
Equipment suppliers visit(open house)
Possibility share experience with Austria
maintenance staff
Press audits + training
5.10.2016.
MANPOWER – NEW SHIFT MODEL
Inovative solution in TZ- duty on call
No over times-no weekend fix maintenance staff
More responsibility for printers,shift leaders and
operaters
5.10.2016.
WEEK 1 WEEK 2 WEEK 3 WEEK 4
Working
hours check
održavanje Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak
7h - 15h
First shift (both presses) 15h - 23h 23h - 07h 7h - 15h 15h - 23h
Keser D 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176
Briški V(Jambrešak) 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176
Fabijanić 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176
Gamilec J 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176
Gamilec D 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176
Visić K 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176
5.10.2016.
Thank you

maintenance project

  • 1.
  • 2.
    PROJECT GOAL Reduce thedown time of presses-sucess indicator Better press cleaning Better organising preventive maintenance Maintenance scheme Implementation of schedule for calibration,monitoring and maintenance Training programm Manpower New shift model 5.10.2016.
  • 3.
    REDUCE THE PRESSDOWN TIME This is a maintenance value indicator According IFRA standards we can measure our maintennace effiencience Down times/operating times Example : 24sata Geoman production Operating time 16 hours for 26 days(September) 16 x 26 = 416 operative monthly hours 68 hours was down time 68/416 Geoman efficiency ratio is 16 % 0 % efficiency – no press down time 5.10.2016.
  • 4.
    GEOMAN MONTHLY EFFICIENCYRATIO 5.10.2016. 0 50 100 150 200 250 300 350 400 450 operative hours down time hours efficience main. ratio
  • 5.
    UNISET 75 MONTHLYEFFICIENCY RATIO 5.10.2016. 0 100 200 300 400 500 600 700 operative hours down time hours efficience main. ratio
  • 6.
    BETTER PRESSES CLEANING Donot underestimate cleaning like maintennace begining 5.10.2016.
  • 7.
    BETTER PREVENTIVE MAINTENANCE ORGANISING Specialmaintennace list for printers Special maintenance list for electrical&mechanical staff Special maintenance list for mailroom Daily,weekly,monthly and annualy checking maintenance TZMaintenance_List_Printers_Tiskara all presses.xls maintenance TZMaintenance_List_MECHANICAL&ELECTRICA L_Tiskara all equipment.xls 5.10.2016.
  • 8.
    MAINTENANCE SCHEME MAINTENANCE TZMASTERMAINTENANCE PLAN KBA COLORA.MPP 5.10.2016.
  • 9.
    MAINTENANCE PROCESS MONITORING Newsoftware programmmaintenance TZGraph maintenance.jpg Easy tool handling Easy checking and controling Efficience reporting(server visible,multi language) 1 month implementation 5.10.2016.
  • 10.
    TRAINING PROGRAMM Manpower motivation Printinghouse visits Equipment suppliers visit(open house) Possibility share experience with Austria maintenance staff Press audits + training 5.10.2016.
  • 11.
    MANPOWER – NEWSHIFT MODEL Inovative solution in TZ- duty on call No over times-no weekend fix maintenance staff More responsibility for printers,shift leaders and operaters 5.10.2016. WEEK 1 WEEK 2 WEEK 3 WEEK 4 Working hours check održavanje Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak Srijeda Četvrtak Petak Subota Nedjelja Ponedjeljak Utorak 7h - 15h First shift (both presses) 15h - 23h 23h - 07h 7h - 15h 15h - 23h Keser D 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176 Briški V(Jambrešak) 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176 Fabijanić 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176 Gamilec J 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176 Gamilec D 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176 Visić K 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 8 8 8 0 0 8 8 176
  • 12.