Mastes Scheduling Producción I IITI MC. Ma. del Pilar C. León Franco
Master  Scheduling  (MPS) It forms the link between production planning and what manufacturing will actually build. It forms the basis for calculating the capacity and resources needed The MPS drives the material requirements plan It keeps priorities valid. The MPS is a priority plan for manufacturing.
Master Scheduling (MPS) The end items made by the company are assembled from component and subcomponents parts. These must be available in the right quantities at the right time to support the master production schedule.  The material requirements planning system plan the schedule for these components based on the needs of the MPS.
Master Scheduling (MPS) The master production schedule is a plan for manufacturing.  It reflects the needs of the marketplace and the capacity of manufacturing and forms a priority plan for manufacturing to follow.
Master Scheduling (MPS) MPS Makes possible valid order promises Sales Production The production plan Forecasts for individual end items Actual orders received from customers and for stock replenishment Inventory levels for individual end items Capacity restraints
Relationship to  produce plan 500 Aggregate Inventory (units) Production Plan 250 215 160 160 160 160 Aggregate  Forecast (units) 6 5 4 3 2 1 Week
Developing a Master production Schedule The objectives in developing an MPS are: To maintain the desired level of customer service by maintaining finished-goods inventory levels or by schedule to meet customer delivery requirements To make the best use of material, labor and equipment To maintain inventory investment at the required levels
Developing a Master production Schedule The plan must satisfy customer demand, be within the capacity of manufacturing, and be within the guidelines of the production plan
Developing a Master production Schedule Steps: Develop a preliminary MPS Check the preliminary MPS against available capacity Resolve differences between the preliminary MPS and capacity availability
Preliminary Master Production  Schedule   100 100   100   MPS 20 80 40 0 60 20 80 Projected Available 60 60 60 60 60 60 Forecast 6 5 4 3 2 1 0 Week
Rough-Cut Capacity Planning RCCP checks whether critical resources are available to support the preliminary master production schedules.  Critical resources include bottleneck operations, labor, and critical materials.
Rough-Cut Capacity  Planning           Total Horas           Fine           Medium Total 3 2 1 0 Week hrs./unit 1.2 Fine hrs./unit 0.5 Medium 80 20 30 10 20 Fine 120 15 40 25 40 Medium Total 3 2 1 0 Week
Resolution of Differences Compare the total time required to the available capacity of the work center Resources use Customer service Cost
Master Schedule Decisions The MPS should represent as efficiently as possible what manufacturing will make. Make to stock products:  Limited number of standard items are assembled from many components Make to order products:  Many different ended items are made form a small number of components Assemble to order products:  Many end items can be made form combinations of basic components and subassemblies.
Master Schedule Decisions Make to stock Assemble to Order Make to order End Product Raw Material End Product Raw Material End Product Raw Material MPS MPS MPS FAS FAS FAS = Finaly Assembly Schedule

More Related Content

PPT
Master production schedule
PPTX
Production Planning & Control
PPTX
Mrp
PDF
Production planning hierarchy
PPTX
Capacity planning ppt
PPTX
MRP I and MRP II
PPT
Material Requirement Planning (MRP)
PPTX
Material requirement planning (mrp1)
Master production schedule
Production Planning & Control
Mrp
Production planning hierarchy
Capacity planning ppt
MRP I and MRP II
Material Requirement Planning (MRP)
Material requirement planning (mrp1)

What's hot (20)

PPT
Operation scheduling
PPTX
MASTER PRODUCTION SCHEDULE (MPS).pptx
PPT
material requirement planning
PPT
Aggregate planning
PDF
What is master production schedule
PPTX
PPTX
Aggregate planning
PPT
Ch17 Mrp
PPT
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
PPT
Production planning hierarchy
PPT
Objective of inventory management
PDF
Presentation on operation scheduling
PPTX
Inventory management
 
DOCX
Material requirement planning
PPT
Inventory management
PPTX
Material Requirement Planning (mrp)
PPT
Production planning and scheduling
PPT
Aggregate Production Planning
PPTX
Materials requirements planning
Operation scheduling
MASTER PRODUCTION SCHEDULE (MPS).pptx
material requirement planning
Aggregate planning
What is master production schedule
Aggregate planning
Ch17 Mrp
MATERIAL REQUIREMENT PLANNING AND BILLS OF MATERIAL
Production planning hierarchy
Objective of inventory management
Presentation on operation scheduling
Inventory management
 
Material requirement planning
Inventory management
Material Requirement Planning (mrp)
Production planning and scheduling
Aggregate Production Planning
Materials requirements planning
Ad

Similar to Master Scheduling (20)

PPT
Master Production scheduling Plan in Production
PPT
mastes Production scheduling Plan in production
PPTX
CAPACITY MANAGEMENT-GROUP CAPACITY REQUIRMENTS
PPTX
Production Planning
PPTX
S2019302018 m saqib nawaz mps
PDF
Master schedualing
PPTX
MPS.pptx
PPTX
Master scheduling
PPT
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
PPTX
SCM Chap 6mmmmmmmmmmmmmmmmmmmmmmmmm.pptx
PPTX
Master Production Scheduling (MPS)
PPT
PPTX
Operations Planning
PPT
Manufacturing plng and control
PPTX
MRP Theory: Master Schedule, Bill of Material and Lead Times
PPTX
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
PPTX
5. introduction to manufacturing_plannin
PPTX
small and effective ppt on master production schedule
PPT
Lect 6.ppt
PPTX
Advanced Planning & Scheduling
Master Production scheduling Plan in Production
mastes Production scheduling Plan in production
CAPACITY MANAGEMENT-GROUP CAPACITY REQUIRMENTS
Production Planning
S2019302018 m saqib nawaz mps
Master schedualing
MPS.pptx
Master scheduling
SCHEDULING.pptdjdgjgjdjgajdjasdjadasgdgdduaa
SCM Chap 6mmmmmmmmmmmmmmmmmmmmmmmmm.pptx
Master Production Scheduling (MPS)
Operations Planning
Manufacturing plng and control
MRP Theory: Master Schedule, Bill of Material and Lead Times
MRP Theory: Master Production Schedule, Bill of Material and Lead Times
5. introduction to manufacturing_plannin
small and effective ppt on master production schedule
Lect 6.ppt
Advanced Planning & Scheduling
Ad

Recently uploaded (20)

DOCX
Handbook of entrepreneurship- Chapter 7- Types of business organisations
PDF
From Legacy to Velocity: how we rebuilt everything in 8 months.
PDF
Handouts for Housekeeping.pdfbababvsvvNnnh
PDF
Challenges of Managing International Schools (www.kiu. ac.ug)
DOCX
ola and uber project work (Recovered).docx
PDF
Sustainable Digital Finance in Asia_FINAL_22.pdf
PPTX
Chapter 2 strategic Presentation (6).pptx
PPT
BCG内部幻灯片撰写. slide template BCG.slide template
PPTX
Supply Chain under WAR (Managing Supply Chain Amid Political Conflict).pptx
PPTX
Capital Investment in IS Infrastracture and Innovation (SDG9)
PDF
QT INTRODUCTION chapters that help to study
PDF
The Impact of Historical Events on Legal Communication Styles (www.kiu.ac.ug)
PDF
Comments on Clouds that Assimilate Parts I&II.pdf
PDF
Life Cycle Management of Lessons Learned
PDF
dataZense for Data Analytics unleashed features
PPTX
Accounting Management SystemBatch-4.pptx
PDF
Clouds that Assimilate the Build Parts I&II .pdf
PDF
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
DOCX
Center Enamel Can Provide Pressure Vessels for Maldives Chemical Industry.docx
PDF
Second Hand Fashion Call to Action March 2025
Handbook of entrepreneurship- Chapter 7- Types of business organisations
From Legacy to Velocity: how we rebuilt everything in 8 months.
Handouts for Housekeeping.pdfbababvsvvNnnh
Challenges of Managing International Schools (www.kiu. ac.ug)
ola and uber project work (Recovered).docx
Sustainable Digital Finance in Asia_FINAL_22.pdf
Chapter 2 strategic Presentation (6).pptx
BCG内部幻灯片撰写. slide template BCG.slide template
Supply Chain under WAR (Managing Supply Chain Amid Political Conflict).pptx
Capital Investment in IS Infrastracture and Innovation (SDG9)
QT INTRODUCTION chapters that help to study
The Impact of Historical Events on Legal Communication Styles (www.kiu.ac.ug)
Comments on Clouds that Assimilate Parts I&II.pdf
Life Cycle Management of Lessons Learned
dataZense for Data Analytics unleashed features
Accounting Management SystemBatch-4.pptx
Clouds that Assimilate the Build Parts I&II .pdf
Cross-Cultural Leadership Practices in Education (www.kiu.ac.ug)
Center Enamel Can Provide Pressure Vessels for Maldives Chemical Industry.docx
Second Hand Fashion Call to Action March 2025

Master Scheduling

  • 1. Mastes Scheduling Producción I IITI MC. Ma. del Pilar C. León Franco
  • 2. Master Scheduling (MPS) It forms the link between production planning and what manufacturing will actually build. It forms the basis for calculating the capacity and resources needed The MPS drives the material requirements plan It keeps priorities valid. The MPS is a priority plan for manufacturing.
  • 3. Master Scheduling (MPS) The end items made by the company are assembled from component and subcomponents parts. These must be available in the right quantities at the right time to support the master production schedule. The material requirements planning system plan the schedule for these components based on the needs of the MPS.
  • 4. Master Scheduling (MPS) The master production schedule is a plan for manufacturing. It reflects the needs of the marketplace and the capacity of manufacturing and forms a priority plan for manufacturing to follow.
  • 5. Master Scheduling (MPS) MPS Makes possible valid order promises Sales Production The production plan Forecasts for individual end items Actual orders received from customers and for stock replenishment Inventory levels for individual end items Capacity restraints
  • 6. Relationship to produce plan 500 Aggregate Inventory (units) Production Plan 250 215 160 160 160 160 Aggregate Forecast (units) 6 5 4 3 2 1 Week
  • 7. Developing a Master production Schedule The objectives in developing an MPS are: To maintain the desired level of customer service by maintaining finished-goods inventory levels or by schedule to meet customer delivery requirements To make the best use of material, labor and equipment To maintain inventory investment at the required levels
  • 8. Developing a Master production Schedule The plan must satisfy customer demand, be within the capacity of manufacturing, and be within the guidelines of the production plan
  • 9. Developing a Master production Schedule Steps: Develop a preliminary MPS Check the preliminary MPS against available capacity Resolve differences between the preliminary MPS and capacity availability
  • 10. Preliminary Master Production Schedule   100 100   100   MPS 20 80 40 0 60 20 80 Projected Available 60 60 60 60 60 60 Forecast 6 5 4 3 2 1 0 Week
  • 11. Rough-Cut Capacity Planning RCCP checks whether critical resources are available to support the preliminary master production schedules. Critical resources include bottleneck operations, labor, and critical materials.
  • 12. Rough-Cut Capacity Planning           Total Horas           Fine           Medium Total 3 2 1 0 Week hrs./unit 1.2 Fine hrs./unit 0.5 Medium 80 20 30 10 20 Fine 120 15 40 25 40 Medium Total 3 2 1 0 Week
  • 13. Resolution of Differences Compare the total time required to the available capacity of the work center Resources use Customer service Cost
  • 14. Master Schedule Decisions The MPS should represent as efficiently as possible what manufacturing will make. Make to stock products: Limited number of standard items are assembled from many components Make to order products: Many different ended items are made form a small number of components Assemble to order products: Many end items can be made form combinations of basic components and subassemblies.
  • 15. Master Schedule Decisions Make to stock Assemble to Order Make to order End Product Raw Material End Product Raw Material End Product Raw Material MPS MPS MPS FAS FAS FAS = Finaly Assembly Schedule