Abstract
• As many utilities have elected to deploy advanced metering systems
and millions of new solid-state, microprocessor based end-points
with communications under glass, a dramatic shift has begun
regarding where metering resources are being deployed and what
they are doing.
• This presentation will highlight the new value proposition for
metering personnel at their respective utility companies in a post-
AMI World.
• Examples of issues which have arisen or been identified over the
course of various deployments and in the immediate aftermath of an
AMI deployment.
Slide 3
Pre-AMI Meter Operations
• Fewer meter techs in the field and in the shop than
there were 25 years ago
• Fewer Field checks and site verifications due to lack of
personnel, lack of experience and lack of expertise
• More features under glass in the meters even before
AMI deployed
• Significantly more features under glass in every AMR
and AMI system being considered or being deployed
• Metering losses starting to be identified “by accident” as
opposed to being “by design”.
Common Features and Common Sources of Concern
Slide 4
The Pendulum Starts to Move
• Meter Operations. Prior to deployment many larger utilities take an attitude
of “this is only metering – how hard can that be?” Over the course of
deployment meter operations gains a stature and a respect from the rest of
the organization that was not previously accorded them – even if this is only
begrudging respect.
• New tests for AMI meters (e.g. communication,
disconnect) are identified.
• The complexity and issues around high revenue
metering are at least acknowledged by the rest of
the organization.
• Tests which have not been performed in years are
suddenly back in vogue.
Slide 5
The New Realities
• Electro-Mechanical Meters typically lasted 30 years and more. Electronic AMI
meters are typically envisioned to have a life span of 15 years and given the
pace of technology advances in metering are not expected to last much longer
than this.
• This means entire systems are envisioned to be exchanged every 15 years or
so. In the interim the meter population and communication network inherent in
the infrastructure for each utility must be maintained.
• Meter communication and meter data
management are becoming as important to
metering operations as meter accuracy.
• Firmware upgrades, firmware stability and cyber
security are becoming increasingly important to
metering departments
Slide 6
Expected and Unexpected Trends at the
End of Deployment
Expected:
• The AMI deployment team will declare victory at some point and move on.
Clean-up will be left for the meter service department
• Change Management continues to be a tremendous challenge for every vendor
through every deployment
• Meter Acceptance testing including far more than accuracy testing for every
deployment
• Firmware upgrades must be checked and tested before mass deployment
Unexpected:
• Not all forms are available by the end
of deployment and must be installed
as part of normal operations by the
meter service department
• Meter Certification Testing never
slowed down over the course of any of
the deployments
Slide 7
Why Do AMI Meters Fail?
Looking back at various deployments – what are the chief
causes to reject meter shipments?
Meter functional test failures including but not limited to;
• Incorrect firmware
• Bad settings
• Alarms and errors that do not clear
• Communication test failures
• Bad tables
• Failed disconnect switches
Slide 8
Lessons for the Future?
• Are these infant mortality issues or are these issues to be concerned about
going forward?
• What was NEVER the reason for rejecting a shipment – meter accuracy.
• Which are the most difficult meters for every deployment – the transformer
rated meters. Often these forms are not available until very late in the
deployment and sometimes not until the deployment has officially ended.
Slide 9
• Most AMI deployments utilize third-party contractors to handle the
residential and some self contained non-2S services. The balance are
typically handled by the meter service department of the utility.
• No AMI deployment has used the AMI communication network to handle the
communication with the largest customer meters. The risk from even a
short term interruption of communication or loss of data far outweighs to
benefit of meters which are already being communicated with daily or even
several times a day.
• As these services are evaluated for new metering technology issues are
being found at some accounts. These issues represent revenue losses due
to inappropriate metering schemes or partially failed metering components
(e.g. transformers, electronic components).
Commercial and Industrial Metering Challenges
Slide 10
• Metering is becoming more about IT. Some metering departments have
been reorganized after AMI as part of the IT department.
• Metering emphasis will shift strongly toward C&I customers and further and
further away from residential meters
• Metering resources are being refocused on C&I accounts.
• There are fewer levels of meter tech. Every meter tech needs to be at the
higher level as there is not enough lower level work to warrant full time
employees
• Provincial Governments are starting to look closer at AMI technology and
deployment issues
• More pressure is being put on the Utility to perform more testing in their own
labs and at third party labs. We need to once again be the experts in all
things metering.
How Are These New Realities Starting to Affect
Metering Operations?
Slide 11
• Responsible for either reviewing ANSI Tests or even performing some of
these ANSI Tests
• Perform Meter Functionality testing on new and returned AMI meters
• Register and communication module energy measurement comparison
• Disconnect/Reconnect Functionality
• Outage Performance
• Meter Communications Performance
• Consumer safety and combating real and perceived issues
• Near continuous research into the “next” technology and the next
deployment
New or Expanded Roles for Metering
Departments of All Sizes
Slide 12
• Accuracy testing
• Meter Communications
Performance
• Software and firmware
verification
• Setting verification
• Functional testing
• Disconnect/reconnect
Functionality
and as left setting
Shop Testing
Slide 13
Field Testing
• Accuracy Testing
• Meter Communications Performance
• Software & Firmware Verification
• Setting Verification
• Functional Testing
• Disconnect/Reconnect Functionality
and as left setting
• Tamper Verification
• Site Audits appropriate to the type
of meter
Slide 14
RMA’s, Root Cause Analysis, and
In-Service Testing
Opportunities to Learn:
• Meters returned from the field as bad or flagged on incoming inspection. These
RMA’s need to be tracked not only for warranty purposes but more importantly to
understand the root cause of the issues.
• In Service Test programs need to be utilized to understand
the overall performance of AMI meters and as failures are
identified these meters need to be dissected and the
failure mode understood. If necessary, once the failure
mode is understood the meter population may need to also
be dissected to identify sub-groups of meter that may be
similarly affected. This could be a group of meters…
• from the same shipment.
• that were deployed in the same geographic area.
• that saw the same type of usage or environment.
No one knows the actual life of their AMI meter. To do this we must learn as much
as we can from the failures and the performance of the meters we have deployed.
Slide 15
Post-Deployment Needs
• Once deployment is complete the certification and acceptance testing does not stop.
• Everyone understands the importance of acceptance testing, but future generations
of a smart meter also require certification testing.
• New software and firmware needs to be tested and compared against the
performance of older generations.
• New hardware must be tested and compared to older generations.
• Firmware upgrades need to be checked
• New head end systems or IT protocols need to be tested against a large
group of meters before going live.
Slide 16
Real Life Examples of Change
Management in Action
• Issues in the system not the components – what is the definition of a meter and
when did the meter change?
– Meter and communication device interface
• Feature Creep – every manufacturer wants to differentiate themselves –
sometimes this works in unanticipated ways
– Recovery from power outages
– Short and long demand periods
• But we only changed….lessons we
should have learned from Microsoft
– Over the air upgrades
• Thank Goodness for test plans – right?
– Half closed disconnect devices
– Disconnect devices of unknown state
– Meters with incorrect firmware
– Hot Sockets and Meter failures during and after deployment
Slide 17
Summary
• The focus is on far more than accuracy
• The meter man of the future knows not only metering but they are communication
experts and are involved with handling, reporting and analyzing far more customer
and system data
• There are fewer “routine jobs” in the field and many of the standard tasks are no
longer required. This will lead to fewer classifications of meter techs going forward
and the need for a more highly trained tech.
• Each Utility must take a far more active role as part of checking, certifying, and
rechecking the functionality of their meters.
• Metering will be in a near constant cycle of looking for
the next technology, evaluating those technologies,
planning for deploying these technologies, and
cleaning up the aftermath of the deployment of
these technologies.
Slide 18
Questions and Discussion
Tom Lawton
TESCO – The Eastern Specialty Company
Bristol, PA
215-785-2338
This presentation can also be found under Meter
Conferences and Schools on the TESCO web site:
www.tesco-advent.com

More Related Content

PPT
Meter Operations in a Post AMI World
PPT
Metering in a Post AMI World
PPT
Meter Asset Tracking and the Power of Analytics in an AMI System
PPT
Managing Vendor Issues on AMI Design
PPT
Meter Operations in a Post AMI World
PPT
Meter Operations in a Post AMI World
PPT
Meter Operations in a Post AMI World
Meter Operations in a Post AMI World
Metering in a Post AMI World
Meter Asset Tracking and the Power of Analytics in an AMI System
Managing Vendor Issues on AMI Design
Meter Operations in a Post AMI World
Meter Operations in a Post AMI World
Meter Operations in a Post AMI World

What's hot (20)

PPT
Meter Operations in a Post AMI World
PPT
Meter Operations in a Post AMI World
PPT
Tesco's AMI Specific Products and Services
PPT
SEMA 2016 - Managing Meter Shops of the Future
PPT
Meter Operations in a Post AMI World
PPT
Meter Operations In a Post AMI World
PPT
Meter Operations in a Post AMI World
PPT
Meter Shops of the Future
PPT
Meter Operations in a Post AMI World
PPT
Advanced Metering Infrastructure (AMI) Overview
PPTX
New Challenges for the Meter Shop
PPT
Meter Operations in a Post AMI World
PPTX
ECNC 2016 - Managing Meter Shops of the Future
PPT
Meter Operations in a Post AMI World
PPT
SEMA - 2016 Meter Farms, New Tools for AMR and AMI Meters
PPT
Meter Operations During and After AMI Deployment
PPT
Meter Operations in a Post AMI World
PPT
Asset Tracking Systems for Meter Services
PPT
Asset Management Gas Meter Farms
Meter Operations in a Post AMI World
Meter Operations in a Post AMI World
Tesco's AMI Specific Products and Services
SEMA 2016 - Managing Meter Shops of the Future
Meter Operations in a Post AMI World
Meter Operations In a Post AMI World
Meter Operations in a Post AMI World
Meter Shops of the Future
Meter Operations in a Post AMI World
Advanced Metering Infrastructure (AMI) Overview
New Challenges for the Meter Shop
Meter Operations in a Post AMI World
ECNC 2016 - Managing Meter Shops of the Future
Meter Operations in a Post AMI World
SEMA - 2016 Meter Farms, New Tools for AMR and AMI Meters
Meter Operations During and After AMI Deployment
Meter Operations in a Post AMI World
Asset Tracking Systems for Meter Services
Asset Management Gas Meter Farms
Ad

Similar to Managing the Meter Shop of the Future Through Better Tools and Information (14)

PPTX
AMI Technology Overview
PPTX
AMI Technology Overview
PPTX
AMI Technology Overview
PPTX
Fundamentals of AMI Testing
PPT
Meter Asset Management at Coop's, IOU's and Muni's
PPT
Meter Asset Management at Coop's, IOU's, & Muni's
PPTX
New Uses For Electric Meters as We Continue to Leverage AMI Technology
PPT
AGA 2017 Gas Meter Farms
PPT
Meter Farms: AEIC Measurement Technologies Working Group
PPT
Meter Testing and AMI Deployment - Before, During and After
PPT
You Went AMI, Where Will You Go Next_Mid-South
AMI Technology Overview
AMI Technology Overview
AMI Technology Overview
Fundamentals of AMI Testing
Meter Asset Management at Coop's, IOU's and Muni's
Meter Asset Management at Coop's, IOU's, & Muni's
New Uses For Electric Meters as We Continue to Leverage AMI Technology
AGA 2017 Gas Meter Farms
Meter Farms: AEIC Measurement Technologies Working Group
Meter Testing and AMI Deployment - Before, During and After
You Went AMI, Where Will You Go Next_Mid-South
Ad

Recently uploaded (20)

PDF
The influence of sentiment analysis in enhancing early warning system model f...
DOCX
search engine optimization ppt fir known well about this
PPTX
future_of_ai_comprehensive_20250822032121.pptx
PDF
sustainability-14-14877-v2.pddhzftheheeeee
PPTX
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
PDF
Transform-Quality-Engineering-with-AI-A-60-Day-Blueprint-for-Digital-Success.pdf
PDF
Taming the Chaos: How to Turn Unstructured Data into Decisions
PDF
Enhancing plagiarism detection using data pre-processing and machine learning...
PPTX
Microsoft User Copilot Training Slide Deck
PDF
Dell Pro Micro: Speed customer interactions, patient processing, and learning...
PDF
Early detection and classification of bone marrow changes in lumbar vertebrae...
PPTX
Training Program for knowledge in solar cell and solar industry
PDF
Improvisation in detection of pomegranate leaf disease using transfer learni...
PDF
The-Future-of-Automotive-Quality-is-Here-AI-Driven-Engineering.pdf
PDF
Transform-Your-Factory-with-AI-Driven-Quality-Engineering.pdf
PPTX
AI IN MARKETING- PRESENTED BY ANWAR KABIR 1st June 2025.pptx
PPTX
MuleSoft-Compete-Deck for midddleware integrations
PDF
Transform-Your-Supply-Chain-with-AI-Driven-Quality-Engineering.pdf
PDF
CXOs-Are-you-still-doing-manual-DevOps-in-the-age-of-AI.pdf
PPTX
Build Your First AI Agent with UiPath.pptx
The influence of sentiment analysis in enhancing early warning system model f...
search engine optimization ppt fir known well about this
future_of_ai_comprehensive_20250822032121.pptx
sustainability-14-14877-v2.pddhzftheheeeee
GROUP4NURSINGINFORMATICSREPORT-2 PRESENTATION
Transform-Quality-Engineering-with-AI-A-60-Day-Blueprint-for-Digital-Success.pdf
Taming the Chaos: How to Turn Unstructured Data into Decisions
Enhancing plagiarism detection using data pre-processing and machine learning...
Microsoft User Copilot Training Slide Deck
Dell Pro Micro: Speed customer interactions, patient processing, and learning...
Early detection and classification of bone marrow changes in lumbar vertebrae...
Training Program for knowledge in solar cell and solar industry
Improvisation in detection of pomegranate leaf disease using transfer learni...
The-Future-of-Automotive-Quality-is-Here-AI-Driven-Engineering.pdf
Transform-Your-Factory-with-AI-Driven-Quality-Engineering.pdf
AI IN MARKETING- PRESENTED BY ANWAR KABIR 1st June 2025.pptx
MuleSoft-Compete-Deck for midddleware integrations
Transform-Your-Supply-Chain-with-AI-Driven-Quality-Engineering.pdf
CXOs-Are-you-still-doing-manual-DevOps-in-the-age-of-AI.pdf
Build Your First AI Agent with UiPath.pptx

Managing the Meter Shop of the Future Through Better Tools and Information

  • 1. Slide 1 Prepared by Tom Lawton,TESCO for the 2017 North Carolina Electric Meter School Management Session, Kensington B Tuesday, June 27, 2017 at 9:30 a.m. Managing the Meter Shop of the Future Through Better Tools & Information
  • 2. Slide 2 Abstract • As many utilities have elected to deploy advanced metering systems and millions of new solid-state, microprocessor based end-points with communications under glass, a dramatic shift has begun regarding where metering resources are being deployed and what they are doing. • This presentation will highlight the new value proposition for metering personnel at their respective utility companies in a post- AMI World. • Examples of issues which have arisen or been identified over the course of various deployments and in the immediate aftermath of an AMI deployment.
  • 3. Slide 3 Pre-AMI Meter Operations • Fewer meter techs in the field and in the shop than there were 25 years ago • Fewer Field checks and site verifications due to lack of personnel, lack of experience and lack of expertise • More features under glass in the meters even before AMI deployed • Significantly more features under glass in every AMR and AMI system being considered or being deployed • Metering losses starting to be identified “by accident” as opposed to being “by design”. Common Features and Common Sources of Concern
  • 4. Slide 4 The Pendulum Starts to Move • Meter Operations. Prior to deployment many larger utilities take an attitude of “this is only metering – how hard can that be?” Over the course of deployment meter operations gains a stature and a respect from the rest of the organization that was not previously accorded them – even if this is only begrudging respect. • New tests for AMI meters (e.g. communication, disconnect) are identified. • The complexity and issues around high revenue metering are at least acknowledged by the rest of the organization. • Tests which have not been performed in years are suddenly back in vogue.
  • 5. Slide 5 The New Realities • Electro-Mechanical Meters typically lasted 30 years and more. Electronic AMI meters are typically envisioned to have a life span of 15 years and given the pace of technology advances in metering are not expected to last much longer than this. • This means entire systems are envisioned to be exchanged every 15 years or so. In the interim the meter population and communication network inherent in the infrastructure for each utility must be maintained. • Meter communication and meter data management are becoming as important to metering operations as meter accuracy. • Firmware upgrades, firmware stability and cyber security are becoming increasingly important to metering departments
  • 6. Slide 6 Expected and Unexpected Trends at the End of Deployment Expected: • The AMI deployment team will declare victory at some point and move on. Clean-up will be left for the meter service department • Change Management continues to be a tremendous challenge for every vendor through every deployment • Meter Acceptance testing including far more than accuracy testing for every deployment • Firmware upgrades must be checked and tested before mass deployment Unexpected: • Not all forms are available by the end of deployment and must be installed as part of normal operations by the meter service department • Meter Certification Testing never slowed down over the course of any of the deployments
  • 7. Slide 7 Why Do AMI Meters Fail? Looking back at various deployments – what are the chief causes to reject meter shipments? Meter functional test failures including but not limited to; • Incorrect firmware • Bad settings • Alarms and errors that do not clear • Communication test failures • Bad tables • Failed disconnect switches
  • 8. Slide 8 Lessons for the Future? • Are these infant mortality issues or are these issues to be concerned about going forward? • What was NEVER the reason for rejecting a shipment – meter accuracy. • Which are the most difficult meters for every deployment – the transformer rated meters. Often these forms are not available until very late in the deployment and sometimes not until the deployment has officially ended.
  • 9. Slide 9 • Most AMI deployments utilize third-party contractors to handle the residential and some self contained non-2S services. The balance are typically handled by the meter service department of the utility. • No AMI deployment has used the AMI communication network to handle the communication with the largest customer meters. The risk from even a short term interruption of communication or loss of data far outweighs to benefit of meters which are already being communicated with daily or even several times a day. • As these services are evaluated for new metering technology issues are being found at some accounts. These issues represent revenue losses due to inappropriate metering schemes or partially failed metering components (e.g. transformers, electronic components). Commercial and Industrial Metering Challenges
  • 10. Slide 10 • Metering is becoming more about IT. Some metering departments have been reorganized after AMI as part of the IT department. • Metering emphasis will shift strongly toward C&I customers and further and further away from residential meters • Metering resources are being refocused on C&I accounts. • There are fewer levels of meter tech. Every meter tech needs to be at the higher level as there is not enough lower level work to warrant full time employees • Provincial Governments are starting to look closer at AMI technology and deployment issues • More pressure is being put on the Utility to perform more testing in their own labs and at third party labs. We need to once again be the experts in all things metering. How Are These New Realities Starting to Affect Metering Operations?
  • 11. Slide 11 • Responsible for either reviewing ANSI Tests or even performing some of these ANSI Tests • Perform Meter Functionality testing on new and returned AMI meters • Register and communication module energy measurement comparison • Disconnect/Reconnect Functionality • Outage Performance • Meter Communications Performance • Consumer safety and combating real and perceived issues • Near continuous research into the “next” technology and the next deployment New or Expanded Roles for Metering Departments of All Sizes
  • 12. Slide 12 • Accuracy testing • Meter Communications Performance • Software and firmware verification • Setting verification • Functional testing • Disconnect/reconnect Functionality and as left setting Shop Testing
  • 13. Slide 13 Field Testing • Accuracy Testing • Meter Communications Performance • Software & Firmware Verification • Setting Verification • Functional Testing • Disconnect/Reconnect Functionality and as left setting • Tamper Verification • Site Audits appropriate to the type of meter
  • 14. Slide 14 RMA’s, Root Cause Analysis, and In-Service Testing Opportunities to Learn: • Meters returned from the field as bad or flagged on incoming inspection. These RMA’s need to be tracked not only for warranty purposes but more importantly to understand the root cause of the issues. • In Service Test programs need to be utilized to understand the overall performance of AMI meters and as failures are identified these meters need to be dissected and the failure mode understood. If necessary, once the failure mode is understood the meter population may need to also be dissected to identify sub-groups of meter that may be similarly affected. This could be a group of meters… • from the same shipment. • that were deployed in the same geographic area. • that saw the same type of usage or environment. No one knows the actual life of their AMI meter. To do this we must learn as much as we can from the failures and the performance of the meters we have deployed.
  • 15. Slide 15 Post-Deployment Needs • Once deployment is complete the certification and acceptance testing does not stop. • Everyone understands the importance of acceptance testing, but future generations of a smart meter also require certification testing. • New software and firmware needs to be tested and compared against the performance of older generations. • New hardware must be tested and compared to older generations. • Firmware upgrades need to be checked • New head end systems or IT protocols need to be tested against a large group of meters before going live.
  • 16. Slide 16 Real Life Examples of Change Management in Action • Issues in the system not the components – what is the definition of a meter and when did the meter change? – Meter and communication device interface • Feature Creep – every manufacturer wants to differentiate themselves – sometimes this works in unanticipated ways – Recovery from power outages – Short and long demand periods • But we only changed….lessons we should have learned from Microsoft – Over the air upgrades • Thank Goodness for test plans – right? – Half closed disconnect devices – Disconnect devices of unknown state – Meters with incorrect firmware – Hot Sockets and Meter failures during and after deployment
  • 17. Slide 17 Summary • The focus is on far more than accuracy • The meter man of the future knows not only metering but they are communication experts and are involved with handling, reporting and analyzing far more customer and system data • There are fewer “routine jobs” in the field and many of the standard tasks are no longer required. This will lead to fewer classifications of meter techs going forward and the need for a more highly trained tech. • Each Utility must take a far more active role as part of checking, certifying, and rechecking the functionality of their meters. • Metering will be in a near constant cycle of looking for the next technology, evaluating those technologies, planning for deploying these technologies, and cleaning up the aftermath of the deployment of these technologies.
  • 18. Slide 18 Questions and Discussion Tom Lawton TESCO – The Eastern Specialty Company Bristol, PA 215-785-2338 This presentation can also be found under Meter Conferences and Schools on the TESCO web site: www.tesco-advent.com