UPDATE : 02/06/2016
faulty OK
ASRS Faulty Equipment History :
- This fault history would be essential
on reviewing re-occuring faults that
may have the similar counter-measure
for us to rectify it on the fastest time as
possible.
- The equipment on the next graph are
the most trouble-sum of each month.
(please see accordingly)
CMT PERFORMANCE SUMMARY :
- PCHS sustained 99% since last month.
- while ASRS increases +2% gain from
94% to 96% performance.
Change Point
*Earlier fault detection before 8am
*Fault feedback every 11am & 2pm
WEEKLY KPI
CMT Availability Projection :
- PCHS will sustain its 99% performance
as it shows consistent average
performance on the next graph.
- ASRS will vary from -1% loss or will stay
at 96% performance based on Linear
interpolation method and the variation
behaviour from now and then.
ASRS - FAULTY EQUIPMENT HISTORY
PERFORMANCE : MAY 2016
ASRS - TOP FREQUENT FAULT (MAY 2016)
FIXED EQUIPMENT
dnata CMT
JAN FEB MAR APR 1WK 2WK 3WK 4WK 1WK 2WK 3WK 4WK
2016 MAY 2016 JUNE 2016
PROJECTION
PCHS 97% 98% 98% 99% 99% 99% 99% 99% 99%
ASRS 92% 94% 94% 94% 95% 96% 97% 97% 96%
90%
95%
100%
WEEKLY KPI
ASRS
PCHS
Legend
n : present
--- : projection
minor
faults
PCHS ASRS
CMT 99% 96%
99%
96%
90%
95%
100%
MAY 2016
90%
minimum target : 95%
12
0
2
T-CAR
19
2
STACKER
33
0
HOIST L51E01,
L51F01
R71A01,R72A01
BARCODE
POSITIONING
FAULT
90%
95%
100%
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
2016
L55A01 - VERT BPS FAULT
L56E01 - HORIZ. DRIVE FAULT
L52A01 - PROX. SWITCH FORK IN CENTER
L61E01 - PROX. SWITCH FORK IN CENTER
+2%
R71A01 STACKERS - BARCODE POSITIONING FAULTS
prepared by : Stephen Austria

MAY2016 - CMT REPORT

  • 1.
    UPDATE : 02/06/2016 faultyOK ASRS Faulty Equipment History : - This fault history would be essential on reviewing re-occuring faults that may have the similar counter-measure for us to rectify it on the fastest time as possible. - The equipment on the next graph are the most trouble-sum of each month. (please see accordingly) CMT PERFORMANCE SUMMARY : - PCHS sustained 99% since last month. - while ASRS increases +2% gain from 94% to 96% performance. Change Point *Earlier fault detection before 8am *Fault feedback every 11am & 2pm WEEKLY KPI CMT Availability Projection : - PCHS will sustain its 99% performance as it shows consistent average performance on the next graph. - ASRS will vary from -1% loss or will stay at 96% performance based on Linear interpolation method and the variation behaviour from now and then. ASRS - FAULTY EQUIPMENT HISTORY PERFORMANCE : MAY 2016 ASRS - TOP FREQUENT FAULT (MAY 2016) FIXED EQUIPMENT dnata CMT JAN FEB MAR APR 1WK 2WK 3WK 4WK 1WK 2WK 3WK 4WK 2016 MAY 2016 JUNE 2016 PROJECTION PCHS 97% 98% 98% 99% 99% 99% 99% 99% 99% ASRS 92% 94% 94% 94% 95% 96% 97% 97% 96% 90% 95% 100% WEEKLY KPI ASRS PCHS Legend n : present --- : projection minor faults PCHS ASRS CMT 99% 96% 99% 96% 90% 95% 100% MAY 2016 90% minimum target : 95% 12 0 2 T-CAR 19 2 STACKER 33 0 HOIST L51E01, L51F01 R71A01,R72A01 BARCODE POSITIONING FAULT 90% 95% 100% JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 2016 L55A01 - VERT BPS FAULT L56E01 - HORIZ. DRIVE FAULT L52A01 - PROX. SWITCH FORK IN CENTER L61E01 - PROX. SWITCH FORK IN CENTER +2% R71A01 STACKERS - BARCODE POSITIONING FAULTS prepared by : Stephen Austria